MONTHYEARIR 05000263/20240042025-01-30030 January 2025 Integrated Inspection Report 05000263/2024004 ML25006A1522025-01-16016 January 2025 Section 106 Consultation of Monticello SLR-Shakopee ML25006A1502025-01-16016 January 2025 Section 106 Consultation for Monticello SLR-Lower Sioux Indian Community ML25006A1512025-01-16016 January 2025 Section 106 Consultation for Monticello SLR-Mille Lacs Band of Ojibwe ML25010A0722025-01-10010 January 2025 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000263/2025002 IR 05000263/20244042025-01-0606 January 2025 Material Control and Accounting Program Inspection Report 05000263/2024404 (Public) ML24310A3442024-12-30030 December 2024 Transmittal Letter for Renewed License ML24270A1552024-12-19019 December 2024 Issuance of Amendment No. 213 Revise Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (Ptlr), and Update Neutron Fluence Methodology ML24354A2952024-12-18018 December 2024 ISFSI and Monticello Nuclear Generating Plant - Independent Spent Fuel Storage Installation Decommissioning Funding Plans L-MT-24-045, 2024 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.462024-12-13013 December 2024 2024 Annual Report of Changes in Emergency Core Cooling System Evaluation Models Pursuant to 10 CFR 50.46 ML24353A1192024-12-12012 December 2024 Usepa Monticello Re-license Feis Comments (1) IR 05000263/20244022024-12-0606 December 2024 – Security Baseline Inspection Report 05000263/2024402; Independent Spent Fuel Storage Installation Security Inspection Report 07200058/2024401 IR 05000263/20244032024-12-0606 December 2024 – Security Baseline Inspection Report 05000263/2024403 ML24324A0082024-12-0404 December 2024 Letter to Minnesota State Historic Preservation Office Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renewal Application IR 05000263/20243012024-11-27027 November 2024 NRC Initial License Examination Report 05000263/2024301 L-MT-24-042, Update to the Technical Specifications Bases2024-11-22022 November 2024 Update to the Technical Specifications Bases ML24323A2142024-11-21021 November 2024 – Relief Request RR-017, Inservice Inspection (ISI) Impracticality During the Fifth Ten-Year Interval ML24318C5002024-11-19019 November 2024 Letter to Robert Blanchard Tribal Chairman Bad River Band of Lake Superior Chippewa Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5102024-11-18018 November 2024 Letter to Louis Taylor Chairman Lac Courte Oreilles Band of Lake Superior Chippewa Indians Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5092024-11-18018 November 2024 Letter to Doreen Blaker President Keweenaw Bay Indian Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5012024-11-18018 November 2024 Letter to Catherine Chavers Tribal Chairwoman Bois Forte Band Chippewa Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5202024-11-18018 November 2024 Letter to Grant Johnson President Prairie Island Indian Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5182024-11-18018 November 2024 Letter to Gena Kakkak Chairwoman Menominee Indian Tribe of Wisconsin Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5222024-11-18018 November 2024 Letter to Darrell Seki Chairman Red Lake Nation Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5282024-11-18018 November 2024 Letter to Jamie Azure Chairman Turtle Mountain Band of Chippewa Indians Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5322024-11-18018 November 2024 Letter to Robert Vanzile Jr Chairman Sokaogon Chippewa Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24312A1732024-11-18018 November 2024 Ltr. to Shawn Hafen, Site Vice President, Monticello Nuclear Generating Plant, Re., NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5032024-11-18018 November 2024 Letter to Anthony Reider President Flandreau Santee Sioux Tribe NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5232024-11-18018 November 2024 Letter to Alonzo Denney Chairman Santee Sioux Nation Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5022024-11-18018 November 2024 Letter to Reggie Wassana Governor Cheyenne and Arapaho Tribes NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5162024-11-18018 November 2024 Letter to James Williams Jr Chairman Lac Vieux Desert Band of Lake Superior Chippewa Indians Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5212024-11-18018 November 2024 Letter to Nicole Boyd Chairwoman Red Cliff Band of Lake Superior Chippewa Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5312024-11-18018 November 2024 Letter to Virgil Wind Chief Executive Mille Lacs Band of Ojibwe Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5292024-11-18018 November 2024 Letter to Kevin Jensvold Tribal Chairman Upper Sioux Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5042024-11-18018 November 2024 Letter to Jeffrey Stiffarm President Fort Belknap Indian Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5112024-11-18018 November 2024 Letter to John Johnson President Lac Du Flambeau Band of Lake Superior Chippewa Indians Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24312A3512024-11-18018 November 2024 Letter to Amy Spong, Deputy State Historic Preservation Officer, Re., NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5172024-11-18018 November 2024 Letter to Robert Larsen President Lower Sioux Indian Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5072024-11-18018 November 2024 Letter Timothy Rhodd Chairman Iowa Tribe of Kansas and Nebraska Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5252024-11-18018 November 2024 Letter to J Garrett Renville Tribal Chairman Sisseton Wahpeton Oyate of the Lake Traversee Re NOA Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5262024-11-18018 November 2024 Letter to Lonna Johnson Street Chairperson Spirit Lake Nation Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5192024-11-18018 November 2024 Letter to Michael Laroque President Minnesota Chippewa Tribe Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5302024-11-18018 November 2024 Letter to Michael Fairbanks Chairman White Earth Nation Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5052024-11-18018 November 2024 Letter to Bruce Savage Tribal Chairperson Found Du Lac Band of Lake Superior Chippewa Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5062024-11-18018 November 2024 Letter to Robert Deschampe Tribal Chair Grand Portage Band of Lake Superior Chippewa Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5152024-11-18018 November 2024 Letter to Faron Jackson Sr Chairman Leech Lake Band of Ojibwe Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24312A3462024-11-18018 November 2024 Letter to Jaime Loichinger Director Office of Federal Agency Programs, Achp NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24318C5242024-11-18018 November 2024 Letter to Cole Miller Chairman Shakopee Mdewakaton Sioux Community Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR ML24312A3202024-11-18018 November 2024 Letter to Durell Cooper Tribal Chairman Apache Tribe of Oklahoma Re NOA of the Final EIS for the Monticello Nuclear Generating Plant Unit 1 SLR ML24318C5272024-11-18018 November 2024 Letter to Thomas Fowler Chairman St. Croix Chippewa of Wisconsin Re NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR 2025-01-06
[Table view] Category:Inspection Plan
MONTHYEARIR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) IR 05000263/20230062024-02-28028 February 2024 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2023006) IR 05000263/20230052023-08-30030 August 2023 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2023005) IR 05000263/20220062023-03-0101 March 2023 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2022006) ML23058A1522023-02-27027 February 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2023002 IR 05000263/20220052022-08-29029 August 2022 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2022005) IR 05000263/20210062022-03-0202 March 2022 Annual Assessment Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2021006) ML21322A2362021-11-18018 November 2021 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2022401 IR 05000263/20210052021-09-0101 September 2021 Updated Inspection Plan for Monticello Nuclear Generating Plant 2 (Report 05000263/2021005) ML21215A2172021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21147A5082021-06-0303 June 2021 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21085A8582021-03-26026 March 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000263/2021010 IR 05000263/20200062021-03-0404 March 2021 Annual Assessment Letter for the Monticello Nuclear Generating Plant (Report 05000263/2020006) ML21029A2982021-01-29029 January 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2021002 ML20275A3942020-10-0101 October 2020 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at the Monticello Nuclear Generating Plant IR 05000263/20200052020-09-0101 September 2020 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2020005) ML20134H9282020-05-12012 May 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000263/2020013 IR 05000263/20190062020-03-0303 March 2020 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2019006 and 07200058/2019006) ML19324F8512019-11-20020 November 2019 Long-Term Replacement Steam Dryer Inspection Plan ML19322C0512019-11-14014 November 2019 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report Number 05000263/2020011 IR 05000263/20190052019-08-28028 August 2019 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2019005) ML19136A0202019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19065A0832019-03-0505 March 2019 Ltr. 03/05/19 Monticello Nuclear Generating Plant - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2019002 (DRS-E.Fernandez) IR 05000263/20180062019-03-0404 March 2019 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2018006 and 07200058/2018006) IR 05000263/20180052018-08-28028 August 2018 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2018005) IR 05000263/20170062018-03-0202 March 2018 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2017006) ML17345A8402017-12-11011 December 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Monticello Nuclear Generating Plant IR 05000263/20170052017-08-28028 August 2017 Updated Inspection Plan for Monticello Nuclear Generating Plant (Report 05000263/2017005) IR 05000263/20174092017-06-0808 June 2017 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2017409 ML17094A4352017-04-0303 April 2017 Monticello - Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000263/20160062017-03-0101 March 2017 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2016006) ML17026A4302017-01-26026 January 2017 Notification of NRC Triennial Fire Protection Baseline Inspection and Request for Information 05000263/2017007 IR 05000263/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2016005) IR 05000263/20150062016-03-0202 March 2016 Annual Assessment Letter for Monticello Nuclear Generating Plant (Inspection Report 05000263/2015006) ML16041A0482016-02-0909 February 2016 Ltr. 02/09/16 Monticello Nuclear Generating Plant - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000263/2016002 IR 05000263/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2015005) IR 05000263/20140012015-03-0404 March 2015 Annual Assessment Letter for the Monticello Nuclear Generating Plant, (Report 05000263/2014001) ML15027A0412015-01-26026 January 2015 ISI Request for Information ML14245A1442014-09-0202 September 2014 Mid-Cycle Assessment Letter for Monticello Nuclear Generating Plant ML14216A5132014-08-0404 August 2014 Information Request to Support Upcoming Biennial Problem Identification and Resolution Inspection at the Monticello Nuclear Generating Plant IR 05000263/20130012014-03-0404 March 2014 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2013001) ML13246A2312013-09-0303 September 2013 2013 Monticello MOC Letter Combined ML13221A5712013-08-0909 August 2013 Ltr 8/9/13 Monticello MOD 50.59 Request for Information IR 05000263/20120012013-03-0404 March 2013 Annual Assessment Letter for Monticello Nuclear Generating Plant, (Report 05000263-12-001) ML12249A4222012-09-0404 September 2012 Mid-Cycle Assessment Letter for Monticello Generating Plant IR 05000263/20110072012-03-0505 March 2012 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263/2011007) IR 05000263/20110062011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plant for Monticello Nuclear Plant 05000263-11-006 IR 05000263/20110012011-03-0404 March 2011 Annual Assessment Letter for Monticello Nuclear Generating Plant (Report 05000263-11-001) ML1104705722011-02-16016 February 2011 Request Notification of NRC Inspection and Request for Information ISI ML1024400642010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Monticello Nuclear Generating Plant 2024-08-30
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 August 9, 2013 Mr. Mark Schimmel Site Vice President Monticello Nuclear Generating Plant Northern States Power Company, Minnesota 2807 West County Road 75 Monticello, MN 55362-9637
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT - INFORMATION REQUEST FOR AN NRC TRIENNIAL PERMANENT MODIFICATIONS AND 10 CFR 50.59 BASELINE INSPECTION 05000263/2013007
Dear Mark Schimmel:
On November 4, 2013, the U.S. Nuclear Regulatory Commission (NRC) will begin a Triennial Permanent Modifications and 10 CFR 50.59 (MOD/50.59) Baseline Inspection at the Monticello Nuclear Generating Plant. This inspection will be performed in accordance with the NRC baseline Inspection Procedure (IP) 71111.17. The onsite portion of the inspection will take place on November 4, 2013, and November 18, 2013.
Experience has shown that these baseline inspections are extremely resource intensive, both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for documents needed for the inspection. These documents have been divided into three groups.
The first group of information is necessary to ensure that the inspection team is adequately prepared for the inspection. This information should be made available via compact disc and delivered to the regional office no later than September 16, 2013. The inspection team will review this information and by September 26, 2013, will request specific items that should be provided for review in the regional office by October 23, 2013.
The second group of requested documents contains additional items that the team will review, or need access to, during the inspection. Certain documents contained within Group II (i.e., Item (1)), will be requested for review in the regional office prior to the inspection by October 23, 2013, as identified above. The remaining documents should be available by the first day of the onsite inspection, November 4, 2013.
The third group lists information necessary to aid the inspection team in tracking issues identified as a result of the inspection. The remaining documents in group three should be available by the first day of onsite inspection, November 4, 2013. It is requested that this information be provided to the lead inspector as the information is generated during the inspection.
M. Schimmel It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.
The lead inspector for this inspection is Mr. Andrew Dunlop. We understand that our regulatory contact for this inspection is Ms. Sandra OConner of your organization. If there are any questions about the inspection or the material requested, please contact the lead inspector at (630) 829-9726 or via e-mail at andrew.dunlop@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA by R. A. Langstaff Acting For/
Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety Docket No. 50-263 License No. DPR-22
Enclosure:
Modification and 50.59 Inspection Document Request cc w/encl:
Distribution via ListServ'
MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST Enclosure 1
Inspection Report:
05000263/2013007 Inspection Dates:
November 4 - 8, 2013 November 18 - 22, 2013 Inspection Procedure:
Inspection Procedure 71111.17, Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications Lead Inspector:
Andrew Dunlop (630) 829-9726 andrew.dunlop@nrc.gov I.
Information Requested for In-Office Preparation Week The following information is requested by September 16, 2013, or sooner, to facilitate the selection of specific items that will be reviewed during the onsite inspection week.
The inspection team will select specific items from the information requested below and submit a list to your staff by September 26, 2013. We will request that certain items be made available to the regional office prior to the inspection by October 23, 2013. We request that the remaining items selected from the lists be available and ready for review on the first day of inspection. All requested information should identify the associated system and cover the time frame from the receipt of information for the last MOD/50.59 inspection to the present.
The required information identified below should be provided on compact disc (CD).
Please provide three copies of each CD submitted (i.e., one for each inspector). The preferred file format is a searchable pdf file. The CDs should be indexed and hyper-linked to facilitate ease of use, if possible. If you have any questions regarding this information, please call the inspection team leader as soon as possible.
(1)
List of permanent plant modifications to systems, structures or components that are field work complete. (For the purpose of this inspection, permanent plant modifications include permanent: plant changes, design changes, set point changes, equivalency evaluations, suitability analyses, and commercial grade dedications.)
The list should contain the number of each document, the title, the revision (or date), and the affected system. In addition to the list, please provide a description of each modification and a list of associated calculations and affected procedures.
MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST Enclosure 2
(2)
List of all 10 CFR 50.59 completed evaluations involving (a) calculations, (b) procedure revisions, (c) changes to the facility (modifications), (d) non-routine operating configurations, or (e) departures in methods of analyses. This list should include 50.59 evaluations for the following:
- a.
Changes that have been made under the provisions of 10 CFR 50.59 that have been updated in accordance with 10 CFR 50.71(e)(4) since February 1, 2010;
- b.
Modifications that are field work complete; and
- c.
Changes to calculations (or initiation of new calculations) that have been issued. The list should contain the number and title of each document, a brief description of the change, and the corresponding number and type of the affected document (i.e., the modification or procedure to which the evaluation applies). The list should NOT include any evaluations in which prior NRC approval was sought and obtained.
(3)
A list of all 10 CFR 50.59 changes that have been screened out as not requiring a full evaluation involving: (a) calculations; (b) procedure revisions; (c) changes to the facility (modifications); (d) non-routine operating configurations; or (e) departures in methods of analyses.
The list should contain the number and title of each document, a brief description of the change, and the corresponding number and type of the affected document (i.e., the modification or procedure to which the evaluation applies).
(4)
A list of any modifications, procedure revisions, or UFSAR changes where it was determined that 10 CFR 50.59 did not apply.
(5)
A list of calculation changes that have been issued for use.
(6)
A list of corrective action documents (open and closed) that address permanent plant modifications or 10 CFR 50.59 issues, concerns, or processes. These documents should also include the corrective action documents associated with the modification and the MOD 50.59 change implementation.
The list should contain the number, title and revision (or date) of each document, the affected system and corresponding documentation (if applicable), and should be sorted in order of significance.
(7)
Copies of procedures addressing the following: modifications, design changes, set point changes, equivalency evaluations or suitability analyses, commercial grade dedications, post-modification testing, 10 CFR 50.59 evaluations and screenings, and UFSAR updates.
(8)
UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide copies of the complete submittal.
MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST Enclosure 3
(9)
Copy of the UFSAR change log or a synopsis of the changes. This should include all of the changes made to the UFSAR that were incorporated in the last 10 CFR 50.71(e)(4) submittal.
(10)
Electronic copy of the UFSAR and Technical Specifications, if available.
(11)
Name(s) and phone numbers for the regulatory and technical contacts.
(12)
Current management and engineering organizational chart.
II.
Information Requested to be Available Prior to Inspection. Requests will be Made for Specific Item (1) Documents by September 26, 2013, for Availability of Requested Item (1) Documents in Regional Office by October 23, 2013, and Items (2), (3), and (4) Documents on First Day of Inspection (November 4, 2013).
(1)
Copies of all selected items from Section I. This includes copies of associated documents such as calculations, post-modification test packages, 10 CFR 50.59 evaluations or screenings, and any corrective action documents.
(2)
Copies of these documents do not need to be solely available to the inspection team as long as the inspectors have easy and unrestrained access to them.
- a.
Updated Final Safety Analysis Report, if not previously provided;
- b.
Original FSAR Volumes;
- c.
Original SER and Supplements;
- d.
FSAR Question and Answers;
- e.
Quality Assurance Plan;
- f.
Technical Specifications, if not previously provided;
- g.
Latest IPE/PRA Report;
- h.
Vendor Manuals; and
- i.
The latest 10 CFR 50.59 UFSAR Update Submittal.
(3)
Please ensure that other supporting documents for the selected items have been located and are readily retrievable as the inspection team will likely be requesting these documents during the inspection. Examples of supporting documents are:
- a.
Drawings supporting the modifications;
- b.
Procedures affected by the modifications; and
- c.
UFSAR change papers generated due to a 10 CFR 50.59 evaluation.
MODIFICATIONS AND 50.59 INSPECTION DOCUMENT REQUEST Enclosure 4
(4)
Assessment and Corrective Actions:
- a.
The most recent MOD/50.59 Quality Assurance (QA) audit and/or self-assessment; and
- b.
Corrective action documents (e.g., condition reports, including status of corrective actions) generate as a result of the most recent MOD/50.59 Quality Assurance (QA) audit and/or self-assessment.
III.
Information Requested to be provided throughout the inspection (1)
Copies of any corrective action documents generated as a result of the inspection teams questions or queries during this inspection.
(2)
Copies of the list of questions submitted by the inspection team members and the status/resolution of the information requested (provide daily during the inspection to each inspection team member).
If you have any questions regarding the information requested, please contact the inspection team leader.
M. Schimmel It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.
The lead inspector for this inspection is Andrew Dunlop. We understand that our regulatory contact for this inspection is Ms. Sandra OConner of your organization. If there are any questions about the inspection or the material requested, please contact the lead inspector at (630) 829-9726 or via e-mail at andrew.dunlop@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS),
accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA by R. A. Langstaff Acting For/
Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety Docket No. 50-263 License No. DPR-22
Enclosure:
Modification and 50.59 Inspection Document Request cc w/encl:
Distribution via ListServ' DISTRIBUTION:
Vivian Campbell RidsNrrDorlLpl3-1 Resource RidsNrrPMMonticello RidsNrrDirsIrib Resource Cynthia Pederson Anne Boland Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak DOCUMENT NAME: Ltr 80913 Monticello MOD 50.59 RFI AXD.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME RLanfstaff for ADunlop:ls RDaley DATE 8/09/13 8/09/13 OFFICIAL RECORD COPY