MONTHYEARML22235A7862022-08-23023 August 2022 Acceptance Review: Exemption Request from 10 CFR 20, Appendix G, LLW Shipping Investigation Requirements ML21181A1882021-06-30030 June 2021 E-mail from S. Johnston, Holtec, to A. Snyder and F. Bower, NRC - Oyster Creek Nuclear Generating Station - Readiness Status for ISFSI Only Inspection ML21175A2092021-06-24024 June 2021 E-mail from A. Sterdis to P. Longmire - Oyster Creek Nuclear Generating Station: ISFSI-only Physical Security Plan (Stating Implementation Intent) ML21162A3602021-06-11011 June 2021 E-mail Response from the State of New Jersey Regarding the Pending Revision to the Emergency Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21162A1172021-06-11011 June 2021 E-mail to HDI: Acceptance Review - FOF Exemption ML21168A0172021-06-10010 June 2021 E-mail from HDI: RAI Response ML21161A2572021-06-0707 June 2021 State Consultation: ISFSI-only Physical Security Plan (Email Response) ML21175A0712021-06-0202 June 2021 Issuance of Request for Additional Information: Oyster Creek Nuclear Generating Station. Request for Amendment to Technical Specifications ML21148A0562021-05-27027 May 2021 E-mail to State of New Jersey Informing of the Pending Revision to the Emergency Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21132A3182021-05-12012 May 2021 E-Mail from V. Gubbi, DEP to Z. Cruz, NRC - Oyster Creek Nuclear Generating Station - State of New Jersey Response to the Pending Revision to the Defueled Technical Specifications to Reflect Independent Spent Fuel Storage Installation Only ML21132A0312021-05-11011 May 2021 E-mail to State of New Jersey Informing of the Pending Revision to the Physical Security Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21119A1422021-04-28028 April 2021 E-mail to State of New Jersey Informing of the Pending Revision to the Emergency Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21113A0742021-04-23023 April 2021 Acceptance Review Email - April 20, 2021 Oyster Creek Request for Exemption from 10 CFR Part 73 Requirements Due to Covid ML21099A0382021-04-0808 April 2021 Email from Z. Cruz to A. Sterdis - Request for Additional Information - HDI Request for Approval of Oyster Creek Nuclear Generating Station Independent Spent Fuel Storage Installation Facility Only Emergency Plan ML21085A4872021-03-26026 March 2021 E-mail from Z. Cruz to A. Sterdis - Acceptance Review: Oyster Creek Nuclear Generating Station - Request for Approval of Independent Spent Fuel Storage Installation Only Permanently Defueled Technical Specifications ML21064A2432021-03-0505 March 2021 Email from Z. Cruz to A. Sterdis Acceptance Review_ Oyster Creek Nuclear Generating Station - Request for Approval of Independent Spent Fuel Storage Installation Facility Only Emergency Plan and Emergency Action Level Scheme ML21064A2392021-03-0202 March 2021 E-mail from Z. Cruz to A. Sterdis Acceptance Review - Oyster Creek Nuclear Generating Station - Request for Approval of Independent Spent Fuel Storage Installation Only Physical Security Plan ML20345A1462020-12-0909 December 2020 E-mail - Response to Request for Additional Information: HDI Request for One-Time Exemption from Part 73, Appendix B FOF Requirements ML20335A3112020-11-30030 November 2020 Request for Additional Information Regarding Request for a one-time Exemption from Part 73, Appendix B Requirements for Oyster Creek Nuclear Generating Station ML20332A1472020-11-24024 November 2020 Acceptance Review: November 20 2020 Exemption Request from 10 CFR Part 73 Appendix B Requirements for Oyster Creek ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20279A5082020-10-0505 October 2020 Email to Holtec - Response to Notification of Oyster Creek Onsite Property Insurance Coverage ML20266G4032020-09-22022 September 2020 Acceptance Review Email - Request for Approval of HDI Fleet Decommissioning Quality Assurance Program, Revision 0 ML20134H8742020-05-12012 May 2020 Request for Additional Information Regarding Request for Temporary Exemption from Part 73, Appendix B Requirements ML20133J9182020-05-11011 May 2020 Acceptance Review Email - Oyster Creek Request for Exemption from Part 73 Qualification Requirements ML20120A0252020-04-22022 April 2020 NRR E-mail Capture - (External_Sender) Oyster Creek Sea Turtle Handling and Conservation Recommendation Obligations NRC-2019-0073, Response from NEIMA Local Community Advisory Board Questionnaire 10-30-2019 R Discenza2019-10-30030 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-30-2019 R Discenza ML19344C8022019-10-20020 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-20-2019 a Dressler ML19344C8002019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 W Mcmullin ML19344C7982019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 M Noto ML19344C7992019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 s Feldman ML19344C7932019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 C Bischoff ML19344C7962019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 G Adams ML19344C7912019-10-0808 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-08-2019 J Branciforte ML19344C7902019-10-0808 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-08-2019 Anonymous ML19344C7892019-10-0505 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-05-2019 P Dressler ML19263D1222019-09-20020 September 2019 for Your Action Request for Additional Information Hdi Oyster Creek PSDAR ML19214A0452019-08-0202 August 2019 NRC to NMFS, Revised Proposed Action for Oyster Creek Endangered Species Act Section 7 Consultation ML19182A3422019-07-0101 July 2019 Transaction ML19178A0702019-06-26026 June 2019 Email to State of New Jersey - Oyster Creek - Request Comments on Proposed Amendment to Remove Reference to the Oyster Creek Cyber Security Plan and Update License Condition 2.C.(4) in the Renewed Facility License ML19196A3422019-06-20020 June 2019 Email: Courtesy Notice on the Issuance of the Oyster Creek License Transfer and Exemption (Sierra Club) ML19196A3342019-06-20020 June 2019 Email: Courtesy Notice on the Issuance of the Oyster Creek License Transfer and Exemption ML19162A2242019-06-11011 June 2019 NRC to NMFS, NRC Responses to NMFS Requests for Additional Information for Oyster Creek ESA Section 7 Consultation NRC-2018-0237, Comment from Paul Dressler of the Concerned Citizens for Lacey Coalition, Regarding the Oyster Creek Nuclear Plant License Transfer Application2019-06-0707 June 2019 Comment from Paul Dressler of the Concerned Citizens for Lacey Coalition, Regarding the Oyster Creek Nuclear Plant License Transfer Application ML19155A1182019-06-0404 June 2019 Incoming E-mail from State of New Jersey on the Oyster Creek Exemption for Reduced Insurances and Use of Decommissioning Trust Fund for Spent Fuel Management and Site Restoration ML19155A1192019-06-0404 June 2019 State of New Jersey Comments - Oyster Creek Conforming Amendment Associated with the Oyster Creek Generating Station License Transfer Application ML19154A0582019-05-31031 May 2019 E-mail Response from State of New Jersey Dated May 31, 2019, Notification-and-Request-Oyster Creek License Transfer Application L-2018-LLM-0002 ML19158A2912019-05-30030 May 2019 NRR E-mail Capture - Oyster Creek ESA Consultation: Information Requests from NMFS ML19158A2772019-05-28028 May 2019 NRR E-mail Capture - Oyster Creek ESA Consultation: Information Requests from NMFS ML19148A4392019-05-24024 May 2019 NMFS to NRC, Requests for Additional Information to Support Oyster Creek Reinitiated Section 7 Consultation 2022-08-23
[Table view] |
Text
D. Ashlev - Fwd: Questions Pa~ie 1; D. Ashley Fwd: Questions From: D. Ashley To: John Hufnagel Date: 11/06/2006 8:18:04 AM
Subject:
Fwd: Questions John-Attached are the questions from ACRS.
regards, Donnie Ashley NRR/DLR/RLRA Oyster Creek License Renewal Project Manger 301-415-3191 dial @nrc.gov
>>> Cayetano Santos 11/06/2006 >>>
Donnie, Attached are the list of questions that the staff and AmerGen should be prepared to address during the January 2007 subcommittee meeting for the Oyster Creek license renewal. Please forward them on to John Hufnagel.
Thanks, Tanny CC: Hansraj Ashar; Louise Lund; Michael Modes; Noel Dudley; Richard Conte; Sujit Samaddar
c:\temp\GW}00003.TMP Page 1iiJ Page Mail Envelope Properties (454F360C.5C3 : 9: 10848)
Subject:
Fwd: Questions Creation Date 11/06/2006 8:18:04 AM From: D. Ashley Created By: DJA1 @nrc.gov Recipients Actiox Date & Time exeloncorp.com Transf 'erred 06 November, 2006 8:18:31 AM john.hufnagel (John Hufnagel) nrc.gov OWGWPO01.HQGWDOO1 Delive,red 06 November, 2006 8:18:04 AM HGA CC (Hansraj Ashar) Opene d 06 November, 2006 11:11:18 AM nrc.gov OWGWPOO3.HQGWDOO 1 Delive red 06 November, 2006 8:18:11 AM NFD CC (Noel Dudley) Opene d 06 November, 2006 10:08:49 AM nrc.gov TWGWPOO1 .HQGWDOO1 Delive red 06 November, 2006 8:18:11 AM LXL CC (Louise Lund) Opene d 06 November, 2006 8:47:23 AM nrc.gov TWGWPO02.HQGWDOO1 Delive red 06 November, 2006 8:18:11 AM SKS3 CC (Sujit Samaddar) Opene d 06 November, 2006 8:47:18 AM nrc.gov kpl-po.KP_DO D elive red 06 November, 2006 8:18:30 AM MCM CC (Michael Modes) Opene d 06 November, 2006 8:28:42 AM RJC CC (Richard Conte) Opene d 06 November, 2006 8:35:09 AM
00003.TMP -Pacie'21 c:\temD\GWIOOOO3.TMP Pac~e 21 Post Office Delivered Route exeloncorp.com OWGWPO01.HQGWDO01 06 November, 2006 8:18:04 AM nrc.gov OWGWPO03.HQGWDO01 06 November, 2006 8:18:11 AM nrc.gov TWGWPOO1.HQGWDO01 06 November, 2006 8:18:11 AM nrc.gov TWGWPO02.HQGWDOO1 06 November, 2006 8:18:11 AM nrc.gov kpl-po.KPDO 06 November, 2006 8:18:30 AM nrc.gov Files Size Date & Time MESSAGE 1329 06 November, 2006 8:18:04 AM TEXT.htm 914 Questions Revised.wpd 13991 03 November, 2006 4:24:33 PM D. Ashley.vcf 302 08 August, 2006 2:46:52 PM Options Auto Delete: No Expiration Date: None Notify Recipients: Yes Priority: Standard ReplyRequested: No Return Notification: None Concealed
Subject:
No Security: Standard To Be Delivered: Immediate Status Tracking: Delivered & Opened
D. Ashley - Questions Revisedý-wpýd Pagej]
ACRS Plant License Renewal Subcommittee Questions Regarding Oyster Creek License Renewal Application
- 1. Describe in detail the current condition of the entire drywell (including the embedded and sand bed regions). How were these individual measurements averaged? What are the uncertainties in the UT thickness measurements? How was measurement uncertainty addressed? What were the results of any statistical analyses of UT measurement data?
What is the lowest measured thickness of the drywell? Where is this located? How extensive is this thinned region? What thicknesses were assumed for those areas that were not measured (including the embedded region)? What are the bases for these assumptions? How do the measured thicknesses compare to the minimum required thicknesses and design thicknesses? How much margin is left in the drywell?
- a. Provide a map showing tho locations of all UT measurements of the drywell.
Provide spreadsheets showing all UT data taken on the drywell (segregate data by year and provide comments on data validity).
b., Provide scatter charts for each data set (by year taken and by bay).
- c. Provide a statistical analysis of each of these data sets. Identify best fit statistical distributions and provide means, minimums and 95/95 confidence limits.
- d. Combine data sets into 90 degree sectors, 180 degree sectors, and a full 360 degrees. Identify best fit statistical distributions, means, minimums and 95/95 confidence limits for each data set.
- 2. Discuss the UT measurement results and other findings from the October 2006 inspections. Was any leakage identified? Where was the water found? How much water was found? What was the source of leakage? How does this water effect corrosion of the drywell in the embedded region? How will these findings impact the aging management programs and commitments for license renewal? Provide a copy of the staff's inspection report.
- 3. Water leakage to the drywell should be stopped. Mitigating the effects of water leakage without addressing the source of leakage is unacceptable and inconsistent with the Generic Aging Lessons Learned Report. Describe actions and plans for preventing water from draining down and wetting the external surface of the drywell liner. If water leakage does occur, what analyses were performed to ensure that leakage would flow to the ends of the drain lines and not evaporate or collect in another location?
- a. After the strippable coating applied to the reactor cavity liner, what leakage monitoring activities are performed? What leak rates are observed?
- 4. Describe the condition of the exterior surface of the drywell and the sand bed floor.
Include photographs if available.
- 5. Provide an expert corrosion analysis of the expected corrosion phenomenon in the embedded region for three pH levels (basic, neutral, and acidic). Identify corrosion rates for each case as a function of depth into the embedded region.
- 6. Describe the original drywell analysis performed by GE in the early 1990s. Provide copies of this report.
D. Ashley- Questions Revised.wpd 'Page 2
- 7. Describe the bases for the drywell thicknesses assumed in the Sandia finite element model? What changes were made as a result of the October 2006 UT inspections?
What UT measurement data was used? How was this data averaged? How would these results change as a result of different assumed thicknesses (sensitivity study)?
Resolve the discrepancies between the thicknesses reported by the applicant and those used in Sandia's finite element model. Provide copies of the final Sandia report.
- 8. Sandia's model included locally thinned areas of the drywell directly below the vent lines.
What effect would moving these locally thinned areas to different locations have on the results (sensitivity studies)?
- 9. How does corrosion and removal of the sand affect the loads and seismic response of the drywell?
- 10. Provide a buckling analysis of the drywell liner in the embedded region taking into account the strengthening effect of the concrete above and below. Assume no damage, as well as damage equal to the worse case send bed region. Identify the most vulnerable area of the embedded region (most likely the interface between the sand bed and embedded regions).
- 11. How is the air gap between the concrete and drywell created? What are the dimensions of this air gap? What is the function of Firebar D? What are its properties and chemical composition? What species could be leached out of Firebar D as a result of water leakage from the refueling cavity? What species were found in the sand after it was removed? What were the concentrations of these species? What effects did these chemicals have on corrosion of the drywell?
- 12. Was any pitting found in the drywell or torus?
- 13. Given the problems with implementing commitments in the past (monitoring for water),
what assurances are there that the commitments made during license renewal will be implemented?