|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARTXX-9924, Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span1999-10-22022 October 1999 Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span ML20217M5711999-10-20020 October 1999 Forwards Insp Repts 50-445/99-15 & 50-446/99-15 on 990822- 1002.Two Severity Level IV Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy TXX-9923, Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred1999-10-15015 October 1999 Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred ML20217E7951999-10-12012 October 1999 Forwards COLR for Unit 1,Cycle 8,per TS 5.6.5 ML20212L2891999-10-0101 October 1999 Discusses Closeout of GL 97-06, Degradation of Steam Generator Internals. Purpose of GL Was to Obtain Info That Would Enable NRC to Verify That Condition of Licensee SG Internals Comply with Current Licensing Bases TXX-9922, Forwards Revised COLR, for Cycle 5 for Unit 21999-10-0101 October 1999 Forwards Revised COLR, for Cycle 5 for Unit 2 ML20216J5571999-10-0101 October 1999 Provides Final Response to GL 98-01,suppl 1, Y2K Readiness of Computer Sys at Npps ML20212G0721999-09-24024 September 1999 Forwards Rev 4 to Augmented Inservice Insp Plan for CPSES, Unit 1. Future Changes & Revs to Unit 1 Augmented Inservice Insp Plan Will Be Available on Site ML20212H0461999-09-24024 September 1999 Forwards Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820 ML20212F7481999-09-24024 September 1999 Forwards SER Authorizing Relief from Exam Requirement of 1986 Edition ASME Code,Section XI Pursuant to 10CFR50.55a(a)(3)(ii) for Relief Request A-3 & 10CFR50.55a(g)(6)(i) for Relief Requests B15,16,17 & C-4 ML20212F1041999-09-23023 September 1999 Requests That NRC Be Informed of Any Changes in Scope of Y2K System Deficiencies Listed or Util Projected Completion Schedule for Comanche Peak Steam Electric Station,Units 1 & 2 ML20212E6661999-09-21021 September 1999 Advises That Info Contained in Application & Affidavit, (CAW-99-1342) Re WCAP-15009,Rev 0, Comache Peak Unit 1 Evaluation for Tube Vibration Induced Fatigue, Will Be Withheld from Public Disclosure ML20212D9111999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of CPSES & Did Not Identify Any Areas in Which Performance Warranted Insp Beyond Core Insp Program.Core Insp Plan at Facility Over Next 7 Months.Insp Plan Through March 2000 Encl ML20212A7601999-09-14014 September 1999 Forwards Insp Repts 50-445/99-14 & 50-446/99-14 on 990707-0821.Four Violations Occurred & Being Treated as Ncvs.Conduct of Activities Was Generally Characterized by safety-conscious Operations & Sound Radiological Controls TXX-9921, Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC1999-09-10010 September 1999 Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC ML20211P3761999-09-0707 September 1999 Ack Receipt of Ltr Dtd 990615,transmitting Rev 30 to Physical Security Plan,Per 10CFR50.54(p).No NRC Approval Is Required ML20211L9871999-09-0303 September 1999 Forwards Rev 31 to Technical Requirements Manual. All Changes Applicable to Plants Have Been Reviewed Under Util 10CFR50.59 Process & Found Not to Include Any USQs TXX-9915, Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl1999-09-0303 September 1999 Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl ML20211K2231999-08-31031 August 1999 Forwards Txu Electric Comments of Rvid,Version 2 ML20211J3801999-08-27027 August 1999 Forwards Corrected TS Page 3.8-26 to Amend 66 to Licenses NPF-87 & NPF-89,respectively.Footnote on TS Page 3.8-26 Incorrectly Deleted ML20211G7301999-08-26026 August 1999 Forwards Revs 29 & 30 to CPSES Technical Requirements Manual (Trm). Attachments 1 & 2 Contain Description of Changes for Revs 29 & 30 Respectively ML20211G1081999-08-26026 August 1999 Responds to NRR Staff RAI Re Util Mar 1999 Submittal for NRC Review & Approval of Changes to CPSES Emergency Classification Procedure ML20211G3441999-08-25025 August 1999 Forwards Response to NRC RAI on LAR 98-010 for Cpses,Units 1 & 2.Communication Contains No New Licensing Commitments Re Cpses,Units 1 & 2 ML20211B2861999-08-18018 August 1999 Forwards Insp Repts 50-445/99-13 & 50-446/99-13 on 990720- 23.No Violations Noted.Insp Included Implementation of Licensee Emergency Plan & Procedures During Util Biennial Emergency Preparedness Exercise ML20211C4661999-08-18018 August 1999 Discusses Proprietary Info Re Thermo-Lag.NRC Treated Bisco Test Rept 748-105 as Proprietary & Withheld It from Public Disclosure,Iaw 10CFR2.790 ML20210U3981999-08-17017 August 1999 Forwards Monthly Operating Repts for July 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs or SVs for Plant Occurred ML20211C0991999-08-17017 August 1999 Forwards Rev 3 to ASME Section XI ISI Program Plan,Unit 2 - 1st Interval, Replacing Rev 2 in Entirety ML20211C4571999-08-16016 August 1999 Forwards Omitted Subj Page of Contractor TER TXX-9919, Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 9908021999-08-16016 August 1999 Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 990802 ML20210R6561999-08-13013 August 1999 Forwards Response to NRR 990805 Telcon RAI Re License Amend Request 98-010,to Increase Power for Operation of CPSES Unit 2 to 3445 Mwth & Incorporating Addl Changes Into Units 1 & 2 TS ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210S6411999-08-12012 August 1999 Informs That Wg Guldemond,License SOP-43780,is No Longer Performing Licensed Duties.Discontinuation of License Is Requested ML20210R2221999-08-12012 August 1999 Forwards Insp Repts 50-445/99-10 & 50-446/99-10 on 990510-0628.Violations Noted & Being Treated as Ncvs, Consistent with App C of Enforcement Policy ML20210N1101999-08-0404 August 1999 Provides Supplemental Info to Util 990623 License Amend Request 99-005 Re Bypassing DG Trips.Info Replaces Info Contained in Subject Submittal in Attachment 2,Section II, Description of TS Change Request ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML20210J2301999-08-0202 August 1999 Forwards Amend 96 to CPSES Ufsar.Replacement of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,Rev 2 ML20210J6071999-08-0202 August 1999 Forwards line-by-line Descriptions of Changes in Amend 96 to CPSES UFSAR Transmitted by Util Ltr TXX-99166,dtd 990802. Replacment of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,rev 2 TXX-9916, Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 9907271999-08-0202 August 1999 Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 990727 TXX-9918, Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-9906301999-08-0202 August 1999 Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 ML20210K2321999-07-29029 July 1999 Forwards Insp Repts 50-445/99-12 & 50-446/99-12 on 990530-0710.No Violations Noted ML20210G5861999-07-29029 July 1999 Forwards fitness-for-duty Program Performance Data for Six Month Period of Jan-June 1999 ML20210J0121999-07-27027 July 1999 Forwards Summary of Methodology for Determination of NDE Measurement Uncertainty,In Response to Recent Discussions with NRC Re LAR 98-006 Concerning Rev to SG Tube Plugging Criteria TXX-9917, Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES1999-07-26026 July 1999 Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES ML20210F3121999-07-26026 July 1999 Responds to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal, ML20210D8231999-07-23023 July 1999 Forwards Safety Evaluation of Relief Requests Re Use of 1998 Edition of Subsections IWE & Iwl of ASME Code for Containment Insp ML20210D3211999-07-21021 July 1999 Provides List of Estimates of Licensing Actions,In Response to Administrative Ltr 99-02,dtd 990603 ML20210C2931999-07-21021 July 1999 Supplements 880323 Response to NRC Bulletin 88-02, Rapidly Propagating...Sg Tubes, Non-proprietary WCAP-15010 & Proprietary Rev 0 to WCAP-15009, CP Unit 1 Evaluation for Tube Vibration... Encl.Proprietary Rept Withheld ML20209H0111999-07-16016 July 1999 Forwards Relief Request C-4 to CPSES Unit 2 ISI Program for Approval ML20210C3331999-07-16016 July 1999 Forwards Exam Repts 50-445/99-301 & 50-446/99-301 on 990618- 24.Exam Included Evaluation of Six Applicants for Senior Operator Licenses ML20209H2551999-07-16016 July 1999 Forwards ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2 & Containment ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2,per ASME Boiler & Pressure Vessel Code,Section Xi,Paragraph IWA-6230 1999-09-07
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARTXX-9924, Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span1999-10-22022 October 1999 Forwards Responses to Questions by NRC Re Application for Amends to Licenses NPF-87 & NPF-89,by Incorporating Changes Increasing RWST low-level Setpoint from Greater than But Equal to 40% to Greater than But Equal to 45% of Span TXX-9923, Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred1999-10-15015 October 1999 Forwards Monthly Operating Repts for Sept 1999 for CPSES, Units 1 & 2,per Plant TS 5.6.4.No Failures of Challenges to PORVs of SV for Units Occurred ML20217E7951999-10-12012 October 1999 Forwards COLR for Unit 1,Cycle 8,per TS 5.6.5 ML20216J5571999-10-0101 October 1999 Provides Final Response to GL 98-01,suppl 1, Y2K Readiness of Computer Sys at Npps TXX-9922, Forwards Revised COLR, for Cycle 5 for Unit 21999-10-0101 October 1999 Forwards Revised COLR, for Cycle 5 for Unit 2 ML20212G0721999-09-24024 September 1999 Forwards Rev 4 to Augmented Inservice Insp Plan for CPSES, Unit 1. Future Changes & Revs to Unit 1 Augmented Inservice Insp Plan Will Be Available on Site ML20212H0461999-09-24024 September 1999 Forwards Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820 TXX-9921, Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC1999-09-10010 September 1999 Suppls 981221 LAR 98-010 to Licenses NPF-87 & NPF-89, Clarfying Conditions of Use Re Analytical Methods Used to Determine Core Operating Limits,Per Telcon with NRC ML20211L9871999-09-0303 September 1999 Forwards Rev 31 to Technical Requirements Manual. All Changes Applicable to Plants Have Been Reviewed Under Util 10CFR50.59 Process & Found Not to Include Any USQs TXX-9915, Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl1999-09-0303 September 1999 Responds to 990701 & 0825 RAI Telcons Re Spent Fuel Pool Temp,Per LAR 98-008,which Requested Increase in Spent Fuel Storage capacity.Marked-up Page 4-1 of CPSES Fuel Storage Licensing Rept, Encl ML20211K2231999-08-31031 August 1999 Forwards Txu Electric Comments of Rvid,Version 2 ML20211G1081999-08-26026 August 1999 Responds to NRR Staff RAI Re Util Mar 1999 Submittal for NRC Review & Approval of Changes to CPSES Emergency Classification Procedure ML20211G7301999-08-26026 August 1999 Forwards Revs 29 & 30 to CPSES Technical Requirements Manual (Trm). Attachments 1 & 2 Contain Description of Changes for Revs 29 & 30 Respectively ML20211G3441999-08-25025 August 1999 Forwards Response to NRC RAI on LAR 98-010 for Cpses,Units 1 & 2.Communication Contains No New Licensing Commitments Re Cpses,Units 1 & 2 ML20210U3981999-08-17017 August 1999 Forwards Monthly Operating Repts for July 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs or SVs for Plant Occurred ML20211C0991999-08-17017 August 1999 Forwards Rev 3 to ASME Section XI ISI Program Plan,Unit 2 - 1st Interval, Replacing Rev 2 in Entirety TXX-9919, Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 9908021999-08-16016 August 1999 Forwards Relief Request A-3,Rev 1 to Unit 1 ISI Program,Per Conversations Between NRC & Txu Electric on 990802 ML20210R6561999-08-13013 August 1999 Forwards Response to NRR 990805 Telcon RAI Re License Amend Request 98-010,to Increase Power for Operation of CPSES Unit 2 to 3445 Mwth & Incorporating Addl Changes Into Units 1 & 2 TS ML20210S6411999-08-12012 August 1999 Informs That Wg Guldemond,License SOP-43780,is No Longer Performing Licensed Duties.Discontinuation of License Is Requested ML20210N1101999-08-0404 August 1999 Provides Supplemental Info to Util 990623 License Amend Request 99-005 Re Bypassing DG Trips.Info Replaces Info Contained in Subject Submittal in Attachment 2,Section II, Description of TS Change Request TXX-9918, Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-9906301999-08-0202 August 1999 Forwards CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802-990201 & CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 ML20210J2301999-08-0202 August 1999 Forwards Amend 96 to CPSES Ufsar.Replacement of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,Rev 2 ML20210J6071999-08-0202 August 1999 Forwards line-by-line Descriptions of Changes in Amend 96 to CPSES UFSAR Transmitted by Util Ltr TXX-99166,dtd 990802. Replacment of FSAR Figures with Plant Process Flow Diagrams Meets Intent & Requirements of NRC Reg Guide 1.70,rev 2 TXX-9916, Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 9907271999-08-0202 August 1999 Notifies NRC That CPSES Units 1 & 2,improved TS Implemented on 990727 ML20210G5861999-07-29029 July 1999 Forwards fitness-for-duty Program Performance Data for Six Month Period of Jan-June 1999 ML20210J0121999-07-27027 July 1999 Forwards Summary of Methodology for Determination of NDE Measurement Uncertainty,In Response to Recent Discussions with NRC Re LAR 98-006 Concerning Rev to SG Tube Plugging Criteria TXX-9917, Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES1999-07-26026 July 1999 Provides Info Re Augmented Inservice Insp Plan,Which Requires Periodic Insp of Rv Head & Internals Lifting Devices at CPSES ML20210F3121999-07-26026 July 1999 Responds to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal, ML20210C2931999-07-21021 July 1999 Supplements 880323 Response to NRC Bulletin 88-02, Rapidly Propagating...Sg Tubes, Non-proprietary WCAP-15010 & Proprietary Rev 0 to WCAP-15009, CP Unit 1 Evaluation for Tube Vibration... Encl.Proprietary Rept Withheld ML20210D3211999-07-21021 July 1999 Provides List of Estimates of Licensing Actions,In Response to Administrative Ltr 99-02,dtd 990603 ML20209H2551999-07-16016 July 1999 Forwards ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2 & Containment ISI Summary Rept for Fourth Refueling Outage of CPSES Unit 2,per ASME Boiler & Pressure Vessel Code,Section Xi,Paragraph IWA-6230 ML20209H0111999-07-16016 July 1999 Forwards Relief Request C-4 to CPSES Unit 2 ISI Program for Approval ML20209G0721999-07-13013 July 1999 Forwards Monthly Operating Repts for June 1999 for CPSES, Units 1 & 2,per TS 6.9.1.5.No Failures or Challenges to PORVs of SV Occurred During Reporting Period ML20209F0681999-07-0909 July 1999 Informs That Effective 990514,TU Electric Formally Changed Name to Txu Electric.Change All Refs of TU Electric to Txu Electric on Correspondence Distribution Lists ML20209E0421999-07-0909 July 1999 Forwards Response to NRC Request for Addl Info on LAR 98-010.Attachment 1 Is Affidavit for Info Supporting LAR 98-010 ML20209B6021999-06-30030 June 1999 Submits Second Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Readiness Disclosure for Reporting Status of Facility Y2K Readiness Encl ML20195J6981999-06-15015 June 1999 Provides Addl Info Related to Open Issue,Discussed in 990610 Conference Call with D Jaffe Re ISI Program Relief Request L-1 Submitted by Util on 980220 ML20196A4921999-06-15015 June 1999 Forwards Rev 30 to Physical Security Plan.Rev Withheld,Per 10CFR73.21 ML20195J0491999-06-14014 June 1999 Submits Response to RAI Re Implementation of 1.0 Volt Repair Criteria ML20195J0651999-06-14014 June 1999 Submits Response to RAI Re GL 95-07, Pressure Locking & Thermal Binding of Safety Related Power Operated Gate Valves 05000445/LER-1999-001, Forwards LER 99-001-00, Some Electrical Contacts for RCS Pressure Relief Valves Were Not Included in Surveillance Testing Procedures. New Licensing Commitments Identified in Attachment 11999-06-0808 June 1999 Forwards LER 99-001-00, Some Electrical Contacts for RCS Pressure Relief Valves Were Not Included in Surveillance Testing Procedures. New Licensing Commitments Identified in Attachment 1 ML20195F0091999-06-0808 June 1999 Forwards Response to RAI Re Units 1 & 2 ISI Program for Relief Requests E-1 & L-1.Communication Contains No New Licensing Basis Commitments Re Cpses,Units 1 & 2 ML20207E1921999-05-28028 May 1999 Submits Updated Request for NRC Staff to Review & Approve Certain Changes to CPSES Emergency Plan Submitted in 981015 & s Prior to Changes Being Implemented at CPSES ML20207E1711999-05-28028 May 1999 Supplements 990526 LAR 99-004 as TU Electric Believes Extingency Exists in That Proposed Amend Was Result of NOED Granted to Prevent Shudown of CPSES Unit 1 ML20207D9841999-05-26026 May 1999 Requests That NRC Exercise Enforcement Discretion to Allow Cpses,Unit 1 to Remain in Mode 1,power Operation,Without Having Performed Svc Test,Per SR 4.8.2.1d on Unit 1 Battery BT1ED2 ML20195B6351999-05-25025 May 1999 Submits Response to RAI Re GL 95-07, Pressure Locking & Thermal Binding of Safety Related Power Operated Gate Valves TXX-9912, Forwards Txu Electric (Formerly TU Electric) CPSES Emergency Preparedness Exercise Scenario Manual for 990721-22,Graded Exercise1999-05-21021 May 1999 Forwards Txu Electric (Formerly TU Electric) CPSES Emergency Preparedness Exercise Scenario Manual for 990721-22,Graded Exercise ML20206U1981999-05-20020 May 1999 Forwards Form 10K Annual Rept,Per 10CFR50.71(b). Communication Contains No New Licensing Basis Commitments Re Cpses,Units 1 & 2 ML20196L1931999-05-20020 May 1999 Forwards MOR for Apr 1999 for Cpses,Units 1 & 2.During Reporting Period There Have Been No Failures or Challenges to Power Operated Relief Valves or Safety Valves TXX-9911, Forwards non-proprietary & Proprietary Responses to RAI Re LAR 98-010 by Incorporating Attached Changes Into CPSES Unit 2 OL NPF-89 & CPSES Units 1,OL NPF-87 & 2 TS to Increase Licensed Power.W & Caldon Proprietary Responses Withheld1999-05-14014 May 1999 Forwards non-proprietary & Proprietary Responses to RAI Re LAR 98-010 by Incorporating Attached Changes Into CPSES Unit 2 OL NPF-89 & CPSES Units 1,OL NPF-87 & 2 TS to Increase Licensed Power.W & Caldon Proprietary Responses Withheld 1999-09-03
[Table view] |
Text
..
= = = = = = = Log # TXX-93254 7 9 File # 10035(GL-92-08)
-. _- 10119 (NRCB 92-01) 909.5 TUELECTRIC R'I' #
10&Sj July 13, 1993 William J. Cahm, Jr.
tinmp Vice President U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NO. 50-445 SUPPLEMENTAL RESPONSE FOR GENERIC LETTER 92-08 AND CONFIRMATORY TESTING OF THERM 0-LAG FIRE BARRIERS REF: 1) TV Electric letter logged TXX-93038 from William J. Cahill, Jr., to NRC dated January 19, 1993
- 2) TV Electric letter logged TXX-93091 from William J. Cahill, Jr., to NRC dated April 15, 1993
- 3) NRC letter from Suzanne C. Black, to William J. Cahill Jr., dated October 29, 1993 Gentlemen:
Generic Letter 92-08, dated December 17, 1992, stated that all addressees are required, pursuant to section 182(a) of the Atomic Energy Act of 1954, as amended, and 10CFR50.54(f), to submit a written report within 120 days from the date of this generic letter. TU Electric has reviewed the actions requested and reporting requirements of this Generic Letter.
Thermo-Lag 330-1 fire barriers are relied upon to satisfy physical independence of electrical systems as required by Regulatory Guide 1.75 where such systems requiring physical independence also require protection for ensuring fire safe shutdown capability.
Via references 1 and 2, TU Electric provided responses to Generic Letter 92-08 for the Thermo-Lag fire barrier installations at CPSES Units l'and 2.
The response for Unit 1 (reference 2) stated that TU Electfic is currently participating in a generic effort with the rest of the nuclear industry and.
Nuclear Management and Resources Council (NUMARC) to ascertain designs and. ;
installations of fire barriers which satisfy 10CFR50 Appendix A, General 1 Design Criteria (GDC) 3. Additionally, TU Electric identified that there were various options under consideration to resolve the issue, and.that further assessment was needed to determine an approach which would satisfy O.
190070 l i
ag72200seeaoy,a -
400 N. Olive Street LB. 8 L Dallas, Texas 75201 p ADOCM 05000445 g PDR g
,. i
.. A TXX-93254 Page 2 of 6 were various options under consideration to resolve the~ issue, and that ,
further assessment was needed to determine an approach which would satisfy l GDC-3, without causing an unjustified impact on the industry.
The various options identified in reference 2' included the following:
Performing additional testing to demonstrate the acceptability of the installed configurations.
Identifying, testing (if further testing is deemed appropriate) and installing " upgrades" to existing configurations.
During a teleconference with the NRC staff on June 29,.1993, TO Electric verbally provided " preliminary" details regarding the methodology to be used in completion of Thermo-Lag certification for CPSES Unit 1, including additional Thermo-Lag Barrier Fire Endurance Testing.
In completing the Unit 1 Thermo-Lag certification activities, TU Electric will rely upon various certification methods for example, TV Electric will utilize previously accepted Unit 2 test results for some Unit 1 upgrades.
Additionally, TU Electric will perform tests to certify other possible upgrade techniques and other Thermo-Lag configurations.
During this teleconference the NRC staff requested a description of subjects ,
which were verbally discussed. TU Electric is complying with the NRC: Staff's !
request, however, TU Electric wishes to make certain that the Staff is fully- 1 cognizant that the information being provided is " preliminary" in nature and >
may change as the proposed testing and work activities progresses. The -)
teleconference subjects of discussion are addressed below, including J descriptions of the evaluation process, test attributes, test i configurations, and the required reports: ]
A) Evaluation Process Evaluate Thermo-Lag configurations to determine:
i) which installed raceway configurations in Unit 1 are qualified based on the results of the existing CPSES tests; ^
ii) which installed raceway configurations warrant adoitional fire endurance testing to qualify cost effective upgrades; iii)whichconfigurationswillbeupgraded; iv) cable functional performance acceptability for 1-1/2 inch and 2 inch non-upgraded conduits using the temperature profiles obtained from the existing CPSES fire test results of non-upgraded conduits (refer to previous CPSES test scheme 9-3);
J
'l 1
... .= . -. .. --
I I
TXX-93254 Page 3 of 6 v) acceptability of Unit i raceway supports which may be impacted oy the preferred upgrades (i.e., weight). Confirm the acceptability of the supports and/or initiate design changes as required; and j vi) potential impact to existing ampacity derating factors. Reevaluate the cables utilizing the results of the recently performed tests.
Initiate cable modification as required.
A preliminary review of the above evaluations is depicted in attachment 1 of this letter.
B) Test Attributes i Testing will be performed utilizing the acceptance criteria established in your staff's memorandum dated October 29, 1992 (reference 3), and as ;
amended by CPSES Safety Evaluation Report (NUREG-0797), Supplement 26 and Supplement 27. The exceptions would be: :
I No continuous circuit monitoring during performance of the tests.
Utilization of a seven day cure time versus the thirty day cure time, as was approved via SSER Supplement 27 for previous CPSES test scheme 15-1.
C) Test Configurations -
, TV Electric currently plans to perform fire endurance tests on five (5) !
raceway configurations (also referred tc as test schemes) during the upcoming tests. These schemes are described below.
i) Scheme #11-2; consists of a 24"x4" ladder back tray with two air drop configurations (2 inch and 1-1/2 inch diameter).
1 (a) The cable air drop bundles are protected with two layers of Thermo-Lag 330-660 "flexi-blanket" material.
i (b) The cable tray is protected with 1/2 inch (nominal) thick i Thermo-Lag board sections with ribs. Vertical and bottom- :
butt joints will be reinforced with a layer of stress skin with trowel grade Thermo-Lag material. ,
(c) Tne 2 inch airdrop and a single' cable protruding airdrop will be reinforced where they enter the 24 inch cable tray using flexible stainless steel mesh with trowel grade Thermo-Lag material.
~,-.r - . . , , .,, ,
+ , -- ------e- - _ . - - . _ - - - . - - - - - _ _ . - - . _ . - -
TXX-93254 Page.4 of 6 (d) The Thermo-Lag attributes being tested are 2 inch and 1-1/2 inch diameter airdrops protected with 2 layers of "flexi-blanket" and the interface region between airdrops and cable ,
trays reinforced with flexible mesh with trowel grade Thermo-Lag material.
ii) Scheme #11-4; consists of cables airdropping from embedded wall ~
sleeves-into two, stacked, 24"x4" ladder back trays.
(a) A Thermo-Lag box design enclosure will cover the airdrop cables including both trays and continuing over to the wall penetration. The box will be constructed of 1/2 inch (nominal) thick Thermo-Lag board sections with ribs. All joints will be reinforced with a layer of stress skin with trowel grade Thermo-Lag material.
(b) The remainder of the 2 cable trays not included;with the box coverage will be protected with 1/2 inch (nominal) thick Thermo-Lag board sections with ribs. Vertical and bottom butt joints will be reinforced with a layer of stress skin with trowel grade Thermo-Lag material.
(c) The Thermo-Lag attribute being tested is the " box" design configuration protected with a single layer of.Thermo-Lag :
prefabricated panels and its interface region to the concrete structure surrounding the embedded sleeves, iii) Scheme #11-5; consists of three 24"x4" ladder back tray assemblies with various methods of joint reinforcement methods.
(a) The trays will be protected with 1/2 inch (nominal) thick Thermo-Lag board sections with ribs.
(b) One tray will be upgraded with circumferential1'y wrapped stress skin and trowel grade Thermo-Lag material around butt joints and on 2 foot intervals. One tray will be upgraded with stress skin and trowel grade material applied along longitudinal joints only. One tray will be upgraded with a braided ceramic banding material wrapped circumferential1y around butt joints and on 2 foot intervals. *
(c) The Thermo-Lag attributes being tested are the various cable tray joint upgrade techniques utilizing stress skin and- e trowel grade Thermo-Lag material and ceramic banding material. N, iv) Scheme #13-2; consists of a 12"x4" ladder back cable tray with 90 i degree bends and a 2 inch diameter conduit with two radial bends.
l l
, l i
.l l
TXX-93254 Page 5 of 6 u
(a) The cable tray is-protected with 1/2 inch (nominal) thick Thermo-Lag board sections with ribs. This tray configuration will be tested as currently installed in Unit I without any upgrade of butt.or longitudinal joints.
(b) A 2 inch diameter conduit is protected with 1/2 inch i (nominal) thick prefabricated Thermo-Lag material. The l radial bends will be upgraded with flexible stainless steel mesh and trowel grade Thermo-Lag material.
(c) The Thermo-Lag attributes being tested are 12 inch cable tray coverage with no joint upgrade and conduit radial bend upgrade with the flexible mesh.
v) Scheme #15-2; consists of Thermo-Lag 330-660 "flexi-blanket" ,
material wrapped cables in an exposed 36"x4" ladder back cableL ,
tray.
(a) There will be two wrapped cable bundles, one with two layers of "flexi-blanket" and one with three layers of-flexi- a blanket".
(b) The 36 inch cable tray in which the wrapped cables are !
installed will have no Thermo-Lag protection for the tray or '
for the cable tray supports.
(c) The Thermo-Lag attributes being. tested are "flexi-blanket" wrapped cables in exposed cable tray.
r D) Reports Provide reports to the NRC which; i) identifies which installed Unit 1 Thermo-Lag configurations are qualified and the basis for their qualification, -'
ii) identifies which installed Unit 1 configurations will be upgraded d and the basis for the qualification of the upgrades, and j P
iii) identifies any Unit 1 configurations which deviate.from a one-hour
~
fire rating and the basis for the deviation.
Please note that the description above and the attached tables are l preliminary.
a A preliminary schedule of the testing at Omega Point Laboratory, San j Antonio, Texas, has been provided to your staff. The preliminary sketches j of the configurations-(schemes) will be hand delivered to your staff as soon-as they become available.
1 i
TXX-93254' Page 6 of 6
-Please contact Obaid Bhatty at (817) 897-5839 should you require additional information.
Sincerely, fe 3hr William J. Cahill, Jr.
By: M '
N Roger D. Walker Manager of Regulatory Affairs for Nuclear Production 08:tg .
Attachment cc: Mr. J. L. Milhoan, Region IV Mr. L. A. Yandell, Region IV Mr. T. A. Bergman, NRR Mr. S. K. West, NRR Resident inspectors, CPSES (2) s I
\
1
I 1
l Attachment 1 to TXX-93254 Page 1 of 5 l
l PRELIMINARY PLAN FOR CERTIFYING CPSES UNIT 1 THERMO-LAG CONDUITS (1) (2) (3) (4)
ACCEPTANCE SUPPORT COMMODITY TEST UPGRADE ,,
EVAL. AMPACITY 3/4" UNIT 2 YES/ UPGRADE YES UNIT 2 TEST COMPLETED I" UNIT 2 YES/ UPGRADE YES UNIT 2 TEST COMPLETED 1 1/2" UNIT 2 W/ CABLE RADIAL BENDS & YES UNIT 2 TEST FUNCTION EVAL. COUPLINGS ONLY 2" UNIT 2 W/ CABLE RADIAL BENDS & YES UNIT 2 TEST FUNCTION EVAL. COUPLINGS ONLY (RE-TEST SCHEME) 3" & UNIT 2 RADIAL BENDS YES UNIT 2 TEST LARGER ONLY
i i
l i'
Attachment 1 to TXX-93254 Page 2 of 5 l
l PRELIMINARY PLAN FOR CERTIFYING CPSES UNIT 1 THERMO-LAG (CONT'D)
FLEXIBLE CONDUITS & AIRDROPS (1) (2) (3) (4)
ACCEPTANCE SUPPORT COMMODITY TEST UPGRADE EVAL. AMPACITY 3/4" & UNIT 2 YES YES UNIT 2 TEST SMALLER 1" UNIT 2 YES YES UNIT 2 TEST 1 1/2" RE-TEST NO NO UNIT 2 TEST (SCHEME 11-2) 2" RE-TEST NO NO UNIT 2 TEST (SCHEME 11-2) 3" & UNIT 2 NO NO UNIT 2 TEST .
LARGER
Attachment I to TXX-93254 Page 3 of 5 PRELIMINARY PLAN FOR CERTIFYING CPSES UNIT 1 THERMO-LAG (CONT *D)
MISCELLANEOUS (1) (2) (3) (4)
ACCEPTANCE SUPPORT COMMODITY TEST UPGRADE EVAL, AMPACITY AIRDROPS RE-TEST YES YES UNIT 2 TEST AT CABLE (SCHEME 11-2) l TRAYS CONDUIT UNIT 2 YES YES UNIT 2 TEST LATERAL BENDS &
PULL BOXES CONDUIT RE-TEST YES YES UNIT 2 TEST RADIAL (SCHEME 13-2) l BENDS 1
JUNCTION UNIT 2 YES YES UNIT 2 TEST BOXES "B0X" RE-TEST YES YES UNIT 2 TEST CONFIG- (SCHEME 11-4)
URATIONS l
1 A
l l
Attachment 1 to'TXX-93254 Page 4 of 5 PRELIMINARY PLAN FOR CERTIFYING CPSES UNIT 1 THERMO-LAG (CONT'D)
CABLE' TRAYS (1) (2) (3) (4)
ACCEPTANCE SUPPORT COMMODITY TEST __, UPGRADE EVAL. AMPACITY 12" RE-TEST NO NO UNIT 2 TEST (SCHEME 13-2) 18" RE-TEST YES YES UNIT 2 TEST (SCHEME 11-5) 24" RE-TEST YES YES UNIT 2 TEST (SCHEME 11-5) 3 C UNIT 2 YES- YES UNIT 2 TEST 36" UNIT 2 YES YES UNIT 2 TEST TEES UNIT 2 YES YES UNIT 2 TEST FIRE STOPS UNIT 2 YES YES UNIT 2 TEST CABLES RE-TEST NO NO UNIT 2 TEST WRAPPED (SCHEME 15-2)
IN EXPOSED TRAY i
I i
~
Attachment 1 to TXX-93254 Page 5 of 5 LEGEND (1) ACCEP1ANCE TEST: This is either the existing CPSES test or the retest' which will be the basis for the acceptability of the Thermo-Lag coverage on the commodity.
(2) UPGRADE: This refers to whether physical work will need to be done on the existing Thermo-Lag configuration to make it acceptable. For commodities being retested, a "NO" entry assumes the test will be satisfactory to qualify the specific configuration without upgrade.
(3) SUPPORT EVALUATION: This pertains to taking into consideration the additional Thermo-Lag weights on the structural steel support qualification.
Special Note: 1-1/2 inch and larger flexihle conduits and air drops stow " upgrade" but no support evaluation because the' upgrade only involves reinforcement of "flexi-blanket" material coverage where it ,
overlaps onto the Thermo-Lag material.
Ini; refers to evaluating the affect of Thermo-Lag coverage (4) AMPACITY:
on the ampacity of the enveloped cables. This involves incorporating the results of the recently performed CPSES ampacity test results into the applicable cable ampacity evaluations and evaluating the effect of any upgrades.
B i
.I
')
--