Mid-Cycle Performance Review and Inspection Plan - Peach Bottom Atomic Power Station
ML052420701
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 08/30/2005
From: Brian Holian
Division Reactor Projects I
To: Crane C
Exelon Generation Co, Exelon Nuclear
Shanbaky M RGN-I/DRP/PB4/610-337-5209
References
Download: ML052420701 (6)


Text

August 30, 2005 Mr. Christopher M. Crane President and CNO Exelon Nuclear Exelon Generation Company, LLC 200 Exelon Way KSA 3-E Kennett Square, PA 19348

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

PEACH BOTTOM ATOMIC POWER STATION

Dear Mr. Crane:

On August 4, 2005, the NRC staff completed its performance review of Peach Bottom Atomic Power Station Units 2 and 3 for the first half of the calendar year 2005 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.

Plant performance at Peach Bottom Unit 2 for the most recent quarter was within the Regulatory Response column of the NRCs Action Matrix based on one White PI in the Initiating Events cornerstone. Peach Bottom Unit 2 had three scrams with a Loss of Normal Heat Removal within twelve calendar quarters causing this PI to change from Green to White. Inspection findings at Unit 2 were all classified as having very low safety significance (Green). We will perform reactor oversight process (ROP) baseline inspections and one supplemental inspection at Peach Bottom Unit 2 for the instance of a White PI as scheduled in the enclosed inspection plan.

Plant performance at Peach Bottom Unit 3 for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct ROP baseline inspections at Peach Bottom Unit 3.

The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through March 31, 2007. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.

The inspections in the last nine months of the inspection plan are tentative and may be revised

Mr. Christopher M. Crane 2 during the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Dr. Mohamed Shanbaky at 610-337-5209 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Brian E. Holian, Director Division of Reactor Projects Docket Nos.: 50-277, 50-278 License Nos.: DPR-44, DPR-56

Enclosure:

Peach Bottom Inspection/Activity Plan cc w/encl Chief Operating Officer, Exelon Generation Company, LLC Site Vice President, Peach Bottom Atomic Power Station Plant Manager, Peach Bottom Atomic Power Station Regulatory Assurance Manager - Peach Bottom Associate General Counsel, Exelon Generation Company J. Bradley Fewell, Assistant General Counsel, Exelon Nuclear Manager, Financial Control & Co-Owner Affairs Director, Nuclear Training Correspondence Control Desk Director, Bureau of Radiation Protection (PA)

R. McLean, Power Plant and Environmental Review Division (MD)

R. Fletcher, Maryland Department of Environment T. Snyder, Director, Air and Radiation Management Administration, Maryland Department of the Environment (SLO, MD)

Public Service Commission of Maryland, Engineering Division Board of Supervisors, Peach Bottom Township B. Ruth, Council Administrator of Harford County Council Mr. & Mrs. Dennis Hiebert, Peach Bottom Alliance TMI - Alert (TMIA)

J. Johnsrud, National Energy Committee, Sierra Club Mr. & Mrs. Kip Adams

Mr. Christopher M. Crane 3 Distribution w/encl: (via E-mail)

S. Collins, RA M. Dapas, DRA M. Shanbaky, DRP A. Burritt, DRP F. Bower, DRP - NRC Senior Resident Inspector D. Schroeder, DRP - NRC Resident Inspector S. Schmitt, DRP - NRC Resident OA D. Screnci, PAO N. Sheehan, PAO DRS Director DRS Deputy Director DRS Branch Chiefs RidsNrrDipmlipb@nrc.gov Institute of Nuclear Power Operations (INPO)

S. Lee, RI OEDO J. Clifford, NRR G. Wunder, PM, NRR T. Tate, PM, NRR (Backup)

Region I Docket Room (with concurrences)

ROPreports@nrc.gov (All IRs)

DOCUMENT NAME: S:\ROP-6 Mid-Cycle Review\2005 Mid-Cycle Letters\PB ROP 6 MC letterR1.wpd SISP Review Complete: MMS (Reviewers Initials)

After declaring this document An Official Agency Record it will/will not be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP /

NAME FBower MShanbaky DATE 08/24/05 08/30/05 OFFICIAL RECORD COPY

Page 1 of 3 Peach Bottom 08/30/2005 14:26:00 Inspection / Activity Plan Report 22 08/01/2005 - 03/31/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71121 - OCC RAD SAFETY 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 08/15/2005 08/19/2005 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 08/15/2005 08/19/2005 Baseline Inspections 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 08/15/2005 08/19/2005 Baseline Inspections 36801 - ORGANIZATION, MANAGMENT, COST CONTROLS 1 1 IP 36801 Organization, Management, And Cost Controls At Permanently Shutdown Reactors 07/06/2005 08/06/2005 Other Routine 37801 - SAFETY REVIEWS, DESIGN CHANGES, AND MODS 1 1 IP 37801 Safety Reviews, Design Changes, And Modifications At Permanently Shutdown Reactors 07/06/2005 08/06/2005 Other Routine 40801 - SELF ASSESSMENT,AUDIT, CORRECTIVE ACTION 1 1 IP 40801 Self-Assessment, Auditing, And Corrective Action At Permanently Shutdown Reactors 07/06/2005 08/06/2005 Other Routine 64704 - FIRE PROTECTION 1 1 IP 36801 Organization, Management, And Cost Controls At Permanently Shutdown Reactors 07/06/2005 08/06/2005 Other Routine 81700 - PHYSICAL SECURITY ASSESSMENT 1 1 IP 81700 Physical Security Program For Power Reactors 07/06/2005 08/06/2005 Other Routine 83750 - OCCUPATIONAL RADIATION EXPOSURE 1 1 IP 83750 Occupational Radiation Exposure 07/06/2005 08/06/2005 Other Routine 84750 - RADWSTE TREAT, EFFLUENT, ENVIRONMENTAL 1 1 IP 84750 Radioactive Waste Treatment, And Effluent And Environmental Monitoring 07/06/2005 08/06/2005 Other Routine 86750 - SOLID RADWST MANAGMENT 1 1 IP 86750 Solid Radioactive Waste Management And Transportation Of Radioactive Materials 07/06/2005 08/06/2005 Other Routine 71121 - OCC RAD SAFETY 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 08/08/2005 08/12/2005 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 08/08/2005 08/12/2005 Baseline Inspections 2, 3 IP 7112202 Radioactive Material Processing and Transportation 08/08/2005 08/12/2005 Baseline Inspections 7111111B - LSRO INSPECTION-PASS/FAIL RESULTS 2 2, 3 IP 7111111B Licensed Operator Requalification Program 11/15/2005 11/19/2005 Baseline Inspections 7111108G - INSERVICE INSPECTION - U3 1 3 IP 7111108G Inservice Inspection Activities - BWR 09/26/2005 09/30/2005 Baseline Inspections 71121 - OCC RAD SAFETY 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 09/26/2005 09/30/2005 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 09/26/2005 09/30/2005 Baseline Inspections 95001 - U2 SCRAM WITH LOSS OF HEAT SINK WHITE PI 1 2 IP 95001 Supplemental Inspection For One Or Two White Inputs In A Strategic Performance Area 11/07/2005 11/11/2005 Supplemental Program 71121 - OCC RAD SAFETY 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 11/14/2005 11/18/2005 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 3 Peach Bottom 08/30/2005 14:26:00 Inspection / Activity Plan Report 22 08/01/2005 - 03/31/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71121 - OCC RAD SAFETY 1 2, 3 IP 7112102 ALARA Planning and Controls 11/14/2005 11/18/2005 Baseline Inspections 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 11/14/2005 11/18/2005 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 11/14/2005 11/18/2005 Baseline Inspections TRI FIRE - TRIENNIAL FIRE PROTECTION INSPECTION 3 2, 3 IP 7111105T Fire Protection [Triennial] 01/23/2006 01/28/2006 Baseline Inspections 2, 3 IP 7111105T Fire Protection [Triennial] 02/06/2006 02/10/2006 Baseline Inspections 7111121 - SSD&PC 5 2, 3 IP 7111121 Safety System Design and Performance Capability 03/13/2006 03/17/2006 Baseline Inspections 2, 3 IP 7111121 Safety System Design and Performance Capability 03/27/2006 03/31/2006 Baseline Inspections 2, 3 IP 7111121 Safety System Design and Performance Capability 04/10/2006 04/14/2006 Baseline Inspections 2, 3 IP 7111121 Safety System Design and Performance Capability 04/17/2006 04/21/2006 Baseline Inspections 71121 - OCCUPATIONAL RAD PROT 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 04/17/2006 04/21/2006 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 04/17/2006 04/21/2006 Baseline Inspections 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 04/17/2006 04/21/2006 Baseline Inspections 7111401 - EXERCISE EVALUATION & EP PI VERIFICATION 5 2, 3 IP 7111401 Exercise Evaluation 04/24/2006 04/28/2006 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 04/24/2006 04/28/2006 Baseline Inspections 71122 - PUBLIC RAD PROT 1 2, 3 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 06/12/2006 06/16/2006 Baseline Inspections 7111112B - MAINTENANCE RULE 1 2, 3 IP 7111112B Maintenance Effectiveness 07/17/2006 07/21/2006 Baseline Inspections 7111107B - HEAT SINK 2 2, 3 IP 7111107B Heat Sink Performance 07/24/2006 07/28/2006 Baseline Inspections 71121 - OCC RAD SAF 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 08/07/2006 08/11/2006 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 08/07/2006 08/11/2006 Baseline Inspections 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 08/07/2006 08/11/2006 Baseline Inspections 7111108G - INSERVICE INSPECTION - UNIT 2 1 2 IP 7111108G Inservice Inspection Activities - BWR 09/18/2006 09/22/2006 Baseline Inspections 71121 - OCC RAD PROT 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 09/25/2006 09/29/2006 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 09/25/2006 09/29/2006 Baseline Inspections 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 09/25/2006 09/29/2006 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 3 of 3 Peach Bottom 08/30/2005 14:26:00 Inspection / Activity Plan Report 22 08/01/2005 - 03/31/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71121 - OCC RAD PROT 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 10/30/2006 11/03/2006 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 10/30/2006 11/03/2006 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 10/30/2006 11/03/2006 Baseline Inspections 2/5EXAM - OPERATOR LICENSING INITIAL EXAMS 3 2 U01612 PEACH BOTTOM, UNIT 2&3 INITIAL EXAM (2/07) 01/08/2007 01/12/2007 Not Applicable 2 U01612 PEACH BOTTOM, UNIT 2&3 INITIAL EXAM (2/07) 02/05/2007 02/09/2007 Not Applicable 7111111B - LO REQUAL PROGRAM INSPECTION 3 2, 3 IP 7111111B Licensed Operator Requalification Program 03/19/2007 03/30/2007 Baseline Inspections 71121 - OCC RAD SAFETY 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 02/12/2007 02/16/2007 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 02/12/2007 02/16/2007 Baseline Inspections 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 02/12/2007 02/16/2007 Baseline Inspections 71111117 - MODS AND 50.59 3 2, 3 IP 7111102 Evaluation of Changes, Tests, or Experiments 03/05/2007 03/09/2007 Baseline Inspections 2, 3 IP 7111117B Permanent Plant Modifications 03/05/2007 03/09/2007 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.