Similar Documents at Fermi |
---|
Category:Inspection Plan
MONTHYEARIR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 ML23237B4332023-08-25025 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI IR 05000341/20230052023-08-24024 August 2023 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2023005) ML23219A1792023-08-0707 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Fermi Power Plant, Unit 2 ML23118A3612023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 IR 05000341/20220062023-03-0101 March 2023 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2022006) IR 05000341/20220052022-08-25025 August 2022 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2022005) ML22096A2672022-04-0606 April 2022 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000341/2022010 IR 05000341/20210062022-03-0202 March 2022 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2021006) ML22027A3612022-01-26026 January 2022 U1: CY2022 Inspection Plan, Docket No. 05000016, License No. DPR-9 ML22004A2682022-01-0404 January 2022 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2022001 IR 05000341/20210052021-09-0101 September 2021 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2021005) ML21232A2122021-08-20020 August 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Fermi Power Plant, Unit 2 ML21078A4832021-03-19019 March 2021 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000341/2021011 IR 05000341/20200062021-03-0404 March 2021 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2020006) ML20303A2872020-10-29029 October 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000341/2021012 IR 05000341/20200052020-09-0101 September 2020 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2020005) IR 05000341/20190062020-03-0303 March 2020 Annual Assessment Letter for Fermi Nuclear Plant, Unit 2 (Report 05000341/2019006) ML19353D1082019-12-19019 December 2019 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2020001 IR 05000341/20190052019-08-28028 August 2019 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2019005) ML19114A0262019-04-23023 April 2019 Inspection Plan for Fermi Power Plant, Unit 2, for Design Bases Assurance Inspection (Team); Inspection Report 05000341/2019012 (DRS-N.Feliz-Adorno) IR 05000341/20180062019-03-0404 March 2019 Annual Assessment Letter for Fermi 2 (Report 05000341/2018006) ML18351A2652018-12-17017 December 2018 CY2019 Master Inspection Plan IR 05000341/20180052018-08-28028 August 2018 Updated Inspection Plan for Fermi 2 (Report 05000341/2018005) ML17354B0162017-12-20020 December 2017 U1: CY2018 Master Inspection Plan IR 05000341/20170052017-08-28028 August 2017 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2017005) ML17157B6702017-06-0505 June 2017 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000341/2017012 IR 05000341/20160062017-03-0101 March 2017 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2016006) ML16288A7402016-10-14014 October 2016 Information Request to Support Upcoming Temporary Instruction 191 Inspection at Fermi Power Plant, Unit 2 IR 05000341/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Fermi Power Plant (Report 05000341/2016005) ML15357A2382015-12-21021 December 2015 Master Inspection Plan - Calendar Year 2016 ML15279A6282015-10-0606 October 2015 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Fermi Power Plant IR 05000341/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2015005) IR 05000341/20140012015-03-0404 March 2015 Annual Assessment Letter for Fermi Power Plant, Unit 2, (Report 05000341/2014001) ML14353A2752014-12-18018 December 2014 Master Inspection Plan - Calendar Year 2015 ML14302A5792014-10-28028 October 2014 MOD 50.59 Request for Information ML14245A2342014-09-0202 September 2014 Mid-Cycle Assessment Letter for Fermi Power Plant, Unit 2 IR 05000341/20140072014-04-30030 April 2014 Fermi, Unit 2, Request for Information - Notification of NRC Triennial Fire Protection Baseline IR 05000341-14-007 ML14121A2712014-04-30030 April 2014 Request for Information - Notification of NRC Triennial Fire Protection Baseline IR 05000341-14-007 IR 05000341/20130012014-03-0404 March 2014 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2013001) ML13353A6092013-12-19019 December 2013 ISI Request for Information ML13246A2332013-09-0303 September 2013 2013 Fermi Power Plant Mid-Cycle Letter Combined IR 05000341/20120012013-03-0404 March 2013 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2012001) ML12248A3702012-09-0404 September 2012 Mid-Cycle Assessment Letter for Fermi Power Plant Unit 2 IR 05000341/20110072012-03-0505 March 2012 Annual Assessment Letter for Fermi Nuclear Power Plant, Unit 2 (Report 05000341/2011007) 2024-08-22
[Table view] Category:Letter
MONTHYEARIR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) ML23283A0222023-10-0909 October 2023 Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval ML23276B4542023-10-0505 October 2023 Cyber Security Inspection Report 05000341/2023402 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 September 2, 2014 Mr. Joseph Plona Senior Vice President and CNO DTE Energy Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR FERMI POWER PLANT, UNIT 2
Dear Mr. Plona:
On August 6, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of the Fermi Power Plant, Unit 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2013, through June 30, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined the performance at Fermi Power Plant, Unit 2, during the most recent quarter, was within the Regulatory Response Column (Column 2) of the NRCs Reactor Oversight Process (ROP) Action Matrix because of one or more greater-than-green Security Cornerstone inputs. In a letter dated June 9, 2014, we informed you that Fermi Unit 2 had transitioned from the Licensee Response Column (Column 1) to Column 2 as of the first quarter of 2014.
In addition to ROP baseline inspections, the NRC plans to conduct a supplemental inspection, in accordance with Inspection Procedure (IP) 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area, when you notify us of your readiness for the NRC to review the actions taken to address this finding.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year 2014 reflect this revision to Inspection Manual Chapter (IMC) 0310. Cross-cutting aspects identified in 2013 using the 2013 terminology were converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.
J. Plona The enclosed inspection plan lists the inspections scheduled through December 31, 2015.
Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. The inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.
The NRC also plans to conduct non-routine inspections and temporary instructions at your facility, including: Inspection Procedure (IP) 71111.17T, Evaluations of Changes, Tests and Experiments and Permanent Plant Modifications (Triennial); IP 71111.11(B),
Licensed Operator Requalification Program and Licensed Operator Performance (Biennial);
and IP 71152(B), Problem Identification and Resolution (Biennial).
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
J. Plona Please contact Mr. Michael Kunowski, Branch 5 Chief, Division of Reactor Projects, at 630-829-9618 with any questions you may have regarding this letter.
Sincerely,
/RA/
Anne T. Boland, Director Division of Reactor Projects Docket No. 50-341 License No. NPF-43
Enclosure:
Fermi Power Plant Inspection/Activity Plan cc w/encl: Distribution via LISTSERV
J. Plona Please contact Mr. Michael Kunowski, Branch 5 Chief, Division of Reactor Projects, at 630-829-9618 with any questions you may have regarding this letter.
Sincerely,
/RA/
Anne T. Boland, Director Division of Reactor Projects Docket No. 50-341 License No. NPF-43
Enclosure:
Fermi Power Plant Inspection/Activity Plan cc w/encl: Distribution via LISTSERV DISTRIBUTION w/encl:
Anthony Bowers RidsNrrDorlLpl3-1 Resource RidsNrrPMFermi2 Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Carmen Olteanu ROPassessment.Resource@nrc.gov DOCUMENT NAME: Fermi MOC Letter Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" =
Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME MKunowski:rj ABoland DATE 08/26/14 09/02/14 OFFICIAL RECORD COPY
Page 1 of 1 Fermi 08/22/2014 09:39:04 Inspection / Activity Plan Report 22 09/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site BI FP - FIRE PROTECTION INSPECTION& BAG TRIP 4 2 08/11/2014 09/12/2014 IP 7111105T Fire Protection [Triennial]
BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 2 11/17/2014 11/21/2014 IP 71124.02 Occupational ALARA Planning and Controls BI MODS - MODIFICATIONS 50;59 TRI INSPECTION 3 2 01/26/2015 02/13/2015 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications RENEWAL - LICENSE RENEWAL INSPECTION 71002 5 2 04/13/2015 05/01/2015 IP 71002 License Renewal Inspection BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 2 05/18/2015 05/22/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2 05/18/2015 05/22/2015 IP 71124.04 Occupational Dose Assessment BI EPR - EP ROUTINE INSPECTION / PI VERIFICATION 2 2 06/15/2015 06/19/2015 IP 7111402 Alert and Notification System Testing 2 06/15/2015 06/19/2015 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 2 06/15/2015 06/19/2015 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 2 06/15/2015 06/19/2015 IP 71151 Performance Indicator Verification BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 2 07/06/2015 07/10/2015 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 2 07/06/2015 07/10/2015 IP 71151-BI01 2 07/06/2015 07/10/2015 IP 71151-OR01 2 07/06/2015 07/10/2015 IP 71151-PR01 OL PREP - INIT EXAM/SEPT 2015 3 2 08/24/2015 08/28/2015 W90330 OL - INITIAL EXAM - 2015 FEB-MAR - FERMI 2 OL EXAM - OL EXAM/SEPT 2015 3 2 09/14/2015 09/18/2015 W90330 OL - INITIAL EXAM - 2015 FEB-MAR - FERMI 2 BI ISI - ISI INSPECTION 1 2 09/28/2015 10/28/2015 IP 7111108G Inservice Inspection Activities - BWR BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 2 10/19/2015 10/23/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls BI OLRQ - BIENNIAL REQUAL PROGRAM INSPECTION 2 2 11/16/2015 11/20/2015 IP 7111111B Licensed Operator Requalification Program PIR - BIENNIAL PIR INSPECTION 2 2 11/30/2015 12/18/2015 IP 71152B Problem Identification and Resolution This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.