UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 September 3, 2013 Mr. Joseph Plona Senior Vice President and Chief Nuclear Officer Detroit Edison Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR FERMI POWER PLANT UNIT 2 (REPORT 05000341/2013006)
Dear Mr. Plona:
On August 13, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of the Fermi Power Plant, Unit 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2012, through June 30, 2013. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined the performance at Fermi Power Plant, Unit 2, during the most recent quarter, ending June 30, 2013, was within the Regulatory Response Column (Column 2) of the NRCs Reactor Oversight Process (ROP) Action Matrix because of a White PI for Unplanned Scrams per 7000 Critical Hours. On June 25, 2013, the NRC completed a 95001 supplemental inspection at your facility to evaluate the corrective actions taken by members of your staff to address the performance indicator issue and prevent recurrence. The NRC determined you met the objectives of that inspection and documented the results in NRC Inspection Report and Assessment Follow-up Letter 05000341/2013009 (ADAMS Accession Number ML13198A509). In that letter, the NRC also updated its assessment of Fermi Power Plant, Unit 2, and informed you that Fermi Unit 2 transitioned back to the Licensee Response Column (Column 1) of the ROP Action Matrix, effective July 17, 2013.
Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The NRC also plans to conduct non-routine inspections and temporary instructions at your facility, including: Inspection Procedure (IP) 71111.05(T), Fire Protection (Triennial); IP 71111.07(T), Heat Sink Performance (Triennial); IP 71111.11(B), Licensed Operator Requalification Program and Licensed Operator Performance (Biennial); IP 71152(B),
Problem Identification and Resolution (Biennial); Temporary Instruction (TI) 2201/004, Inspection of Implementation of Interim Cyber Security Milestones 1-7; TI 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks; and TI 2515/186, Inspection of Procedures and Processes for Responding to Potential Aircraft Threats.
The enclosed inspection plan lists the inspections scheduled through December 31, 2014.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. The inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Mr. Michael Kunowski, Branch 5 Chief, Division of Reactor Projects, at 630-829-9618 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Kenneth G. OBrien, Acting Director Division of Reactor Projects Docket Nos. 50-341; 072-071 License No. NPF-43
Enclosure:
Fermi Power Plant Inspection/Activity Plan cc w/encl:
Distribution via ListServTM
The enclosed inspection plan lists the inspections scheduled through December 31, 2014.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. The inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Mr. Michael Kunowski, Branch 5 Chief, Division of Reactor Projects, at 630-829-9618 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Kenneth G. OBrien, Acting Director Division of Reactor Projects Docket Nos. 50-341; 072-071 License No. NPF-43
Enclosure:
Fermi Power Plant Inspection/Activity Plan cc w/encl:
Distribution via ListServTM DISTRIBUTION:
See next page DOCUMENT NAME: Fermi MOC Letter Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII-DRP E RIII-DRP RIII RIII NAME MKunowski:rj KOBrien DATE 08/28/13 08/28/13 OFFICIAL RECORD COPY
Letter to J. Plona from K. OBrien dated September 3, 2013
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR FERMI POWER PLANT UNIT 2 (REPORT 05000341/2013006)
DISTRIBUTION:
Vivian Campbell RidsNrrDorlLpl3-1 Resource RidsNrrPMFermi2 Resource RidsNrrDirsIrib Resource Cynthia Pederson Anne Boland Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPassessment.Resource@nrc.gov
Page 1 of 2 08/26/2013 07:07:14 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Fermi Inspection / Activity Plan 09/01/2013 - 12/31/2014 BI PI&R
- BIENNIAL PI&R TEAM INSPECTION 4
2 IP Problem Identification and Resolution 71152B 11/04/2013 11/22/2013 OL EXAM
- FERMI INIT EXAM - 09/2013 3
2 OL - INITIAL EXAM - 2013 AUG-SEPT - FERMI 2 W90287 09/09/2013 09/13/2013 TI 182
- TI 182 BURIED PIPING PHASE 2 2
2 IP Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 2515/182 09/16/2013 09/20/2013 ISFSI
- ISFSI INSPECTION 1
2 IP Review of 10 CFR 72.212(b) Evaluations at Operating Plants 60856.1 11/01/2013 12/31/2013 BI OLRQ
- BIENNIAL REQUAL PROGRAM INSPECTION 2
2 IP Licensed Operator Requalification Program 7111111B 11/04/2013 11/08/2013 BI HS
- TRIENNIAL HEAT SINK INSPECTION 2
2 IP Heat Sink Performance 7111107T 12/02/2013 12/06/2013 ISFSI
- ISFSI INSPECTION 1
2 IP On-Site Fabrication Of Components And Construction On An ISFSI 60853 12/01/2013 12/31/2013 ISFSI
- ISFSI INSPECTION 1
2 IP On-Site Fabrication Of Components And Construction On An ISFSI 60853 01/01/2014 01/31/2014 ISFSI
- ISFSI INSPECTION 1
2 IP Review of 10 CFR 72.212(b) Evaluations at Operating Plants 60856.1 01/01/2014 01/31/2014 BI EPX
- EP EXERCISE INSPECTION / PI VERIFICATION 2
2 IP Performance Indicator Verification 71151 04/28/2014 05/02/2014 BI ISI
- INSERVICE INSPECTION 1
2 IP Inservice Inspection Activities - BWR 7111108G 02/10/2014 03/17/2014 ISFSI
- ISFSI INSPECTION 1
2 IP Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants 60854.1 04/01/2014 05/31/2014 ISFSI
- ISFSI INSPECTION - SCHEDULE DEPENDENT 1
2 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 06/01/2014 08/31/2014 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
2 IP Radiation Monitoring Instrumentation 71124.05 05/12/2014 05/16/2014 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 07/14/2014 07/18/2014 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
2 IP Radiological Environmental Monitoring Program 71124.07 08/18/2014 08/22/2014 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 08/26/2013 07:07:14 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Fermi Inspection / Activity Plan 09/01/2013 - 12/31/2014 BI FP
- FIRE PROTECTION INSPECTION& BAG TRIP 3
2 IP Fire Protection [Triennial]
7111105T 08/11/2014 09/12/2014 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 09/22/2014 09/26/2014 2
IP Reactor Coolant System Activity 71151-BI01 09/22/2014 09/26/2014 2
IP Occupational Exposure Control Effectiveness 71151-OR01 09/22/2014 09/26/2014 2
IP RETS/ODCM Radiological Effluent 71151-PR01 09/22/2014 09/26/2014 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.