IR 05000440/2007001

From kanterella
Revision as of 05:27, 13 July 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
03/02/2007 Perry EOC Annual Assessment Letter (Report 05000440-07-001)
ML070610120
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 03/02/2007
From: Caldwell J
Region 3 Administrator
To: Pearce L
FirstEnergy Nuclear Operating Co
References
IR-07-001 IR-07-001
Download: ML070610120 (8)


Text

March 2, 2007 Mr. L. William Pearce Site Vice President

FirstEnergy Nuclear Operating Company

Perry Nuclear Power Plant

P. O. Box 97, 10 Center Road, A290

Perry, OH 44081-0097SUBJECT:ANNUAL ASSESSMENT LETTER - PERRY NUCLEAR POWER PLANT (REPORT 05000440/2007001)

Dear Mr. Pearce:

On February 13, 2007, the NRC staff completed its performance review of the Perry Nuclear Power Plant. Our technical staff reviewed performance indicators (PIs) for the most recent

quarter and inspection results for the period from January 1 through December 31, 2006. The

purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated as "Exempt from Public Disclosure in Accordance

with 10 CFR 2.390" and marked as "Official Use Only - Security-Related Information" will

include the physical protection review and resultant inspection plan.

Plant performance for the most recent quarter remained within the Multiple/Repetitive Degraded Cornerstone column of the Action Matrix. This is based on two longstanding White findings in

the Mitigating Systems cornerstone that have been open since 2003. FirstEnergy Nuclear

Operating Company (FENOC) was initially notified that Perry had entered the

Multiple/Repetitive Degraded Cornerstone column in our August 12, 2004, assessment followup

letter. Although Perry remained within the Multiple/Repetitive Degraded Cornerstone column for

the 2006 assessment period due, in large part, to these White findings, we recently concluded

that the two White findings could be closed. A detailed discussion of this decision, as well as

our decision to close Confirmatory Action Letter (CAL) 3-05-001 and transition Perry out of the

Multiple/Repetitive Degraded Cornerstone column, are contained in separate correspondence

dated March 2, 2007.

In addition, a second quarter 2006 Emergency Alternating Current Power System Mitigating System Performance Index (MSPI) that was orig inally reported to be Green, was identified by your staff in the fourth quarter of 2006 to be White. Consequently, you corrected the second

quarter 2006, MSPI from Green to White. This White MSPI subsequently returned to Green for

both the third and fourth quarters of 2006. Although this White MSPI occurred in the second

quarter of 2006, it is being discussed in this annual assessment letter since we had not had an

opportunity to discuss it previously. A supplemental inspection was conducted for this White

MSPI in accordance with Inspection Procedure 95001, "Inspection for One or Two White Inputs

in a Strategic Performance Area." That inspection concluded that you understood the root L. Pearce-2-causes and contributing causes of the issues, that you identified the extent of condition and extent of cause of the issues, and that your corrective actions were sufficient to address the

cause and to prevent recurrence of the issues.

In our mid-cycle assessment letter, dated September 2, 2006, we advised you of the continuation of substantive cross-cutting issues in the areas of problem identification and

resolution (PI&R) and human performance.

Regarding the area of PI&R, during this assessment period we have noted that the number and significance of PI&R related findings have declined measurably. These results have

been realized through the effective implementat ion of the CAL and Performance Improvement Initiative efforts in the Corrective Action Program area, as demonstrated by no new safety

significant (Greater-than-Green) findings and not more than three Green findings identified with

a common cross-cutting aspect of PI&R, i.e., the findings did not establish a theme. In addition, based upon the results of NRC inspections and our assessments of the results of your actions

to address the PI&R area, we have concluded that you have satisfactorily addressed the underlying issues that led to PI&R probl ems at Perry and have established programs and procedures to effect sustained performance impr ovements. Therefore, we have concluded that the substantive cross-cutting issue in the PI&R area is closed. We will monitor this area in the

future through our baseline inspection program inspection activities.

Regarding the area of human performance, during this assessment period we have also noted that the number and significance of human performance related findings have declined. These

results have been realized through the effective implementation of the CAL and Performance Improvement Initiative efforts in the hum an performance area, as demonstrated by no new safety significant findings and not more than three Green findings identified with a common

cross-cutting aspect, i.e., the findings did not establish a theme. In addition, based upon the

results of NRC inspections and our assessments of the results of your actions to address the

human performance area, we have concluded that you have satisfactorily addressed the underlying issues that led to human perform ance problems at Perry and have established programs and procedures to effect sustained per formance improvements. Therefore, we have concluded that the substantive cross-cutting issue in the human performance area is closed.

We will monitor this area in the future through our baseline inspection program inspection

activities.

In accordance with IMC 0305, "Operating Reac tor Assessment Program," your plant will be discussed at the upcoming Agency Action Review Meeting. We will notify you through

separate correspondence if any agency actions change as a result of this meeting.

This letter advises you of our planned inspection effort resulting from the Perry end-of-cycle review. The enclosed inspection plan details the inspections, less those related to physical

protection, through June 30, 2008. The inspection plan is provided to allow for the resolution of

any scheduling conflicts and personnel availability issues well in advance of inspector arrival

onsite. Routine resident inspection activities are not listed due to their ongoing and continuous

nature. The inspections in the last 9 months of the inspection plan are tentative and may be

revised at the mid-cycle review.

L. Pearce-3-In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public

Document Room or from the Publicly Ava ilable Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Eric Duncan at (630) 829-9628

with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/James L. Caldwell Regional Administrator Docket No. 50-440 License No. NPF-58 Enclosure:

Perry Inspection/ Activity Plan DISTRIBUTION See next page