|
---|
Category:Inspection Report
MONTHYEARIR 05000373/20240032024-11-0606 November 2024 County Station - Integrated Inspection Report 05000373/2024003 and 05000374/2024003 IR 05000373/20243012024-10-31031 October 2024 Initial License Examination Report 05000373/2024301 05000374/2024301 IR 05000373/20244042024-10-23023 October 2024 County Station – Security Baseline Inspection Report 05000373/2024404 and 05000374/2024404 IR 05000373/20244012024-09-27027 September 2024 County Station – Security Baseline Inspection Report 05000373/2024401 and 05000374/2024401 IR 05000373/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Lasalle County Station (Report 05000373/2024005; 05000374/2024005) IR 05000373/20244022024-08-28028 August 2024 County Station - Cyber Security Inspection Report 05000373/2024402 and 05000374/2024402 IR 05000373/20240022024-08-13013 August 2024 County Station - Integrated Inspection Report 05000373/2024002 and 05000374/2024002 IR 05000373/20244202024-08-0505 August 2024 County Station - Security Baseline Inspection Report 05000373 2024420 and 05000374 2024420 IR 05000373/20240102024-05-29029 May 2024 County Station - Commercial Grade Dedication Inspection Report 05000373/2024010 and 05000374/2024010 ML24131A1512024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 IR 05000373/20240012024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 IR 05000373/20244032024-05-0202 May 2024 Public Lasalle County Station - Security Baseline Inspection Report 05000373/2024403 and 05000374/2024403; NRC Investigation Report No. 3-2023-006 IR 05000373/20230062024-02-28028 February 2024 Annual Assessment Letter for Lasalle County Station, Units 1 and 2 (Report 05000373/2023006; 05000374/2023006) IR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 IR 05000373/20234022023-12-20020 December 2023 County Station - Security Baseline Inspection Report 05000373/2023402 and 05000374/2023402 IR 05000373/20230032023-11-0909 November 2023 County Station Integrated Inspection Report 05000373/2023003, 05000374/2023003, and 07200070/2023001 IR 05000373/20234012023-11-0707 November 2023 County Station Security Baseline Inspection Report 05000373/2023401 and 05000374/2023401 IR 05000374/20230102023-10-11011 October 2023 NRC Inspection Report 05000374/2023010 IR 05000373/20233012023-09-15015 September 2023 Errata to NRC Initial License Examination Report 05000373/2023301; 05000374/2023301 IR 05000373/20230052023-08-25025 August 2023 Updated Inspection Plan and Assessment Follow-Up Letter for LaSalle County Station (Report 05000373/2023005; 05000374/2023005) IR 05000373/20230022023-08-0101 August 2023 County Station - Integrated Inspection Report 05000373/2023002 and 05000374/2023002 IR 05000373/20230112023-06-26026 June 2023 County Station - Quadrennial Fire Protection Team Inspection Report 05000373/2023011 and 05000374/2023011 IR 05000373/20230012023-05-10010 May 2023 County Station - Integrated Inspection Report 05000373/2023001 and 05000374/2023001 IR 05000373/20220062023-03-0101 March 2023 Annual Assessment Letter for LaSalle County Station, Units 1 and 2 (Report 05000373/2022006 and 05000374/2022006) IR 05000373/20220042023-01-31031 January 2023 County Station - Integrated Inspection Report 05000373/2022004 and 05000374/2022004 IR 05000373/20224042022-12-21021 December 2022 County Station - Material Control and Accounting Program Inspection Report 05000373/2022404 and 05000374/2022404 IR 05000373/20225012022-12-0505 December 2022 County Station - Emergency Preparedness Biennial Exercise Inspection Report 05000373/2022501 and 05000374/2022501 IR 05000373/20224022022-11-17017 November 2022 County Station - Security Baseline Inspection Report 05000373/2022402 and 05000374/2022402 IR 05000373/20220032022-11-0101 November 2022 County Station - Integrated Inspection Report 05000373/2022003 and 05000374/2022003 IR 05000373/20220052022-08-22022 August 2022 Updated Inspection Plan for Lasalle County Station (Report 05000373/2022005; 05000374/2022005) IR 05000373/20220022022-08-10010 August 2022 County Station - Integrated Inspection Report 05000373/2022002 and 05000374/2022002 IR 05000373/20224012022-05-18018 May 2022 County Station - Security Baseline Inspection Report 05000373/2022401 and 05000374/2022401 IR 05000373/20220012022-04-26026 April 2022 County Station - Integrated Inspection Report 05000373/2022001 and 05000374/2022001 IR 05000373/20220112022-04-19019 April 2022 Information Request for an NRC Triennial Baseline Design Bases Assurance Inspection (Team) Inspection Report 05000373/2022011 05000374/20220 IR 05000373/20224032022-04-0707 April 2022 County Station Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000373/2022403 and 05000374/2022403 IR 05000373/20220102022-03-15015 March 2022 County Station License Renewal Phase 2 Report 05000373/2022010 IR 05000373/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000373/2021006 and 05000374/2021006) IR 05000373/20210042022-02-0707 February 2022 County Station Integrated Inspection Report 05000373/2021004 and 05000374/2021004 IR 05000373/20210132022-01-20020 January 2022 County Station Biennial Problem Identification and Resolution Inspection Report 05000373/2021013 and 05000374/2021013 IR 05000373/20214022021-12-15015 December 2021 County Station - Security Baseline Inspection Report 05000373/2021402 and 05000374/2021402 IR 05000373/20210032021-11-0808 November 2021 County Station Integrated Inspection Report 05000373/2021003; 05000374/2021003 and 07200070/2021001 IR 05000373/20210022021-11-0101 November 2021 County Station Integrated Inspection Report 05000373/2021002 and 05000374/2021002 IR 05000373/20210122021-10-28028 October 2021 County Station- 50.59 Team Inspection Report 05000373/2021012 and 05000374/2021012 IR 05000373/20210052021-09-0101 September 2021 Updated Inspection Plan for Lasalle County Station, Units 1 and 2; Report 05000373/2021005 and 05000374/2021005 IR 05000373/20210112021-08-23023 August 2021 County Station - Design Basis Assurance Inspection (Programs) Inspection Report 05000373/2021011 and 05000374/2021011 IR 05000373/20215012021-06-16016 June 2021 County Station - Emergency Preparedness Biennial Exercise Inspection Report 05000373/2021501 and 05000374/2021501 IR 05000373/20214012021-05-18018 May 2021 County Station - Security Baseline Inspection Report 05000373/2021401 and 05000374/2021401 IR 05000373/20210012021-05-0404 May 2021 Lssalle County Station - Integrated Inspection Report 05000373/2021001 and 05000374/2021001 IR 05000374/20210102021-04-0505 April 2021 County Station - Post-Approval Site Inspection for License Renewal (Phase I) Report 05000374/2021010 2024-09-27
[Table view] Category:Letter
MONTHYEARML24319A2552024-11-14014 November 2024 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000373/2025001 and 05000374/2025001 IR 05000373/20240032024-11-0606 November 2024 County Station - Integrated Inspection Report 05000373/2024003 and 05000374/2024003 ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000373/20243012024-10-31031 October 2024 Initial License Examination Report 05000373/2024301 05000374/2024301 IR 05000373/20244042024-10-23023 October 2024 County Station – Security Baseline Inspection Report 05000373/2024404 and 05000374/2024404 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000373/LER-2023-001-01, Air Circuit Breaker (Acb) Mechanically Operated Contacts (MOC) Switch Failed to Actuate2024-10-0909 October 2024 Air Circuit Breaker (Acb) Mechanically Operated Contacts (MOC) Switch Failed to Actuate ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000373/20244012024-09-27027 September 2024 County Station – Security Baseline Inspection Report 05000373/2024401 and 05000374/2024401 RS-24-094, Request to Recategorize an Indeterminate Exercise2024-09-20020 September 2024 Request to Recategorize an Indeterminate Exercise ML24263A2062024-09-19019 September 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for LaSalle County Station - Holtec MPC-68MCBS ML24260A0492024-09-16016 September 2024 Operator Licensing Examination Approval - Lasalle County Station, Unit 1 and 2, September 2024 RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000373/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Lasalle County Station (Report 05000373/2024005; 05000374/2024005) IR 05000373/20244022024-08-28028 August 2024 County Station - Cyber Security Inspection Report 05000373/2024402 and 05000374/2024402 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 05000373/LER-2024-004-01, Emergency Diesel Generator Auto-Start and Load Due to Loss of System Auxiliary Transformer2024-08-22022 August 2024 Emergency Diesel Generator Auto-Start and Load Due to Loss of System Auxiliary Transformer IR 05000373/20240022024-08-13013 August 2024 County Station - Integrated Inspection Report 05000373/2024002 and 05000374/2024002 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000373/20244202024-08-0505 August 2024 County Station - Security Baseline Inspection Report 05000373 2024420 and 05000374 2024420 05000373/LER-2024-003-01, Supplement to Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded2024-07-31031 July 2024 Supplement to Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification RS-24-064, Nuclear Radiological Emergency Plan Document Revisions2024-06-28028 June 2024 Nuclear Radiological Emergency Plan Document Revisions ML24178A2522024-06-27027 June 2024 County Station – Acknowledgement of Response to NRC Inspection Report 05000373/2024001 and 05000374/2024001 and Disputed Non-Cited Violation 05000373/LER-2024-004, Emergency Diesel Generator Auto-Start and Load Due to Loss of Station Auxiliary Transformer2024-06-19019 June 2024 Emergency Diesel Generator Auto-Start and Load Due to Loss of Station Auxiliary Transformer RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations 05000373/LER-2024-003, Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded2024-06-0606 June 2024 Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded IR 05000373/20240102024-05-29029 May 2024 County Station - Commercial Grade Dedication Inspection Report 05000373/2024010 and 05000374/2024010 ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes 05000373/LER-2024-002, Reactor Protection System Half Scram Due to Motor Generator Set Electric Power Monitoring Assembly Output Breaker Trip2024-05-17017 May 2024 Reactor Protection System Half Scram Due to Motor Generator Set Electric Power Monitoring Assembly Output Breaker Trip RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24131A1512024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 IR 05000373/20240012024-05-13013 May 2024 County Station - Integrated Report 05000373/2024001 and 05000374/2024001 RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000373/LER-2024-001, Core Operating Limits Report Thermal Limits Exceeded2024-04-26026 April 2024 Core Operating Limits Report Thermal Limits Exceeded ML24108A1562024-04-15015 April 2024 Updated Final Safety Analysis Report (Ufsar), Revision 26 and Fire Protection Report (Fpr), Revision 11 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24071A2122024-03-12012 March 2024 County Station - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000373/20230062024-02-28028 February 2024 Annual Assessment Letter for Lasalle County Station, Units 1 and 2 (Report 05000373/2023006; 05000374/2023006) RS-24-014, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-02-22022 February 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors ML24018A0682024-02-0909 February 2024 Issuance of Amendment Nos. 262 and 247 Revised Design Bases of Lower Downcomer Braces ML24024A1332024-01-24024 January 2024 Confirmation of Initial License Examination IR 05000373/20230042024-01-24024 January 2024 County Station - Integrated Inspection Report 05000373/2023004 and 05000374/2023004 IR 05000373/20230122024-01-18018 January 2024 County Station - Biennial Problem Identification and Resolution Inspection Report 05000373/2023012 and 05000374/2023012 2024-09-06
[Table view] |
Text
January 29, 2019
Mr. Bryan Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2-NRC INITIAL LICENSE EXAMINATION REPORT 05000373/2018301; 05000374/2018301
Dear Mr. Hanson:
On December 1 1, 201 8, the U.S. Nuclear Regulatory Commission (NRC) completed the initial operator licensing examination process for license applicants employed at your LaSalle County Station, Units 1 and 2.
The enclosed report documents the results of those examinations.
Preliminary observations noted during the examination process were discussed on November 16, 201 8, with Mr. W. Trafton and other members of your staff.
An exit meeting was conducted by telephone on December 20, 201 8, between Mr. W. Trafton of your staff, and Mr. C. Zoia, Chief Operator Licensing Examiner, to review the proposed final grading of the written examination for the license applicants.
The NRC examiners administered an initial license examination operating test during the weeks of November 5 , 2018, and November 12, 201 8. The written examination was administered by training department personnel on November 16, 201 8. Eight Senior Reactor Operator and six Reactor Operator applicants were administered license examinations.
The results of the examinations were finalized on January 3, 2019. One applicant failed one or more sections of the administered examination and was issued a proposed license denial letter. Thirteen applicants passed all sections of their respective examinations; seven were issued senior operator licenses and s ix were issued operator licenses.
The written examination and other related written examination documentation will be withheld from public disclosure for 24 months per your request. However, since one applicant received a proposed license denial letter because of a written examination grade that was less than 80.0 percent, the applicant was provided a copy of the administered written examination.
For examination security purposes, your staff should consider that written examination uncontrolled and exposed to the public.
B.Hanson-2-This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading
-rm/adams.html and at the NRC Public Documen t Room in accordance with Title 10 of the Code of Federal Regulations, Part 2.390, "Public Inspections, Exemptions, Requests for Withholding."
Sincerely,
/RA/ Randal Baker , Acting Chief Operations Branch Division of Reactor Safety Docket Nos. 50
-373; 50-374 License Nos. NPF
-11; NPF-18 Enclosures:
1.OL Examination Report 05000373/2018301;05000374/2018301 2.Simulation Facility Fidelity Reportcc: Distribution via LISTSERV M.Martin, Training Director,LaSalle County Station B.Hanson-3-Letter to Bryan from Randal Baker dated January 29, 2019.
SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2
-NRC INITIAL LICENSE EXAMINATION REPORT 05000373/2018301; 05000374/2018301 DISTRIBUTION: Aida Rivera-Varona RidsNrrDorlLpl3 RidsNrrPMLaSalle RidsNrrDirsIrib Resource Darrell Roberts John Giessner Jamnes Cameron Allan Barker DRPIII DRSIII Caroline Randiki Colleen Schmidt ADAMS Accession Number: ML19029B258 OFFICE RIII RIII NAME CZoia:jw RBaker DATE 01/28/19 01//19 OFFICIAL RECORD COPY
Enclosure 1 U.S. NUCLEAR REGULATORY COMMISSION
REGION III
Docket Nos:
50-373;05-374 License Nos:
NPF-11; NPF-18 Report No:
05000373/2016301; 05000374/2016301 Enterprise Identifier:
I-2018-003-0030 Licensee: Exelon Generation Company, LLC Facility: LaSalle County Station, Units 1 and 2 Location: Marseilles, IL Dates: November 5, 2018, through December 11, 201 8 Examiners: C. Zoia , Senior Operations Engineer
- Chief Examiner R. Baker , Senior Operations Engineer
- Examiner D. Reeser, Operations Engineer
- Examiner G. Roach, Senior Operations Engineer
- Examiner Approved by:
R. Baker, Acting Chief Operations Branch Division of Reactor Safety 2
SUMMARY
Examination
Report 05000 440/20 1 8 301; 11/0 5/201 8-1 2/1 1/201 8; Exelon Generation Company, LLC; LaSalle County Station; Units 1 and 2; Initial License Examination Report. The announced initial operator licensing examination was conducted by regional Nuclear Regulatory Commission examiners in accordance with the guidance of NUREG
-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 1 1. Examination Summary Thirteen of fourteen applicants passed all sections of their respective examinations. Seven applicant s were issued a senior operator licenses and six applicants were issued operator licenses. One applicant failed one or more sections of th e administered examination and was issued a proposed license denial. (Section 4OA5.1).
3
REPORT DETAILS
4OA5 Other Activities
.1 Initial Licensing Examinations
a. Examination Scope
The U.S. Nuclear Regulatory Commission (NRC)examiners and members of the facility licensee's staff used the guidance prescribed in NUREG
-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 1 1, to develop, validate, administer, and grade the written examination and operating test. The written examination outlines were prepared by the NRC staff and were transmitted to the facility licensee's staff.
Members of the facility licensee's staff prepared the operating test outlines and developed the written examination and operating test. The NRC examiners validated the proposed examination during the week of October 1, 201 8, with the assistance of members of the facility licensee's staff. During the onsite validation week, the examiners audited two license application s for accuracy. The NRC examiners, with the assistance of members of the facility licensee's staff, administered the operating test, consisting of job performance measures and dynamic simulator scenarios, during the period of November 5, 2018, through November 1 4 , 2 01 8. The facility licensee administered the written examination on November 16, 201 8.
b. Findings
- (1) Written Examination The NRC examiners determined that the written examination, as proposed by the licensee, was within the range of acceptability expected for a proposed examination.
Less than 20 percent of the proposed examination questions were determined to be unsatisfactory and required modification or replacement.
All changes made to the proposed written examination, were made in accordance with NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," and documented on Form ES 9, "Written Examination Review Worksheet
." On December 11, 201 8 , the licensee submitted documentation noting that there were no post-examination comment s for consideration by the NRC examiners when grading the written examination. The written examination outlines and worksheets, the proposed written examination (ADAMS Accession Number ML17164A413
), as well as the final as-administered examination and answer key (ADAMS Accession Number ML17164A409
), will be available
, in 24 months
, electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's Agencywide Document Access and Management System (ADAMS)
. The NRC examiners graded the written examination on December 4, 201 8, and conducted a review of each missed question to determine the accuracy and validity of the examination questions.
4
- (2) Operating Test The NRC examiners determined that the operating test, as originally proposed by the licensee, was within the range of acceptability expected for a proposed examination.
All changes made to the operating test were made in accordance with NUREG
-1021, "Operator Licensing Examination Standards for Power Reactors,"
and were documented o n Form ES-301-7, "Operating Test Review Worksheet."
The operating test outlines and worksheets, the proposed operating test and worksheets, as well as the final Form ES-301-7, and the final as
-administered operating test, will be available electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's ADAMS, on August 13, 2020.
(ADAMS Accession Numbers ML17164A411 , ML17164A413 , ML17164A408, and ML17164A409, respectively.)
On December 11, 2018, the licensee submitted documentation noting that there were no post-examination facility licensee comments, and no post
-examination applicant comments for consideration by the NRC examiners when grading the operating test.
The NRC examiners completed operating test grading on January 3, 201 9.
- (3) Examination Results Eight applicants at the Senior Reactor Operator level and six applicants at the Reactor Operator level were administered written examinations and operating tests.
Thirteen applicants passed all portions of their examinations and were issued their respective operating licenses on January 3, 2019
. One applicant failed one or more sections of the administered examination and was issued a proposed license denial.
.2 Examination Security
a. Scope
The NRC examiners reviewed and observed the licensee's implementation of examination security requirements during the examination validation and administration to assure compliance with Title 10 of the Code of Federal Regulations , Part 55.49, "Integrity of Examinations and Tests.
" The examiners used the guidelines provided in NUREG-1021, "Operator Licensing Examination Standards for Power Reactors
," to determine acceptability of the licensee
's examination security activities.
b. Findings
None
4OA6 Management Meetings
.1 Debrief The chief examiner presented the examination team's preliminary observations and findings on November 16, 2018
, to Mr. W. Trafton, Site Vice President, and other members of the LaSalle County Station staff.
.2 Exit Meetin
g The chief examiner conducted an exit meeting on December 20, 2018, with Mr. W. Trafton, Site Vice President, and other members of the LaSalle County Station , Unit s 1 and 2, staff by telephone. The NRC
's final disposition of the written exam grading was disclosed and discussed with during the telephone discussion. The examiners asked the licensee whether any of the material used to develop or administer the examination should be considered proprietary. No proprietary or sensitive information was identified during the examination or debrief/exit meetings.
ATTACHMENT:
SUPPLEMENTAL INFORMATION
SUPPLEMENTAL INFORMATION KEY POINTS OF CONTAC
T Licensee
- J. Van Fleet, Operations Director
- M. Martin, Training Director
- D. Fuson, Operations Training Manager
- J. Messina, Site Exam Representative
- C. Betken, Exam Author
- T. Messner, Exam Author
- D. Murray, Regulatory Assurance Manager
U.S. Nuclear Regulatory
Commission
- W. Schaup, Senior Resident Inspector
- J. Havertape, Resident Inspector
- C. Zoia, Chief Examiner
- R. Baker, Examiner
- D. Reeser, Examiner
- G. Roach, Examiner
ITEMS OPENED, CLOSED, AND DISCUSSED
Opened, Closed, and Discussed
None LIST OF ACRONYMS USE
D ADAMS Agencywide Document Access and Management System
NRC U.S. Nuclear Regulatory Commission
SIMULATION FACILITY
FIDELITY REPORT
Facility Licensee:
LaSalle County Station, Units 1 and 2
Facility Docket Nos:
50-373; 50-374 Operating Tests Administered:
November 5, 2018, through November 14, 2018 The following documents observations made by the U.S. Nuclear Regulatory
Commission examination team during the initial operator license examination. These observations do
not constitute audit or inspection findings and are not, without further verification and review, indicative of non
-compliance with Title 10 of the Code of Federal Regulations
, Part 55.45(b). These observations do not affect U.S. Nuclear Regulatory
Commission certification or approval of the simulation facility other than to provide information which may be used in future evaluations. No licensee action is required in response to these observations.
During the conduct of the simulator portion of the operating tests, the following items were
observed: ITEM DESCRIPTION
SWR 0134795
During one scenario, a
spurious annunciator alarmed causing a minor disruption. The alarm was
quickly addressed, and no further incidents occurred.