MONTHYEARML14077A3712014-03-18018 March 2014 Notice of Public Meeting with Arizona Public Service Company to Discuss Extension of Authorized Repair to Palo Verde, Unit 3, Bottom-Mounted Instrumentation to End of Unit 3 Operating Life Project stage: Meeting ML14098A1832014-04-0202 April 2014 4/2/2014 Meeting Slide for Bottom-Mounted Instrument (Bmi) Relief Request 52 Pre-Submittal Meeting Project stage: Meeting ML14099A4692014-04-21021 April 2014 Summary of 4/2/2014 Pre-Application Meeting with Arizona Public Service Company to Discuss Extension of Authorized Repair to Palo Verde, Unit 3, Bottom Mounted Instrumentation to End-of-Unit Life Project stage: Meeting 2014-04-02
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24282A9072024-10-17017 October 2024 Summary of June 28, 2024, Pre-submittal Meeting with Arizona Public Service Company to Discuss a Planned License Amendment Request Changes to Technical Specifications 3.5.1 and 3.5.2 ML24271A3052024-10-0404 October 2024 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss a LAR to Modify the TS 5.6.5 List of Allowable Methodologies for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML24269A1542024-09-27027 September 2024 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Proposed Life-of-Plant Alternatives for a Pressurizer Thermowell Nozzle Repair at Palo Verde Nuclear Generating Station, Unit 1 ML23258A1402023-09-27027 September 2023 Summary of August 31, 2023, Presubmittal Meeting with Arizona Public Service Company to Discuss Planned Submittal of License Renewal Commitment Regarding Alloy 600 Management Program Plan at Palo Verde Station, Units 1, 2, & 3 ML23150A1982023-06-0505 June 2023 Summary of 5/25/2023, Presubmittal Meeting with Arizona Public Service Company to Discuss ASME, Section XI Appendix L Alternate Approach to Pressurizer Surge Line Inspections at Palo Verde, Units 1, 2, and 3 ML23097A0692023-04-14014 April 2023 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Proposed License Amendment Request Regarding Containment Temperature and Safety Injection Tank Volume at Palo Verde Units 1, 2, and 3 ML23095A0932023-04-0606 April 2023 Summary of April 4, 2023, Presubmittal Meeting with Arizona Public Service Company to Discuss Proposed License Amendment Request to Adopt TSTF-266 at Palo Verde Nuclear Generating Station ML23072A0312023-03-14014 March 2023 March 1, 2023, Summary of Meeting with Arizona Public Service Company to Discuss Proposed 10 CFR 20.1703 and 20.1705 Requests to Use Supplied Air Suits at Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML22314A2742022-11-15015 November 2022 October 27, 2022 Meeting with Arizona Public Service Company to Discuss Proposed LAR to Adopt TSTF-107, Revision 4, Separate Control Rods That Are Untrippable Versus Inoperable, for Palo Verde, Units 1, 2, & 3 ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22098A0322022-04-20020 April 2022 Summary of April 6, 2022, Public Meeting with Arizona Public Service Company to Discuss Upcoming License Amendment Request to Adopt Technical Specification Task Force Traveler TSTF-487 (EPID L-LRM-0025) ML21347A9522021-12-14014 December 2021 Summary of December 9, 2021, Public Meeting with Arizona Public Service Company to Discuss Upcoming LAR to Adopt TSTF-567, Add Containment TS to Address GSI-191 Issues for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML21333A0022021-12-0202 December 2021 Summary of Pre-Submittal Meeting with Arizona Public Service Company RIPE Exemption for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML21278A5462021-10-13013 October 2021 Summary of Meeting with Arizona Public Service Company to Discuss Relief Request No. 68 for Certain ASME Code Piping for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML21245A4152021-09-0808 September 2021 Summary of Public Meeting with Arizona Public Service Company to Discuss Upcoming Exemption to Eliminate Diverse Auxiliary Feedwater Actuation System Using Risk-Informed Process for Evaluations for Palo Verde Nuclear Generating Station ML21168A2632021-06-24024 June 2021 Summary of June 16, 2021, Public Meeting with Arizona Public Service Company to Discuss Upcoming Relief Request No. 67, Extension of Containment Tendon Inservice Testing from 10 Years to 20 Years for Palo Verde Nuclear Generating Station, U ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21134A0002021-05-18018 May 2021 Summary of Public Meeting with Arizona Public Service Company to Discuss Upcoming Order License Transfer from Pnm to Salt River Project Agriculture Improvement and Power District for Palo Verde, Units 1 and 2 and the ISFSI ML21061A3202021-03-10010 March 2021 Summary of February 25, 2021, Public Meeting with Nuclear Energy Institute to Further Discuss the Inclusion of TSTF-425 Under the Risk-Informed Process for Evaluations Initiative ML21055A8502021-02-24024 February 2021 Public Meeting Summary ML21011A2742021-01-26026 January 2021 Summary of January 6, 2021, Public Meeting with Arizona Public Service Company to Discuss Upcoming LAR Regarding Containment Integrated Leak Rate Test Permanent Extension to 15 Years for Palo Verde Nuclear Generating Station, Units 1, 2, an ML20189A2832020-07-0707 July 2020 Summary of Region IV Annual Assessment Public Meeting ML19219A6122019-08-13013 August 2019 Summary of July 11, 2019, Teleconference with APS to Discuss Proposed License Amendment Request to Revise the Emergency Plan for Palo Verde Nuclear Generating Station ML17353A1902017-12-29029 December 2017 Summary of 12/12/2017, Public Meeting with Arizona Public Service Company, on Proposed Relief Request 50 for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML17003A0352017-01-0404 January 2017 Summary of Pre-Application Meeting with Arizona Public Service to Discuss a Proposed Second Emergency License Amendment Request to Revise Technical Specification 3.8.1, AC (Alternating Current) Sources - Operating, for Palo Verde Nuclear ML16088A0602016-04-15015 April 2016 3/24/16 Summary of Pre-application Meeting with Arizona Public Service Company to Discuss Next Generation Fuel License Amendment Request for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 ML16028A3942016-02-12012 February 2016 Summary of Prelicensing Meeting with Arizona Public Service Company to Discuss Next Generation Fuel License Amendment Request for Palo Verde, Units 1, 2, and 3 ML16011A0582016-01-21021 January 2016 Summary of Public Meeting Via Conference Call with Arizona Public Service Company Regarding Ongoing Resolution of Generic Letter 2004-02 for Palo Verde, Units 1, 2, and 3 ML15306A2352015-11-13013 November 2015 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Degraded Voltage Relay Setpoints License Amendment Request for Palo Verde, Units 1, 2, and 3 ML15286A0282015-10-23023 October 2015 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Revised Methodology for Spent Fuel Pool Criticality Analysis and Associated Technical Specification Changes for Palo Verde, Units 1, 2, and 3 (CAC MF6600-MF6602) ML15268A1312015-10-0505 October 2015 Summary of Public Meeting Via Conference Call with Arizona Public Service Company Regarding Ongoing Resolution of Generic Letter 2004-02 for Palo Verde, Units 1, 2, and 3 ML15239B3222015-09-0909 September 2015 Summary of Public Meeting Via Conference Call with Arizona Public Service Company Regarding Ongoing Resolution of Generic Letter 2004-02 for Palo Verde, Units 1, 2, and 3 ML15244B0772015-09-0101 September 2015 Summary of Annual Assessment Meeting with Arizona Public Service Regarding Palo Verde Nuclear Generating Station 2014 Performance ML15173A2892015-06-30030 June 2015 June 9, 2015, Summary of Category 1 Public Meeting with Arizona Public Service Company to Discuss Palo Verde Nuclear Generating Station Seismic Hazard Reevaluation Associated with Implementation of Japan Lessons-Learned NTTF Recommendation ML15140A3142015-06-16016 June 2015 Summary of Preapplication Meeting with Arizona Public Service Company to Discuss Revised Methodology for Spent Fuel Pool Criticality Analysis and Associated Technical Specification Changes for Palo Verde, Units 1, 2, and 3 (TAC MF5843-MF584 ML15117A0422015-04-29029 April 2015 Memorandum to File Summarizing 4/24/15 Telephone Conference Granting Verbal Relief for Relief Request 53, Request for Approval of an Alternative to ASME Code, Section XI, Requirements for Flaw Removal ML15078A0052015-03-25025 March 2015 Summary of 2/18/2015 Preapplication Meeting with Arizona Public Service Company to Discuss License Amendment Request for Palo Verde, Units 1, 2, and 3 on TSTF-505, Risk-Informed Technical Specifications ML14150A1772014-06-0202 June 2014 Summary of Conference Call Regarding Spring 2014 Steam Generator Tube Inspections ML14136A0582014-06-0202 June 2014 5/14/2014 Summary of Meeting with Arizona Public Service Company to Discuss Flooding Hazard Reevaluation Extension Request for Palo Verde, Units 1, 2, and 3; Near-Term Task Force Recommendation 2.1 ML14099A4692014-04-21021 April 2014 Summary of 4/2/2014 Pre-Application Meeting with Arizona Public Service Company to Discuss Extension of Authorized Repair to Palo Verde, Unit 3, Bottom Mounted Instrumentation to End-of-Unit Life ML13333B5742013-12-0505 December 2013 Summary of 11/1/2013 Conference Call Regarding the Fall 2013 Steam Generator Tube Inspections ML13330A5732013-12-0505 December 2013 Verbal Authorization of Relief Request 51, Alternative to ASME Code for Flaw Removal, Reactor Vessel Bottom-mounted Instrumentation Nozzle, Third 10-Year ISI Interval ML13312A5402013-11-18018 November 2013 11/5/2013 Summary of Preapplication Meeting to Discuss License Amendment Request to Incorporate Nuclear Energy Institute NEI-11-04 Quality Assurance Program at Palo Verde, Units 1, 2, and 3 ML13311B1832013-11-18018 November 2013 Summary of Meeting with Arizona Public Service Company to Discuss Non-destructive Examination Efforts, Repairs, and Progress on Root Cause Identified During Inspection of Bottom-Mounted Instrumentation Nozzles at Palo Verde, Unit 3 ML13234A0052013-08-26026 August 2013 8/21/2013 - Summary of Preapplication Meeting with Arizona Public Service Company Low Pressure Safety Injection Pump Single Failure Analysis for Minimum Required Refueling Water Tank Transfer Volume at Palo Verde, Units 1, 2, and 3 ML13203A0852013-08-0505 August 2013 Summary of Preapplication Meeting with Arizona Public Service Company to Discuss License Amendment Request Related to the Startup Test Activity Reduction Program at Palo Verde, Units 1, 2, and 3 (TAC Nos. MF1932-MF1934) ML13161A2522013-06-26026 June 2013 Summary of Conference Call with Arizona Public Service Company to Discuss Draft Requests for Additional Information for Palo Verde, Units 1, 2, and 3 NRC Order Number EA-12-049 Related to Mitigation Strategies (TAC Nos. MF0829-MF0831) ML13154A4502013-06-26026 June 2013 Summary of Meeting Via Conference Call with Arizona Public Service Co. to Discuss Palo Verde Request to Revise Technical Specifications; Eliminate Use of the Term Core Alteration Consistent w/TSTF-471 and NUREG-1432, Rev 3 (TAC ME8160-ME816 ML13154A4322013-06-13013 June 2013 5/30/13 Summary of Conference Call with Arizona Public Service Company to Discuss Draft Requests for Additional Information for Palo Verde, Units 1, 2, and 3 NRC Order Number EA-12-049 Related to Mitigation Strategies (TAC Nos. MF0829-MF083 ML12244A2152012-09-20020 September 2012 8/30/2012 Summary of Meeting with Arizona Public Service Company to Discuss Relief Request 48 - Alternative to ASME Section III, Phased Array Ultrasonic Examination Techniques for Palo Verde, Units 1, 2, and 3 2024-09-27
[Table view] |
Text
LICENSEE:
Arizona Public Service Company FACILITY:
Palo Verde Nuclear Generating
- Station, Unit 3
SUBJECT:
SUMMARY OF APRIL 2, 2014, PREAPPLICATION PUBLIC MEETING WITH ARIZONA PUBLIC SERVICE COMPANY REGARDING RELIEF REQUEST 52 TO EXTEND AUTHORIZED REPAIR TO PALO VERDE NUCLEAR GENERATING
- STATION, UNIT 3, BOTTOM-MOUNTED INSTRUMENT FOR REMAINDER OF LICENSED OPERATING LIFE (TAC NO. MF3520) On April 2, 2014, a public meeting was held between the U.S. Nuclear Regulatory Commission (NRC), and representatives of Arizona Public Service Company (APS, the licensee),
at NRC Headquarters, Rockville, Maryland.
The purpose of the meeting was for APS to discuss its forthcoming Relief Request 52, which will seek authorization to operate Palo Verde Nuclear Generating Station (PVNGS),
Unit 3, with the bottom-mounted instrument (BMI) nozzle penetration 3 half-nozzle repair for the duration of the facility operating license.
In November 2013, the NRC granted verbal authorization to APS for Relief Request 51, the proposed alternative half-nozzle repair and flaw evaluation of BMI nozzle penetration 3, for the duration of the current fuel operating cycle (U3C18).
The meeting notice and agenda are publicly available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML 14077A371.
The licensee's meeting slide presentation is available at ADAMS Accession No. ML 14098A 183. A list of attendees is provided in the Enclosure.
The licensee's presentation began with an overview of the BMI nozzle 3 flaw discovery and repairs.
The licensee then described the boat sample location and collection, which attempted to capture the reactor coolant system (RCS) leak entrance point, weld defect, known axial cracks, and unaffected weld and nozzle material for analysis.
During the destructive evaluation of the boat sample, the licensee noted a void inside the sample, which appeared to be the source of one solidification crack and multiple primary water stress-corrosion cracking (PWSCC)-indicative cracks. However, the through-wall crack from the RCS pressure boundary was not found in the boat sample. The licensee continued the presentation with an overview of the methods and analysis used to evaluate the remnant flaw propagation and acceptability for the duration of the Unit 3 facility operating license.
Analyses presented included stress and fatigue analysis, welding residual stress analysis, remnant flaw growth analysis, remnant nozzle structural integrity and dynamic analysis, a corrosion assessment, and a loose parts evaluation.
Additionally, the licensee discussed its schedule for submitting Relief Request 52 to the NRC staff for review. The NRC staff asked the licensee numerous questions during the presentation regarding analysis
- methods, bases for calculations, model types used, and proposed schedule for submitting the request.
The NRC suggested that APS consider the following as it develops the Relief Request 52 submittal:
- Provide sufficient detail and information regarding the plant-specific models, analyses, and data used to support extended operation with the remnant flaw and half-nozzle repair.
- Include identification of excitation frequencies and natural frequencies for the remnant nozzle (slide 23 of the licensee's presentation).
During the meeting, the licensee noted that the detailed metallurgy report regarding the cracking in BMI nozzle 3 was expected to be shared with the NRC Resident Inspectors.
The NRC staff noted that information contained in the metallurgy report may be of use during the review of Relief Request 52. Subsequent to the meeting, the NRC Resident Inspectors at PVNGS confirmed that they have received the referenced metallurgy report. One Public Meeting Feedback Form was received for this meeting.
Please direct any inquiries to me at 301-415-1530 or at Jennivine.Rankin@nrc.gov.
Docket No. 50-530
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv
(\<cVY\ GLA__, Yennie K. Rankin, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation LIST OF ATTENDEES APRIL 2, 2014. PUBLIC MEETING WITH ARIZONA PUBLIC SERVICE COMPANY REGARDING RELIEF REQUEST 52 TO EXTEND REPAIR TO PALO VERDE NUCLEAR GENERATING
- STATION, UNIT 3, BOTTOM-MOUNTED INSTRUMENT FOR REMAINDER OF LICENSED OPERATING LIFE NAME Delbert Elkinton Tom Weber Ed Fernandez Ken House Michael Hooshmand Doug Hansen Gene Montgomery Winston Borrero Mike DiLorenzo*
Robert Roehler*
Mark McGhee
- Paul Hom* Douglas Berg* Matthew Glenn* Rex Meeden* Carl Stephenson*
David Kelsey* Doug Killian Ashok Nana Sarah Davidsaver*
Steve Fyfitch*
DOCKET NO. 50-530 ORGANIZATION Arizona Public Service Company (APS) APS APS APS APS APS APS APS APS APS APS APS APS APS APS APS APS AREVA AREVA AREVA AREVA MPR Associates, Inc. JNES Dave Rackiewicz*
Kensaku Arai Robert Hardies Jay Collins U.S. Nuclear Regulatory Commission (NRC) NRC Andrea George Jennie Rankin Carol Nove* Mike Markley Stacey Rosenberg Simon Sheng Ganesh Cheruvenki Steven Vitto David Alley
- participated via telephone NRC NRC NRC NRC NRC NRC NRC NRC NRC Enclosure submitting the request.
The NRC suggested that APS consider the following as it develops the Relief Request 52 submittal:
- Provide sufficient detail and information regarding the plant-specific models, analyses, and data used to support extended operation with the remnant flaw and half-nozzle repair.
- Include identification of excitation frequencies and natural frequencies for the remnant nozzle (slide 23 of the licensee's presentation).
During the meeting, the licensee noted that the detailed metallurgy report regarding the cracking in BMI nozzle 3 was expected to be shared with the NRC Resident Inspectors.
The NRC staff noted that information contained in the metallurgy report may be of use during the review of Relief Request 52. Subsequent to the meeting, the NRC Resident Inspectors at PVNGS confirmed that they have received the referenced metallurgy report. One Public Meeting Feedback Form was received for this meeting.
Please direct any inquiries to me at 301-415-1530 or at Jennivine.Rankin@nrc.gov.
Docket No. 50-530
Enclosure:
List of Attendees IRA/ Jennie K. Rankin, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL4-1 Reading RidsAcrsAcnw_MaiiCTR Resource RidsNrrDeEvib Resource RidsNrrDeEpnb Resource RidsNrrDorl Resource RidsNrrDorllpl4-1 Resource RidsNrrLAJBurkhardt Resource RidsNrrPMPaloVerde Resource RidsOpaMail Resource RidsRgn4MaiiCenter Resource JNick, EDO RIV NTaylor, RIV RHardies, NRR/DE SRosenberg, NRR/DE/EVIB
- JCollins, NRR/DE/EPNB SSheng, NRR/DE/EVIB GCheruvenki, NRR/DE/EVIB ADAMS Accession No.: ML14099A469 OFFICE NRRIDORULPL4-1/PM N RR!DORULPL4-1/PM NRR!DORU
/LPL4-1/LA NRRIDE/EPNB/BC NAME A George JRankin JBurkhardt SRosenberg DATE 4/15/14 4/15/14 4/15/14 4/18/14 OFFICE NRR!DORULPL4-1/BC NRRIDORULPL4-1/PM NAME MMarkley JRankin DATE 4/21/14 4/21/14 OFFICIAL RECORD COPY