ML23097A069

From kanterella
Jump to navigation Jump to search

Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Proposed License Amendment Request Regarding Containment Temperature and Safety Injection Tank Volume at Palo Verde Units 1, 2, and 3
ML23097A069
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 04/14/2023
From: Dennis Galvin
NRC/NRR/DORL/LPL4
To:
Arizona Public Service Co
References
EPID L-2023-LRM-0016
Download: ML23097A069 (1)


Text

April 14, 2023 LICENSEE: Arizona Public Service Company FACILITY: Palo Verde Nuclear Generating Station, Units 1, 2, and 3

SUBJECT:

SUMMARY

OF APRIL 5, 2023, PRESUBMITTAL MEETING WITH ARIZONA PUBLIC SERVICE COMPANY TO DISCUSS PROPOSED LICENSE AMENDMENT REQUEST REGARDING CONTAINMENT TEMPERATURE AND SAFETY INJECTION TANK VOLUME AT PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 (EPID L-2023-LRM-0016)

On April 5, 2023, an Observation public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and Arizona Public Service Company (the licensee) via webinar. The purpose of this meeting was to discuss the licensees proposed license amendment request (LAR) regarding containment temperature in Technical Specification (TS) 3.6.5 and safety injection tank volume in TSs 3.5.1 and 3.5.2 at Palo Verde Nuclear Generating Station, Units 1, 2, and 3. The meeting notice and agenda, dated March 21, 2023, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML23093A0651. A list of attendees is provided in the enclosure.

The licensee presented informational slides at the meeting, which are available in ADAMS at Accession No. ML23093A025. The licensees presentation included a description of the proposed changes, proposed TSs and TS bases changes, precedents, and a submittal timeline.

The NRC staff discussed several observations regarding information that should be considered for inclusion in the LAR as follows:

Description of how instrument uncertainties for containment temperature measurement are accounted for.

A summary of the calculation of the total loop uncertainty (or total instrument uncertainty regarding Slides 4, 10, and 11 of the presentation).

Indication that the proposed changes do not impact any assumptions in the accident analyses.

Description of why the proposed change is departing from the Standard TSs, especially with regard to the use of narrow range.

In addition, the NRC staff did not object to the submission of one LAR for proposed changes to both the containment temperature and safety injection tank volume TSs.

1 The meeting notice and agenda are dated March 21, 2023. However, when the presentation slides were added to the NRC public meeting notification system, the notice was updated and the ADAMS document date changed to April 3, 2023.

No members of the public called into the meeting. No regulatory decisions or commitments were made at the meeting. Additionally, the NRC staff did not receive Public Meeting Feedback forms.

Please direct any inquiries to me at 301-415-1564 or by email at Siva.Lingam@nrc.gov.

/RA by Dennis Galvin for/

Siva P. Lingam, Project Manager Plant Licensing Branch IV Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-528, STN 50-529, and STN 50-530

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES APRIL 4, 2023, PRESUBMITTAL WEBINAR REGARDING A PLANNED LICENSE AMENDMENT REQUEST REGARDING CONTAINMENT TEMPERATURE AND SAFETY INJECTION TANK VOLUME ARIZONA PUBLIC SERVICE COMPANY PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 U.S. Nuclear Regulatory Commission Dennis Galvin Matthew Hamm Siva Lingam Ahsan Sallman Hang Vu Hanry Wagage Arizona Public Service Company Nawaporn Aaronscooke Jill Anderson Matthew Cox Nicholas Doyle Justin Gunther Robert Hicks Sarah Kane David Medek Carl Stephenson Asif Tanvir Enclosure

ML23097A068 (Package)

ML23093A065 (Meeting Notice)

ML23093A025 (Public Meeting Slides)

ML23097A069 (Meeting Summary) *by email OFFICE NRR/DORL/LPL4/PM* NRR/DORL/LPL4/LA* NRR/DEX/EICB/BC*

NAME DGalvin PBlechman MWaters DATE 04/10/2023 04/10/2023 04/06/2023 OFFICE NRR/DSS/STSB/BC* NRR/DSS/SCPB/BC* NRR/DSS/SNSB/BC(A)*

NAME VCusumano BWittick DWoodyatt DATE 04/13/2023 04/06/2023 04/10/2023 OFFICE NRR/DORL/LPL4/BC* NRR/DORL/LPL4/PM*

NAME JDixon-Herrity SLingam (DGalvin for)

DATE 04/14/2023 04/14/2023