June 24, 2021 LICENSEE: Arizona Public Service Company FACILITY: Palo Verde Nuclear Generating Station, Units 1 and 3

SUBJECT:

SUMMARY

OF JUNE 16, 2021, PUBLIC MEETING WITH ARIZONA PUBLIC SERVICE COMPANY TO DISCUSS UPCOMING RELIEF REQUEST NO. 67, EXTENSION OF CONTAINMENT TENDON INSERVICE TESTING FROM 10 YEARS TO 20 YEARS FOR PALO VERDE NUCLEAR GENERATING STATION, UNITS 1 AND 3 On June 16, 2021, an Observation public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and Arizona Public Service Company (the licensee) via teleconference. The purpose of this meeting was to discuss the licensees upcoming Relief Request No. 67 regarding the proposed extension of containment tendon inservice testing from 10 years to 20 years for Palo Verde Nuclear Generating Station, Units 1 and 3. The meeting notice and agenda, dated June 2, 2021, are available in the NRCs Agencywide Documents Access and Management System (ADAMS) at Accession No. ML21153A201. A list of attendees is provided in the enclosure.

The licensee provided slides for this public meeting, which are available in ADAMS at Accession No. ML21165A183. The licensees presentation included a summary of the pending alternative request, discussions of the current and alternative regulatory requirements, and justifications for the planned alternatives. In addition, the licensee stated that it is planning to submit this application in early July 2021 and will request NRC approval by June 2022.

No members of the public called into the meeting. No regulatory decisions or commitments were made at the meeting. No Public Meeting Feedback forms were received.

Please direct any inquiries to me at (301) 415-1564 or by e-mail at Siva.Lingam@nrc.gov.

/RA/

Siva P. Lingam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-528 and STN 50-530

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES JUNE 16, 2021, PUBLIC MEETING WITH ARIZONA PUBLIC SERVICE COMPANY REGARDING RELIEF REQUEST NO. 67 TO EXTEND CONTAINMENT TENDON INSERVICE TESTING FROM 10 YEARS TO 20 YEARS PALO VERDE NUCLEAR GENERATING STATION, UNITS 1 AND 3 Nan Chien U.S. Nuclear Regulatory Commission (NRC)

Joe Colaccino NRC Bhagwat Jain NRC Siva Lingam NRC John Ma NRC Brian Wittick NRC Matthew Cox Arizona Public Service Company (APS)

Doug Hansen APS Sarah Kane APS Christine King APS Jordan Neuss APS Carl Stephenson APS Kyle Wakefield APS Mark Ferlisi APS Consultant Daniel Lamond APS Consultant Enclosure

ML21168A262 (Package)

ML21153A201 (Meeting Notice)

ML21165A183 (Public Meeting Slides)

ML21168A263 (Meeting Summary) *by email OFFICE NRR/DORL/LPL4/PM* NRR/DORL/LPL4/LA* NRR/DORL/LPL4/BC* NRR/DORL/LPL4/PM*

JDixon-Herrity NAME SLingam PBlechman (TWengert for) SLingam DATE 6/17/2021 6/21/2021 6/24/2021 6/24/2021