Summary of January 6, 2021, Public Meeting with Arizona Public Service Company to Discuss Upcoming LAR Regarding Containment Integrated Leak Rate Test Permanent Extension to 15 Years for Palo Verde Nuclear Generating Station, Units 1, 2, an
ML21011A274
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 01/26/2021
From: Siva Lingam
Plant Licensing Branch IV
To:
Arizona Public Service Co
Lingam S, 301-415-1564
References
Download: ML21011A274 (3)


Text

January 26, 2021 LICENSEE: Arizona Public Service Company FACILITY: Palo Verde Nuclear Generating Station, Units 1, 2, and 3

SUBJECT:

SUMMARY

OF JANUARY 6, 2021, PUBLIC MEETING WITH ARIZONA PUBLIC SERVICE COMPANY TO DISCUSS UPCOMING LICENSE AMENDMENT REQUEST RE: CONTAINMENT INTEGRATED LEAK RATE TEST PERMANENT EXTENSION TO 15 YEARS FOR PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 On January 6, 2021, the U.S. Nuclear Regulatory Commission (NRC) staff held a Category 1 public meeting between the U.S. Nuclear Regulatory Commission (NRC) staff and Arizona Public Service Company (APS, the licensee) via teleconference. The purpose of this meeting was to discuss the licensees upcoming license amendment request (LAR) regarding the permanent extension of the containment integrated leak rate test (ILRT) from 10 years to 15 years for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Palo Verde). The meeting notice and agenda, dated December 15, 2020, are available in NRCs Agencywide Documents Access and Management System (ADAMS) at Accession No. ML20350B784. A list of attendees is provided in the enclosure.

The licensee provided slides for this public meeting, which are available in ADAMS at Accession No. ML21011A275. APS is planning to submit this Palo Verde LAR during the week of January 11, 2021.

No members of the public called into the meeting. No regulatory decisions or commitments were made at the meeting.

Please direct any inquiries to me at (301) 415-1564 or by e-mail at Siva.Lingam@nrc.gov.

/RA/

Siva P. Lingam, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-528, STN 50-529, and STN 50-530

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES JANUARY 6, 2021, PUBLIC MEETING WITH ARIZONA PUBLIC SERVICE COMPANY REGARDING EXTENSION OF CONTAINMENT ILRT TO 15 YEARS PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 Clinton Ashley U.S. Nuclear Regulatory Commission (NRC)

Joseph Colaccino NRC Nan Chien NRC Jennifer Dixon-Herrity NRC Zachary Gran NRC Siva Lingam NRC John Ma NRC Henry Marchlewski NRC Stephen Smith NRC Shilp Vasavada NRC Brian Wittick NRC Nawaporn AaronsCooke Arizona Public Service Company (APS)

Boris Bolf APS Ryan Burbank APS Matthew Cox APS Michael Cymbor APS Michael DiLorenzo APS Thomas Hook APS Sarah Kane APS Francis Liu APS Carl Stephenson APS Enclosure

ML20350B784 (Meeting Notice)

ML21011A275 (Public Meeting Slides)

ML21011A274 (Meeting Summary) *by email OFFICE NRR/DORL/LPL4/PM* NRR/DORL/LPL4/LA* NRR/DORL/LPL4/BC* NRR/DORL/LPL4/PM*

NAME SLingam PBlechman JDixon-Herrity SLingam DATE 1/25/2021 1/25/2021 1/26/2021 1/26/2021