==Dear Mr. Pacilio:==
==Dear Mr. Pacilio:==
On October 31, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your LaSalle County Station, Units 1 and 2. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on October 31, 2013
On October 31, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your LaSalle County Station, Units 1 and 2. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclose d inspection report documents the inspection results, which were discussed on October 31, 2013 , with Mr. R. Immke and other members of your staff.
, with Mr. R. Immke and other members of your staff.


The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
Line 41: Line 40:
Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security
Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security
-Related Information
-Related Information
-Withhold from public disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
-Withhold from public disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response. Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
 
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.


Sincerely,/RA/ Richard A. Skokowski, Chief Plant Support Branch Division of Reactor Safety Docket Nos.
Sincerely,/RA/ Richard A. Skokowski, Chief Plant Support Branch Division of Reactor Safety Docket Nos.
Line 53: Line 50:


===w/Attachment:===
===w/Attachment:===
Supplemental Information cc w/encl
Supplemental Information cc w/encl: S. Coker, NSIR/DSO/DDSO/ST R. Albert, NSIR T. Dimitriadis, RI B. Desai, RII M. Haire, RIV C. Wilson, LaSalle Station Security Manager J. Klinger, State Liaison Officer, Illinois Emergency Management Agency Illinois Emergency Management Agency cc w/o encl:
: S. Coker, NSIR/DSO/DDSO/ST R. Albert, NSIR T. Dimitriadis, RI B. Desai, RII M. Haire, RIV C. Wilson, LaSalle Station Security Manager J. Klinger, State Liaison Officer, Illinois Emergency Management Agency Illinois Emergency Management Agency cc w/o encl:
Distribution via ListServŽ
Distribution via ListServŽ
}}
}}

Revision as of 19:42, 13 July 2018

IR 05000373/2013407; 05000374/2013407; 10/28/2013 - 10/31/2013, LaSalle County Station, Units 1 and 2; Routine Security Baseline Inspection. (Cover Letter Only)
ML13345A068
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 12/10/2013
From: Skokowski R A
Plant Support Branch II
To: Pacilio M J
Exelon Generation Co
Joseph Maynen
References
IR-13-407
Download: ML13345A068 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532

-4352 December 10, 2013 Mr. Michael Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO), Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2 NRC SECURITY BASELINE INSPECTION REPORT 05000373/2013407; 05000374/2013407

Dear Mr. Pacilio:

On October 31, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your LaSalle County Station, Units 1 and 2. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclose d inspection report documents the inspection results, which were discussed on October 31, 2013 , with Mr. R. Immke and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings were identified during this inspection

. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide

Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Enclosure contains Sensitive Unclassified Non

-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1)

and its disclosure to unauthorized individuals could present a security vulnerability.

Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security

-Related Information

-Withhold from public disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response. Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,/RA/ Richard A. Skokowski, Chief Plant Support Branch Division of Reactor Safety Docket Nos.

50-373; 50-374 License Nos. NPF-11; NPF-18 Nonpublic