February 25, 2020
SUBJECT:
LASALLE COUNTY STATION, UNIT 1 - POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL (PHASE I) REPORT 05000373/2020010
Dear Mr. Hanson:
On February 19, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at LaSalle County Station, Unit 1 and discussed the results of this inspection with Mr.
John Washko and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Ann Marie J. Stone, Chief Engineering Branch 1 Division of Reactor Safety
Docket No. 50-373 License No. NPF-11
Enclosure:
As stated
Inspection Report
Docket Number:
05000373
License Number:
Report Number:
Enterprise Identifier: I-2020-010-0025
Licensee:
Exelon Generation Company, LLC
Facility:
LaSalle County Station, Unit 1
Location:
Marseilles, IL
Inspection Dates:
February 10, 2020 to February 19, 2020
Inspectors:
J. Park, Reactor Inspector
S. Sheldon, Project Engineer
Approved By:
Ann Marie J. Stone, Chief
Engineering Branch 1
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Post-Approval Site Inspection for License Renewal (Phase I) at LaSalle County Station, Unit 1, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
OTHER ACTIVITIES
- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL
===71003 - Post-Approval Site Inspection for License Renewal
The inspectors verified the licensee implement the "outage-related" Aging Management Programs included in "Safety Evaluation Report Related to the License Renewal of LaSalle County Station, Units 1 and 2," dated September 2016 (ML16271A039) in accordance with 10 CFR Part 54, "Requirements for the Renewal of Operating Licenses for Nuclear Power Plants."
Post-Approval Site Inspection for License Renewal===
- (1) The team conducted a Phase 1 license renewal inspection. The following aging management programs were evaluated by the team:
- Open-Cycle Cooling Water System (Commitment Item 12)o The inspectors observed general material condition of the 1A Residual Heat Removal (RHR) heat exchanger channel head. The inspectors reviewed the condition report AR 04318456 that documented the as-found condition of the channel head and the licensee assessment of the condition.
- Closed Treated Water Systems (Commitment Item 13)o The inspectors observed the eddy current testing of the evaporator portion of 1A Primary Containment Ventilation Chiller. The inspectors also observed general condition of the tubes and tubesheet on its condenser water box and reviewed the condition report that documented the conditions.
- Inspection of Overhead Heavy Load and Light Load (Related to Refueling)
Handling Systems (Commitment Item 14)o The inspectors performed review of records for the completed inspection of jib crane on the scorpion platform performed in accordance with LMS-HC-01D, Jib Crane Annual Preventive Maintenance and Examination, and LMP-GM-51, Portable Hoist Examination.
o The inspectors performed review of records for the inspection of bolting tightness on the scorpion.
- Fire Protection Program (Commitment 16)o The inspectors observed watertight penetration inspections.
- One-Time Inspection Program (Commitment Item 21)o The inspectors performed review of records from a sample of completed inspections. The records reviewed included one-time non-destructive examination inspection performed on 1MS04AA-8" spare relief valve connection piping, 1FW74AA-1 1/2" drain piping (inboard of Drain Valve 1FW112A), and 0DG30A-1" capped end connection (inboard to "tie-ins").
o The inspectors observed inspection of the 1A Low Pressure Core Spray motor cooler.
o The inspectors observed inspection of the 1A Control Rod Drive pump oil cooler.
- Structures Monitoring (Commitment Item 34)o The inspectors observed general visual inspection of the structure and structural components in the Unit 1 Steam Tunnel area and the portion of Auxiliary Building on Elevation 740' in accordance with ER-AA-450, "LaSalle Structures Monitoring Program."
o The inspectors performed partial walkdown of the Outboard Main Steam Isolation Valve room and observed general visual inspection of the structural components in the area.
- Protective Coating Monitoring and Maintenance Program (Commitment Item 36)o The inspectors observed general visual inspection of the Service Level I coatings on the primary containment drywell liner in accordance with ER-AA-330-008, "Exelon Safety-Related (Service Level I)
Protective Coatings."
o The inspectors observed the visual inspection of the exterior and interior coatings on the drywell head.
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On February 19, 2020, the inspectors presented the Post-Approval Site Inspection for License Renewal (Phase I) results to Mr. J. Washko, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71003
Corrective Action
Documents
231943
LR OTI Results 2MS04BC-12 SRV Tailpipe Pit Depth
Measurement
03/22/2019
254293
LR Inspection Required for U1 LPCS Motor Cooler
06/04/2019
275026
(LR) L1R18 Insulation Removal Support Needed for
Walkdown
08/29/2019
281839
License Renewal (LR) Coating Inspection for 1E22-S001
09/24/2019
282589
License Renewal (LR) Closed Cooling Water System 1E22-
S001
09/26/2019
282924
License Renewal (LR) Coating Inspection for 0WR01A HX
09/27/2019
04316738
Visual Exam Results for ISI Component HPCS Pump
2/10/2020
04317676
License Renewal Inspections for LPCS Motor Cooler
2/13/2020
04318084
LR Inspection Performed for 1A CRD Pump Oil Cooler
2/14/2020
04318123
License Renewal (LR) Coating Inspection for Drywell -
L1R18
2/15/2020
04318124
License Renewal (LR) Coating Inspection for Suppression
Chamber
2/15/2020
04318302
1MSA1AA-3/4 License Renewal Inspection Results
2/16/2020
04318307
1MSA1AB-3/4" License Renewal Inspection Results
2/16/2020
04318366
LR Inspection for 1A CRD Pump Gearbox Oil Drain Piping
2/16/2020
04318417
LROT Inspection Results of 1RR04AB-4"
2/16/2020
04318456
UT to be Performed on the 1A RHR HX Channel Head
2/17/2020
04318671
Degraded Coating on 1A VP Chiller
2/17/2020
Procedures
Exelon Safety-Related (Service Level I) Protective Coatings
License Renewal Project Turnover and Station Preparations
for PEO Entry
ER-LA-450
LaSalle Structures Monitoring Program
LMS-HC-01D
Jib Crane Annual Preventive Maintenance and Examination
LTS-1000-29
Water Tight Penetration Inspection
Work Orders
01889160-01
ES (LR) Perform Eddy Current Test & Clean W/ IDNS
Inspection 1VP01CA Chiller W/WO 1868192
2/15/2020
01933084
(LROT) One-Time Inspection 1MS04AA-8"
03/10/2018
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
01934284
License Renewal (LR) One-Time Inspections (FW)
03/10/2018
01935409
License Renewal One-Time Inspections for System (DG)
2/20/2018
04753434 01
LRA Watertight Penetration Inspection, Unit 1
2/12/2020
04757662-01
LRA SSP U-1 Primary Containment Coatings Inspection
2/12/2020
04801309-08
EWP MM (LR) Pre-Outage Inspect Bolting Tightness on
Scorpion
11/27/2019
04801309-09
EWP MM (LR) Inspect Scorpion Jib Hoist
01/30/2020
04928256 01
LR Inspection Required for U1 LPCS Motor Cooler
2/13/2020
04943366 01
Inspect CRD Feed Pump Gearbox RBCCW Heat Exchanger
2/14/2020