February 25, 2020

SUBJECT:

LASALLE COUNTY STATION, UNIT 1 - POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL (PHASE I) REPORT 05000373/2020010

Dear Mr. Hanson:

On February 19, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at LaSalle County Station, Unit 1 and discussed the results of this inspection with Mr.

John Washko and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Ann Marie J. Stone, Chief Engineering Branch 1 Division of Reactor Safety

Docket No. 50-373 License No. NPF-11

Enclosure:

As stated

Inspection Report

Docket Number:

05000373

License Number:

NPF-11

Report Number:

05000373/2020010

Enterprise Identifier: I-2020-010-0025

Licensee:

Exelon Generation Company, LLC

Facility:

LaSalle County Station, Unit 1

Location:

Marseilles, IL

Inspection Dates:

February 10, 2020 to February 19, 2020

Inspectors:

J. Park, Reactor Inspector

S. Sheldon, Project Engineer

Approved By:

Ann Marie J. Stone, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Post-Approval Site Inspection for License Renewal (Phase I) at LaSalle County Station, Unit 1, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

===71003 - Post-Approval Site Inspection for License Renewal

The inspectors verified the licensee implement the "outage-related" Aging Management Programs included in "Safety Evaluation Report Related to the License Renewal of LaSalle County Station, Units 1 and 2," dated September 2016 (ML16271A039) in accordance with 10 CFR Part 54, "Requirements for the Renewal of Operating Licenses for Nuclear Power Plants."

Post-Approval Site Inspection for License Renewal===

(1) The team conducted a Phase 1 license renewal inspection. The following aging management programs were evaluated by the team:
  • Open-Cycle Cooling Water System (Commitment Item 12)o The inspectors observed general material condition of the 1A Residual Heat Removal (RHR) heat exchanger channel head. The inspectors reviewed the condition report AR 04318456 that documented the as-found condition of the channel head and the licensee assessment of the condition.
  • Closed Treated Water Systems (Commitment Item 13)o The inspectors observed the eddy current testing of the evaporator portion of 1A Primary Containment Ventilation Chiller. The inspectors also observed general condition of the tubes and tubesheet on its condenser water box and reviewed the condition report that documented the conditions.
  • Inspection of Overhead Heavy Load and Light Load (Related to Refueling)

Handling Systems (Commitment Item 14)o The inspectors performed review of records for the completed inspection of jib crane on the scorpion platform performed in accordance with LMS-HC-01D, Jib Crane Annual Preventive Maintenance and Examination, and LMP-GM-51, Portable Hoist Examination.

o The inspectors performed review of records for the inspection of bolting tightness on the scorpion.

  • One-Time Inspection Program (Commitment Item 21)o The inspectors performed review of records from a sample of completed inspections. The records reviewed included one-time non-destructive examination inspection performed on 1MS04AA-8" spare relief valve connection piping, 1FW74AA-1 1/2" drain piping (inboard of Drain Valve 1FW112A), and 0DG30A-1" capped end connection (inboard to "tie-ins").

o The inspectors observed inspection of the 1A Low Pressure Core Spray motor cooler.

o The inspectors observed inspection of the 1A Control Rod Drive pump oil cooler.

  • Structures Monitoring (Commitment Item 34)o The inspectors observed general visual inspection of the structure and structural components in the Unit 1 Steam Tunnel area and the portion of Auxiliary Building on Elevation 740' in accordance with ER-AA-450, "LaSalle Structures Monitoring Program."

o The inspectors performed partial walkdown of the Outboard Main Steam Isolation Valve room and observed general visual inspection of the structural components in the area.

  • Protective Coating Monitoring and Maintenance Program (Commitment Item 36)o The inspectors observed general visual inspection of the Service Level I coatings on the primary containment drywell liner in accordance with ER-AA-330-008, "Exelon Safety-Related (Service Level I)

Protective Coatings."

o The inspectors observed the visual inspection of the exterior and interior coatings on the drywell head.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On February 19, 2020, the inspectors presented the Post-Approval Site Inspection for License Renewal (Phase I) results to Mr. J. Washko, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71003

Corrective Action

Documents

231943

LR OTI Results 2MS04BC-12 SRV Tailpipe Pit Depth

Measurement

03/22/2019

254293

LR Inspection Required for U1 LPCS Motor Cooler

06/04/2019

275026

(LR) L1R18 Insulation Removal Support Needed for

Walkdown

08/29/2019

281839

License Renewal (LR) Coating Inspection for 1E22-S001

09/24/2019

282589

License Renewal (LR) Closed Cooling Water System 1E22-

S001

09/26/2019

282924

License Renewal (LR) Coating Inspection for 0WR01A HX

09/27/2019

04316738

Visual Exam Results for ISI Component HPCS Pump

2/10/2020

04317676

License Renewal Inspections for LPCS Motor Cooler

2/13/2020

04318084

LR Inspection Performed for 1A CRD Pump Oil Cooler

2/14/2020

04318123

License Renewal (LR) Coating Inspection for Drywell -

L1R18

2/15/2020

04318124

License Renewal (LR) Coating Inspection for Suppression

Chamber

2/15/2020

04318302

1MSA1AA-3/4 License Renewal Inspection Results

2/16/2020

04318307

1MSA1AB-3/4" License Renewal Inspection Results

2/16/2020

04318366

LR Inspection for 1A CRD Pump Gearbox Oil Drain Piping

2/16/2020

04318417

LROT Inspection Results of 1RR04AB-4"

2/16/2020

04318456

UT to be Performed on the 1A RHR HX Channel Head

2/17/2020

04318671

Degraded Coating on 1A VP Chiller

2/17/2020

Procedures

ER-AA-330-008

Exelon Safety-Related (Service Level I) Protective Coatings

ER-AA-700-1001

License Renewal Project Turnover and Station Preparations

for PEO Entry

ER-LA-450

LaSalle Structures Monitoring Program

LMS-HC-01D

Jib Crane Annual Preventive Maintenance and Examination

LTS-1000-29

Water Tight Penetration Inspection

Work Orders

01889160-01

ES (LR) Perform Eddy Current Test & Clean W/ IDNS

Inspection 1VP01CA Chiller W/WO 1868192

2/15/2020

01933084

(LROT) One-Time Inspection 1MS04AA-8"

03/10/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

01934284

License Renewal (LR) One-Time Inspections (FW)

03/10/2018

01935409

License Renewal One-Time Inspections for System (DG)

2/20/2018

04753434 01

LRA Watertight Penetration Inspection, Unit 1

2/12/2020

04757662-01

LRA SSP U-1 Primary Containment Coatings Inspection

2/12/2020

04801309-08

EWP MM (LR) Pre-Outage Inspect Bolting Tightness on

Scorpion

11/27/2019

04801309-09

EWP MM (LR) Inspect Scorpion Jib Hoist

01/30/2020

04928256 01

LR Inspection Required for U1 LPCS Motor Cooler

2/13/2020

04943366 01

Inspect CRD Feed Pump Gearbox RBCCW Heat Exchanger

2/14/2020