{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 October 30, 2012 Enclosure transmitted herewith contain SUNSI. When separated from enclosure, this transmittal document is d econtrolled. Mr. Jon Vice President, Crystal River Nuclear Plant Crystal River Nuclear Plant (NA2C)
{{#Wiki_filter:UNITED STATES ber 30, 2012


15760 W. Power Line Street Crystal River, FL 34428-6708
==SUBJECT:==
 
CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT - U.S. NUCLEAR REGULATORY COMMISSION SECURITY INSPECTION REPORT 05000302/2012404
SUBJECT: CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT - U.S. NUCLEAR REGULATORY COMMISSION SECURITY INSPECTION REPORT  
 
05000302/2012404


==Dear Mr. Franke:==
==Dear Mr. Franke:==
On October 18, 2012, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Crystal River Nuclear Generating Plant, Unit 3. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed report documents the inspection results, which were discussed with Mr. T. Hobbs and members of your staff.
On October 18, 2012, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Crystal River Nuclear Generating Plant, Unit 3. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed report documents the inspection results, which were discussed with Mr. T. Hobbs and members of your staff.


This inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations, and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
This inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations, and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.


Based on the results of this inspection, no findings were identified.
Based on the results of this inspection, no findings were identified.


In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
 
However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390 (d)(1) and its disclosure to unauthorized individuals could present a security


vulnerability. Therefore, the materials in the enclosure will not be made available electronically - SECURITY-RELATED INFORMA TION for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAM. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security Related Information - Withhold form public disclosure under 10 CFR 2.390" in accordance with10 CFR 2.390 (d)(1) and follow the instructions for withhold10 CFR 2.390 (b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390 (d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the materials in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRCs ADAM. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security Related Information - Withhold form public disclosure under 10 CFR 2.390 in accordance with10 CFR 2.390 (d)(1) and follow the instructions for withhold10 CFR 2.390 (b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.


Sincerely,
Sincerely,
/RA/
/RA/
Binoy Desai, Chief  
Binoy Desai, Chief Plant Support Branch 2 Division of Reactor Safety Docket No. 50-302 License No. DPR-72 Enclosure:
 
Plant Support Branch 2  
 
Division of Reactor Safety Docket No. 50-302 License No. DPR-72  
 
Enclosure:
NRC Security Inspection Report 05000302/2012404 W/Att: Supplemental Information (OUO)
NRC Security Inspection Report 05000302/2012404 W/Att: Supplemental Information (OUO)
cc w/encl.: (See page 3)  
cc w/encl.: (See page 3) ML12305A518 X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII: DRS/PSB2 RII: DRS/PSB2 RII: DRS/PSB2 RII: DRP/BR3 SIGNATURE RA/RP RA/KD RA/BD RA/DR NAME R. Patterson K. Davis B. Desai D. Rich DATE 10/29/2012 10/30/2012 10/30/2012 10/30/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO cc w/Encl:
 
Jon Joseph W. Donahue Vice President  Vice President Crystal River Nuclear Plant (NA2C) Nuclear Oversight 15760 West Power Line Street Progress Energy Crystal River, FL 34428-6708 TPP-15 100 E. Davie Street Terry Hobbs   Raleigh, NC 27601 Plant General Manager Crystal River Nuclear Plant (NA2C) Edward T. O'Neil 15760 W. Power Line Street Director Crystal River, FL 34428-6708 Nuclear Protective Serv and Emergency Preparedness Mark Rigsby   Progress Energy Manager, Support Services - Nuclear TPP-15 Crystal River Nuclear Plant (NA2C) 100 East Davie Street 15760 W. Power Line Street Raleigh, NC 27601 Crystal River, FL 34428-6708 Matthew Widener Daniel R. Westcott Manager Supervisor   Nuclear Security Licensing & Regulatory Programs Crystal River Nuclear Plant Crystal River Nuclear Plant (NA1B) 15760 West Power Line Street 15760 W. Power Line Street Crystal River, FL 34428-6708 Crystal River, FL 34428-6708
ML12305A518 X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII: DRS/PSB2 RII: DRS/PSB2 RII: DRS/PSB2 RII: DRP/BR3 SIGNATURE RA/RP RA/KD RA/BD RA/DR NAME R. Patterson K. Davis B. Desai D. Rich DATE 10/29/2012 10/30/2012 10/30/2012 10/30/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO cc w/Encl:  
 
Jon Vice President Crystal River Nuclear Plant (NA2C)
15760 West Power Line Street Crystal River, FL 34428-6708  
 
Terry Hobbs  
 
Plant General Manager Crystal River Nuclear Plant (NA2C)
15760 W. Power Line Street Crystal River, FL 34428-6708  
 
Mark Rigsby Manager, Support Services - Nuclear Crystal River Nuclear Plant (NA2C)
15760 W. Power Line Street Crystal River, FL 34428-6708  
 
Daniel R. Westcott  
 
Supervisor Licensing & Regulatory Programs Crystal River Nuclear Plant (NA1B)  
 
15760 W. Power Line Street Crystal River, FL 34428-6708 Joseph W. Donahue Vice President Nuclear Oversight
 
Progress Energy TPP-15 100 E. Davie Street
 
Raleigh, NC 27601
 
Edward T. O'Neil Director Nuclear Protective Serv and Emergency
 
Preparedness
 
Progress Energy TPP-15 100 East Davie Street Raleigh, NC 27601
 
Matthew Widener
 
Manager Nuclear Security Crystal River Nuclear Plant 15760 West Power Line Street Crystal River, FL 34428-6708
}}
}}

Latest revision as of 20:43, 11 November 2019

Nuclear Generating Plant - U.S. Nuclear Regulatory Commission Security Inspection Report 05000302-12-404
ML12305A518
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 10/30/2012
From: Binoy Desai
NRC/RGN-II/DRS/PSB2
To: Franke J
Progress Energy Florida
References
IR-12-404
Download: ML12305A518 (4)


Text

UNITED STATES ber 30, 2012

SUBJECT:

CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT - U.S. NUCLEAR REGULATORY COMMISSION SECURITY INSPECTION REPORT 05000302/2012404

Dear Mr. Franke:

On October 18, 2012, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Crystal River Nuclear Generating Plant, Unit 3. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed report documents the inspection results, which were discussed with Mr. T. Hobbs and members of your staff.

This inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations, and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, no findings were identified.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390 (d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the materials in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRCs ADAM. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security Related Information - Withhold form public disclosure under 10 CFR 2.390 in accordance with10 CFR 2.390 (d)(1) and follow the instructions for withhold10 CFR 2.390 (b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.

Sincerely,

/RA/

Binoy Desai, Chief Plant Support Branch 2 Division of Reactor Safety Docket No. 50-302 License No. DPR-72 Enclosure:

NRC Security Inspection Report 05000302/2012404 W/Att: Supplemental Information (OUO)

cc w/encl.: (See page 3) ML12305A518 X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII: DRS/PSB2 RII: DRS/PSB2 RII: DRS/PSB2 RII: DRP/BR3 SIGNATURE RA/RP RA/KD RA/BD RA/DR NAME R. Patterson K. Davis B. Desai D. Rich DATE 10/29/2012 10/30/2012 10/30/2012 10/30/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO cc w/Encl:

Jon Joseph W. Donahue Vice President Vice President Crystal River Nuclear Plant (NA2C) Nuclear Oversight 15760 West Power Line Street Progress Energy Crystal River, FL 34428-6708 TPP-15 100 E. Davie Street Terry Hobbs Raleigh, NC 27601 Plant General Manager Crystal River Nuclear Plant (NA2C) Edward T. O'Neil 15760 W. Power Line Street Director Crystal River, FL 34428-6708 Nuclear Protective Serv and Emergency Preparedness Mark Rigsby Progress Energy Manager, Support Services - Nuclear TPP-15 Crystal River Nuclear Plant (NA2C) 100 East Davie Street 15760 W. Power Line Street Raleigh, NC 27601 Crystal River, FL 34428-6708 Matthew Widener Daniel R. Westcott Manager Supervisor Nuclear Security Licensing & Regulatory Programs Crystal River Nuclear Plant Crystal River Nuclear Plant (NA1B) 15760 West Power Line Street 15760 W. Power Line Street Crystal River, FL 34428-6708 Crystal River, FL 34428-6708