|
|
Line 3: |
Line 3: |
| | issue date = 10/30/2012 | | | issue date = 10/30/2012 |
| | title = Nuclear Generating Plant - U.S. Nuclear Regulatory Commission Security Inspection Report 05000302-12-404 | | | title = Nuclear Generating Plant - U.S. Nuclear Regulatory Commission Security Inspection Report 05000302-12-404 |
| | author name = Desai B B | | | author name = Desai B |
| | author affiliation = NRC/RGN-II/DRS/PSB2 | | | author affiliation = NRC/RGN-II/DRS/PSB2 |
| | addressee name = Franke J A | | | addressee name = Franke J |
| | addressee affiliation = Progress Energy Florida, Inc | | | addressee affiliation = Progress Energy Florida, Inc |
| | docket = 05000302 | | | docket = 05000302 |
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 October 30, 2012 Enclosure transmitted herewith contain SUNSI. When separated from enclosure, this transmittal document is d econtrolled. Mr. Jon Vice President, Crystal River Nuclear Plant Crystal River Nuclear Plant (NA2C) | | {{#Wiki_filter:October 30, 2012 |
|
| |
|
| 15760 W. Power Line Street Crystal River, FL 34428-6708
| | ==SUBJECT:== |
| | | CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT - U.S. NUCLEAR REGULATORY COMMISSION SECURITY INSPECTION REPORT |
| SUBJECT: CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT - U.S. NUCLEAR REGULATORY COMMISSION SECURITY INSPECTION REPORT | |
|
| |
|
| 05000302/2012404 | | 05000302/2012404 |
Revision as of 14:13, 22 June 2019
|
---|
Category:Letter
MONTHYEARIR 05000302/20240012024-09-23023 September 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, NRC Inspection Report No. 05000302/2024001 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24226B2392024-08-27027 August 2024 Application for License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Acknowledgement of Withdrawal ML24179A0702024-07-26026 July 2024 SHPO S106 Completion Crystal River Unit 3 ML24205A2192024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Muscogee Nation ML24205A2182024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Nation of Oklahoma ML24179A0912024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Tribe of Florida ML24205A2202024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3_Miccosukee Tribe of Florida ML24190A1912024-07-0808 July 2024 Fws Concurrence for Crystal River Unit 3 ML24172A2552024-06-20020 June 2024 Fws to NRC Species List: Florida Ecological Services Field Office 06/20/2024 ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24114A2262024-04-24024 April 2024 Amended Special Package Authorization for the Cr3 Middle Package (Crystal River 3 Middle Package - Docket No. 71-9393) IR 05000302/20230022024-04-17017 April 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2023002 ML24054A0612024-04-0202 April 2024 Request to Initiate Section 106 Consultation Regarding the License Termination Plan for Crystal River Unit 3 in Citrus County, Florida ML24079A2492024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Johnson, Lewis Johnson ML24054A0582024-04-0202 April 2024 Achp S106 Initiation Crystal River Unit 3 - Letter 1 ML24079A2472024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Cypress, Talbert ML24079A2482024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Hill, David Hill ML24054A0812024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Osceola, Marcellus ML24089A0362024-03-29029 March 2024 Response to Audit Plan in Support of Accelerated Decommissioning Partners and Request to Add License Condition to Include License Termination Plan Requirements. W/Enclosures 1 to 5 ML24073A1922024-03-11011 March 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24054A6452024-02-29029 February 2024 Letter - Reply to Request for RAI Extension Related to the Crystal River License Termination Plan ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23342A0942024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 – Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commissions Analysis of ADP CR3, LLCs Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan 2024-09-23
[Table view] |
Text
October 30, 2012
SUBJECT:
CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT - U.S. NUCLEAR REGULATORY COMMISSION SECURITY INSPECTION REPORT
05000302/2012404
Dear Mr. Franke:
On October 18, 2012, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Crystal River Nuclear Generating Plant, Unit 3. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed report documents the inspection results, which were discussed with Mr. T. Hobbs and members of your staff.
This inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations, and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.
However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390 (d)(1) and its disclosure to unauthorized individuals could present a security
vulnerability. Therefore, the materials in the enclosure will not be made available electronically - SECURITY-RELATED INFORMA TION for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAM. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security Related Information - Withhold form public disclosure under 10 CFR 2.390" in accordance with10 CFR 2.390 (d)(1) and follow the instructions for withhold10 CFR 2.390 (b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Sincerely,
/RA/
Binoy Desai, Chief
Plant Support Branch 2
Division of Reactor Safety Docket No. 50-302 License No. DPR-72
Enclosure:
NRC Security Inspection Report 05000302/2012404 W/Att: Supplemental Information (OUO)
cc w/encl.: (See page 3)
ML12305A518 X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII: DRS/PSB2 RII: DRS/PSB2 RII: DRS/PSB2 RII: DRP/BR3 SIGNATURE RA/RP RA/KD RA/BD RA/DR NAME R. Patterson K. Davis B. Desai D. Rich DATE 10/29/2012 10/30/2012 10/30/2012 10/30/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO cc w/Encl:
Jon Vice President Crystal River Nuclear Plant (NA2C)
15760 West Power Line Street Crystal River, FL 34428-6708
Terry Hobbs
Plant General Manager Crystal River Nuclear Plant (NA2C)
15760 W. Power Line Street Crystal River, FL 34428-6708
Mark Rigsby Manager, Support Services - Nuclear Crystal River Nuclear Plant (NA2C)
15760 W. Power Line Street Crystal River, FL 34428-6708
Daniel R. Westcott
Supervisor Licensing & Regulatory Programs Crystal River Nuclear Plant (NA1B)
15760 W. Power Line Street Crystal River, FL 34428-6708 Joseph W. Donahue Vice President Nuclear Oversight
Progress Energy TPP-15 100 E. Davie Street
Raleigh, NC 27601
Edward T. O'Neil Director Nuclear Protective Serv and Emergency
Preparedness
Progress Energy TPP-15 100 East Davie Street Raleigh, NC 27601
Matthew Widener
Manager Nuclear Security Crystal River Nuclear Plant 15760 West Power Line Street Crystal River, FL 34428-6708