IR 05000313/2007001: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION rch 2, 2007 | ||
==SUBJECT:== | |||
ANNUAL ASSESSMENT LETTER - ARKANSAS NUCLEAR ONE (NRC INSPECTION REPORT 05000313/368-2007001) | |||
==Dear Mr. Mitchell:== | ==Dear Mr. Mitchell:== | ||
On February 7, 2007, the NRC staff completed its performance review of Arkansas Nuclear One (ANO). Our technical staff reviewed performance indicators for the most recent quarter and inspection results for the period from January 1 through December 31 , 2006. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility | On February 7, 2007, the NRC staff completed its performance review of Arkansas Nuclear One (ANO). Our technical staff reviewed performance indicators for the most recent quarter and inspection results for the period from January 1 through December 31 , 2006. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility. | ||
A separate letter designated and marked as | This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Official Use Only - Security-Related Information will include the physical protection review and resultant inspection plan. | ||
Overall, AN0 Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the | Overall, AN0 Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all performance indicators indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. | ||
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through September 30, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the midcycle review. | The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through September 30, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the midcycle review. | ||
In accordance with 10 CFR 2.390 of the | In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.aov/reading-rm/adams.html (the Public Electronic Reading Room). | ||
a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of | |||
UNITED STATES NUCLEAR REGULATORY COMMISSION | UNITED STATES NUCLEAR REGULATORY COMMISSION rch 2, 2007 | ||
==SUBJECT:== | |||
ANNUAL ASSESSMENT LETTER - ARKANSAS NUCLEAR ONE (NRC INSPECTION REPORT 05000313/368-2007001) | |||
==Dear Mr. Mitchell:== | ==Dear Mr. Mitchell:== | ||
On February 7, 2007, the NRC staff completed its performance review of Arkansas Nuclear One (ANO). Our technical staff reviewed performance indicators for the most recent quarter and inspection results for the period from January 1 through December 31 , 2006. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility | On February 7, 2007, the NRC staff completed its performance review of Arkansas Nuclear One (ANO). Our technical staff reviewed performance indicators for the most recent quarter and inspection results for the period from January 1 through December 31 , 2006. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility. | ||
A separate letter designated and marked as | This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Official Use Only - Security-Related Information will include the physical protection review and resultant inspection plan. | ||
Overall, AN0 Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the | Overall, AN0 Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all performance indicators indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. | ||
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through September 30, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the midcycle review. | The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through September 30, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the midcycle review. | ||
In accordance with 10 CFR 2.390 of the | In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.aov/reading-rm/adams.html (the Public Electronic Reading Room). | ||
a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of | |||
Entergy Operations, Inc. | Entergy Operations, Inc. -5-Electronic distribution by RIV: | ||
Regional Administrator (BSMI) | |||
DRP Director (ATH) | |||
DRS Director (DDC) | |||
DRS Deputy Director (RJCI) | |||
Senior Resident Inspector (RWD) | |||
Branch Chief, DRPIE (JAC) | |||
Project Engineer, DRPIE (JCK3) | |||
Team Leader, DRPITSS (RLNI) | |||
RlTS Coordinator (MSH3) | |||
V. Dricks, PA0 (VLD) | |||
W. Maier, RSLO (WAM) | |||
L. Owen, RA Secretary (LAO) | |||
DRS Branch Chiefs (WBJ, ATG, LJS, MPSI) | |||
C. Miller, Chief, TRPS, OED0 (CGM) | |||
S. Richards, Deputy Director, DIRS, NRR (SAR) | |||
J. Lubinski, Deputy Director, DORL, NRR (JWL) | |||
C. Haney, Director, DORL, NRR (CXH) | |||
D. Terao, Chief, PLB IV, DORL, NRR (DXT) | |||
F. Saba, NRR Project Manager for A N 0 (FES) | |||
RidsNrrDirslpab@,nrc.gov ROPrepor&s@nrc.gov SUNS1 Review Completed: -JAC- ADAMS: Byes 0 No Initials: -JAC Publicly Available 0 Non-Publicly Available 0 Sensitive ixj Non-Sensitive | |||
/RA/ /RA/ AVegel for /RA/ | |||
2114/07 2114/07 2/25/07 3/2/07 OFFICIAL RECORD COPY T=Tele phone E=E-mail F=Fax | |||
-5- Electronic distribution by RIV: Regional Administrator (BSMI) DRP Director (ATH) DRS Director (DDC) DRS Deputy Director (RJCI) Senior Resident Inspector (RWD) Branch Chief, DRPIE (JAC) Project Engineer, DRPIE (JCK3) Team Leader, DRPITSS (RLNI) RlTS Coordinator (MSH3) V. Dricks, PA0 (VLD) W. Maier, RSLO (WAM) L. Owen, RA Secretary (LAO) DRS Branch Chiefs (WBJ, ATG, LJS, MPSI) C. Miller, Chief, TRPS, OED0 (CGM) S. Richards, Deputy Director, DIRS, NRR (SAR) J. Lubinski, Deputy Director, DORL, NRR (JWL) C. Haney, Director, DORL, NRR (CXH) D. Terao, Chief, PLB IV, DORL, NRR (DXT) F. Saba, NRR Project Manager for | Entergy Operations, Inc. -5-Electronic distribution by RIV: | ||
/RA/ /RA/ AVegel for /RA/ | Regional Administrator (BSMI) | ||
DRP Director (ATH) | |||
DRS Director (DDC) | |||
DRS Deputy Director (RJCI) | |||
Senior Resident Inspector (RWD) | |||
Branch Chief, DRPIE (JAC) | |||
Project Engineer, DRPIE (JCK3) | |||
Team Leader, DRPITSS (RLNI) | |||
RlTS Coordinator (MSH3) | |||
V. Dricks, PA0 (VLD) | |||
W. Maier, RSLO (WAM) | |||
L. Owen, RA Secretary (LAO) | |||
DRS Branch Chiefs (WBJ, ATG, LJS, MPSI) | |||
C. Miller, Chief, TRPS, OED0 (CGM) | |||
S. Richards, Deputy Director, DIRS, NRR (SAR) | |||
J. Lubinski, Deputy Director, DORL, NRR (JWL) | |||
C. Haney, Director, DORL, NRR (CXH) | |||
D. Terao, Chief, PLB IV, DORL, NRR (DXT) | |||
F. Saba, NRR Project Manager for A N 0 (FES) | |||
RidsNrrDirslpab@,nrc.gov ROPrepor&s@nrc.gov SUNS1 Review Completed: -JAC- ADAMS: Byes 0 No Initials: -JAC Publicly Available 0 Non-Publicly Available 0 Sensitive ixj Non-Sensitive | |||
/RA/ /RA/ AVegel for /RA/ | |||
2114/07 2114/07 2/25/07 3/2/07 OFFICIAL RECORD COPY T=Tele phone E=E-mail F=Fax | |||
Entergy Operations, Inc. -2-If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (817) 860-8147 with any questions you may have regarding this letter or the inspection plan. | |||
Sincerely | Sincerely, V J e f f Clark, Chief Project Branch E Division of Reactor Projects Dockets: 50-313 50-368 Licenses: DPR-51 NPF-6 Enclosure: | ||
, | Arkansas Nuclear One Inspection/Activity Plan cc w/enclosure: | ||
Senior Vice President Manager, Licensing | |||
& Chief Operating Officer Entergy Operations, Inc. | |||
P.O. Box 31995 Jackson, MS 39286- | Entergy Operations, Inc. Arkansas Nuclear One P.O. Box 31995 1448 S. R. 333 Jackson, MS 39286-1995 Russellville, AR 72802 Vice President Director, Nuclear Safety & Licensing Operations Support Entergy Operations, Inc. | ||
P.O. Box 31995 Jackson, MS 39286- | Entergy Operations, Inc. 1340 Echelon Parkway P.O. Box 31995 Jackson, MS 39213-8298 Jackson, MS 39286-1995 Section Chief, Division of Health General Manager Plant Operations Radiation Control Section Entergy Operations, Inc. Arkansas Department of Health and Arkansas Nuclear One Human Services 1448 S. R. 333 4815 West Markham Street, Slot 30 Russellville, AR 72802 Little Rock, AR 72205-3867 Director, Nuclear Safety Assurance Section Chief, Division of Health Entergy Operations, Inc. Emergency Management Section Arkansas Nuclear One Arkansas Department of Health and 1448 S. R. 333 Human Services Russellville, AR 72802 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867 | ||
Entergy Operations, Inc. -3-Manager, Washington Nuclear Operations Josh Johnston ABB Combustion Engineering Nuclear Emergency Service Coordinator Power Johnson County Office of Emergency 12300 Twinbrook Parkway, Suite 330 Services Rockville, MD 20852 P.O. Box 546 Clarksville, AR 72830 James Mallay Director, Regulatory Affairs Don Fairbanks Framatome ANP Emergency Service Coordinator 3815 Old Forest Road Logan County Office of Emergency Lynchburg, VA 24501 Services Logan County Courthouse Chairperson Paris, AR 72855 Denton Field Office Chemical and Nuclear Preparedness The Honorable Steve Pfeifer and Protection Division Mayor of Danville Office of Infrastructure Protection P.O. Box 69 Preparedness Directorate Danville, AR 72833 Dept. of Homeland Security 800 North Loop 288 The Honorable Bill Elsken Federal Regional Center Mayor of Paris Denton, TX 76201-3698 P.O. Box 271 Paris, AR 72855 David Maxwell Arkansas Department of The Honorable Billy Helms Emergency Management Mayor of Clarksville P.O. Box 758 205 Walnut Street Conway, AR 72033 Clarksville, AR 72830-3005 David Freeman, Acting The Honorable Carolyn McGee Emergency Service Coordinator Mayor of Dardanelle Pope County P.O. Box 360 No. 4 Emergency Lane Dardanelle, AR 72834 Russellville, AR 72801 The Honorable Allen Bradley Charlie Smith Mayor of Dover Emergency Service Coordinator P.O. Box 258 Yell County Courthouse Russellville, AR 7281 1 Union Street Dardanelle, AR 72834 The Honorable Jerry Don Barrett Mayor of Atkins P.O. Box 128 Atkins, AR 72823 | |||
- | Entergy Operations, Inc. -4-The Honorable Tyrone Williamson Institute of Nuclear Power Operations (INPO) | ||
Mayor of Russellville Records Center P.O. Box 428 700 Galleria Parkway SE, Suite 100 Russellville, AR 7281 1 Atlanta, GA 30339 The Honorable Edwin Price Mayor of London P.O. Box 130 London, AR 72847 The Honorable Bobby Kirby Mayor of Morrilton City Hall P.O. Box 583 Morrilton, AR 721 10 The Honorable Brad Wear Judge of Yell County Danville Courthouse P.O. Box 219 Danville, AR 72833 The Honorable Jimmy Hart Judge of Conway County 117 South Moose, Room 203 Morrilton, AR 721 10 The Honorable Mike Jacobs Judge of Johnson County P.O. Box 278 Clarksville, AR 72830 The Honorable Edgar Holt Judge of Logan County Room 22 Paris, AR 72855 Misty Sutton Emergency Service Coordinator P.O. Box 119 Morrilton, AR 721 10 The Honorable Jim Ed Gibson Judge of Pope County Courthouse 100 West Main Street Russellville, AR 72801 | |||
m m m m m m u ) | |||
C C C C C C C | |||
.c P .P c | |||
.P c | |||
.P c | |||
.o c | |||
.o c | |||
.P c | |||
0 0 0 0 0 0 0 m c u c u m a , m a , | |||
R R R R Q a n m m m m m m m-K - C - C - C - C -C -K a , a , a , a , a , m a , | |||
- | |||
.E - .E | |||
.E - .E - .e a , a r a , a , a , | |||
- .r .E | |||
- | |||
ais m m m m m m m m m m m m m m m 3 3 m m b b b b b b b 0 0 0 0 0 0 0 0 0 0 0 0 0 0 aN aN aN Na Na ??e 2 s 7 - | |||
$ $ $ $ $ | |||
0 0 0 0 0 0 0 b b b b b b b 0 0 0 0 0 0 0 0 0 0 0 0 0 0 gg$?ss 2 s | |||
$T - | |||
$s$; | |||
T - | |||
o o o o i | |||
- T - - | |||
k | |||
-5- Electronic distribution by RIV: Regional Administrator (BSMI) DRP Director (ATH) DRS Director (DDC) DRS Deputy Director (RJCI) Senior Resident Inspector (RWD) Branch Chief, DRPIE (JAC) Project Engineer, DRPIE (JCK3) Team Leader, DRPITSS (RLNI) RlTS Coordinator (MSH3) V. Dricks, PA0 (VLD) W. Maier, RSLO (WAM) L. Owen, RA Secretary (LAO) DRS Branch Chiefs (WBJ, ATG, LJS, MPSI) C. Miller, Chief, TRPS, OED0 (CGM) S. Richards, Deputy Director, DIRS, NRR (SAR) J. Lubinski, Deputy Director, DORL, NRR (JWL) C. Haney, Director, DORL, NRR (CXH) D. Terao, Chief, PLB IV, DORL, NRR (DXT) F. Saba, NRR Project Manager for | 0 s& | ||
/RA/ /RA/ AVegel for /RA/ | 0 0 co c u m cu 7 | ||
0 | |||
d | |||
0 0 N N a: a: | |||
L W-I L | |||
Y 0 0 a: | |||
W a | |||
W Z Z W W 0 0 0 0 n: a: | |||
za, z | |||
or Ym | |||
0 m zti m | |||
e C | |||
R G | |||
(0 m | |||
.-0 e a, C | |||
s | |||
._ | |||
m C | |||
.- | |||
e | |||
.- | |||
c c c c | |||
._ | |||
c 0 c C a, CL m | |||
.-0 | |||
C | |||
C 0 m | |||
._ 8 m-C c I a, | |||
._ | |||
0 .- | |||
-I1 - | |||
C C 0 z e | |||
c | |||
& e 5 m | |||
> I1 0 > 0 a, c | |||
z z a, | |||
m a, | |||
m a, | |||
n: Y z m a, | |||
a: m m | |||
._m 0 a: a: t 8 | |||
._ C U U U e ._ | |||
or m | |||
- C C m | |||
C m 2 - | |||
UC (D (D n a, L C C a, l- | |||
C | |||
b .- | |||
c 0 ._ | |||
P ._ .- | |||
c | |||
m | |||
U a, | |||
.- | |||
C m | |||
U i= .-Na, c | |||
C C | |||
E0 I I I | |||
rn c c 3 3 R | |||
z c e m 0) Z a, a F m | |||
k a - n Y! C C 'tr: | |||
a, a, a, 2 a a - | |||
U +! a 0 P l- 2 3 I I l-P m P W W I I I I m m N | |||
IC | |||
N L n W | |||
'D i | |||
IC T- | |||
. | |||
(D W | |||
rD | |||
T- IC IC b N N a a d a a c | |||
a m - | |||
W a a m W | |||
I | |||
m C c 0) m m m m c 0 m m m m m m m m m m C C C C c c C C C C C C C C | |||
.-0 | |||
+a. | |||
._ | |||
Y | |||
.P .P .P .o Y Y Y Y | |||
._ | |||
Y 0 .P .P C Y | |||
.P .P .P .o Y Y Y C | |||
.P .o .P .o Y Y Y Y 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 a, a, m a m a , a, a l a , c u c u m a , m t u c u a , | |||
a a n a a n CL a n a a a a a a a a m m m m m m m m m m m m m m m | |||
- f -C 0) | |||
-C - C - K - C -mC -C -C - | |||
C - C - K - C -K - C - C - C a, a, a , a , a a , a, m a l a l a , a , a , a,cua,a, | |||
- | |||
._C -C | |||
.- .r - | |||
- .r - | |||
.r - .E -C | |||
.- .r-m a.r | |||
-, - | |||
.r .E .r .c .r | |||
- .r - | |||
- .r .G-m a, a, 0) | |||
a , m a , a , | |||
m m m m a, | |||
0) m m a | |||
m | |||
m | |||
m | |||
m a , a , a , a , | |||
m m m m m m m m m m m m m m a m a m m m m m m m m m m m m m m m m m m m m m I- b m m m m W m m m m m m m m m c n | |||
. | |||
O | |||
. | |||
N c1 | |||
. | |||
0 N | |||
T- | |||
0 y | |||
m N | |||
0 | |||
c u " N | |||
0 N | |||
0 | |||
N 2 . | |||
0 | |||
. | |||
N | |||
0 | |||
g g | |||
$ $ | |||
0 | |||
0 | |||
0 2 2 2 2 | |||
0 | |||
0 | |||
0 N | |||
0 N | |||
a 5 5 5 | |||
$?$?$?g | |||
0 N | |||
0 N | |||
m c! | |||
m 2 2 & & | |||
Lo 0 0 0 0 0 0 0 0 0 0 0 0 0 I- I- m m m m m m m m m m m m m m m 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 | |||
$ 3 0 0 0 0 0 ssss 0 0 0 0 | |||
. | |||
c! c! N N N N c! CUN" | |||
m | |||
. | |||
b cu m | |||
%-+a%- . | |||
y N m & & 2 0 0 N | |||
N | |||
Lo | |||
Lo | |||
7 7 - | |||
0 0 | |||
S q S o S o o I -0S 0S 0 | |||
S S | |||
N ss&& | |||
N | |||
N | |||
N | |||
r b 7 m | |||
0 0 a, a, c C | |||
.-> | |||
a, e | |||
>, | |||
a | |||
.- | |||
c | |||
. | |||
h | |||
m c i I K | |||
7 z=a, W | |||
.-0 - a 3, | |||
L 0 0 - | |||
Y | |||
.-m0 e e | |||
c E e e | |||
c 0 C | |||
G | |||
> z .-m 0 0 b v) C -1 2 | |||
vi a, | |||
-I $? | |||
+ C | |||
.-a, 4 m m 4 3 m | |||
.-m0 n W L t 0 a | |||
C m t 0 a | |||
TI) | |||
- c I-t C | |||
z 3 6 z Lz a, z ._ | |||
0 L - | |||
0 Y 0 m W 0 K C | |||
Z a, k .-0 | |||
!.ti5 II a e | |||
4-Z | |||
Y | |||
3 | |||
't a, a $? | |||
z 0 a 0 | |||
ii-I a i; I | |||
L 6 n W | |||
I I-I I , .0... 7 W | |||
I I 0 L L LT E N a | |||
0) | |||
8 4 l-- ?- | |||
Lo Lo z | |||
(5) | |||
Lo m | |||
9T | |||
..-. | |||
Lo L" I - K Z cu a | |||
T T- T ln 7 7 7 7 7 7 | |||
?? I- I- I- I- I-r- | |||
0 liaa a - | |||
LT a i; W | |||
a a q l i a a a-a a | |||
Entergy Operations, Inc. -5-Electronic distribution by RIV: | |||
Regional Administrator (BSMI) | |||
DRP Director (ATH) | |||
DRS Director (DDC) | |||
DRS Deputy Director (RJCI) | |||
Senior Resident Inspector (RWD) | |||
Branch Chief, DRPIE (JAC) | |||
Project Engineer, DRPIE (JCK3) | |||
Team Leader, DRPITSS (RLNI) | |||
RlTS Coordinator (MSH3) | |||
V. Dricks, PA0 (VLD) | |||
W. Maier, RSLO (WAM) | |||
L. Owen, RA Secretary (LAO) | |||
DRS Branch Chiefs (WBJ, ATG, LJS, MPSI) | |||
C. Miller, Chief, TRPS, OED0 (CGM) | |||
S. Richards, Deputy Director, DIRS, NRR (SAR) | |||
J. Lubinski, Deputy Director, DORL, NRR (JWL) | |||
C. Haney, Director, DORL, NRR (CXH) | |||
D. Terao, Chief, PLB IV, DORL, NRR (DXT) | |||
F. Saba, NRR Project Manager for A N 0 (FES) | |||
RidsNrrDirslpab@,nrc.gov ROPrepor&s@nrc.gov SUNS1 Review Completed: -JAC- ADAMS: Byes 0 No Initials: -JAC Publicly Available 0 Non-Publicly Available 0 Sensitive ixj Non-Sensitive | |||
/RA/ /RA/ AVegel for /RA/ | |||
2114/07 2114/07 2/25/07 3/2/07 OFFICIAL RECORD COPY T=Tele phone E=E-mail F=Fax | |||
}} | }} |
Latest revision as of 08:57, 23 November 2019
ML070610584 | |
Person / Time | |
---|---|
Site: | Arkansas Nuclear |
Issue date: | 03/02/2007 |
From: | Clark J NRC Region 4 |
To: | Mitchell T Entergy Operations |
References | |
IR-07-001 | |
Download: ML070610584 (10) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION rch 2, 2007
SUBJECT:
ANNUAL ASSESSMENT LETTER - ARKANSAS NUCLEAR ONE (NRC INSPECTION REPORT 05000313/368-2007001)
Dear Mr. Mitchell:
On February 7, 2007, the NRC staff completed its performance review of Arkansas Nuclear One (ANO). Our technical staff reviewed performance indicators for the most recent quarter and inspection results for the period from January 1 through December 31 , 2006. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Official Use Only - Security-Related Information will include the physical protection review and resultant inspection plan.
Overall, AN0 Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all performance indicators indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through September 30, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the midcycle review.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.aov/reading-rm/adams.html (the Public Electronic Reading Room).
UNITED STATES NUCLEAR REGULATORY COMMISSION rch 2, 2007
SUBJECT:
ANNUAL ASSESSMENT LETTER - ARKANSAS NUCLEAR ONE (NRC INSPECTION REPORT 05000313/368-2007001)
Dear Mr. Mitchell:
On February 7, 2007, the NRC staff completed its performance review of Arkansas Nuclear One (ANO). Our technical staff reviewed performance indicators for the most recent quarter and inspection results for the period from January 1 through December 31 , 2006. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Official Use Only - Security-Related Information will include the physical protection review and resultant inspection plan.
Overall, AN0 Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all performance indicators indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through September 30, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the midcycle review.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.aov/reading-rm/adams.html (the Public Electronic Reading Room).
Entergy Operations, Inc. -5-Electronic distribution by RIV:
Regional Administrator (BSMI)
DRP Director (ATH)
DRS Director (DDC)
DRS Deputy Director (RJCI)
Senior Resident Inspector (RWD)
Branch Chief, DRPIE (JAC)
Project Engineer, DRPIE (JCK3)
Team Leader, DRPITSS (RLNI)
RlTS Coordinator (MSH3)
V. Dricks, PA0 (VLD)
W. Maier, RSLO (WAM)
L. Owen, RA Secretary (LAO)
DRS Branch Chiefs (WBJ, ATG, LJS, MPSI)
C. Miller, Chief, TRPS, OED0 (CGM)
S. Richards, Deputy Director, DIRS, NRR (SAR)
J. Lubinski, Deputy Director, DORL, NRR (JWL)
C. Haney, Director, DORL, NRR (CXH)
D. Terao, Chief, PLB IV, DORL, NRR (DXT)
F. Saba, NRR Project Manager for A N 0 (FES)
RidsNrrDirslpab@,nrc.gov ROPrepor&s@nrc.gov SUNS1 Review Completed: -JAC- ADAMS: Byes 0 No Initials: -JAC Publicly Available 0 Non-Publicly Available 0 Sensitive ixj Non-Sensitive
/RA/ /RA/ AVegel for /RA/
2114/07 2114/07 2/25/07 3/2/07 OFFICIAL RECORD COPY T=Tele phone E=E-mail F=Fax
Entergy Operations, Inc. -5-Electronic distribution by RIV:
Regional Administrator (BSMI)
DRP Director (ATH)
DRS Director (DDC)
DRS Deputy Director (RJCI)
Senior Resident Inspector (RWD)
Branch Chief, DRPIE (JAC)
Project Engineer, DRPIE (JCK3)
Team Leader, DRPITSS (RLNI)
RlTS Coordinator (MSH3)
V. Dricks, PA0 (VLD)
W. Maier, RSLO (WAM)
L. Owen, RA Secretary (LAO)
DRS Branch Chiefs (WBJ, ATG, LJS, MPSI)
C. Miller, Chief, TRPS, OED0 (CGM)
S. Richards, Deputy Director, DIRS, NRR (SAR)
J. Lubinski, Deputy Director, DORL, NRR (JWL)
C. Haney, Director, DORL, NRR (CXH)
D. Terao, Chief, PLB IV, DORL, NRR (DXT)
F. Saba, NRR Project Manager for A N 0 (FES)
RidsNrrDirslpab@,nrc.gov ROPrepor&s@nrc.gov SUNS1 Review Completed: -JAC- ADAMS: Byes 0 No Initials: -JAC Publicly Available 0 Non-Publicly Available 0 Sensitive ixj Non-Sensitive
/RA/ /RA/ AVegel for /RA/
2114/07 2114/07 2/25/07 3/2/07 OFFICIAL RECORD COPY T=Tele phone E=E-mail F=Fax
Entergy Operations, Inc. -2-If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (817) 860-8147 with any questions you may have regarding this letter or the inspection plan.
Sincerely, V J e f f Clark, Chief Project Branch E Division of Reactor Projects Dockets: 50-313 50-368 Licenses: DPR-51 NPF-6 Enclosure:
Arkansas Nuclear One Inspection/Activity Plan cc w/enclosure:
Senior Vice President Manager, Licensing
& Chief Operating Officer Entergy Operations, Inc.
Entergy Operations, Inc. Arkansas Nuclear One P.O. Box 31995 1448 S. R. 333 Jackson, MS 39286-1995 Russellville, AR 72802 Vice President Director, Nuclear Safety & Licensing Operations Support Entergy Operations, Inc.
Entergy Operations, Inc. 1340 Echelon Parkway P.O. Box 31995 Jackson, MS 39213-8298 Jackson, MS 39286-1995 Section Chief, Division of Health General Manager Plant Operations Radiation Control Section Entergy Operations, Inc. Arkansas Department of Health and Arkansas Nuclear One Human Services 1448 S. R. 333 4815 West Markham Street, Slot 30 Russellville, AR 72802 Little Rock, AR 72205-3867 Director, Nuclear Safety Assurance Section Chief, Division of Health Entergy Operations, Inc. Emergency Management Section Arkansas Nuclear One Arkansas Department of Health and 1448 S. R. 333 Human Services Russellville, AR 72802 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867
Entergy Operations, Inc. -3-Manager, Washington Nuclear Operations Josh Johnston ABB Combustion Engineering Nuclear Emergency Service Coordinator Power Johnson County Office of Emergency 12300 Twinbrook Parkway, Suite 330 Services Rockville, MD 20852 P.O. Box 546 Clarksville, AR 72830 James Mallay Director, Regulatory Affairs Don Fairbanks Framatome ANP Emergency Service Coordinator 3815 Old Forest Road Logan County Office of Emergency Lynchburg, VA 24501 Services Logan County Courthouse Chairperson Paris, AR 72855 Denton Field Office Chemical and Nuclear Preparedness The Honorable Steve Pfeifer and Protection Division Mayor of Danville Office of Infrastructure Protection P.O. Box 69 Preparedness Directorate Danville, AR 72833 Dept. of Homeland Security 800 North Loop 288 The Honorable Bill Elsken Federal Regional Center Mayor of Paris Denton, TX 76201-3698 P.O. Box 271 Paris, AR 72855 David Maxwell Arkansas Department of The Honorable Billy Helms Emergency Management Mayor of Clarksville P.O. Box 758 205 Walnut Street Conway, AR 72033 Clarksville, AR 72830-3005 David Freeman, Acting The Honorable Carolyn McGee Emergency Service Coordinator Mayor of Dardanelle Pope County P.O. Box 360 No. 4 Emergency Lane Dardanelle, AR 72834 Russellville, AR 72801 The Honorable Allen Bradley Charlie Smith Mayor of Dover Emergency Service Coordinator P.O. Box 258 Yell County Courthouse Russellville, AR 7281 1 Union Street Dardanelle, AR 72834 The Honorable Jerry Don Barrett Mayor of Atkins P.O. Box 128 Atkins, AR 72823
Entergy Operations, Inc. -4-The Honorable Tyrone Williamson Institute of Nuclear Power Operations (INPO)
Mayor of Russellville Records Center P.O. Box 428 700 Galleria Parkway SE, Suite 100 Russellville, AR 7281 1 Atlanta, GA 30339 The Honorable Edwin Price Mayor of London P.O. Box 130 London, AR 72847 The Honorable Bobby Kirby Mayor of Morrilton City Hall P.O. Box 583 Morrilton, AR 721 10 The Honorable Brad Wear Judge of Yell County Danville Courthouse P.O. Box 219 Danville, AR 72833 The Honorable Jimmy Hart Judge of Conway County 117 South Moose, Room 203 Morrilton, AR 721 10 The Honorable Mike Jacobs Judge of Johnson County P.O. Box 278 Clarksville, AR 72830 The Honorable Edgar Holt Judge of Logan County Room 22 Paris, AR 72855 Misty Sutton Emergency Service Coordinator P.O. Box 119 Morrilton, AR 721 10 The Honorable Jim Ed Gibson Judge of Pope County Courthouse 100 West Main Street Russellville, AR 72801
m m m m m m u )
C C C C C C C
.c P .P c
.P c
.P c
.o c
.o c
.P c
0 0 0 0 0 0 0 m c u c u m a , m a ,
R R R R Q a n m m m m m m m-K - C - C - C - C -C -K a , a , a , a , a , m a ,
-
.E - .E
.E - .E - .e a , a r a , a , a ,
- .r .E
-
ais m m m m m m m m m m m m m m m 3 3 m m b b b b b b b 0 0 0 0 0 0 0 0 0 0 0 0 0 0 aN aN aN Na Na ??e 2 s 7 -
$ $ $ $ $
0 0 0 0 0 0 0 b b b b b b b 0 0 0 0 0 0 0 0 0 0 0 0 0 0 gg$?ss 2 s
$T -
$s$;
T -
o o o o i
- T - -
k
0 s&
0 0 co c u m cu 7
0
d
0 0 N N a: a:
L W-I L
Y 0 0 a:
W a
W Z Z W W 0 0 0 0 n: a:
za, z
or Ym
0 m zti m
e C
R G
(0 m
.-0 e a, C
s
._
m C
.-
e
.-
c c c c
._
c 0 c C a, CL m
.-0
C
C 0 m
._ 8 m-C c I a,
._
0 .-
-I1 -
C C 0 z e
c
& e 5 m
> I1 0 > 0 a, c
z z a,
m a,
m a,
n: Y z m a,
a: m m
._m 0 a: a: t 8
._ C U U U e ._
or m
- C C m
C m 2 -
UC (D (D n a, L C C a, l-
C
b .-
c 0 ._
P ._ .-
c
m
U a,
.-
C m
U i= .-Na, c
C C
E0 I I I
rn c c 3 3 R
z c e m 0) Z a, a F m
k a - n Y! C C 'tr:
a, a, a, 2 a a -
U +! a 0 P l- 2 3 I I l-P m P W W I I I I m m N
N L n W
'D i
IC T-
.
(D W
rD
a m -
W a a m W
I
m C c 0) m m m m c 0 m m m m m m m m m m C C C C c c C C C C C C C C
.-0
+a.
._
Y
.P .P .P .o Y Y Y Y
._
Y 0 .P .P C Y
.P .P .P .o Y Y Y C
.P .o .P .o Y Y Y Y 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 a, a, m a m a , a, a l a , c u c u m a , m t u c u a ,
a a n a a n CL a n a a a a a a a a m m m m m m m m m m m m m m m
- f -C 0)
-C - C - K - C -mC -C -C -
C - C - K - C -K - C - C - C a, a, a , a , a a , a, m a l a l a , a , a , a,cua,a,
-
._C -C
.- .r -
- .r -
.r - .E -C
.- .r-m a.r
-, -
.r .E .r .c .r
- .r -
- .r .G-m a, a, 0)
a , m a , a ,
m m m m a,
0) m m a
m
m
m
m a , a , a , a ,
m m m m m m m m m m m m m m a m a m m m m m m m m m m m m m m m m m m m m m I- b m m m m W m m m m m m m m m c n
.
O
.
N c1
.
0 N
T-
0 y
m N
0
c u " N
0 N
0
N 2 .
0
.
N
0
g g
$ $
0
0
0 2 2 2 2
0
0
0 N
0 N
a 5 5 5
$?$?$?g
0 N
0 N
m c!
m 2 2 & &
Lo 0 0 0 0 0 0 0 0 0 0 0 0 0 I- I- m m m m m m m m m m m m m m m 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
$ 3 0 0 0 0 0 ssss 0 0 0 0
.
c! c! N N N N c! CUN"
m
.
b cu m
%-+a%- .
y N m & & 2 0 0 N
N
Lo
Lo
7 7 -
0 0
S q S o S o o I -0S 0S 0
S S
N ss&&
N
N
N
r b 7 m
0 0 a, a, c C
.->
a, e
>,
a
.-
c
.
h
m c i I K
7 z=a, W
.-0 - a 3,
L 0 0 -
Y
.-m0 e e
c E e e
c 0 C
G
> z .-m 0 0 b v) C -1 2
vi a,
-I $?
+ C
.-a, 4 m m 4 3 m
.-m0 n W L t 0 a
C m t 0 a
TI)
- c I-t C
z 3 6 z Lz a, z ._
0 L -
0 Y 0 m W 0 K C
Z a, k .-0
!.ti5 II a e
4-Z
Y
3
't a, a $?
z 0 a 0
ii-I a i; I
L 6 n W
I I-I I , .0... 7 W
I I 0 L L LT E N a
0)
8 4 l-- ?-
Lo Lo z
(5)
Lo m
9T
..-.
Lo L" I - K Z cu a
T T- T ln 7 7 7 7 7 7
?? I- I- I- I- I-r-
0 liaa a -
LT a i; W
a a q l i a a a-a a
Entergy Operations, Inc. -5-Electronic distribution by RIV:
Regional Administrator (BSMI)
DRP Director (ATH)
DRS Director (DDC)
DRS Deputy Director (RJCI)
Senior Resident Inspector (RWD)
Branch Chief, DRPIE (JAC)
Project Engineer, DRPIE (JCK3)
Team Leader, DRPITSS (RLNI)
RlTS Coordinator (MSH3)
V. Dricks, PA0 (VLD)
W. Maier, RSLO (WAM)
L. Owen, RA Secretary (LAO)
DRS Branch Chiefs (WBJ, ATG, LJS, MPSI)
C. Miller, Chief, TRPS, OED0 (CGM)
S. Richards, Deputy Director, DIRS, NRR (SAR)
J. Lubinski, Deputy Director, DORL, NRR (JWL)
C. Haney, Director, DORL, NRR (CXH)
D. Terao, Chief, PLB IV, DORL, NRR (DXT)
F. Saba, NRR Project Manager for A N 0 (FES)
RidsNrrDirslpab@,nrc.gov ROPrepor&s@nrc.gov SUNS1 Review Completed: -JAC- ADAMS: Byes 0 No Initials: -JAC Publicly Available 0 Non-Publicly Available 0 Sensitive ixj Non-Sensitive
/RA/ /RA/ AVegel for /RA/
2114/07 2114/07 2/25/07 3/2/07 OFFICIAL RECORD COPY T=Tele phone E=E-mail F=Fax