MONTHYEARML24023A0652024-01-23023 January 2024 Inservice Inspection Request for Information IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle ML23178A0892023-06-26026 June 2023 August 2023 Emergency Preparedness Program Inspection-Request for Information ML23118A3202023-05-0808 May 2023 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000313;05000368/2023010) ML22229A4862022-08-23023 August 2022 ANO Inspection Plan Letter 2022 Mid Cycle-FINAL ML22122A2952022-05-0404 May 2022 Notification of Inspection NRC Inspection Report 05000368/2022003 and Request for Information ML22075A2052022-03-31031 March 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection (05000313/2022002 and 05000368/20220020 and Request for Information ML22083A2182022-03-30030 March 2022 NRC Initial Operator Licensing Operating Test Approval 05000313/2022301 IR 05000313/20210062022-03-0202 March 2022 Annual Assessment Letter for Arkansas Nuclear One, Units 1 & 2 (Report 05000313/2021006 and 05000368/2021006) ML21286A7132021-10-15015 October 2021 ANO2022010 Tfp RFI Stg, Arkansas Nuclear One, Units 1 and 2 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000313/2022010 and 05000368/2022010) and Request for Information ML21232A2232021-09-0101 September 2021 ANO Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21215A2932021-08-0303 August 2021 Inservice Inspection Request for Information ML21109A2432021-04-19019 April 2021 Arkansan Nuclear One, Unit 1 - Notification of Inspection (NRC Inspection Report 05000313/2021003) and Request for Information ML21077A0162021-03-22022 March 2021 Notification of NRC Design Bases Assurance Inspection (Team) (05000313/2021010 and 05000368/2021010) and Initial Request for Information IR 05000313/20200062021-03-0303 March 2021 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2020006 and 05000368/2020006) ML21053A4032021-02-23023 February 2021 Document Request List - ANO IR 2021402 IR 05000313/20200052020-09-0101 September 2020 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Reports 05000313/2020005 and 05000368/2020005) ML20119A0982020-04-28028 April 2020 Notification of Inspection (NRC Inspection Report 05000368/2020003 and Request for Information ML20106E8522020-04-13013 April 2020 Information Request, NRC Inspection Report 05000313/2020410 and 05000368/2020410 IR 05000313/20190062020-03-0303 March 2020 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2019006 and 05000368/2019006) ML19331A3132019-11-27027 November 2019 ANO Unit 2 Request for Information IR 05000313/20190052019-08-30030 August 2019 Updated Inspection Plan for Arkansas Nuclear One, Unit 1 and 2, Report 05000313/2019005 and 05000368/2019005 ML19080A0372019-03-21021 March 2019 Notification of Inspection (NRC Inspection Report 05000313/2019003 and Request for Information ML18324A8052018-11-19019 November 2018 Notification of an NRC Triennial Fire Protection Baseline Inspection Report 05000313/2019010 and 05000368/2019010) and Request for Information IR 05000313/20180052018-08-31031 August 2018 Updated Inspection Plan for Arkansas Nuclear One (Report 05000313/2018005 and 05000368/2018005) ML18164A3892018-06-14014 June 2018 Arkansas, Notification of NRC Design Bases Assurance Inspection (Teams) (05000313/2018011 and 05000368/2018011), and Initial Request for Information IR 05000313/20170052017-08-28028 August 2017 Arkansas, Units 1 and 2, Update Inspection Plan (Report 05000313/2017005 and 05000368/2017005) IR 05000313/20160062017-03-0101 March 2017 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2016006 and 05000368/2016006) IR 05000313/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2016005 and 05000368/2016005) IR 05000313/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Arkansas Nuclear One NRC Physical Security Inspection Report Numbers 05000313/2016401 and 05000368/2016401) ML16237A4122016-08-31031 August 2016 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2016005 and 05000368/2016005) ML16223A4622016-08-0909 August 2016 Inspection Planning Considerations for ANO CAL Follow-Up Pkg IR 05000313/20150062016-03-0202 March 2016 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2015006 and 05000368/2015006) IR 05000313/20154012015-09-0101 September 2015 Non-Public Security Inspection Plan for Arkansas Nuclear One(Nrc Physical Security Inspection Report Numbers 05000313/2015401 and 05000368/2015401) IR 05000313/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2015005 and 05000368/2015005) IR 05000313/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Arkansas Nuclear One (NRC Physical Security Inspection Report Numbers 05000313/2014402 and 05000368/2014402) IR 05000313/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2014006 and 05000368/2014006) IR 05000313/20130012014-03-0404 March 2014 Annual Assessment Letter for Arkansas Nuclear One Units 1 and 2 (Report 05000313/2013001 and 05000368/2013001) IR 05000313/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313-13-006 and 05000368-13-006) IR 05000313/20128012013-03-0404 March 2013 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2012801 and 05000368/2012801) IR 05000313/20120062012-09-0404 September 2012 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 & 2 (Reports 05000313-12-006 and 05000368-12-006) IR 05000313/20120012012-03-0505 March 2012 Annual Assessment Letter for Arkansas Nuclear One - Units 1 and 2 (Report 05000313/2012001 and 05000368/2012001) ML1124403662011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan - Arkansas Nuclear One, Units 1 and 2 IR 05000313/20110012011-03-0404 March 2011 Annual Assessment Letter for Arkansas Nuclear One Units 1 & 2 (Report 05000313-11-001 and 05000368-11-001) ML1024305372010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Arkansas Nuclear One IR 05000313/20100012010-03-0303 March 2010 Annual Assessment Letter - Arkansas Nuclear One (Report 05000313-10-001 and 05000368-10-001) 2CAN110904, Snubber Testing Program for Fourth Inspection Interval2009-11-10010 November 2009 Snubber Testing Program for Fourth Inspection Interval ML0924001192009-09-0101 September 2009 9/1/2009 Arkansas Nuclear One 2009 Midcycle Performance Review and Inspection Plan ML0906303132009-03-0404 March 2009 Annual Assessment Letter and Inspection Plan 2008 (NRC Inspection Report 05000313/368-2009001) 2024-01-23
[Table view] Category:Letter
MONTHYEARML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle IR 05000313/20243012023-08-14014 August 2023 Notification of NRC Initial Operator Licensing Examination 05000313/2024301 IR 05000313/20230022023-08-11011 August 2023 Integrated Inspection Report 05000313/2023002 and 05000368/2023002 and Notice of Violation ML23209A6022023-08-0909 August 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk- Informed Completion Times IR 05000416/20230022023-08-0808 August 2023 Integrated Inspection Report 05000416/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200050/2023001 ML23208A2132023-08-0303 August 2023 Regulatory Audit Summary Concerning Review of License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23188A1732023-07-12012 July 2023 Request for Withholding Information from Public Disclosure ML23142A2022023-06-29029 June 2023 Issuance of Amendment Nos. 279 and 332 Emergency Plan Staffing Requirements IR 05000313/20234032023-06-28028 June 2023 Security Baseline Inspection Report 05000313/2023403 and 05000368/2023403 ML23178A0892023-06-26026 June 2023 August 2023 Emergency Preparedness Program Inspection-Request for Information ML23166B0902023-06-21021 June 2023 Request for Relief ANO1 ISI 036 Regarding Volumetric Examination Requirements ML23180A1082023-06-20020 June 2023 ANO Unit 1 SAR Amendment 31, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report IR 05000313/20234012023-06-13013 June 2023 Cyber Security Inspection Report 05000313/2023401 and 05000368/2023401 ML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23121A3012023-05-10010 May 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk - Informed Completion Times ML23114A3572023-05-10010 May 2023 Regulatory Audit Summary Concerning Review of Request for Alternative ANO-CISI-002 Regarding Containment Inservice Inspection Frequency ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000313/20230012023-05-0909 May 2023 Integrated Inspection Report 05000313/2023001 and 05000368/2023001 ML23118A3202023-05-0808 May 2023 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000313;05000368/2023010) IR 05000368/20233012023-05-0101 May 2023 NRC Examination Report 05000368/2023301 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23108A1362023-04-24024 April 2023 Approval of Request for Half-Nozzle Repair of Reactor Vessel Closure Head Penetration No. 46 ML23110A1122023-04-20020 April 2023 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G 2024-01-24
[Table view] |
Text
August 23, 2022 Mr. Joseph Sullivan, Site Vice President Arkansas Nuclear One Entergy Operations, Inc.
N-TSB-58 1448 S.R. 333 Russellville, AR 72802-0967
SUBJECT:
UPDATED INSPECTION PLAN FOR ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 (REPORT 05000313/2022005 AND 05000368/2022005)
Dear Mr. Sullivan:
The enclosed inspection plan lists the inspections scheduled through June 30, 2024, for Arkansas Nuclear One, Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
Beginning on January 1, 2023, the engineering inspection frequency will transition from a triennial (3-year) to a quadrennial (4-year) cycle. The new engineering inspection program will consist of a Comprehensive Engineering Team Inspection (CETI)1 and three Focused Engineering Inspections (FEIs) that will be performed in each quadrennial cycle. For the cycle beginning in 2023, the FEIs will be: Fire Protection Team Inspection, Commercial Grade Dedication and an engineering inspection that reviews age-related degradation and management2.
In response to the COVID-19 public health emergency (PHE), the NRC adjusted inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. While the PHE continues, overall conditions throughout the country support performance of our inspection and oversight activities to return to normal onsite presence by our resident and region-based inspectors and completion of nominal baseline inspection samples. We continue to monitor site-specific conditions and as discussed in our November 2, 2021 memo, Implementation of Inspection Programs Following Re-Entry from the Public Health Emergency for the Reactor Safety Program (ML21295A302), it may be necessary to alter how and when we perform our inspection and oversight activities as 1 Aspects of the Design Basis Assurance Inspection (DBAI), Evaluations of Changes, Tests, & Experiments, and Heat Sink inspections will be included in the CETI inspection. Attached Report 22 will reference DBAI procedure until the CETI procedure is made publicly available. Previously scheduled Evaluation of Changes, Tests, & Experiments and Heat Sink inspections have been cancelled and removed from attached Report 22.
2 The age-related degradation and management procedure is under development and will be publicly available by the end of calendar year 2022.
J. Sullivan 2 we balance the importance of protecting the health and safety of our staff with the need to conduct effective oversight that supports the NRCs critical safety mission.
For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
The Regional Administrator has approved the staffs plan to conduct Inspection Procedure 93812, Special Inspection, at your facility, as indicated in the enclosed inspection plan.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 817-200-1574 with any questions you have regarding this letter.
Sincerely, Signed by Dixon, John on 08/23/22 John L. Dixon, Jr., Chief Projects Branch D Division of Operating Reactor Safety Docket Nos. 05000313, 05000368 License Nos. DPR-51, NPF-6
Enclosure:
Inspection Plan Distribution:
cc w/ encl: Distribution via LISTSERV
ML22229A486 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: Yes No Publicly Available Sensitive NRC-002 OFFICE SPE:DORS/D BC:DORS/D NAME ASanchezJLD for JDixon DATE 8/23/2022 8/23/2022 Site Inspection Activity Plan 07200013 - ANO (ISFSI) 07/01/2022 - 06/30/2024 Unit Start End Activity CAC Title Staff Count ANO ISFSI Inspection for Transition to Holtec FW System (Part 72) (Multiple weeks during timeframe) 4 9/1/2023 10/31/2023 IP 60854 001000 Preoperational Testing Of An ISFSI 9/1/2023 10/31/2023 IP 60855 001001 Operation Of An ISFSI 9/1/2023 10/31/2023 IP 60856 001003 Review of 10 CFR 72.212(b) Evaluations Prepared on 8/17/2022 12:38:51 PM 1 of 4
Site Inspection Activity Plan Arkansas Nuclear One 07/01/2022 - 06/30/2024 Unit Start End Activity CAC Title Staff Count Special Inspection, Security 1 1,2 8/1/2022 8/4/2022 IP 93812 Special Inspection EP 2022 Biennial Exercise & PI Inspection - ANO 4 1,2 8/8/2022 8/12/2022 IP 71114.01 000716 Exercise Evaluation 1,2 8/8/2022 8/12/2022 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 8/8/2022 8/12/2022 IP 71151 001397 Performance Indicator Verification Heat Exchanger/Sink Performance Inspection - 07T - Arkansas Nuclear 2 1,2 8/22/2022 8/26/2022 IP 71111.07T 000700 Heat Exchanger/Sink Performance Security Access Control .02 1 1,2 9/12/2022 9/16/2022 IP 71130.02 000734 Access Control 1,2 9/12/2022 9/16/2022 IP 71130.09 001656 Security Plan Changes 1,2 9/12/2022 9/16/2022 IP 71151 001338 Performance Indicator Verification Target Set Inspection -ANO 1 1,2 9/12/2022 9/16/2022 IP 71130.14 000743 Review of Power Reactor Target Sets ANO 2022 4Q Resident Baseline 5 1,2 10/1/2022 12/31/2022 IP 71151 000746 Performance Indicator Verification Inservice Inspection 1RF30 - ANO 1 1 10/10/2022 10/21/2022 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP 1,3,PI - ANO 2 1,2 10/17/2022 10/21/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 10/17/2022 10/21/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 10/17/2022 10/21/2022 IP 71151 000746 Performance Indicator Verification ANO 2023 1Q Resident Baseline 5 1,2 1/1/2023 3/31/2023 IP 71151 000746 Performance Indicator Verification Cyber Security Inspection - ANO 4 1,2 2/6/2023 2/9/2023 IP 71130.10 000741 Cybersecurity ANO UNIT 2 2023 INITIAL EXAM 4 2 2/12/2023 2/18/2023 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV) 2 3/19/2023 3/25/2023 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
RP 1,4,PI - 2 1,2 3/27/2023 3/31/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 3/27/2023 3/31/2023 IP 71124.04 000728 Occupational Dose Assessment 1,2 3/27/2023 3/31/2023 IP 71151 000746 Performance Indicator Verification Prepared on 8/17/2022 12:38:51 PM 2 of 4
Site Inspection Activity Plan ANO 2023 2Q Resident Baseline 5 1,2 4/1/2023 6/30/2023 IP 71151 000746 Performance Indicator Verification Inservice Inspection 2R29 - ANO 1 2 4/17/2023 4/28/2023 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP 6,7 2 1,2 6/12/2023 6/16/2023 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1,2 6/12/2023 6/16/2023 IP 71124.07 000731 Radiological Environmental Monitoring Program Security Access Authorization .01 - Access Control .02 + PIV + Plan Change .09 2 1,2 6/12/2023 6/16/2023 IP 71130.01 000733 Access Authorization 1,2 6/12/2023 6/16/2023 IP 71130.02 000734 Access Control 1,2 6/12/2023 6/16/2023 IP 71130.09 001656 Security Plan Changes 1,2 6/12/2023 6/16/2023 IP 71151 001338 Performance Indicator Verification ANO 2023 3Q Resident Baseline 5 1,2 7/1/2023 9/30/2023 IP 71151 000746 Performance Indicator Verification ANO UNIT 1 2023 BRQ 3 1 7/9/2023 7/15/2023 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance EP 2023 Program Inspection - ANO 1 1,2 8/28/2023 9/1/2023 IP 71114.02 000717 Alert and Notification System Testing 1,2 8/28/2023 9/1/2023 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 8/28/2023 9/1/2023 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 8/28/2023 9/1/2023 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 8/28/2023 9/1/2023 IP 71151 001397 Performance Indicator Verification Commercial Grade Dedication Inspection - 21N - Arkansas Nuclear 3 1,2 9/11/2023 9/15/2023 IP 71111.21N.03 001808 Commercial Grade Dedication 1,2 9/25/2023 9/29/2023 IP 71111.21N.03 001808 Commercial Grade Dedication ANO 2023 4Q Resident Baseline 5 1,2 10/1/2023 12/31/2023 IP 71151 000746 Performance Indicator Verification FORCE-ON-FORCE PLANNING AND EXERCISE - ANO 4 1,2 11/13/2023 11/17/2023 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1,2 12/11/2023 12/15/2023 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Security FFD .08 1 1,2 11/13/2023 11/17/2023 IP 71130.08 000740 Fitness For Duty Program MC&A - 1 1,2 11/27/2023 12/1/2023 IP 71130.11 000742 Material Control and Accounting (MC&A)
ANO UNIT 1 2024 INITIAL EXAM 7 Prepared on 8/17/2022 12:38:51 PM 3 of 4
Site Inspection Activity Plan 1 2/4/2024 2/10/2024 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV) 1 3/3/2024 3/9/2024 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
Inservice Inspection - ANO (U1) 1 1 4/15/2024 4/26/2024 IP 71111.08P 000702 Inservice Inspection Activities (PWR)