| {{#Wiki_filter:OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION August 25, 2021 Mr. Lance Stephens Richland Site Manager Framatome, Inc. | | {{#Wiki_filter:OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION |
| | |
| | August 25, 2021 |
| | |
| | Mr. Lance Stephens Richland Site Manager Framatome, Inc. |
| 2101 Horn Rapids Road Richland, WA 99354-0130 | | 2101 Horn Rapids Road Richland, WA 99354-0130 |
|
| |
|
Line 23: |
Line 27: |
|
| |
|
| ==Dear Mr. Stephens:== | | ==Dear Mr. Stephens:== |
| | On July 29, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Framatome and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the en closed report. |
| | |
| | No violations of more than minor significance were identified d uring this inspection. |
| | |
| | This letter will be made available for public inspection and co pying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.3 90, Public Inspections, Exemptions, Requests for Withholding. |
| | |
| | The enclosed report contains Security-Related Information, so t he enclosed report will not be made publicly available in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390(d)(1). If you choose to provide a response that con tains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the |
| | |
| | Enclosure(s) transmitted herewith contain(s) SUNSI. When separa ted from enclosure(s), this transmittal document is decontrolled. |
| | |
| | OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION |
| | |
| | L. Stephens 2 |
|
| |
|
| On July 29, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Framatome and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
| | instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390( b)(1)(ii). |
| No violations of more than minor significance were identified during this inspection.
| |
| This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
| |
| The enclosed report contains Security-Related Information, so the enclosed report will not be made publicly available in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the Enclosure(s) transmitted herewith contain(s) SUNSI. When separated from enclosure(s), this transmittal document is decontrolled.
| |
| OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
| |
|
| |
|
| OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION L. Stephens 2 instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
| |
| Sincerely, | | Sincerely, |
| /RA/
| | |
| Eric C. Michel, Chief Projects Branch 2 Division of Fuel Facility Inspection Docket No. 07001257 License No. SNM-1227 | | /RA/ |
| | |
| | Eric C. Michel, Chief Projects Branch 2 Division of Fuel Facility Inspection |
| | |
| | Docket No. 07001257 License No. SNM-1227 |
|
| |
|
| ==Enclosure:== | | ==Enclosure:== |
| | As stated |
|
| |
|
| As stated cc w/o encl: Distribution via LISTSERV OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
| | cc w/o encl: Distribution via LISTSERV |
| | |
| | OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION |
|
| |
|
| ML21237A309 (Cover letter) | | ML21237A309 (Cover letter) |
| Entire Report: Non-Sensitive Publicly Available x SUNSI Review x Sensitive x Non-Publicly Available Cover Letter Only: Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RII/DFFI RII/DRP RII/DFFI NAME M. Romano M. Toth E. Michel DATE 8/20/21 8/23/21 8/23/2021}} | | Entire Report: Non-Sensitive Publicly Available x SUNSI Review x Sensitive x Non-Publicly Available Cover Letter Only: Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RII/DFFI RII/DRP RII/DFFI NAME M. Romano M. Toth E. Michel DATE 8/20/21 8/23/21 8/23/2021}} |
|
---|
Category:Inspection Report
MONTHYEARML24211A0592024-07-29029 July 2024 Framatome Inc. – Physical Security Core Inspection Report 07001257-2024401 Public ML24190A0292024-07-19019 July 2024 Framatome - Richland - Core Inspection Report 07001257/2024002 ML24116A2922024-04-29029 April 2024 Framatome-Richland - Core Inspection Report 07001257/2024001 ML24026A2792024-01-31031 January 2024 Framatome - Richland – Integrated Inspection Report 07001257/2023004 ML23296A0072023-10-25025 October 2023 Framatome-Richland - Core Inspection Report 07001257/2023003 ML23202A2022023-07-24024 July 2023 Framatome Richland Core Inspection Report 07001257/2023002 ML23089A2592023-04-10010 April 2023 2023-001 Framatome-Richland - NRC Integrated Inspection Report 07001257/2023001 ML23030B6172023-01-31031 January 2023 Framatome-Richland - Core Inspection Report 07001257/2022004 ML22291A0342022-10-17017 October 2022 Framatome Inspection Request (2022 Nuclear Criticality and Emergency Preparedness) ML22201A5352022-07-21021 July 2022 Framatome 2022-002 Integrated Quarterly Inspection Report ML22024A2152022-01-25025 January 2022 Framatome, Inc. - Richland, U.S. Nuclear Regulatory Commission Integrated Inspection Report 07001257/2021004 ML21298A2242021-10-25025 October 2021 Framatome-Richland Integrated Inspection Report 07001257/2021003 ML21237A3092021-08-25025 August 2021 Framatome - Material Control and Accounting Program Inspection Report 07001257/2021401 (OUO Removed) ML21221A1852021-08-0606 August 2021 NRC Doc Request Fram OPS-PMA IR 2021-003 ML21189A0042021-07-0707 July 2021 Framatome-Richland Integrated Inspection Report 07001257/2021002 ML21113A2292021-04-23023 April 2021 Framatome - Richland, U.S. Nuclear Regulatory Commission Inspection Report Number 70-1257/2021-001 ML21025A2902021-01-22022 January 2021 Framatome Inc. - U. S. Nuclear Regulatory Commission Integrated Inspection Report 07001257/2020004 ML20303A2512020-10-29029 October 2020 Framatome, Inc. - U.S. Nuclear Regulatory Commission Integrated Inspection Report Number 70-1257/2020-003 ML20302A4312020-10-28028 October 2020 Framatome Inc., U.S. Nuclear Regulatory Commission Inspection Report 2020-401 Public ML20184A2822020-07-0202 July 2020 Framatome Inc., - NRC Integrated Inspection Report 701257/2020001 and 701257/2020-002 ML20030A2612020-01-29029 January 2020 Framatome Quarterly IR 2019-005 ML19301A0762019-10-25025 October 2019 Framatome Inc. - U. S. Nuclear Regulatory Commission Integrated Inspection Report 70-1257/2019-004 ML19214A1162019-08-0202 August 2019 Framatome, Inc., Nuclear Regulatory Commission Integrated Inspection Report 07001257/2019003 ML19109A0022019-04-17017 April 2019 Framatome Quarterly IR 2019-002 ML19025A0172019-01-25025 January 2019 Framatome, Inc. - Nuclear Regulatory Commission Integrated Inspection Report 70-1257/2018-005 ML18297A0902018-10-24024 October 2018 Framatome Quarterly IR 2018-004 ML18200A2402018-07-19019 July 2018 Framatome Inc., - Nuclear Regulatory Integrated Inspection Report 07001257/2018003 ML18110A0232018-04-20020 April 2018 Framatome Inc., - Nuclear Regulatory Commission Integrated Inspection Report 70-1257/2018002 ML18025B2502018-01-25025 January 2018 Framatome Inc., - NRC Integrated Inspection Report 0701257/2017005 ML1100306952010-12-30030 December 2010 IR 70-1257-10-010 & Notice of Violation, on 11/18/10, Areva Np, Inc., Richland 2024-07-29
[Table view] Category:Letter
MONTHYEARML24264A1712024-09-20020 September 2024 Framatome, Inc. - License Amendment Request for TRISO Fuel Production at the Framatome Fuel Fabrication Facility in Richland, Wa ML24211A0592024-07-29029 July 2024 Framatome Inc. – Physical Security Core Inspection Report 07001257-2024401 Public ML24190A0292024-07-19019 July 2024 Framatome - Richland - Core Inspection Report 07001257/2024002 ML24179A1172024-06-27027 June 2024 Framatome-Richland – Inspection Schedule for Calendar Year 2025 ML24116A2922024-04-29029 April 2024 Framatome-Richland - Core Inspection Report 07001257/2024001 ML24092A2752024-04-0303 April 2024 Acceptance for Review of Framatome, Incs Triennial Update to Decommissioning Funding Plan - Enterprise Project Identifier Number L-2024-DFA-0000 ML24065A4842024-03-0808 March 2024 Framatome Inc. - Licensee Performance Review - Nuclear Regulatory Commission Inspection Report 07001257/2024005 ML24026A2792024-01-31031 January 2024 Framatome - Richland – Integrated Inspection Report 07001257/2023004 ML24031A5432024-01-23023 January 2024 Triennial Update to Decommissioning Funding Plan (DFP) for the Framatome Inc., Richland Nuclear Fuel Fabrication Facility Cover Letter ML23352A3912023-12-20020 December 2023 Framatome Inc. - Richland Material Control and Accounting Program Inspection Report 07001257-2023401-Public Cover Letter ML23313A0772023-11-27027 November 2023 Framatome Inc. - Request to Amend License and Approve Criticality Safety Methods - License Amendment 19 (Enterprise Project Identification Number L-2023-LLA-0073) ML23296A0072023-10-25025 October 2023 Framatome-Richland - Core Inspection Report 07001257/2023003 ML23291A2042023-10-18018 October 2023 Framatome Inc., Richland Nuclear Fuel Fabrication Facilitys Request to Amend License No. SNM-1227 and Approval of Criticality Safety Methods ML23255A2892023-09-15015 September 2023 Framatome-Richland – Inspection Schedule for Calendar Year 2024 ML23254A2502023-09-13013 September 2023 Request of Additional Information Letter to Framatome ML23202A2022023-07-24024 July 2023 Framatome Richland Core Inspection Report 07001257/2023002 ML23198A3172023-07-17017 July 2023 Framatome Inc. Richland Nuclear Fuel Fabrication Facilitys Revised Chapter 1 of License No. SNM-1227 ML23144A3092023-06-21021 June 2023 Acceptance Letter for Request by Framatome for a License Amendment for an Approval of Criticality Safety Methods ML23144A3372023-06-12012 June 2023 Letter to Framatome Approval of Request to Withhold Proprietary Information ML23145A3082023-06-0202 June 2023 Framatome - Licensing Project Manager Change Letter ML23137A3962023-05-17017 May 2023 Framatome, Inc., Richland Nuclear Fuel Fabrication Facility’S Request to Amend License No. SNM-1227; and Approval of Criticality Safety Methods ML23137A4062023-05-17017 May 2023 Framatome, Inc., Submittal of NRC Form 327s Which Report the Results of Material Balance Accounting and Seid Calculations for the Period March 22, 2022 to March 20, 2023 ML23089A2592023-04-10010 April 2023 2023-001 Framatome-Richland - NRC Integrated Inspection Report 07001257/2023001 ML23089A2602023-03-30030 March 2023 Framatome, Inc. - 2023 Fee Increase for Fuel Cycle Licensees; License No. SNM-1227; Docket No. 70-1257 ML23054A2562023-02-23023 February 2023 60-Day Report to January 2, 2023, Incident Reported Under 10 CFR 70 Appendix a Concurrent Report (NRC Event No. 56292); Framatome Richland Facility; License No. SNWI-1227; Docket No. 70-1257 ML22336A0992023-02-0303 February 2023 Cover Letter - Framatome Proprietary Approval 3x Letter of Intent Submittals 11/21/2022 and 11/29/2022 ML23030B6172023-01-31031 January 2023 Framatome-Richland - Core Inspection Report 07001257/2022004 ML23025A3172023-01-25025 January 2023 Submittal of Integrated Safety Analysis (ISA) Summary Annual Update for Framatome Inc.S (Framatomes) Richland, Washington Fuel Fabrication Facility ML22341A1562022-12-0707 December 2022 60-day Follow Up Report for an Incident Reported Under 10 CFR 70 Appendix a (C) Concurrent Report (NRC Event No.56713); Framatome Richland Facility ML22272A0252022-10-0404 October 2022 Framatome-Richland -Integrated Inspection Report 07001257/2022003 ML22263A4652022-09-20020 September 2022 Framatome, Inc. Submittal of Revised Fundamental Nuclear Material Control Plan ML22255A0122022-08-31031 August 2022 Framatome Inc. - Required Reporting of Effluents Per 10 CFR 70.59 ML22238A1602022-08-24024 August 2022 Framatome Richland Facility Emergency Plan Version 16.0 ML22236A5872022-08-23023 August 2022 Framatome Inc., Richland Nuclear Fuel Fabrication Facilitys Intent to Amend License No. SNM-1227; ML22201A5352022-07-21021 July 2022 Framatome 2022-002 Integrated Quarterly Inspection Report ML22192A1272022-07-11011 July 2022 Framatome, Inc., 60-day Report for a May 12, 2022 Incident Reported Under 10 CFR 70 Appendix a 24-hour Report (NRC Event No. 55897) ML22154A4382022-07-11011 July 2022 Cover Letter - Framatome Inc. - Request to Amend License and Approve Criticality Safety Methods - License Amendment 18 (Enterprise Project Identification Number L-2021-LLA-0218) ML22187A1892022-06-29029 June 2022 Framatome-Richland - Inspection Schedule for Calendar Year 2023 ML22187A0392022-06-28028 June 2022 Framatome Documentation Request - 2022-003 PMT ML22137A1282022-06-23023 June 2022 Cover Letter - Framatome- DFP Info and Form 327 Proprietary Review ML22166A3432022-06-10010 June 2022 Framatome Lnc., Submittal of Quality Assurance Program, FS1-0011462, Revision 8.0, 10 CFR 71, Subpart H Quality Assurance Program Description for Packaging and Transportation of Radioactive Materials for Us Fuel ML22132A2292022-05-12012 May 2022 Framatome, Inc., Submittal of NRC Form 327 ML22132A2952022-05-12012 May 2022 Framatome, Inc., Submittal of Triennial Update to Decommissioning Funding Plan (DFP) for the Richland Nuclear Fuel Fabrication Facility ML22087A1212022-03-31031 March 2022 Cover Letter Framatome Inc., - Request for Additional Information Regarding License Amendment Request for Approval of Criticality Safety Methods (Enterprise Project Identification Number L-2021-LLA-0218) ML22059A7582022-03-0303 March 2022 Framatome, Inc., Licensee Performance Review (Nuclear Regulatory Commission Inspection Report 0701257/2022005) ML22060A1262022-03-0101 March 2022 60-day Report to January 4, 2022 Incident Reported Under 10 CFR 70 Appendix a Concurrent Report (NRC Event No. 55686); Framatome Richland Facility; License No. SNM-1227; Docket No. 70-1257 ML22066B2732022-02-28028 February 2022 Framatome, Inc. - Required Reporting of Effluents Per 10 CFR 70.59 for July-December 2021 ML22033A1722022-01-27027 January 2022 Framatome, Inc. Richland Washington Fuel Fabrication Facility Submittal of Update to Integrated Safety Analysis (ISA) ML22025A3902022-01-25025 January 2022 60-day Report to January 4, 2022 Incident Reported Under 10 CFR 70 Appendix a Concurrent Report (NRC Event No. 55686); Framatome Richland Facility ML22024A2152022-01-25025 January 2022 Framatome, Inc. - Richland, U.S. Nuclear Regulatory Commission Integrated Inspection Report 07001257/2021004 2024-09-20
[Table view] |
Text
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
August 25, 2021
Mr. Lance Stephens Richland Site Manager Framatome, Inc.
2101 Horn Rapids Road Richland, WA 99354-0130
SUBJECT:
FRAMATOME - MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION REPORT 07001257/2021401
Dear Mr. Stephens:
On July 29, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Framatome and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the en closed report.
No violations of more than minor significance were identified d uring this inspection.
This letter will be made available for public inspection and co pying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.3 90, Public Inspections, Exemptions, Requests for Withholding.
The enclosed report contains Security-Related Information, so t he enclosed report will not be made publicly available in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390(d)(1). If you choose to provide a response that con tains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the
Enclosure(s) transmitted herewith contain(s) SUNSI. When separa ted from enclosure(s), this transmittal document is decontrolled.
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
L. Stephens 2
instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390( b)(1)(ii).
Sincerely,
/RA/
Eric C. Michel, Chief Projects Branch 2 Division of Fuel Facility Inspection
Docket No. 07001257 License No. SNM-1227
Enclosure:
As stated
cc w/o encl: Distribution via LISTSERV
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
ML21237A309 (Cover letter)
Entire Report: Non-Sensitive Publicly Available x SUNSI Review x Sensitive x Non-Publicly Available Cover Letter Only: Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RII/DFFI RII/DRP RII/DFFI NAME M. Romano M. Toth E. Michel DATE 8/20/21 8/23/21 8/23/2021