July 6, 2022 Mr. Lance Stephens Site Manager Framatome Inc.

2101 Horn Rapids Road Richland, WA 99354

SUBJECT:

FRAMATOME-RICHLAND - INSPECTION SCHEDULE FOR CALENDAR YEAR 2023

Dear Mr. Stephens:

Enclosed is the schedule of inspections to be performed by the U.S. Nuclear Regulatory Commission (NRC) inspectors at the Framatome-Richland facility in calendar year 2023. The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues, well in advance of inspector arrival onsite.

Please note that any regional initiative or reactive inspections are not included in the schedule.

If circumstances arise which cause the NRC inspectors to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact Cynthia Taylor (404) 997-4480 with any questions or concerns you may have regarding this letter or the inspection schedule.

This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html, and at the NRC Public Document Room, in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Eric C. Digitally signed by Eric C. Michel Michel Date: 2022.07.06 13:16:42 -04'00' Eric C. Michel, Chief Projects Branch 2 Division of Fuel Facility Inspection Docket No. 07001257 License No. SNM-1227

Enclosure:

As stated cc w/ encl: Distribution via LISTSERV

L. Stephens 2

SUBJECT:

FRAMATOME-RICHLAND - INSPECTION SCHEDULE FOR CALENDAR YEAR 2023 DISTRIBUTION:

A. Masters, RII/DFFI A. Rivera-Varona, NMSS/DFM C. Taylor, RII/DFFI G. Goff, RII/DFFI E. Michel, RII/DFFI J. Rubenstone, NMSS/DFM J. Worosilo, RII/DRS/PSB J. Zimmerman, NMSS/DFM K. Everly, NSIR/DSO R. Jervey, NMSS/DFM

2023 U.S. NUCLEAR REGULATORY COMMISSION INSPECTION/ACTIVITY PLAN FOR FRAMATOME-RICHLAND Dates Number of Description/Inspection Procedures (IPs)

Inspectors April 25 - 27 3 Evaluation of Exercises and Drills (IP 88051)

May 15 - 18 1 Nuclear Criticality Safety 1 (IP 88015)

June 12 - 15 2 Operational Safety 1 (IP 88020)

July 17 - 20 2 Fire Protection (IP 88055)

September 11 - 14 2 Material Control and Accounting (Various IPs) 2 Nuclear Criticality Safety 2 (IP 88015)

October 23 - 26 Plant Modifications - Annual (IP 88070)

November 13 - 16 2 Operational Safety 2 (IP 88020)