Monthly Operating Rept for Nov 1996 for Fermi 2
ML20132B921
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 11/30/1996
From: Giles H, Smith P
DETROIT EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
CON-NRC-96-0139, CON-NRC-96-139 NUDOCS 9612180010
Download: ML20132B921 (4)


Text

_ . . _ . . __.. . . .

. .1

~

pr ,

4 IrOlt r.rmi2

~

S O n E*I!lE #*I'i o"#ci ,

perations 4

Reg. Guide 1.16 s

December 13,1996 NRC-96-0139 l

U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D. C. 20555 i

Reference:

Fermi 2 NRC Docket No. 50-341 j NRC Operating License No. NPF-43 L

l

Subject:

Monthly Operating Status Report for November.1996 h

Enclosed for your information and use is the Fermi 2 Monthly Operating Status l

Report for November,1996. This report 'ncludes the Operating Data Report,

Average Daily Unit Power Level, and the Summary of Unit Shutdowns and
Power Reductions identified in NRC Regulatory Guide 1.16 and Fermi 2 4 Technical Specification 6.9.1.6.

! If you have any questions, please contact Harry Giles, at (313) 586-1522.

i 4

i-Sincerely,

/1 Peter W. Smith Director- Nuclear Licensing V

Enclosure /

cc: A. B. Beach D. R. Hahn M. J. Jordan i

A. J. Kugler A. Vegel M. V. Yudasz, Jr.

!(I M0082 Region III 9612180010 961130 PDR ADOCK 05000341 R PDR

.)

\o s

OPERATING DATA REPORT DOCKET NO. 50-341 COMPLETED BY H. r Giles DATE December 13.1996 TELEPHONE (313): ' '522 OPERATING STATUS

1. Unit name: Fermi ", Notes: (1) Calculated using weighted
2. Reporting period: November.1996 averages to reflect variations in rating
3. Licensed thermal power (MWt): 3430 (MDC and DER).
4. Nameplate rating (Gross MWe): 1179 Nameplate and DER ratings reflect 98%
5. Design elect rating (Net MWe): 1116 CTP due to turbine throttle valve
6. Max dependable cap (Gross MWe): 924 limitations.
7. Max dependable cap (Net MWe): 876 Scheduled 53 refuel outage extended due to EDG 11 Automatic Voltage Regulator Failure.
8. If changes occur in capacity ratings (Items number 3 through 7) since last report, give reasons:

N/A

9. Power level to which restricted, if any (MWe Net): N/A
10. Reasons for restriction, if any: N/A THIS MONTH YEAR TO CUMULATIVE DATE
11. Hours in reporting period 720 8.040 77.630
12. Hours reactor was critical 3]A 5.944.8 54.296.4
13. Reactor reserve shutdown hours 0 0 0
14. Hours generator on-line Q 5.859.7 51.496.0
15. Unit reserve shutdown hours Q Q Q
16. Gross thermal energy gen (MWH) Q 18.224.208 157.835.411
17. Gross elect energy gen (MWH) Q 5.058.970 50.449.487
18. Net Elect energy gen (MWH) Q 4.790.020 48.155.489
19. Unit service factor QA 72.9 66.3
20. Unit availability factor 0_A 72.9 66.3
21. Unit cap factor (using MDC net) 0_A 68.0 60.1 (1)
22. Unit cap factor (using DER net) Q 53.4 56.2 (1)
23. Unit forced outage rate 100.0 13.4 20.6
24. Shutdowns scheduled over next 6 months (Type, Date, Duration of each): None
25. If shutdown at end of report period, estimated date of startup: December 19.1996
26. Units in test status (prior to commercial operation): N/A FORECAST ACHIEVED Initial Criticality N/A N/A Initial Electricity N/A N/A l Commercial Operation NLA N/A l 1

4 p' < ,

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-341 UNIT Eermi 2 DATE December 13.1996 COMPLETED BY H. B. Giles TELEPHONE (313) 586-1522 Month November.1996 DAY AVERAGE DAILY DAY AVERAGE DAILY POWER POWER LEVEL LEVEL (MWe-Net) (MWe-Net) 1 0 16 0 l

2 0 17 0 3 0 18 0 4 0 19 0 5 0 20 0

, 6 0 21 0 7 0 22 0 8 0 23 0 9 0 24 0

., 10 0 25 0 11 0 26 0 12 0 27 0 13 0 28 0 14 0 29 0 15 0 30 0

~.  :

UNIT SIIUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-341 DATE December 13.1996 ',

UNIT NAME Fermi 2 COMPLETED BY H. B. Giles .

1 TELEPHONE (313) 586-1522 REPORT MONTH November.1996 r

No. (6) Date TYPE Dur(Hrs) Reason (2) Method of LER Sys Code (4) Comp Cause and Corrective Action to (1) shutting down No. Code Prevent Recurrence reactor or (5) reducing power (3)

S96-02 960927 S 447.5 C 4 N/A N/A N/A Unit shutdown to continue -

Refueling Outage No. 5.

S96-03 961120 F 272.5 A 4 N/A EK RG Unit remained shutdown beyond  !

the 53 day scheduled refuel outage due to EDG 11 Automatic Voltage Regulator Failure.  ;

(1) F: Forced (2) REASON: (3) METHOD: (4) Instructions for preparation ofdata entry ,

S: Scheduled A - Equipment Failure (Explain) 1 - Manual sheets for Licensee Event Report (LER) file ,

B - Maintenance or Test 2 - Manual Scram (NUREG-1022) ,

I C - Refueling 3 - Automatic Scram (5) Same Source as (4)

D - Regulatory Restriction 4 - Continued (6) R - Prefix indicates power reduction.

E - Operations Training and License 5 - Reduced Load S - Prefix indicated plant shutdown.

Examination 9 - Other (7) Duration of reductions reported as zero per  ;

F- Administrative Regulatory Guide 1.16, Revision 4.

G - Operational Error (Explain) ,

H - Other (Explain)