Revised Monthly Operating Rept for June 1996 for Fermi 2
ML20134L798
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 06/30/1996
From: Giles H
DETROIT EDISON CO.
To:
Shared Package
ML20134L775 List:
References
NUDOCS 9702190291
Download: ML20134L798 (1)


Text

.

OPERATING DATA REPORT DOCKET NO. 50-341 COMPLETED BY H. B. Giles DATE July 15.1996 TELEPHONE (313) 586-1522 OPERATING STATUS 1.

Unit name: Fermi 2 NOTES: (1) Calculated using weighted averages to reflect variations in rating (MDC

]

and DER). (2) As of 06/21/96, limiting power l

2.

Reporting period: June.1996 to 91% CTP maximum due to main turbine 3.

Lice 1 sed thermal power (MWt): 3430 bearing vibrations.

4.

Nameplate rating (Gross MWe): 1179 Nameplate and DER ratings reflect 98% CTP 5.

Design elect rating (Net MWe): 1116 due to turbine throttle valve limitations.

6.

Max dependable cap (gross MWe): 924 7.

Max dependable cap (Net MWe): 876 8.

If changes occur in capacity ratings (Items number 3 through 7) since last report, give reasons:

4 N/A 9.

Power level to which restricted, if any (MWe Net):

(2)

10. Reasons for restriction, if any:

(2) j i

THIS MONTH YEAR TO CUMULATIVE DATE 11.

Hours in reporting period 720 4.367 73.957 12.

Hours reactor was critical 720 3.779.5 52.131.1 l

13.

Reactor reserve shutdown hours 9

Q Q

14.

Hours generator on-line L2Q 3.732.2 49.368.5 15.

Unit reserve shutdown hours Q

Q Q

16.

Gross thermal energy gen (MWH) 2.222.088 11.960.712 151.571.915 17.

Gross elect energy gen (MWH) 616.350 L3_27.090 48.717.607 l

1 18.

Net Elect energy gen (MWH) 582.006 3.161.287 46.526.756 19.

Unit service factor 100.0 85.5 66.8 20.

Unit availability factor 100.0 85.5 66.8 4

21.

Unit cap factor (using MDC net) 92.3 82.6 60.5 (1) 22.

Unit cap factor (using DER net) 72.4 64.9 57.0 (1) 23.

Unit forced outage rate Q

14.5 20.9

24. Shutdowns scheduled over next 6 months (Type, Date, Duration of each): Refuel. Sect. 27.

1996. 52 days

25. If shutdown at end of report period, estimated date of startup: N/A 2
26. Units in test status (prior to commercial operation): N/A FORECAST ACHIEVED 4

Initial Criticality N/A N/A Initial Electricity N/A N/A Commercial Operation N/A N/A l