ML20205Q960
| ML20205Q960 | |
| Person / Time | |
|---|---|
| Site: | Fermi |
| Issue date: | 12/31/1997 |
| From: | Burr L DETROIT EDISON CO. |
| To: | |
| Shared Package | |
| ML20205P970 | List: |
| References | |
| NUDOCS 9904220136 | |
| Download: ML20205Q960 (1) | |
Text
.
(['.
l OPERATING DATA REPORT DOCKET NO. 50-341 COMPLETED BY L. Burr DATE April 15.1999 TELEPHONE (734) 586-1525
)
i OPERATING STATUS 1.
Unit name: Fermi 2 Notes: (1) Calculated using weighted 2.
Reporting period: December 1997 averages to reflect variations in rating 3.
Licensed thermal power (MWt): 3430 (MDC and DER) from initial commercial 4.
Nameplate rating (Gross MWe): 1215 (3) operation. (2) Design electrical rating
{
5.
Design elect rating (Net MWe): 1116 (2) reflects 96% reactor power, pending
{
6.
Max dependable cap (Gross MWe): 1123 completion of Power Uprate Program 7.
Max dependable cap (Net MWe): 1074 Testing. (3) General Electric Company Alsthom instruction manual.
8.
If changes occur in capacity ratings (Items number 3 through 7) since last report, give reasons:
MDC cross and net updated based upon analysis of data collected at 96% reactor power operation.
9.
Power level to which restricted, if any (MWe Net):
(2)
- 10. Reasons for restriction,if any:
(2)
THIS MONTH YEAR TO CUMULATIVE DATE 11.
Hours in reporting period 744 DiQ 87.134 12.
Hours reactor was critical 744 5.830.2 60.254.9 13.
Reactor reserve shutdown hours Q
g Q
14.
Hours generator on-line 744 5.461.7 56.957.7 15.
Unit reserve shutdown hours Q
Q g
16.
Gross thermal energy gen (MWH) 2.349.024 16.983.624 174.819.035 17.
Gross elect energy gen (MWH) 824.480 5.830.620 56.279.107 18.
Net Elect energy gen (MWH) 792.337 5.579.948 53.735.437 19.
Unit service factor 100.0 62.3 65.4 20.
Unit availability factor 100.0 62.3 65.4 21.
Unit cap factor (using MDC net) 99.2 64.5 60.1 (1) l 22.
Unit cap factor (using DER net) 95.4 57.1 55.8(1) 23.
Unit forced outage rate Q
33.6 22.8
- 24. Shutdowns scheduled over next 6 months (Type, Date, Duration of each): N/A
- 25. If shutdown at end of report period, estimated date of startup: N/A
- 26. Units in test status (prior to commercial operation): N/A l
9904220136 990415 l
PDR ADOCK 0500034?.
R PDR
,