MONTHYEARNRC-99-0095, Monthly Operating Rept for Sept 1999 for Fermi 2.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Fermi 2.With NRC-99-0067, Monthly Operating Rept for Aug 1999 for Fermi 2.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Fermi 2.With NRC-99-0065, Monthly Operating Rept for July 1999 for Fermi 2.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Fermi 2.With NRC-99-0064, Monthly Operating Rept for June 1999 for Fermi 2.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Fermi 2.With NRC-99-0062, Monthly Operating Rept for May 1999 for Fermi 2.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Fermi 2.With NRC-99-0022, Monthly Operating Rept for Apr 1999 for Fermi 2.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Fermi 2.With ML20205P9721999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Fermi 2 ML20204D0361999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Fermi 2 ML20205Q9621998-12-31031 December 1998 Revised Monthly Operating Rept for Dec 1998 for Fermi 2 NRC-99-0005, Monthly Operating Rept for Dec 1998 for Fermi 2.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Fermi 2.With NRC-98-0153, Monthly Operating Rept for Nov 1998 for Fermi 2.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Fermi 2.With NRC-98-0160, Monthly Operating Rept for Oct 1998 for Fermi 2.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Fermi 2.With NRC-98-0139, Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With NRC-98-0111, Monthly Operating Rept for Aug 1998 for Fermi 2.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Fermi 2.With NRC-98-0109, Monthly Operating Rept for July 1998 for Fermi 21998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Fermi 2 NRC-98-0097, Monthly Operating Rept for June 1998 for Fermi,Unit 21998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Fermi,Unit 2 NRC-98-0079, Monthly Operating Rept for May 1998 for Fermi 21998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Fermi 2 NRC-98-0076, Monthly Operating Rept for Apr 1998 for Fermi 21998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Fermi 2 NRC-98-0072, Monthly Operating Rept for Mar 1998 for Fermi 21998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Fermi 2 NRC-98-0050, Monthly Operating Rept for Feb 1998 for Fermi 21998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Fermi 2 NRC-98-0019, Monthly Operating Rept for Jan 1998 for Fermi 21998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Fermi 2 ML20205Q9601997-12-31031 December 1997 Revised Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-98-0015, Monthly Operating Rept for Dec 1997 for Fermi 21997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-97-0131, Monthly Operating Rept for Nov 1997 for Fermi 21997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Fermi 2 NRC-97-0117, Monthly Operating Rept for Oct 1997 for Fermi 21997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Fermi 2 NRC-97-0099, Monthly Operating Rept for Sept 1997 for Fermi 21997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Fermi 2 ML20210V0441997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Fermi 2 ML20210V0521997-07-31031 July 1997 Revised MOR for July 1997 for Fermi 2 NRC-97-0079, Monthly Operating Rept for Jul 1997 for Fermi 21997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Fermi 2 NRC-97-0068, Monthly Operating Rept for June 1997 for Fermi,Unit 21997-06-30030 June 1997 Monthly Operating Rept for June 1997 for Fermi,Unit 2 NRC-97-0063, Monthly Operating Rept for May 1997 for Fermi 21997-05-31031 May 1997 Monthly Operating Rept for May 1997 for Fermi 2 NRC-97-0057, Monthly Operating Rept for Apr 1997 for Fermi 21997-04-30030 April 1997 Monthly Operating Rept for Apr 1997 for Fermi 2 NRC-97-0044, Monthly Operating Rept for Mar 1997 for Fermi 21997-03-31031 March 1997 Monthly Operating Rept for Mar 1997 for Fermi 2 NRC-97-0023, Monthly Operating Rept for Feb 1997 for Fermi 21997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Fermi 2 ML20134L7851997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for Fermi 2 ML20134L8421996-12-31031 December 1996 Revised Monthly Operating Rept for Dec 1996 for Fermi 2 NRC-97-0011, Monthly Operating Rept for Dec 1996 for Fermi 21996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Fermi 2 ML20134L8381996-11-30030 November 1996 Revised Monthly Operating Rept for Nov 1996 for Fermi 2 NRC-96-0139, Monthly Operating Rept for Nov 1996 for Fermi 21996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Fermi 2 ML20134L8301996-10-31031 October 1996 Revised Monthly Operating Rept for Oct 1996 for Fermi 2 NRC-96-0102, Monthly Operating Rept for Oct 1996 for Fermi 21996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Fermi 2 ML20134L8221996-09-30030 September 1996 Revised Monthly Operating Rept for Sept 1996 for Fermi 2 NRC-96-0080, Monthly Operating Rept for Sept 1996 for Fermi 21996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Fermi 2 ML20134L8081996-08-31031 August 1996 Revised Monthly Operating Rept for Aug 1996 for Fermi 2 NRC-96-0077, Monthly Operating Rept for Aug 1996 for Fermi 21996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Fermi 2 ML20134L8011996-07-31031 July 1996 Revised Monthly Operating Rept for Jul 1996 for Fermi 2 NRC-96-0073, Monthly Operating Rept for Ju1 1996 for Fermi 21996-07-31031 July 1996 Monthly Operating Rept for Ju1 1996 for Fermi 2 ML20134L7981996-06-30030 June 1996 Revised Monthly Operating Rept for June 1996 for Fermi 2 NRC-96-0070, Monthly Operating Rept for June 1996 for Fermi 21996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Fermi 2 ML20134L7911996-05-31031 May 1996 Revised Monthly Operating Rept for May 1996 for Fermi 2 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217N4381999-10-25025 October 1999 Safety Evaluation Supporting Amend 17 to License DPR-9 ML20217P3551999-10-22022 October 1999 LER 99-S01-00:on 990922,loaded 9mm Handgun Was Discovered on Truck Cargo Area of Vehicle Inside Protected Area.Caused by Inadequate Vehicle Search.Guidance in Procedures & Security Training to Address Multiple Vehicle Searches Was Provided NRC-99-0095, Monthly Operating Rept for Sept 1999 for Fermi 2.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Fermi 2.With NRC-99-0067, Monthly Operating Rept for Aug 1999 for Fermi 2.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Fermi 2.With NRC-99-0065, Monthly Operating Rept for July 1999 for Fermi 2.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Fermi 2.With NRC-99-0088, Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with1999-06-30030 June 1999 Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with NRC-99-0064, Monthly Operating Rept for June 1999 for Fermi 2.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Fermi 2.With NRC-99-0062, Monthly Operating Rept for May 1999 for Fermi 2.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Fermi 2.With ML20206J9301999-05-10010 May 1999 SER Concluding That Util Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Powered-Operated Gate Valves ML20206G5081999-05-0505 May 1999 Safety Evaluation Approving Request for Relief PR-8,Rev 2 on Basis That Licensee Committed to Meet All Related Requirements of ASME OM-6 Std & PR-12 on Basis That Proposed Alternative Will Provide Acceptable Level of Safety NRC-99-0022, Monthly Operating Rept for Apr 1999 for Fermi 2.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Fermi 2.With ML20205Q7141999-04-15015 April 1999 Safety Evaluation Supporting Amend 16 to License DPR-9 ML20205P9721999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Fermi 2 ML20204E0371999-03-17017 March 1999 Safety Evaluation Accepting Licensee Request for NRC Approval of Alternative Rv Weld Exam,Per Provisions of 10CFR50.55a(a)(3)(i) & 10CFR50.55a(g)(6)(ii)(A)(5) for Plant,Unit 2 for 40-month Period ML20204D0361999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Fermi 2 ML20198S3341999-01-0606 January 1999 Safety Evaluation Supporting Amend 15 to License DPR-9 NRC-99-0005, Monthly Operating Rept for Dec 1998 for Fermi 2.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Fermi 2.With ML20207B7491998-12-31031 December 1998 1998 Annual Operating Rept for Fermi 2 ML20205Q9621998-12-31031 December 1998 Revised Monthly Operating Rept for Dec 1998 for Fermi 2 NRC-99-0021, 1998 Annual Financial Rept for Detroit Edison Co. with1998-12-31031 December 1998 1998 Annual Financial Rept for Detroit Edison Co. with NRC-98-0153, Monthly Operating Rept for Nov 1998 for Fermi 2.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Fermi 2.With NRC-98-0160, Monthly Operating Rept for Oct 1998 for Fermi 2.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Fermi 2.With ML20154R2331998-10-21021 October 1998 Safety Evaluation Supporting Amend 13 to License DPR-9 ML20154L1031998-10-14014 October 1998 Safety Evaluation Accepting Licensee Response to NRC Bulletin 95-002, Unexpected Clogging of Residual Heat Removal Pump Strainer While Operating in Suppression Pool Cooling Mode NRC-98-0139, Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With ML20154H8161998-09-30030 September 1998 Rev 0 to COLR Cycle 7 for Fermi 2 ML20153B8811998-09-18018 September 1998 Safety Evaluation Accepting Request for Relief from Certain Requirements of ASME Boiler & Pressure Vessel Code,Section Xi,For Plant,Unit 2 ML20151X0651998-09-11011 September 1998 Safety Evaluation Re Inservice Testing Program Relief Request VR-63 for Plant NRC-98-0111, Monthly Operating Rept for Aug 1998 for Fermi 2.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Fermi 2.With ML20153B7921998-08-31031 August 1998 Rev 0 to Fermi 1 Sar ML20237E1171998-08-25025 August 1998 Safety Evaluation Accepting Licensee Relief Requests for First 10-yr Interval Inservice Insp Nondestructive Exam Program ML20236X8611998-08-0505 August 1998 SER Related to Revised Feedwater Nozzle Analysis to Facility Operating License NPF-43,Enrico Fermi Nuclear Power Plant, Unit 2 NRC-98-0109, Monthly Operating Rept for July 1998 for Fermi 21998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Fermi 2 ML20236K3261998-07-0101 July 1998 SER Accepting Licensee Response Related to Revised Feedwater Nozzle Analysis to License NPF-43 for Enrico Fermi Nuclear Power Plant,Unit 2 NRC-98-0097, Monthly Operating Rept for June 1998 for Fermi,Unit 21998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Fermi,Unit 2 NRC-98-0127, Annual Rept for Period 970701-9806301998-06-30030 June 1998 Annual Rept for Period 970701-980630 NRC-98-0079, Monthly Operating Rept for May 1998 for Fermi 21998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Fermi 2 NRC-98-0076, Monthly Operating Rept for Apr 1998 for Fermi 21998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Fermi 2 NRC-98-0072, Monthly Operating Rept for Mar 1998 for Fermi 21998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Fermi 2 NRC-98-0050, Monthly Operating Rept for Feb 1998 for Fermi 21998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Fermi 2 NRC-98-0019, Monthly Operating Rept for Jan 1998 for Fermi 21998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Fermi 2 ML20198L4241998-01-0808 January 1998 Safety Evaluation Accepting Proposed Rev 2 to Relief Request VR-51 Under Fermi 2 Pump & Valve Inservice Testing Program Per 10CFR50.55a(f)(6)(i) for First 10-yr Interval NRC-98-0015, Monthly Operating Rept for Dec 1997 for Fermi 21997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Fermi 2 ML20217N3821997-12-31031 December 1997 Annual Operating Rept for 970101-1231 NRC-98-0053, 1997 Annual Financial Rept for Detroit Edison Company1997-12-31031 December 1997 1997 Annual Financial Rept for Detroit Edison Company ML20205Q9601997-12-31031 December 1997 Revised Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-97-0141, Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility1997-12-23023 December 1997 Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility ML20197A9921997-12-15015 December 1997 Rev 0 to Efp,Unit 1 Fermi 1 Sar NRC-97-0131, Monthly Operating Rept for Nov 1997 for Fermi 21997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Fermi 2 ML20248H1151997-10-31031 October 1997 Rev 1 to Colr,Cycle 6 for Fermi 2 1999-09-30
[Table view] |
Text
- -~- - - -
- j. - '
- . -;; Drugtss R.O pson Senior Vce President l Nuclear Generation Fermi 2 r
NRC-95-0060 t-i U.- S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555
Reference:
Fermi 2 '
NRC Docket No. 50-341 l
WRC Operating License No. NPF-43 l
Subject:
Monthly Operating Status Report for May. 1995 i
Enclosed for your information and use is the Fermi 2 Monthly i Operating Status Report for May, 1995. .This report includes i the Operating Data Report, Average Daily Unit Power Level, and ,
'the Summary of Unit Shutdowns and Power Reductions identified ;
'in NRC Regulatory Guide 1.16 and Feral 2 Technical. '
Specification 6.9.1.6. :
If you have any questions, please contact Brian Stone, at. .I (313) 586-5148. I Sincerely, Enclosure l cc: T. G. Colburn D. R. Hahn J. B. Martin
'M. P. Phillips P. L. Torpey n A.- Vegel Region III A K 0341 R PDR / di
/ -
a F
...:-.. . = - -
v.
l%
OPERATING DATA REPORT DOCKET NO. 50-341 COMPLETED BY B. J. Stone DATE June 15,~1995 TELEPHONE (313) 586-5148 OPERATING STATUS ;
- 1. UNIT NAME:- ' Fermi 2 l Notes: (1) Calculated using weight-l.
l
- 2. REPORTING PERIOD: May, 1995- .l ed averages to reflect variations l' 3 LICENSED THERMAL POWER (MWt): 3430 l in rating (MDC and DER). l
~
- 4. NAMEPLATE RATING (GROSS We): 1179 l (2) Currently. limiting power to l l
- 5. DESIGN ELECT RATING (Net MWe): 1116 l 96% CTP maximum for Startup Test l 4
- 6. MAX DEPENDABLE CAP (GROSS MWe):1132 l Program. All ratings reflect 98%. l 7 MAX D2PENDABLE CAP (Net Me):1085 l CTP due.to. turbine throttle valve l-l-limitations. l
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7)'SINCE LAST REPORT, GIVE REASONS: N/A 9 POWER LEVEL TO WHICH RESTRICTED, IF ANY (We Net):' 965 CTP/3293 MWT
- 10. REASONS FOR RESTRICTION, IF ANY: (2)
THIS MONTH YR TO DATE CUMULATIVE
- 11. HRS IN REPORTING PERIOD 744 3,623' 64,453 ,
- 12. HRS REACTOR WAS CRITICAL 673.5 2,754.5 43,490.1
- 13. REACTOR RESERVE SHUTDOWN HRS 0 0 0 i
- 14. HOURS GENERATOR ON-LINE 626.7 -1,780.6 40,833 0
- 15. UNIT RESERVE' SHUTDOWN HOURS 0 0 0
- 16. GROSS THERMAL ENERGY GEN (MWH) 1,675,272 -4,486,440 124,200,491 ,
- 17. GROSS ELECT ENERGY GEN (WH) 457,640 1,111,020 41,084,977
- 18. NET ELECT ENERGY GEN (MWH) 430.594 1,040,277- 39,273,992 l
- 19. UNIT SERVICE FACTOR 84.2 47.2 63.4
'20. UNIT AVAILABILITY FACTOR 84.2 47.2 63.4
- 21. UNIT CAP FACTOR (USING MDC NET) 53 3 26.5 56.7
- 22. UNIT CAP FACTOR (USING DER NET) 51.9 25.7 55 3
- 23. UNIT FORCED OUTAGE RATE 15.8 49.7 22 9 l
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, DURATION OF EACH):
- 25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
FORECAST ACHIEVED INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A a r w,n-.- ---,,,,.,e.n- -
,, ---,,--n, e --ee
1..
\
- 0 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-341
' UNIT FERMI 2 DATE June 15, 1995
- COMPLETED BY B. Stone TELEPHONE (313) 586-5148 4 Month May, 1995 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) .(MWe-Net) 1 0 17 786 2 0 18 785
, 3 0 19 785-4 ,
0 20 785 5 0 21 785
- 6. 149 22 781 7 149 23 794 8 211 24 815-9 376 25 824 10 442 26 837 11 788 27 850 12 789 28 847 13 660 __ 29 850 14 SS7 30. 850 15 789 31. 857 16 788
.... .- . - . .. < . . .m .. , . . - -
Jr .i
.Wy ..g I: _ s
' UNIT SHUTDOWNS AND.POWEII(LEDUCTIONS DATE
- DOCKET NO. 50-341 June 15. 1995 UNIT NAME Fermi 2 COMPLETED BV' B. J. Stone TELEPHONE (313) 586-$148
-REPORT MONTH May. ~1995 1 METHOD OF SHUTTING DOWN .LER 5YS COMP CAUSE & CORRECTIVE NO .- DATE TYPE DUR ' REASON THE REACTOR NO. , CODE CODE ACTION TO PREVENT (1)
(HRS) (2) OR REDUCING (4) -(5) RECURRENCE -
(6) (7) POWER (3)
S95-09 950425 F 117.3 A 3 L95-005 JJ RG Automatic reactoe scram on APRM . l (B)- I neutron upscale trip resulting from l reactor' pressure rogulator.
I transient; Reactor restart 5/3/95.
R95-10 950513 F 27.5 8 5 N/A SG COND Recuced reactor power ~ to 50% to-repair tube leaks in main concenser.
I.
(1) F: FORCED (2) REASON: . (3) METHODS. (4) INSTRUCTIONS FOR S: SCHEDULED A - EQUIPMENT FAILURE (EXPLAIN) s 1 - MANUAL PREPARATION OF DATA S - MAINTENANCE OR TEST 2 - MANUAL 1 SCRAM ^ ENTRY SHEETS FOR LICENSEE
, C --REFUELING . 3 - AUTOMATIC SCRAM EVENT REPORT (LER) FILE:
D - REGULATORY RESTRICTION 4 - CONTINUED (NUREG-1022)
E - OPERATOR TRAINING & LICENSE EXAMINATION 5 - REDUCED LOAD F - ADMINISTRATIVE . 9 - OTHER G - OPERATIONAL ERROR (EXPLAIN)
H- OTHER (EXPLAIN) (5).SAME SOURCE AS (4)
(6) R' - PREFIX INDICATES POWEF c .t<LDUCTION.
5 - PREFIX INDICATES PLANT SHUTDOWN.
p (7) DURATION OF, REDUCTION $'.
REPORTED AS ZERO PER REG.
-GUIDE 1.16 REv. 4
"(8) UNIT RESTART MAY 3 AND.
3 TURBINE ON LINE MAY 5; 2 1995.
(8) OUTAGE HOURS ARE A CONTINUATION OF THE O' TAGE j~ WHICH BEGAN 04/25/95.
LREACTOR' CRITICAL 05/03/95
-TURBINE ON LINE 05/05/95.
4 4
- . . . - - - .- . .- . _ _ _