SLR - Schedule Change Letter
ML25203A012
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 08/07/2025
From: Michele Sampson
NRC/NRR/DNRL
To: Coffey R
Florida Power & Light Co
References
EPID L-2020-SLR-0002, EPID L-2020-SLE-0002
Download: ML25203A012 (1)


Text

Robert Coffey Executive Vice President, Nuclear Division and Chief Nuclear Officer Florida Power & Light Company 700 Universe Blvd.

Mail Stop: EX/JB Juno Beach, FL 33408

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - SCHEDULE REVISION FOR THE SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW (EPID NOS. L-2020-SLR-0002 AND L-2020-SLE-0002) (DOCKET NUMBERS: 50-266 AND 50-301)

Dear Robert Coffey:

By letter dated November 16, 2020 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML20329A292), as supplemented by letters dated April 21, 2021 (ML21111A155), May 6, 2021 (ML21126A239), May 27, 2021 (ML21147A115),

July 8, 2021 (ML21189A173), July 26, 2021 (ML21207A066), August 11, 2021 (ML21223A308),

August 25, 2021 (ML21237A055), August 30, 2021 (ML21242A230), September 10, 2021 (ML21253A138), September 10, 2021 (ML21253A140), September 13, 2021 (ML21256A129),

September 16, 2021 (ML21259A153), September 20, 2021 (ML21263A052), October 1, 2021 (ML21274A053), October 25, 2021 (ML21298A090), November 3, 2021 (ML21307A286),

November 4, 2021 (ML21308A282), November 4, 2021 (ML21308A283), November 23, 2021 (ML21327A077), November 30, 2021 (ML21334A293), December 9, 2021 (ML21343A294), January 6, 2022 (ML22006A074), and January 6, 2022 (ML22006A046),

NextEra Energy Point Beach, LLC (NextEra) submitted an application for subsequent renewal of Renewed Facility Operating License Nos. DPR-24 and DPR-27 for Point Beach Nuclear Plant, Units 1 and 2 (Point Beach), respectively, to the U.S. Nuclear Regulatory Commission (NRC).

NextEra submitted the application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, for subsequent license renewal (SLR).

By letter dated January 15, 2021 (ML21006A417), the NRC concluded that the application was acceptable for docketing and included the staffs projected review schedule for the Point Beach subsequent license renewal application (SLRA). On January 7, 2025 (ML24347A141), the NRC issued a revised schedule for the Point Beach SLRA.

The purpose of this letter is to inform you of additional changes in the review schedule to the Point Beach SLRA review. The revisions reflect several staff efficiencies that have been applied to the environmental and safety reviews since the original schedule was set.

The revised review schedule for the Point Beach SLRA is provided in the enclosure. The NRC staff will strive to meet the milestones ahead of the revised schedule whenever feasible.

August 7, 2025

Based on the current status of the review and implemented efficiencies, the staff estimates that the review of the SLRA will take approximately 19,075 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> to complete. This reflects an estimate of 12,550 hours0.00637 days <br />0.153 hours <br />9.093915e-4 weeks <br />2.09275e-4 months <br /> for the safety review and 6,525 hours0.00608 days <br />0.146 hours <br />8.680556e-4 weeks <br />1.997625e-4 months <br /> for the environmental review.

The estimate is a reduction from the original estimate of 23,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />.

If you have any questions on this matter, please contact Angela Wu, Senior Project Manager, for the review of the Point Beach SLRA at Angela.Wu@nrc.gov.

Sincerely, Michele M. Sampson, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301

Enclosure:

Revised Review Schedule cc w/encl: Listserv Signed by Sampson, Michele on 08/07/25

ML25203A012 e-concurrence NRR-106 OFFICE NRR/DNRL/PM NRR/DNRL/LA NMSS/REFS/PM NMSS/REFS/BC NAME AWu KBratcher KFolk SKoenick DATE 07/22/2025 07/22/2025 07/23/2025 07/30/2025 OFFICE NRR/DNRL/BC NRR/DNRL/D NAME ANeuhausen MSampson DATE 07/30/2025

Enclosure POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 SUBSEQUENT LICENSE RENEWAL APPLICATION REVISED REVIEW SCHEDULE Milestone Scheduled Actual Receive Subsequent License Renewal Application (SLRA) 11/2020 11/16/2020 Publish Federal Register Notice (FRN) - SLRA Availability 12/2020 12/29/2020 Publish FRN - Docketing Acceptance/Rejection and Opportunity to Request a Hearing 01/2021 01/22/2021 Publish FRN - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 01/2021 02/01/2021 Public Meeting - Overview of Subsequent License Renewal Process and Environmental Scoping 02/2021 02/17/2021 Environmental Scoping Period Ends 02/2021 03/03/2021 Deadline for Filing Hearing Requests and Petitions for Intervention 03/2021 03/23/2021 Issue Draft Supplemental Environmental Impact Statement (DSEIS) 10/2021 11/02/2021 Public Meeting - DSEIS Meeting, If Needed 12/2021 12/08/2022 End of DSEIS Comment Period 01/2022 01/03/2022 Issue Safety Evaluation (SE) 01/2022 02/23/2022 Advisory Committee on Reactor Safeguards Full Committee Meeting 04/2022 04/06/2022 Publish FRN - Issue Notice of Intent (NOI) to Prepare Supplement to Draft Environmental Impact Statement (SEIS) 10/2024 10/2/2024 Publish FRN - Notice of Availability of Supplement to Draft SEIS 04/2025 04/16/2025 Milestone Scheduled Actual Public Meeting - Draft Supplement to DSEIS 05/2025 05/15/2025 Issue Final SEIS 10/2025 08/2025 U.S. Environmental Protection Agency FRN Published -

Availability of Final SEIS 11/2025 08/2025 Decision - Director, NRR 12/2025 9/30/2025