EPID:L-2020-SLE-0002, Comment (2) of Raymond Hardy on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC, Point Beach, Units 1 and 2 (Approved, Closed) EPID:L-2020-SLR-0002, Subsequent License Renewal Application on Aging Management - Request for Additional Information (Rai), Set 4 Response (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance...
|
MONTHYEARML20329A2482020-11-16016 November 2020 Enclosure 3, Attachment 2, Appendix E Applicants Environmental Report Subsequent Operating License Renewal Point Beach Nuclear Plant Units 1 and 2 Project stage: Other ML20329A2642020-11-16016 November 2020 Enclosure 4, Non-proprietary Reference Documents and Redacted Versions of Proprietary Reference Documents (Public Version) Project stage: Request ML20329A2922020-11-16016 November 2020 Application for Subsequent Renewed Facility Operating Licenses Project stage: Request ML20321A1872020-11-16016 November 2020 Single Positive Test Form Collected on 02/11/2020 Project stage: Request ML21005A0582021-01-15015 January 2021 Subsequent License Renewal Application - Portal Letter Project stage: Other ML21015A2142021-01-15015 January 2021 Subsequent License Renewal Application Acceptance Federal Register Notice FRN Project stage: Other ML21006A4172021-01-15015 January 2021 Subsequent License Renewal Acceptance Letter Project stage: Acceptance Review ML21033A4022021-01-22022 January 2021 NextEra Energy Point Beach - Point Beach Nuclear Plant - Units 1 and 2 Subsequent License Renewal Project stage: Other ML20351A3922021-01-26026 January 2021 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process (EPID No. L-2020-SLE-0002) (Docket No. 50 266 and 50-301) - Letter Project stage: Other PMNS20210090, Environmental Scoping Meeting Related to the Point Beach Nuclear Plant, Unit Nos. 1 and 2 (Point Beach), Subsequent License Renewal Application2021-02-0303 February 2021 Environmental Scoping Meeting Related to the Point Beach Nuclear Plant, Unit Nos. 1 and 2 (Point Beach), Subsequent License Renewal Application Project stage: Meeting ML21048A0362021-02-0404 February 2021 Comment (1) of Willard Sielaff on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21040A2232021-02-0505 February 2021 Comment (2) of Raymond Hardy on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC, Point Beach, Units 1 and 2 Project stage: Request ML21040A2282021-02-0808 February 2021 Comment (3) from Hannah Mortensen on Behalf of Physicians for Social Responsibility Wisconsin on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Point Beach Nuclear Plant, Units 1 & 2 Project stage: Request ML21050A0822021-02-12012 February 2021 Comment (4) of Geralyn Leannah Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A0862021-02-14014 February 2021 Comment (6) of Theresa Deluca Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A0832021-02-14014 February 2021 Comment (5) of Bruce Krawisz on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A0892021-02-16016 February 2021 Comment (8) of Eric Newgent on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A0882021-02-16016 February 2021 Comment (7) of Randy Connour on Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21075A3432021-02-17017 February 2021 Meeting Summary: Public Scoping Meeting for the Environmental Review of the Subsequent License Renewal Application for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (EPID No.: L-2020-SLE-0002) - Summary Project stage: Meeting ML21050A0922021-02-17017 February 2021 Comment (9) of Diane Palecek Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21056A5612021-02-17017 February 2021 Physicians for Social Responsibility (Psr) Request for Extension of Scoping Comment Period Project stage: Request ML21050A1052021-02-17017 February 2021 Comment (12) of Shahla Werner Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21062A1922021-02-17017 February 2021 Transcript from Point Beach Nuclear Plant Subsequent License Renewal Scoping Meeting Project stage: Meeting ML21050A0992021-02-17017 February 2021 Comment (10) of Ann Rogers Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A1022021-02-17017 February 2021 Comment (11) of John Duffin Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21042B9452021-02-17017 February 2021 Scoping and Process Meeting - February 17, 2021 Project stage: Meeting ML21050A1092021-02-18018 February 2021 Comment (13) of Pamela Richard Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1212021-02-18018 February 2021 Comment (17) from Stephen Roddy Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1292021-02-18018 February 2021 Comment (22) from Dennis Schaef on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1332021-02-18018 February 2021 Comment (25) of Mark Giese on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1312021-02-18018 February 2021 Comment (23) from Patrick Bosold Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1252021-02-18018 February 2021 Comment (19) of Ellen Atkison Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1382021-02-18018 February 2021 Comment (27) of Leonard Kellum Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1342021-02-18018 February 2021 Comment (26) of Jim Yarbrough Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A1282021-02-18018 February 2021 Comment (21) of Karl Koessel Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A1162021-02-18018 February 2021 Comment (14) of Marie Luna on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1172021-02-18018 February 2021 Comment (15) of Joann Nishiura on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Nexteraenergy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1222021-02-18018 February 2021 Comment (18) of Kristina Mageau on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Nexteraenergy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A1322021-02-18018 February 2021 Comment (24) of Sandra Couch on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Nexteraenergy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1182021-02-18018 February 2021 Comment (16) from Andrew Benson Supporting Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1272021-02-18018 February 2021 Comment (20) from Pam Nelson Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1392021-02-19019 February 2021 Comment (28) of Croitiene Ganmoryn on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0162021-02-19019 February 2021 Comment (31) of Karen Wilson on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0152021-02-19019 February 2021 Comment (30) of Claire Gervais Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1592021-02-19019 February 2021 Comment (29) of Philip Ratcliff on Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21062A0182021-02-20020 February 2021 Comment (32) of Larry Troshynski on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0232021-02-21021 February 2021 Comment (33) of Kristin Womack on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0272021-02-21021 February 2021 Comment (36) of Ernest Fuller on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0282021-02-21021 February 2021 Comment (37) of Karen Kirschling on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0262021-02-21021 February 2021 Comment (35) of Dwight Rousu on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request 2021-02-17
[Table View] |
Text
Robert Coffey Executive Vice President, Nuclear Division and Chief Nuclear Officer Florida Power & Light Company 700 Universe Blvd.
Mail Stop: EX/JB Juno Beach, FL 33408
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - SCHEDULE REVISION FOR THE SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW (EPID NOS. L-2020-SLR-0002 AND L-2020-SLE-0002) (DOCKET NUMBERS: 50-266 AND 50-301)
Dear Robert Coffey:
By letter dated November 16, 2020 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML20329A292), as supplemented by letters dated April 21, 2021 (ML21111A155), May 6, 2021 (ML21126A239), May 27, 2021 (ML21147A115),
July 8, 2021 (ML21189A173), July 26, 2021 (ML21207A066), August 11, 2021 (ML21223A308),
August 25, 2021 (ML21237A055), August 30, 2021 (ML21242A230), September 10, 2021 (ML21253A138), September 10, 2021 (ML21253A140), September 13, 2021 (ML21256A129),
September 16, 2021 (ML21259A153), September 20, 2021 (ML21263A052), October 1, 2021 (ML21274A053), October 25, 2021 (ML21298A090), November 3, 2021 (ML21307A286),
November 4, 2021 (ML21308A282), November 4, 2021 (ML21308A283), November 23, 2021 (ML21327A077), November 30, 2021 (ML21334A293), December 9, 2021 (ML21343A294), January 6, 2022 (ML22006A074), and January 6, 2022 (ML22006A046),
NextEra Energy Point Beach, LLC (NextEra) submitted an application for subsequent renewal of Renewed Facility Operating License Nos. DPR-24 and DPR-27 for Point Beach Nuclear Plant, Units 1 and 2 (Point Beach), respectively, to the U.S. Nuclear Regulatory Commission (NRC).
NextEra submitted the application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, for subsequent license renewal (SLR).
By letter dated January 15, 2021 (ML21006A417), the NRC concluded that the application was acceptable for docketing and included the staffs projected review schedule for the Point Beach subsequent license renewal application (SLRA). On January 7, 2025 (ML24347A141), the NRC issued a revised schedule for the Point Beach SLRA.
The purpose of this letter is to inform you of additional changes in the review schedule to the Point Beach SLRA review. The revisions reflect several staff efficiencies that have been applied to the environmental and safety reviews since the original schedule was set.
The revised review schedule for the Point Beach SLRA is provided in the enclosure. The NRC staff will strive to meet the milestones ahead of the revised schedule whenever feasible.
August 7, 2025
Based on the current status of the review and implemented efficiencies, the staff estimates that the review of the SLRA will take approximately 19,075 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> to complete. This reflects an estimate of 12,550 hours0.00637 days <br />0.153 hours <br />9.093915e-4 weeks <br />2.09275e-4 months <br /> for the safety review and 6,525 hours0.00608 days <br />0.146 hours <br />8.680556e-4 weeks <br />1.997625e-4 months <br /> for the environmental review.
The estimate is a reduction from the original estimate of 23,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />.
If you have any questions on this matter, please contact Angela Wu, Senior Project Manager, for the review of the Point Beach SLRA at Angela.Wu@nrc.gov.
Sincerely, Michele M. Sampson, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosure:
Revised Review Schedule cc w/encl: Listserv Signed by Sampson, Michele on 08/07/25
ML25203A012 e-concurrence NRR-106 OFFICE NRR/DNRL/PM NRR/DNRL/LA NMSS/REFS/PM NMSS/REFS/BC NAME AWu KBratcher KFolk SKoenick DATE 07/22/2025 07/22/2025 07/23/2025 07/30/2025 OFFICE NRR/DNRL/BC NRR/DNRL/D NAME ANeuhausen MSampson DATE 07/30/2025
Enclosure POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 SUBSEQUENT LICENSE RENEWAL APPLICATION REVISED REVIEW SCHEDULE Milestone Scheduled Actual Receive Subsequent License Renewal Application (SLRA) 11/2020 11/16/2020 Publish Federal Register Notice (FRN) - SLRA Availability 12/2020 12/29/2020 Publish FRN - Docketing Acceptance/Rejection and Opportunity to Request a Hearing 01/2021 01/22/2021 Publish FRN - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 01/2021 02/01/2021 Public Meeting - Overview of Subsequent License Renewal Process and Environmental Scoping 02/2021 02/17/2021 Environmental Scoping Period Ends 02/2021 03/03/2021 Deadline for Filing Hearing Requests and Petitions for Intervention 03/2021 03/23/2021 Issue Draft Supplemental Environmental Impact Statement (DSEIS) 10/2021 11/02/2021 Public Meeting - DSEIS Meeting, If Needed 12/2021 12/08/2022 End of DSEIS Comment Period 01/2022 01/03/2022 Issue Safety Evaluation (SE) 01/2022 02/23/2022 Advisory Committee on Reactor Safeguards Full Committee Meeting 04/2022 04/06/2022 Publish FRN - Issue Notice of Intent (NOI) to Prepare Supplement to Draft Environmental Impact Statement (SEIS) 10/2024 10/2/2024 Publish FRN - Notice of Availability of Supplement to Draft SEIS 04/2025 04/16/2025 Milestone Scheduled Actual Public Meeting - Draft Supplement to DSEIS 05/2025 05/15/2025 Issue Final SEIS 10/2025 08/2025 U.S. Environmental Protection Agency FRN Published -
Availability of Final SEIS 11/2025 08/2025 Decision - Director, NRR 12/2025 9/30/2025