September 29, 2023 MEMORANDUM TO:

FROM:

SUBJECT:

William Jessup, Chief Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-power Production and Utilization Facilities Office of Nuclear Reactor Regulation Donna Williams, Senior Project Manager /RA/

Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-power Production and Utilization Facilities Office of Nuclear Reactor Regulation

SUMMARY

OF THE PARTIALLY CLOSED AUGUST 8, 2023, MEETING WITH OKLO TO DISCUSS OPERATIONS ( EPI: L-2022-LRM-0042)

Meeting Information:

Applicant: Oklo, Inc.

Project No.: 99902095 Public Meeting Notice Agencywide Documents Access and Management System (ADAMS)

Accession No.: ML23193A986 (Note: This meeting was originally scheduled for August 3, 2023, but was moved to support staff and applicant availabilities)

Applicant Presentation Slides ADAMS Accession No.: ML23226A132 (Proprietary)

Meeting Attendees: See enclosure 1 for a list of meeting attendees.

CONTACT: Donna Williams, NRR/DANU/UAL1 301-415-1322 to this letter contains proprietary information. When separated from Enclosure 2, this letter is DECONTROLLED.

W. Jessup Meeting Summary:

The U.S. Nuclear Regulatory Commission (NRC) staff conducted the meeting in accordance with NRC Management Directive 3.5, Attendance at NRC Staff-Sponsored Meetings (ML21180A271). Highlights from the meeting include the following:

The NRC staff previously met with Oklo to discuss its approach to plant operations and the roles of operators on August 31, 2022 (ML22257A245). At that time, the staff stated that it would be helpful to have additional discussions during the pre-application phase on this topic. The purpose of the August 8, 2023, meeting was for Oklo provide further operations-related information regarding the design as a continuation of prior discussions.

The staff noted that there are multiple regulatory matters associated with Oklos proposed approach to operations that would be worthy of future discussion during pre-application to align on resolution strategy. The staff recommended further discussions as early as is practical before submittal of a license application so that these matters can be fully considered. For example, the staff would like to have future discussions on the planned implementation of the shift technical advisor role, including any differences from current Commission policy. The staff also noted that additional discussions would be helpful on technically relevant post-Three Mile Island requirements in 10 CFR 50.34(f)(2)(iii), which addresses the application of the state-of-the-art in human factors engineering.

The staff emphasized that through tools such as exemptions and licensing commitments related to alternatives, there is flexibility available for advanced reactor vendors and encouraged further engagement on these topics.

The staff also discussed draft Interim Staff Guidance (ISG) DANU-ISG-2022-05, Advanced Reactor Content of Application Project Chapter 11 - Organization and Human-System Considerations, (ML22048B542) which covers operator licensing examination programs. This ISG was developed to support the draft proposed 10 CFR Part 53, Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors, rule, but can also serve to inform the thinking of advanced reactor applicants that would apply under 10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities, or 10 CFR Part 52, Licenses, Certifications, and Approvals for Nuclear Power Plants, before 10 CFR Part 53 is issued as a final rule.

Enclosures:

1. List of Attendees
2. Meeting Notes (proprietary)

Package ML23240A711 Letter ML23240A713 ML23240A715 NRR-106 OFFICE NRR/DANU/UAL1:PM NRR/DRO/ IOLB:BC NRR/DANU/UAL1:BC NAME DWilliams MScheetz WJessup DATE 8/28/2023 9/06/2023 9/05/2023

W. Jessup List of Meeting Attendees Partially Closed Pre-Application Meeting with Oklo, Inc. to Discuss the Regulatory Approach to Operations August 8, 2023 Name Organization Donna Williams U.S. Nuclear Regulatory Commission (NRC)

Reed Anzalone NRC Candace de Messieres NRC Jesse Seymour NRC Alex Siwy NRC Trace Orf Oklo, Inc. (Oklo)

Ross Moore Oklo Brian Kloiber Oklo Alan Smith Oklo Alex Renner Oklo Scott Auerbach Oklo