MONTHYEARPMNS20230649, Meeting with Oklo to Discuss Seismic Design Categorization and Site Characterization2023-05-19019 May 2023 Meeting with Oklo to Discuss Seismic Design Categorization and Site Characterization Project stage: Request ML23249A1732023-09-11011 September 2023 Summary of Meeting to Discuss Fitness for Duty for the Oklo Auroa X Design Project stage: Meeting ML23220A4342023-09-18018 September 2023 May 30 2023 Oklo Meeting Summary Cover Letter and Enclosure 1 Project stage: Meeting ML23237A7412023-09-18018 September 2023 Oklo August 1, 2023 Meeting Summary Cover Letter and Enclosure 1 Cyber Project stage: Meeting ML23240A7132023-09-29029 September 2023 Oklo August 8, 2023 Meeting Summary Cover Letter and Enclosure 1 Operations Project stage: Meeting ML23242A1562023-10-0303 October 2023 Oklo Meeting Summary August 1 2023 (Cover Letter and Enclosure 1) Project stage: Meeting PMNS20231337, Meeting with Oklo to Discuss Its Planned Approach to Operations for Its Advanced Reactor Design2023-11-27027 November 2023 Meeting with Oklo to Discuss Its Planned Approach to Operations for Its Advanced Reactor Design Project stage: Request PMNS20231336, Meeting with Oklo to Discuss Future Iterations of Its Design2023-11-30030 November 2023 Meeting with Oklo to Discuss Future Iterations of Its Design Project stage: Request ML23249A1352024-01-16016 January 2024 Summary of Partially Closed Public Meeting with Oklo, Inc., to Discuss Materials for the Oklo Advanced Reactor Design Project stage: Meeting ML23256A2772024-01-16016 January 2024 August 8, 2023, Summary of the Meeting to Discuss Safety Classification and Instrumentation and Controls the Reactor Trip System for the Oklo Aurora X Design Project stage: Meeting ML23249A1182024-01-17017 January 2024 June 29, 2023 Oklo Meeting Summary Materials- Cover Letter and Enclosure 1 Project stage: Meeting ML23256A2822024-01-17017 January 2024 June 30, 2023, Summary of the Partially Closed Public Meeting with Oklo to Discuss Probabilistic Risk Assessment for the Oklo Advanced Reactor Design Project stage: Meeting ML23312A0812024-01-18018 January 2024 August 8, 2023, Summary of the Partially Closed Meeting with Oklo to Discuss Safety Analysis for the Oklo Advanced Reactor Design Project stage: Meeting ML23159A1402024-01-31031 January 2024 Summary of Meeting to Discuss Safety Classification for the Oklo Advanced Reactor Design Project stage: Meeting ML24036A0822024-02-0505 February 2024 July 31, 2023, Summary of the Partially Closed Public Meeting with Oklo to Discuss Safety Classification and Regulatory Controls for the Oklo Advanced Reactor Design Project stage: Meeting ML24064A2272024-02-0909 February 2024 December 12, 2023, Summary of Closed Public Meeting to Discuss a Future Iteration of the Oklo Advanced Reactor Design Project stage: Meeting ML24074A3972024-03-12012 March 2024 Summary of Partially Closed Meeting with Oklo to Discuss Concept of Operations for Oklos Advanced Reactor Design Project stage: Meeting PMNS20240377, Meeting with Oklo to Discuss Physical Security for Its Advanced Reactor Design2024-03-14014 March 2024 Meeting with Oklo to Discuss Physical Security for Its Advanced Reactor Design Project stage: Request ML24226B2492024-09-13013 September 2024 June 25 2024 Oklo Met Data Meeting Summary Cover Letter and Enclosure 1 Project stage: Meeting PMNS20241182, Meeting with Oklo to Discuss Its Planned Approach to Operations for Its Advanced Reactor Design2024-09-14014 September 2024 Meeting with Oklo to Discuss Its Planned Approach to Operations for Its Advanced Reactor Design Project stage: Request ML24233A1722024-09-30030 September 2024 April 10 and 11 2024 Oklo Physical Security Meeting Summary Cover Letter and Enclosure 1 Project stage: Meeting PMNS20241327, Meeting with Oklo to Discuss the Information Required in a Combined License Application2024-10-18018 October 2024 Meeting with Oklo to Discuss the Information Required in a Combined License Application Project stage: Meeting ML24285A2232024-11-0606 November 2024 Summary of Partially Closed Meeting with Oklo to Discuss Concept of Operations for Oklos Advanced Reactor Design (EPID L-2022-LRM-0042 Project stage: Meeting PMNS20241541, Meeting with Oklo to Discuss Its Proposed Framework for Operator Licensing for Its Advanced Reactors2025-01-0606 January 2025 Meeting with Oklo to Discuss Its Proposed Framework for Operator Licensing for Its Advanced Reactors Project stage: Request ML25045A2152025-01-22022 January 2025 Fleet Model for Licensed Operator Topical Report - Public Project stage: Other ML24355A1352025-01-30030 January 2025 Summary of Meeting with Oklo, Inc., to Discuss Plan for Readiness Assessment for Future License Application Project stage: Meeting ML25045A2162025-04-11011 April 2025 Oklo, Inc., Meeting Summary January 22, 2025 Cover Letter and Enclosure 1 Project stage: Meeting ML25245A2072025-09-0202 September 2025 Oklo Pre-submittal Audit Plan Project stage: Other ML25218A2622025-11-24024 November 2025 July 23 2025 Summary of Partially Closed Meeting with Oklo to Discuss a Proposed Topical Report in the QA Program Description EPID L-2022-LRM-0042 Cover Letter and Enclosure 1 Project stage: Meeting 2024-11-06
[Table View] |
Text
February 9, 2024 MEMORANDUM TO:
William Jessup, Chief Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-power Production and Utilization Facilities Office of Nuclear Reactor Regulation FROM:
Donna Williams, Senior Project Manager /RA/
Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-power Production and Utilization Facilities Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF THE DECEMBER 12, 2023, CLOSED PUBLIC MEETING TO DISCUSS A FUTURE ITERATION OF THE OKLO ADVANCED REACTOR DESIGN (EPID L-2022-LRM-0042)
Meeting Information:
Applicant: Oklo, Inc. (Oklo)
Project No.: 99902095 Public Meeting Notice Agencywide Documents Access and Management System (ADAMS)
Accession No.: ML23334A101 Applicant Presentation Slides: ML24023A289 Meeting Attendees: See Enclosure 1 for a list of meeting attendees.
CONTACT: Donna Williams, NRR/DANU/UAL1 301-415-1322
W. Jessup 2
Meeting Summary:
The U.S. Nuclear Regulatory Commission (NRC) staff conducted the meeting in accordance with NRC Management Directive 3.5, Attendance at NRC Staff-Sponsored Meetings (ML21180A271). Highlights from the meeting included the following:
The goals of this meeting were to discuss potential design updates to provide early insights to the NRC staff regarding future design iterations. The NRC staff and Oklo discussed the licensing and technical considerations that would need to be addressed for the revised design.
The NRC staff recommended several topics for Oklo to consider as part of future pre-application engagement on its reactor design iterations.
Oklo plans to submit a licensing project plan in 2024 that describes proposed pre-application interactions for this future design iteration.
No regulatory decisions were made as a result of this meeting.
Enclosures:
- 1. List of Attendees
- 2. Meeting Notes (proprietary)
Cc: Oklo Powerhouse via GovDelivery w/o Enclosure 2 to this letter contains proprietary information. When separated from the enclosures, this letter is DECONTROLLED.
ML24064A222 (Package)
ML24064A227 (Cover Letter and Enclosure
- 1) ML24064A223 (Enclosure 2)
OFFICE NRR/DANU/UAL1: PM NRR/DANU/UAL1: BC NRR/DANU/UAL1: PM NAME DWilliams WJessup DWilliams DATE 01/22/24 2/7/24 2/9/24
List of Meeting Attendees
SUMMARY
OF THE DECEMBER 12, 2023, CLOSED PUBLIC MEETING TO DISCUSS A FUTURE ITERATION OF THE OKLO ADVANCED REACTOR DESIGN (EPID L-2022-LRM-0042)
December 12, 2023 Name Organization Donna Williams U.S. Nuclear Regulatory Commission (NRC)
Jason Schaperow NRC Michelle Hart NRC Candace de Messieres NRC Reed Anzalone NRC Alex Siwy NRC Hanh Phan NRC Benjamin Parks NRC Inseok Baek NRC Mohsin Ghazali NRC Trace Orf Oklo, Inc. (Oklo)
Ross Moore Oklo Pat Everett Oklo Liz Porter Oklo Alex Renner Oklo Brian Kloiber Oklo Scott Auerbach Oklo Tyrell Arment Oklo Carmen Tiolis Oklo