Summary of Partially Closed Meeting with Oklo to Discuss Concept of Operations for Oklos Advanced Reactor Design
ML24074A397
Person / Time
Site: 99902095
Issue date: 03/12/2024
From: David Williams
Office of Nuclear Reactor Regulation
To: Jessup W
Office of Nuclear Reactor Regulation
References
EPID L-2022-LRM-0042
Download: ML24074A397 (1)


Text

March 12, 2024 MEMORANDUM TO:

William Jessup, Chief Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-power Production and Utilization Facilities Office of Nuclear Reactor Regulation FROM:

Donna Williams, Senior Project Manager /RA/

Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-power Production and Utilization Facilities Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF THE DECEMBER 11, 2023, PARTIALLY CLOSED MEETING WITH OKLO TO DISCUSS CONCEPT OF OPERATIONS FOR OKLOS ADVANCED REACTOR DESIGN (EPID L-2022-LRM-0042)

Meeting Information:

Applicant: Oklo, Inc. (Oklo)

Project No.: 99902095 Public Meeting Notice Agencywide Documents Access and Management System (ADAMS)

Accession No.: ML23331A968 Applicant Presentation Slides ADAMS Accession No.: ML24023A288 Meeting Attendees: See Enclosure 1 for a list of meeting attendees.

CONTACT: Donna Williams, NRR/DANU/UAL1 301-415-1322

W. Jessup 2

Meeting Summary:

The U.S. Nuclear Regulatory Commission (NRC) staff conducted the meeting in accordance with NRC Management Directive 3.5, Attendance at NRC Staff-Sponsored Meetings (ML21180A271). Highlights from the meeting included the following:

The NRC staff met with Oklo to discuss the concept of operations proposed for its advanced reactors.

The NRC staff had previously met with Oklo in August 2022 (ML22257A246) to discuss standardized operational programs, including Oklos approach to operations and training and exemptions that may be necessary to support implementation of its approach.

During a subsequent meeting in August 2023, Oklo provided more details on its proposed approach to operations. (ML23240A713)

In November 2023, Oklo shared a draft white paper with the NRC staff regarding its proposed concept of operations. The NRC staff discussed preliminary feedback on the draft white paper during the December 11, 2023, meeting (Enclosure 3).

NRC staff and Oklo discussed aspects of its proposed concept of operations, intended to reflect advanced reactor features. NRC staff identified some aspects of Oklo's approach that may be potentially inconsistent with current regulations and underlying statutory requirements. NRC staff discussed potential ways of navigating the issue. Oklo anticipates requesting exemptions to certain existing regulatory requirements to account for the role of humans in its facilities. Both sides agree that this is an area for further engagement.

Oklo indicated that it plans to evaluate the information provided by the NRC staff during the meeting and will determine the next steps which may include revision of the draft white paper, formal submittal, and possibly an additional meeting.

No regulatory decisions were made as a result of this meeting.

Enclosures:

1.

List of Attendees

2.

Meeting Notes (proprietary)

3.

Preliminary NRC staff feedback on draft WP (proprietary) cc: Oklo Powerhouse via GovDelivery w/o Enclosures 2 and 3

Package ML Letter: ML : ML : ML NRR-106 OFFICE NRR/DANU/UAL1:PM NRR/DRO/IOLB NRR/DANU/UAL1:BC NRR/DANU/UAL1:PM NAME DWilliams LNist WJessup DWilliams DATE 1/11/24 1/19/24 2/20/24 3/12/24

List of Meeting Attendees

SUMMARY

OF THE DECEMBER 11, 2023, PARTIALLY CLOSED MEETING WITH OKLO TO DISCUSS CONCEPT OF OPERATIONS FOR THE OKLOS ADVANCED REACTOR DESIGN (EPID L-2022-LRM-0042)

Name Organization Donna Williams U.S. Nuclear Regulatory Commission (NRC)

Mohsin Ghazali NRC Candace de Messieres NRC Maurin Scheetz NRC Jesse Seymour NRC Theresa Buchanan NRC William Jessup NRC Alex Siwy NRC Trace Orf Oklo, Inc. (Oklo)

Ross Moore Oklo Tyrell Arment Oklo Alex Renner Oklo