Letter Sequence Approval |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: ML20258A284, ML20269A465, ML20276A192, ML20303A199, ML21036A060, ML21067A504, ML21067A507, ML21084A182, ML21091A004, ML21097A027, ML21145A217, ML21217A187, ML21239A064, ML21239A066, ML21239A068, ML21256A067, ML21256A069, ML21312A002, ML21312A003, ML21312A007, PMNS20211071, Discussion Between NRC and Dominion Regarding the North Anna Subsequent License Renewal - Safety Issue - Cyclic Fatigue, PMNS20211128, Discussion Between NRC and Dominion Regarding the North Anna Subsequent License Renewal - an Inconsistency in Documentation Regarding Reactor Coolant Pump Code Case N 481, TLAA 4.7.6
|
MONTHYEARML20246G6972020-08-24024 August 2020 Application for Subsequent Renewed Operating Licenses Project stage: Request ML20269A4652020-10-0606 October 2020 SLRA - Portal Letter Project stage: Other ML20276A1922020-10-0909 October 2020 Subsequent License Renewal Aging Management Audit Plan Project stage: Other ML20258A2842020-10-13013 October 2020 SLRA - Acceptance and Opportunity for Hearing Letter Project stage: Other ML20303A1992020-10-29029 October 2020 Subsequent License Renewal Safety Project Management Assignment Project stage: Other ML20352A3942020-12-17017 December 2020 Proposed License Amendment Request to Change Battery Surveillance Requirements Project stage: Request ML21035A3032021-02-0404 February 2021 (Naps), Units 1 and 2 - Update to Subsequent License Renewal Application (SLRA) Supplement 1 Project stage: Supplement ML21063A5602021-03-0404 March 2021 Final Request for Additional Information Set 1 - North Anna SLRA Safety Review (EPID L-2020-SLR-0000) - Enclosure Project stage: RAI ML21063A5522021-03-0404 March 2021 Final Request for Additional Information Set 1 - North Anna SLRA Safety Review (EPID L-2020-SLR-0000) - Email Project stage: RAI ML21067A5072021-03-0808 March 2021 Final Request for Confirmation of Information (RCI) Set 1 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure Project stage: Other ML21067A5042021-03-0808 March 2021 Final Request for Confirmation of Information (RCI) Set 1 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email Project stage: Other ML21076B0252021-03-17017 March 2021 Update to Subsequent License Renewal Application, Supplement 2 Project stage: Supplement ML21084A1822021-03-24024 March 2021 Subsequent License Renewal Application Response to NRC Requests for Confirmation of Information for the Safety Review - Set 1 Project stage: Other ML21091A0032021-04-0101 April 2021 Final Request for Additional Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure 1 - RAIs Project stage: RAI ML21091A0042021-04-0101 April 2021 SLRA Safety Review - Withdrawn Requests for Information (EPID No. L-2020-SLR-0000) - Enclosure 2 Project stage: Other ML21091A0022021-04-0101 April 2021 Final Request for Additional Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email Project stage: RAI ML21091A1872021-04-0101 April 2021 Response to NRC Request for Additional Information Regarding Safety Review - Set 1 & Clarification to Aging Management of Fire Protection System Lined Ductile Iron Valves Project stage: Supplement ML21036A0602021-04-0808 April 2021 Report for the Aging Management Audit Regarding the Subsequent License Renewal Application Review Project stage: Other ML21097A0272021-04-14014 April 2021 Request for Withholding from Public Disclosure Regarding Subsequent License Renewal Application Project stage: Other ML21104A0372021-04-15015 April 2021 Request for Withholding Information Regarding Subsequent License Renewal Application Project stage: Withholding Request Acceptance ML21119A2872021-04-29029 April 2021 (Naps), Unit 1 and 2 - Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Safety Review - Set 2 and Flow Accelerated Corrosion Program Enhancement Completion Project stage: Response to RAI ML21119A3402021-04-29029 April 2021 Preparation and Scheduling of Operator Licensing Examinations Project stage: Request ML21123A2972021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - E-mail Project stage: RAI ML21123A2982021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure Project stage: RAI PMNS20210548, Discussion of Dominion'S Response to Select Staff RAIs on North Anna Subsequent License Renewal Application2021-05-12012 May 2021 Discussion of Dominion'S Response to Select Staff RAIs on North Anna Subsequent License Renewal Application Project stage: RAI ML21145A2172021-05-13013 May 2021 Discussion on May 13, 2021 with Dominion on Select Staff RAIs on North Anna Subsequent License Renewal Application - Dominion Slides Project stage: Other ML21132A2892021-05-13013 May 2021 SLRA RAI Response Public Meeting Project stage: RAI PMNS20210666, Discussion of Dominion'S Response to Select Staff RAIs on North Anna Subsequent License Renewal Application2021-05-27027 May 2021 Discussion of Dominion'S Response to Select Staff RAIs on North Anna Subsequent License Renewal Application Project stage: RAI ML21221A1482021-05-27027 May 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - NRC Slides Project stage: RAI ML21221A1542021-05-27027 May 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Dominion Slides Project stage: Meeting ML21147A2932021-05-27027 May 2021 (Naps), Units 1 and 2 Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Safety Review - Set 3 and Administrative Change to SLRA Table A4.0-1, Item 25 Project stage: Response to RAI ML21145A2122021-06-0909 June 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Memoranda Project stage: RAI ML21145A2132021-06-0909 June 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Enclosure 1 - Summary Project stage: RAI ML21145A2152021-06-0909 June 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Enclosure 2 - List of Attendees Project stage: RAI ML21166A3512021-06-15015 June 2021 Safety RAIs - Set 4 - Draft Project stage: Draft RAI PMNS20210777, Discussion of Dominion'S Response to Select Staff RAIs on North Anna Subsequent License Renewal Application - Topics to Be Determined2021-06-15015 June 2021 Discussion of Dominion'S Response to Select Staff RAIs on North Anna Subsequent License Renewal Application - Topics to Be Determined Project stage: RAI PMNS20210778, Discussion of Dominion'S Response to Select Staff RAIs on North Anna Subsequent License Renewal Application - Topics to Be Determined2021-06-23023 June 2021 Discussion of Dominion'S Response to Select Staff RAIs on North Anna Subsequent License Renewal Application - Topics to Be Determined Project stage: RAI ML21174A3042021-06-23023 June 2021 SLRA RAI Response Public Meeting - 21-06-24 Project stage: RAI ML21174A1952021-06-23023 June 2021 Safety RAIs - Set Y - Draft - Enclosure Project stage: Draft RAI ML21188A1652021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure Project stage: RAI ML21188A1632021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email Project stage: RAI ML21210A3962021-07-29029 July 2021 (Naps), Units 1 and 2 - Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Safety Review - Set 4 and Supplement 3 Project stage: Supplement ML21217A1872021-08-0505 August 2021 (Naps), Units 1 and 2 - Subsequent License Renewal Application First 10 CFR 54.21 (B) Annual Amendment Project stage: Other ML21221A1362021-08-10010 August 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application Project stage: RAI ML21221A1382021-08-10010 August 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Meeting Summary Project stage: RAI ML21221A1412021-08-10010 August 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Attendees Project stage: RAI PMNS20211071, Discussion Between NRC and Dominion Regarding the North Anna Subsequent License Renewal - Safety Issue - Cyclic Fatigue2021-08-13013 August 2021 Discussion Between NRC and Dominion Regarding the North Anna Subsequent License Renewal - Safety Issue - Cyclic Fatigue Project stage: Other ML21225A5642021-08-13013 August 2021 Discussion Point for Public Meeting Regarding Fire Protection Piping Cyclic Loading - Presentation Project stage: Meeting ML21225A5512021-08-13013 August 2021 Discussion Point for Public Meeting Regarding Fire Protection Piping Cyclic Loading - Transmittal E-mail Project stage: Meeting ML21238A0942021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email Project stage: Draft RAI 2021-04-29
[Table View] |
|
---|
Category:Letter
MONTHYEARML24032A1112024-02-0101 February 2024 Owner'S Activity Report for North Anna, Unit 2, Refueling Outage N2R29 - First Period of the Fifth ISI Interval ML24032A4662024-01-16016 January 2024 Response to Comments on Draft Vpdes Permit No. VA0052451 ML24017A0802024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000338/2024301 and 05000339/2024301 ML24003A8372024-01-0909 January 2024 Letter to Elizabeth Toombs, Thpo, Cherokee Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8412024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8502024-01-0909 January 2024 Letter to Wenonah Haire, Thpo, Catawba Indian Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A7272024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8382024-01-0909 January 2024 Letter to G. Anne Richardson, Chief, Rappahannock Tribe, Inc., Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8482024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8392024-01-0909 January 2024 Letter to Gerald Stewart, Chief, Chickahominy Indian Tribe, Eastern Division Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8472024-01-0909 January 2024 Letter to Tom Jonathan, Chief, Tuscarora Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8492024-01-0909 January 2024 Letter to W. Frank Adams, Chief, Upper Mattaponi Tribe Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8462024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8352024-01-0909 January 2024 Letter to Acee Watt, Thpo, United Keetoowah Band of Cherokee Indians in Oklahoma Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8422024-01-0909 January 2024 Letter to Paul Barton, Thpo, Eastern Shawnee Tribe of Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8432024-01-0909 January 2024 Letter to Robert Gray, Chief, Pamunkey Indian Tribe, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8362024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8442024-01-0909 January 2024 Letter to Russell Townsend, Thpo, Eastern Band of Cherokee Indians ML24003A8402024-01-0909 January 2024 Letter to Katelyn Lucas, Thpo, Delaware Nation, Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8452024-01-0909 January 2024 Letter to Stephen Adkins, Chief, Chickahominy Indian Tribe, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML23332A1852024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A0872024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23360A6352024-01-0404 January 2024 Letter to Dominion Availability for North Anna Units 1 and 2 Draft Site Specific Environmental Impact Statement ML23332A1472023-12-21021 December 2023 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23346A0972023-12-11011 December 2023 License Amendment Request to Revise the Emergency Plan Relocation of the Technical Support Center - Response to NRC Request for Additional Information ML23346A1022023-12-11011 December 2023 2024 North Anna Power Station Brq Inspection Notification Letter ML24012A0942023-12-0707 December 2023 GL Report from Dominion Virginia Power Regarding Transfer of Devices ML24012A0892023-12-0707 December 2023 GL Registration from Dominion Virginia Power ML23334A2432023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23362A0602023-11-29029 November 2023 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000339/20234022023-11-27027 November 2023 Security Baseline Inspection Report 05000338 and 05000339/2023402 IR 05000338/20230032023-11-13013 November 2023 Integrated Inspection Report 05000338/2023003 and 05000339/2023003 ML23311A2042023-10-0909 October 2023 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.d IR 05000338/20234032023-10-0505 October 2023 Reissue - North Anna Power Station - Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 (Cover Letter) ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23275A0992023-09-28028 September 2023 Subsequent License Renewal Application Third 10 CFR 54.21(b) Annual Amendment IR 05000338/20230112023-09-26026 September 2023 Quadrennial Focused Engineering Inspection Commercial Grade Dedication Report 05000338/2023011 and 05000339/2023011 ML23242A3482023-09-11011 September 2023 Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 - Cover ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23249A2592023-09-0606 September 2023 Core Operating Limits Report Cycle 30, Pattern Ukr, Revision 0 ML23214A2022023-09-0505 September 2023 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-02-01
[Table view] |
Text
January 4, 2022 Mr. Daniel G. Stoddard Senior Vice President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Blvd Glen Allen, VA 29060
SUBJECT:
NORTH ANNA POWER STATION, UNITS 1 AND 2 - FINAL SAFETY EVALUATION REPORT FOR THE SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW (EPID NO. L-2020-SLR-0000)
Dear Mr. Stoddard:
By letters dated August 24, 2020, (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML20246G703), February 4, 2021 (ADAMS Accession No. ML21035A303), March 17, 2021 (ADAMS Accession No. ML21076B025), March 25, 2021, (ADAMS Accession No. ML21084A182), April 1, 2021 (ADAMS Accession No. ML21091A186),
April 29, 2021 (ADAMS Accession No. ML21119A287), May 27, 2021 (ADAMS Accession No. ML21147A293), July 29, 2021 (ADAMS Accession No. ML21210A396), August 5, 2021 (ADAMS Accession No. ML21217A187), August 26, 2021 (ADAMS Accession No. ML21238A297), and December 6, 2021 (ADAMS Accession No. ML21341B437), Virginia Electric and Power Company (Dominion Energy or the applicant) submitted an application for the subsequent license renewal of Renewed Facility Operating License Nos. NPF-4 and NPF-7 for the North Anna Power Station, Units 1 and 2 (NAPS) to the U.S. Nuclear Regulatory Commission (NRC). Dominion Energy submitted the application pursuant to Title 10 of the Code of Federal Regulations Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, for subsequent license renewal.
The NRC staff determined that the application was complete and acceptable for docketing on October 9, 2021 (ADAMS Accession No. ML20267A340), and noticed it in the Federal Register on October 15, 2021 (85 FR 65438).
The NRC staff has reviewed the NAPS Subsequent License Renewal Application (SLRA) and has developed the enclosed Safety Evaluation Report Related to the Subsequent License Renewal of North Anna Power Station, Units 1 and 2 - Final Report, hereinafter referred to as the Safety Evaluation Report (SER). This SER reflects the status of the NRC staffs safety review of the SLRA, as supplemented, through December 6, 2021. Issuance of the enclosed SER is an important milestone for both the applicant and the NRC staff.
D. Stoddard The next milestone for this project is the Advisory Committee on Reactor Safeguards Full Committee meeting scheduled for February 1 - 4, 2022.
If you have any questions regarding this matter, please contact the license renewal project manager, Ms. Lois M. James, by e-mail at Lois.James@nrc.gov.
Sincerely, Digitally signed by Brian Smith Brian Smith Date: 2022.01.04 13:58:33 -05'00' Brian W. Smith, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-338 and 50-339
Enclosure:
As stated cc w/encl: Listserv
ML21354A174 (PKG)
ML21354A195 (LTR)
ML21354A196 (SER)
ML22004A084 (NCP #1)
ML22004A223 (NCP #2) *via-e-mail NRR-106 OFFICE LA: DNLR/NLRP (ltr) Tech Editing (SER) TR: DNRL/NCSG TR: DNRL/NCSG NAME SGreen Susan Cooke Anastasi BAllik JGavula (PM) RIVA Solutions, Inc. Nonconcur (NCP #1) Nonconcur (NCP #2)
DATE 12/21/2021 10/15/2021 09/27/2021 11/09/21 OFFICE BC: DEX/ELTB BC: DEX/ESEB BC: DSS/SCPB BC: DSS/SNSB NAME JJohnston JColaccino BWittick SKrepel DATE 05/04/2021 08/05/2021 05/28/2021 03/25/2021 OFFICE BC: DRA/APLB BC: DNRL/NPHP BC: DNRL/NVIB BC: DNRL/NCSG NAME SVasavada (A) MMitchell DWidrevitz (A) MYoder (A)
DATE 02/16/2021 05/24/2021 06/03/2021 12/20/21 OFFICE BC: DNLR/NLRP D: DEX D: DSS D: DRA NAME LGibson EBenner JDonoghue MFranovich DATE 12/20/21 09/16/2021 09/20/2021 09/02/2021 OGC (NLO) draft issued OGC (NLO) changes from OFFICE 10/18/21 draft D: DNRL NAME KGamin STurk BSmith DATE 10/13/21 12/20/21 01/04/22