Letter Sequence Withholding Request Acceptance |
---|
EPID:L-2020-LLA-0051, New York State Motion for Leave to Amend Contentions NY-2 and NY-3 (Approved, Closed) |
Results
Other: ML21092A091, ML21194A408, ML21231A182, ML21314A218, ML21346A000, ML21363A165, NL-20-021, Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device, RS-21-077, License Amendment to Revise Technical Specification 3.7.9, Ultimate Heat Sink
|
MONTHYEARNL-20-021, Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-03-24024 March 2020 Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Other ML20084Q1912020-03-24024 March 2020 New York State Motion for Leave to Amend Contentions NY-2 and NY-3 Project stage: Request ML20108E9482020-04-17017 April 2020 Acceptance Review Determination for Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Acceptance Review ML20184A0012020-07-0606 July 2020 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML21363A1582020-07-31031 July 2020 E-mail from A. Peterson,Nyserda to R. Guzman, NRC, Informal Questions Indian Point Unit 3, HI-LIFT Crane License Amendment Request Project stage: Request ML20233B0152020-08-20020 August 2020 Request for Additional Information (E-mail Dated 8/20/20) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device Project stage: RAI ML20268C2352020-09-24024 September 2020 Request for Additional Information (E-mail Dated 9/24/20) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device Project stage: RAI NL-20-070, Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-10-0202 October 2020 Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Response to RAI ML21363A1602020-10-22022 October 2020 E-mail from A. Peterson, NYSERDA, to R. Guzman, NRC, Informal Questions Indian Point Unit 3, HI-LIFT Crane License Amendment Request Project stage: Request NL-20-077, Submittal of Quality Assurance Program Manual Revision 22020-11-0909 November 2020 Submittal of Quality Assurance Program Manual Revision 2 Project stage: Request NL-20-078, Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-11-0909 November 2020 Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Response to RAI ML21013A0142020-12-21021 December 2020 Clarification Call for Draft RAIs (E-mail Dated 12/21/20) License Amendmet Request to Revise Licensing Basis for New Auxiliary Lifting Device Project stage: Draft RAI ML21013A0152021-01-12012 January 2021 Draft Request for Additional Information (E-mail Dated 1/12/2021) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device Project stage: Draft RAI ML21019A5672021-01-19019 January 2021 Second Round Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device Project stage: RAI ML21363A1642021-01-19019 January 2021 E-mail from A. Peterson, NYSERDA, to R. Guzman, NRC, Informal Questions Indian Point Unit 3, HI-LIFT Crane License Amendment Request Project stage: Request NL-21-014, Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2021-01-26026 January 2021 Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Request ML21060B6022021-03-11011 March 2021 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML21078A5102021-03-19019 March 2021 E-mail from P. Couture to R. Guzman) Hi-Lift Crane Proposed License Amendment Request Confirmatory Information Project stage: Request ML21363A1652021-03-23023 March 2021 3/23/2021 E-mail from R. Guzman, NRC, to A. Peterson, NYSERDA, State Comments for IP3 HI-LIFT Crane License Amendment Request Project stage: Other ML21092A0912021-04-0202 April 2021 E-mail NRR Review Hour Estimate Change Supporting the Hi-Lift Crane Proposed License Amendment Request Review Project stage: Other ML21096A3332021-04-0606 April 2021 E-mail Dated 4/6/2021, Transmittal of Draft Safety Evaluation for Proposed License Amendment Revision to Licensing Basis to Incorporate the Installation and Use of of New Auxiliary Lifting Device Project stage: Draft Approval ML21111A3612021-04-21021 April 2021 4/21/2021 Letter from A. Peterson (NYSERDA) to R. Guzman (Nrc), New York State Comments Indian Point Energy Center Unit 3 License Amendment Request (HI-LIFT Crane) Project stage: Request ML21112A2672021-04-22022 April 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (Public Redacted Version) Project stage: RAI NL-21-039, Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary2021-05-20020 May 2021 Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Project stage: Response to RAI ML21194A4082021-07-13013 July 2021 (7-13-2021) E-mail NRR Review Hour Estimate Change Supporting the Hi-Lift Crane Proposed License Amendment Request Review Project stage: Other RS-21-077, License Amendment to Revise Technical Specification 3.7.9, Ultimate Heat Sink2021-08-0202 August 2021 License Amendment to Revise Technical Specification 3.7.9, Ultimate Heat Sink Project stage: Other ML21231A1822021-08-26026 August 2021 Unit, No. 3 - Audit Plan in Support of Review of License Amendment Request Regarding the Installation and Use of a New Auxiliary Lifting Device Project stage: Other ML21337A2952021-12-0303 December 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (E-mail Dated 12/3/2021) Project stage: RAI ML21346A0002021-12-16016 December 2021 Unit, No. 3 - Regulatory Audit Summary Concerning License Amendment Request to Install and Use a New Auxiliary Lifting Device Project stage: Other ML22003A1932022-01-0303 January 2022 Response to Requests for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Response to RAI ML21314A2182022-01-18018 January 2022 Audit Plan in Support of Review of License Amendment Request Regarding the Ultimate Heat Sink Project stage: Other ML22028A1032022-01-28028 January 2022 E-mail Dated 1/28/2022, Transmittal of Draft Safety Evaluation for Proposed License Amendment Revision to Licensing Basis to Incorporate the Installation and Use of of New Auxiliary Lifting Device Project stage: Draft Approval ML21091A3052022-02-28028 February 2022 Issuance of Amendment No. 272 Revision to Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device (EPID L-2020-LLA-0051) (Non-Proprietary) Project stage: Approval 2021-12-03
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 07200051/20244022024-11-20020 November 2024 NRC Independent Spent Fuel Storage Security Inspection Report No. 07200051/2024402 (Public) ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000003/20240022024-08-0606 August 2024 NRC Inspection Report 05000003/2024002, 05000247/2024002, 05000286/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24171A0122024-06-18018 June 2024 Reply to a Notice of Violation EA-24-037 ML24156A1162024-06-0404 June 2024 Correction - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000003/20240052024-05-21021 May 2024 And 3 - NRC Inspection Report Nos. 05000003/2024005, 05000247/2024005, 05000286/2024005, 07200051/2024001, and Notice of Violation ML24128A0632024-05-0707 May 2024 Submittal of 2023 Annual Radiological Environmental Operating Report L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 ML24116A2412024-04-25025 April 2024 Annual Environmental Protection Plan Report ML24114A2282024-04-23023 April 2024 Annual Radioactive Effluent Release Report L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 05000003/20240012024-03-20020 March 2024 NRC Inspection Report Nos. 05000003/2024001, 05000247/2024001, and 05000286/2024001 (Cover Letter Only) ML24080A1722024-03-20020 March 2024 Reply to a Notice of Violation EA-2024-010 ML24045A0882024-02-22022 February 2024 Correction to the Technical Specifications to Reflect Appropriate Pages Removed and Retained by Previous License Amendments ML24053A0642024-02-22022 February 2024 2023 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report IR 05000003/20230042024-02-22022 February 2024 NRC Inspection Report Nos. 05000003/2023004, 05000247/2023004, 05000286/2023004, and 07200051/2023004 and Notice of Violation ML24011A1982024-01-12012 January 2024 ISFSI, Notice of Organization Change for Site Vice President ML23342A1082024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23353A1742023-12-19019 December 2023 ISFSI, Emergency Plan, Revision 23-04 L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23326A1322023-12-0505 December 2023 Issuance of Amendment No. 67, 300 & 276 to Implement the Independent Spent Fuel Storage Installation Only Emergency Plan ML23339A0442023-12-0505 December 2023 Issuance of Amendment No. 68, 301 and 277 Regarding Changes to Implement the Independent Spent Fuel Storage Installation Physical Security Plan ML23338A2262023-12-0404 December 2023 Signed Amendment No. 27 to Indemnity Agreement No. B-19 ML23356A0212023-12-0101 December 2023 American Nuclear Insurers, Secondary Financial Protection (SFP) Program ML23242A2772023-11-30030 November 2023 NRC Letter Issuance - IP LAR for Units 2 and 3 Renewed Facility Licenses and PDTS to Reflect Permanent Removal of Spent Fuel from SFPs ML23338A0482023-11-30030 November 2023 ISFSI, Report of Changes to Physical Security, Training and Qualification, Safeguards Contingency Plan, and ISFSI Security Program, Revision 28 ML22339A1572023-11-27027 November 2023 Letter - Indian Point - Ea/Fonsi Request for Exemptions from Certain Emergency Planning Requirements for 10 CFR 50.47 and 10 CFR Part 50, Appendix E IR 05000003/20230032023-11-21021 November 2023 NRC Inspection Report Nos. 05000003/2023003, 05000247/2023003, 05000286/2023003, and 07200051/2023003 ML23100A1252023-11-17017 November 2023 Letter and Enclosure 1 - Issuance Indian Point Energy Center Units 1, 2, and 3 Exemption for Offsite Primary and Secondary Liability Insurance Indemnity Agreement ML23050A0032023-11-17017 November 2023 Letter - Issuance Indian Point Unit 2 License Amendment Request to Modify Tech Specs for Staffing Requirements Following Spent Fuel Transfer to Dry Storage ML23100A1172023-11-17017 November 2023 NRC Response - Indian Point Energy Center Generating Units 1, 2, and 3 Letter with Enclosures Regarding Changes to Remove the Cyber Security Plan License Condition ML23100A1432023-11-16016 November 2023 Letter - Issuance Indian Point Energy Center Generating Units 1, 2, and 3 Exemption Concerning Onsite Property Damage Insurance (Docket Nos. 50-003, 50-247, 50-286) L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23064A0002023-11-13013 November 2023 NRC Issuance for Approval-Indian Point EC Units 1, 2 and 3 Emergency Plan and Emergency Action Level Scheme Amendments ML23306A0992023-11-0202 November 2023 And Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML23063A1432023-11-0101 November 2023 Letter - Issuance Holtec Request for Indian Point Energy Center Generating Units 1, 2, and 3 Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47 and Part 50 ML23292A0262023-10-19019 October 2023 LTR-23-0211-RI Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report-RI ML23289A1582023-10-16016 October 2023 Decommissioning International - Registration of Spent Fuel Casks and Notification of Permanent Removal of All Indian Point Unit 3 Spent Fuel Assemblies from the Spent Fuel Pit ML23270A0082023-09-27027 September 2023 Registration of Spent Fuel Casks ML23237A5712023-09-22022 September 2023 09-22-2023 Letter to Dwaine Perry, Chief, Ramapo Munsee Nation, from Chair Hanson, Responds to Letter Regarding Opposition of the Release and Dumping of Radioactive Waste from Indian Point Nuclear Power Plant Into the Hudson River ML23242A2182023-09-12012 September 2023 IPEC – NRC Response to the Town of New Windsor, Ny Board Certified Motion Letter Regarding Treated Water Release from IP Site (Dockets 50-003, 50-247, 50-286) ML23250A0812023-09-0707 September 2023 Registration of Spent Fuel Casks ML23255A0142023-08-31031 August 2023 LTR-23-0211 Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report IR 05000003/20230022023-08-22022 August 2023 NRC Inspection Report 05000003/2023002, 05000247/2023002, 05000286/2023002, and 07200051/2023002 ML23227A1852023-08-15015 August 2023 Request for a Revised Approval Date Regarding the Indian Point Energy Center Permanently Defueled Emergency Plan and Emergency Action Level Scheme ML23222A1442023-08-10010 August 2023 Registration of Spent Fuel Casks ML23208A1642023-07-26026 July 2023 Village of Croton-on-Hudson New York Letter Dated 7-26-23 Re Holtec Wastewater ML23200A0422023-07-19019 July 2023 Registration of Spent Fuel Casks 2024-09-18
[Table view] Category:Proprietary Information Review
MONTHYEARML21060B6022021-03-11011 March 2021 Request for Withholding Information from Public Disclosure ML20184A0012020-07-0606 July 2020 Request for Withholding Information from Public Disclosure ML20026A0012020-02-11011 February 2020 Request for Withholding Information from Public Disclosure ML20012H1732020-01-13013 January 2020 Request for Withholding Information from Public Disclosure ML18171A0462018-06-29029 June 2018 Request for Withholding Information from Public Disclosure (Westinghouse) ML18171A0342018-06-29029 June 2018 Request for Withholding Information from Public Disclosure (Holtec) ML17316A0022017-11-27027 November 2017 Request for Withholding Information from Public Disclosure (CAC Nos. MF8991 and MF8992; EPID: L-2016-LLA-0039) ML17316A0012017-11-27027 November 2017 Request for Withholding Information from Public Disclosure (CAC Nos. MF8991 and MF8992; EPID: L-2016-LLA-0039) ML17316A0002017-11-27027 November 2017 Request for Withholding Information from Public Disclosure (CAC Nos. MF8991 and MF8992; EPID: L-2016-LLA-0039) ML16211A0592016-10-21021 October 2016 Request for Withholding Information from Public Disclosure ML16020A2192016-02-17017 February 2016 Request for Withholding Information from Public Disclosure for Indian Point Unit Nos. 2 and 3 ML15288A1402015-12-0404 December 2015 Request for Withholding Information from Public Disclosure ML15288A4022015-12-0404 December 2015 Request for Withholding Information from Public Disclosure ML15288A2122015-12-0404 December 2015 Request for Withholding Information from Public Disclosure ML15230A4102015-09-19019 September 2015 Request for Withholding Information from Public Disclosure ML15083A0792015-04-17017 April 2015 Request for Withholding Information from Public Disclosure for Shutdown Margin Confirmation ML14217A2062014-08-14014 August 2014 Respect for Withholding Information from Public Disclosure ML14119A0732014-06-18018 June 2014 Staff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident ML14139A3592014-06-17017 June 2014 Issuance of Amendments Request for Withholding Information from Public Disclosure ML14139A3962014-06-17017 June 2014 Request for Withholding Information from Public Disclosure ML13298A7082013-11-13013 November 2013 Request for Withholding Information from Public Disclosure Regarding License Amendment Request Concerning Pressure-Temperature Limits and Low Temperature Over-Pressure Protection Requirements for Indian Point Nuclear Generating Unit No. 2 ( ML12150A3832012-06-25025 June 2012 Request for Withholding Information from Public Disclosure (TAC Nos. ME1671, ME1672, and L24299) ML12153A1962012-06-25025 June 2012 Request for Withholding Information from Public Disclosure ML1134001842012-01-13013 January 2012 Request for Withholding Information from Public Disclosure ML1130703802011-12-0505 December 2011 Request for Withholding Information from Public Disclosure (TAC Nos. ME1671, ME1672, and L24299) ML1127701542011-10-31031 October 2011 Request for Withholding Information from Public Disclosure (TAC ME1671, ME1672, and L24299) ML1001908342010-01-22022 January 2010 Entergy Nuclear Operations, Inc. - Request for Withholding Information from Public Disclosure for Extension of Orders Approving Indirect Transfer of Control of Licenses (TAC Nos. ME2515 Through ME2522) ML0930206032009-11-12012 November 2009 Request for Withholding Information from Public Disclosure ML0736500192008-01-0707 January 2008 Entergy Nuclear Operations, Inc.-Request for Withholding Information from Public Disclosure for Indirect Transfer of Control of Licenses (TAC Nos. MD6178 Through MC6185) ML0727500322007-10-11011 October 2007 Entergy Nuclear Operations, Inc. - Request for Withholding Information from Public Disclosure for Indirect Transfer of Control of Licenses (TAC Nos. MD6178 Through MD6185) ML0610703002006-04-20020 April 2006 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure for Indian Point Nuclear Generating Unit No. 2 ML0508101892005-03-23023 March 2005 (IP3), Withholding from Public Disclosure, Polestar-prepared Calculation, Psat 3056CT.QA.04, Calculation of Indian Point 3 Engineered Safety Feature Component Leakage Iodine Release with Boundary Layer Effect, Rev. 1 ML0426703652004-09-23023 September 2004 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure ML0411400692004-04-23023 April 2004 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure ML0320200092003-07-21021 July 2003 Withholding from Public Disclosure, Wcobra/Trac Computer Code and Related Material ML0316209792003-06-11011 June 2003 Caldon, Inc., Request for Withholding Information from Public Disclosure. ML0304501082003-02-13013 February 2003 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure for Indian Point, Unit No. 2 ML0303101292003-01-31031 January 2003 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure ML0232905142002-11-25025 November 2002 Westinghouse Electric Company, Request for Additional Information for Withholding from Public Disclosure for Indian Point Nuclear Generating Unit 3 ML0232904732002-11-25025 November 2002 Caldon, Inc., Request for Withholding Information from Public Disclosure for Indian Point Nuclear Generating Unit No. 3 ML0220507412002-08-15015 August 2002 Request for Withholding Information in Westinghouse WCAP-15902-P, Rev. 0 from Public Disclosure 2021-03-11
[Table view] |
Text
March 11, 2021 Vice President, Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249
SUBJECT:
INDIAN POINT NUCLEAR GENERATING UNIT NO. 3 - REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR (EPID L-2020-LLA-0051)
Dear Sir or Madam:
By letters dated October 2, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20276A322) and November 9, 2020 (ADAMS Accession No. ML20314A355), Entergy Operations, Inc. submitted affidavits dated September 30, 2020, and November 4, 2020, respectively, executed by Kimberly Manzione, Licensing Manager, Holtec International, requesting that the information contained in the following documents be withheld from public disclosure pursuant to Section 2.390 of Title 10 of the Code of Federal Regulations (10 CFR):
, Response to Requests for Additional Information (Proprietary),
and Enclosure 2, Holtec Report HI-2188625, Structural Evaluation of HI-LIFT Device and Fuel Storage Building Walls at Indian Point Unit 3, Revision 2 (Proprietary), to Entergy Letter NL-20-070 dated October 2, 2020
, Response to Requests for Additional Information (Proprietary),, Holtec Report HI-2188549, HI-LIFT Design Specification for IPEC Unit 3 (Proprietary), and Enclosure 3, Holtec Drawing 11654, "IPEC, IP3 HI-LIFT General Arrangement," Revision 2 (Proprietary) to Entergy Letter NL-20-078 dated November 9, 2020 Non-proprietary versions of these documents have been placed in the U.S. Nuclear Regulatory Commissions (NRCs) Public Document Room and added to the NRC Library in ADAMS under Accession Nos. ML20276A322 and ML20314A355, respectively.
The affidavit dated November 4, 2020, stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
(4)a.
Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by Holtecs competitors without license from Holtec International constitutes a competitive economic advantage over other companies; (4)b.
Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product; (4)e.
Information which discloses patentable subject matter for which it may be desirable to obtain patent protection.
The affidavit dated September 30, 2020, stated that the submitted information should be considered exempt from mandatory public disclosure for the aforementioned reasons (4)a. and (4)b. only.
We have reviewed your application and the material accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavits, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the versions of the submitted documents marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-1030 or Richard.Guzman@nrc.gov.
Sincerely,
/RA/
Richard V. Guzman, Senior Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-286 cc:
K.Manzione@holtec.com Listserv
ML21060B602 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DORL/LPL1/BC NAME RGuzman JBurkhardt JDanna DATE 03/02/2021 03/05/2021 03/11/2021 OFFICE NRR/DORL/LPL1/PM NAME RGuzman DATE 03/11/2021