Other: ML21092A091, ML21194A408, ML21231A182, ML21314A218, ML21346A000, ML21363A165, NL-20-021, Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device, RS-21-077, License Amendment to Revise Technical Specification 3.7.9, Ultimate Heat Sink
|
MONTHYEARNL-20-021, Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-03-24024 March 2020 Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Other ML20084Q1912020-03-24024 March 2020 New York State Motion for Leave to Amend Contentions NY-2 and NY-3 Project stage: Request ML20108E9482020-04-17017 April 2020 Acceptance Review Determination for Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Acceptance Review ML20184A0012020-07-0606 July 2020 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML21363A1582020-07-31031 July 2020 E-mail from A. Peterson,Nyserda to R. Guzman, NRC, Informal Questions Indian Point Unit 3, HI-LIFT Crane License Amendment Request Project stage: Request ML20233B0152020-08-20020 August 2020 Request for Additional Information (E-mail Dated 8/20/20) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device Project stage: RAI ML20268C2352020-09-24024 September 2020 Request for Additional Information (E-mail Dated 9/24/20) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device Project stage: RAI NL-20-070, Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-10-0202 October 2020 Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Response to RAI ML21363A1602020-10-22022 October 2020 E-mail from A. Peterson, NYSERDA, to R. Guzman, NRC, Informal Questions Indian Point Unit 3, HI-LIFT Crane License Amendment Request Project stage: Request NL-20-077, Submittal of Quality Assurance Program Manual Revision 22020-11-0909 November 2020 Submittal of Quality Assurance Program Manual Revision 2 Project stage: Request NL-20-078, Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-11-0909 November 2020 Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Response to RAI ML21013A0142020-12-21021 December 2020 Clarification Call for Draft RAIs (E-mail Dated 12/21/20) License Amendmet Request to Revise Licensing Basis for New Auxiliary Lifting Device Project stage: Draft RAI ML21013A0152021-01-12012 January 2021 Draft Request for Additional Information (E-mail Dated 1/12/2021) License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device Project stage: Draft RAI ML21019A5672021-01-19019 January 2021 Second Round Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device Project stage: RAI ML21363A1642021-01-19019 January 2021 E-mail from A. Peterson, NYSERDA, to R. Guzman, NRC, Informal Questions Indian Point Unit 3, HI-LIFT Crane License Amendment Request Project stage: Request NL-21-014, Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2021-01-26026 January 2021 Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Request ML21060B6022021-03-11011 March 2021 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML21078A5102021-03-19019 March 2021 E-mail from P. Couture to R. Guzman) Hi-Lift Crane Proposed License Amendment Request Confirmatory Information Project stage: Request ML21363A1652021-03-23023 March 2021 3/23/2021 E-mail from R. Guzman, NRC, to A. Peterson, NYSERDA, State Comments for IP3 HI-LIFT Crane License Amendment Request Project stage: Other ML21092A0912021-04-0202 April 2021 E-mail NRR Review Hour Estimate Change Supporting the Hi-Lift Crane Proposed License Amendment Request Review Project stage: Other ML21096A3332021-04-0606 April 2021 E-mail Dated 4/6/2021, Transmittal of Draft Safety Evaluation for Proposed License Amendment Revision to Licensing Basis to Incorporate the Installation and Use of of New Auxiliary Lifting Device Project stage: Draft Approval ML21111A3612021-04-21021 April 2021 4/21/2021 Letter from A. Peterson (NYSERDA) to R. Guzman (Nrc), New York State Comments Indian Point Energy Center Unit 3 License Amendment Request (HI-LIFT Crane) Project stage: Request ML21112A2672021-04-22022 April 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (Public Redacted Version) Project stage: RAI NL-21-039, Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary2021-05-20020 May 2021 Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Project stage: Response to RAI ML21194A4082021-07-13013 July 2021 (7-13-2021) E-mail NRR Review Hour Estimate Change Supporting the Hi-Lift Crane Proposed License Amendment Request Review Project stage: Other RS-21-077, License Amendment to Revise Technical Specification 3.7.9, Ultimate Heat Sink2021-08-0202 August 2021 License Amendment to Revise Technical Specification 3.7.9, Ultimate Heat Sink Project stage: Other ML21231A1822021-08-26026 August 2021 Unit, No. 3 - Audit Plan in Support of Review of License Amendment Request Regarding the Installation and Use of a New Auxiliary Lifting Device Project stage: Other ML21337A2952021-12-0303 December 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (E-mail Dated 12/3/2021) Project stage: RAI ML21346A0002021-12-16016 December 2021 Unit, No. 3 - Regulatory Audit Summary Concerning License Amendment Request to Install and Use a New Auxiliary Lifting Device Project stage: Other ML22003A1932022-01-0303 January 2022 Response to Requests for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device Project stage: Response to RAI ML21314A2182022-01-18018 January 2022 Audit Plan in Support of Review of License Amendment Request Regarding the Ultimate Heat Sink Project stage: Other ML22028A1032022-01-28028 January 2022 E-mail Dated 1/28/2022, Transmittal of Draft Safety Evaluation for Proposed License Amendment Revision to Licensing Basis to Incorporate the Installation and Use of of New Auxiliary Lifting Device Project stage: Draft Approval ML21091A3052022-02-28028 February 2022 Issuance of Amendment No. 272 Revision to Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device (EPID L-2020-LLA-0051) (Non-Proprietary) Project stage: Approval 2021-12-03
[Table View] |
Text
From:
Peterson, Alyse L (NYSERDA)
To:
Guzman, Richard
Subject:
[External_Sender] Informal questions: 3/24/20 license amendment request for new IP3 crane Date:
Friday, July 31, 2020 8:34:08 AM Hi Rich, We are continuing our review of theMarch 24, 2020 license amendment request for a new crane at IP3 and have some questions (see below). Please note that our review of this item is still ongoing and we will likely have additional questions and concerns along the way. I provide these now since you've previously expressed that you and the other NRC reviewers generally find our questions to provide a helpful perspective as you conduct your NRC review. The questions have been divided up into several categories: safety, timeline & installation, procedures, operations & training, cost, and precedent.
- Thanks, Alyse
- Safety
- 1. In general, what are the concerns with the wet transfer method of spent fuel removal that would favor the installation of the HI-LIFT crane? Pg. 5/39
- 2. Compared to the wet transfer method, what additional benefits would the installation of Hi-Lift crane provide to plant safety and operations? Pg. 5/39
- 3. Considering there is an existing 40-ton crane in the fuel storage building at IP3, how will the NRC evaluate any potential safety concerns with the installation and operation of the HI-LIFT crane?
- 4. What takeaways from the San Onofre fuel handling issue in August 2018 is the NRC applying to its safety analysis of the proposed HI-LIFT crane and its operation?
- 5. The proposed HI-LIFT crane will have a maintenance position, which will allow the HI-LIFT to pivot further over the truck bay in the Unit 3 spent fuel pool building. Will NRC require Entergy to perform seismic and safety analyses of the HI-LIFT crane when placed in the maintenance position?
- 6. The License Amendment states that the HI-LIFT will be supported entirely by the south Spent Fuel Pool wall, which was built with six-foot thick concrete. What was the original intent/criteria that led to the robust construction of this wall? How does the installation and use of the HI-LIFT not interfere with the original intent of the south Spent Fuel Pool wall?
- Timeline and Installation
- 1. In addition to the installation of the HI-LIFT crane, what other changes does the NRC expect to be implemented by Entergy within 90 days of approval of the license amendment? Pg. 2/39
- 2. Will acceptance of this license amendment relieve Entergy of any other regulatory commitments with regards to safety? Will acceptance of this license amendment require additional regulatory commitments on behalf of Entergy with respect to safety?
- 3. Has Entergy provided additional information on the scope and timeline of work activities associated with the HI-LIFT crane to the NRC? If no, why not? If yes, how does the NRC plan to evaluate the scope and timeline of work activities?
- 4. Does the NRC plan to assess and/or inspect the locations of crane anchors? Pg. 11/39
- 5. Why didnt the NRC require Entergy to locate and validate the anchor pattern prior to submitting a structural evaluation to the NRC? Does the NRC plan to review Entergys structural evaluation again after an anchor pattern and anchor locations have been finalized? Pg. 11/39
- 6. How will the NRC ensure that the installation of the HI-LIFT crane is completed safely and
efficiently?
- Procedures
- 1. How will the NRC evaluate the procedures for testing, inspecting, and maintaining the HI-LIFT crane device?
- 2. Has the impact of dropped loads/canisters on spent fuel pool safety and operations been assessed and provided to the NRC? If no, does the NRC plan to have Entergy study the impact of dropped loads/canisters on spent fuel pool safety and operations? Pg. 13/39
- 3. Has the NRC qualified a spent fuel removal crane as a single failure proof crane in the past? If yes, please specify when and where.
- 4. What criteria will the NRC consider in assessing whether the HI-LIFT crane should be qualified as a single failure proof crane? Pg. 13/39
- 5. Will the NRC have a person on-site to oversee testing of the HI-LIFT crane? Is this required? Will the NRC need to be present for any or all further testing performed on the HI-LIFT crane after initial testing? If not, does the NRC have an oversight or audit program to confirm plant conformance with mandated testing schedules and procedures?
- 6. Has the NRC considered additional requirements, regulations or standards in order to address below-the-hook accidents at nuclear plants? If so, what are they and how would they be implemented or enforced?
- Operation and Training
- 1. How will the NRC evaluate the adequacy of the operator control station? Will the NRC perform unplanned spot-checks, site visits or inspections?
- 2. How will the NRC assess the training of the HI-LIFT crane operators?
- 3. If this license amendment is approved prior to the proposed License Transfer, will any additional filings be required on behalf of the incoming owner in terms of further operations of the HI-LIFT crane?
- 4. Has NRC considered what would happen if the HI-LIFT Seismic Switch disconnected the power supply controlling HI-LIFT motion during spent fuel movement (either because of an earthquake or due to equipment malfunction)? Pg. 8/39
- Cost
- 1. Has Entergy provided the costs to purchase and install the HI-LIFT crane to the NRC? If no, why not? If yes, how does the NRC plan to assess these costs?
- 2. Will the purchase and installation costs of the HI-LIFT crane be funded through the Indian Point decommissioning trust fund? How does the NRC plan to evaluate the funding source for the purchase and installation of the crane?
- Precedent
- 1. Is the NRC aware of any other nuclear plants that utilize a wall-mounted crane for spent fuel transfers?
- 2. Entergy cited the approval of the Davit Crane at the Humboldt Bay Power Plant as precedent for approving this license amendment. How is this crane similar and/or different from the HI-LIFT crane?
Pg. 16/39
- 3. Why should the approval of the Davit crane be used as precedent for approving the HI-LIFT crane?
Pg. 16/39 Alyse Peterson, P.E.
Senior Advisor State Liaison Officer Designee Nuclear Coordination and Radioactive Waste Policy NYSERDA 17 Columbia CirclelAlbany, NY 12203-6399 P: 518-862-1090 x3274lF: 518-862-1091lE:alyse.peterson@nyserda.ny.gov nyserda.ny.gov follow : friend : connect with NYSERDA