MONTHYEARIR 05000280/20240052024-08-26026 August 2024 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2024005 and 05000281-2024005), Rev 1 ML24179A2932024-07-0101 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24115A1952024-04-24024 April 2024 Notification of Surry Power Station Comprehensive Engineering Team Inspection - U.S. NRC Inspection Report 05000280/2024011 and 05000281/2024011 ML24144A2432024-03-0808 March 2024 002 Radiation Safety Baseline Inspection Information Request IR 05000280/20230062024-02-28028 February 2024 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2023006 and 05000281/2023006 IR 05000280/20230052023-08-23023 August 2023 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2023005 and 05000281/2023005) IR 05000280/20220062023-03-0101 March 2023 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2022006 and 05000281/2022006 ML22339A1582022-11-30030 November 2022 Requalification Inspection Notification Letter IR 05000280/20220052022-08-24024 August 2022 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Reports 05000280/2022005 and 05000281/2022005) ML22223A1192022-08-14014 August 2022 RP Inspection Document Request Letter Final ML22168A0272022-06-15015 June 2022 Information Request for the Cyber-Security Baseline Security Inspection, Notification to Perform Inspection 05000280/2022404; 05000281/202240 IR 05000280/20210062022-03-0202 March 2022 Annual Assessment Letter for Surry Power Station, Units 1 and 2 (Reports No. 05000280/2021006 and 05000281/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections IR 05000280/20210052021-08-31031 August 2021 Mid-Cycle Letter Revised Updated Inspection Plan for Surry Power Station, Units 1 and 2 (05000280/2021005 and 05000281/2021005) IR 05000280/20210012021-08-26026 August 2021 Updated Inspection Plan for Surry Power Station, Units 1 and 2 -(05000280/2021001 and 05000281/2021001) ML21239A0052021-08-26026 August 2021 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 - (Report 05000280/2021001 and 05000281/2021001) IR 05000280/20200062021-03-0303 March 2021 Annual Assessment Letter for Surry Power Station, Units 1 and 2 NRC Inspection Reports 05000280/2020006 and 05000281/2020006 ML21061A0292021-03-0101 March 2021 2021 Sur - POV Inspection Information Request ML21050A0352021-02-18018 February 2021 Radiation Safety Baseline Inspection Information Request ML20315A2492020-11-0909 November 2020 Requal Inspection Notification Letter W Materials List IR 05000280/20200052020-08-24024 August 2020 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2020005 and 05000281/2020005) ML20175A7802020-06-23023 June 2020 Heat Sink RFI ML20092J5002020-04-0101 April 2020 Radiation Safety Baseline Inspection Information Request IR 05000280/20190062020-03-0303 March 2020 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2019006 and 05000281/2019006 IR 05000280/20190052019-08-27027 August 2019 Updated Inspection Plan for Surry Power Station, Units 1 and 2, NRC Report 05000280/2019005 and 05000281/2019005 IR 05000280/20180062019-03-0404 March 2019 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Report 05000280/2018006 and 05000281/2018006 ML19057A1052019-02-26026 February 2019 License Renewal Phase 4 2019003 RFI - SD ML18283A7332018-10-0101 October 2018 Rad Safety Inspection RFI IR 05000280/20180052018-08-23023 August 2018 Updated Inspection Plan for Surry Power Station Units 1 and 2, NRC Report 05000280/2018005 and 05000281/2018005 ML18215A1252018-08-0303 August 2018 U2 ISI SGI 2018004 - Notification of Inspection and RFI (Public) IR 05000280/20170062018-02-28028 February 2018 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2017006 and 05000281/2017006, 05000280/2017402 and 05000281/2017402, 05000280/2017501 and 05000281/2017501 ML18037B1092018-02-0505 February 2018 Emergency Preparedness Inspection and Request for Information ML17290A0592017-10-13013 October 2017 Radiation Safety Inspection Document Request IR 05000280/20170052017-08-21021 August 2017 Updated Inspection Plan for Surry Power Station, Units 1 and 2 - Report 05000280/2017005 and 05000281/2017005 IR 05000280/20160062017-03-0101 March 2017 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - Report 05000280/2016006 and 05000281/2016006 ML16307A1972016-11-0202 November 2016 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML16244A1262016-08-31031 August 2016 Mid-Cycle Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Report 05000280,281/2016005 ML16062A2732016-03-0202 March 2016 Annual Assessment Letter IR 05000280/20150052015-09-0101 September 2015 Mid-Cycle Letter for Surry Power Station Units 1 and 2 - NRC Assessment Report 05000280/2015005 and 05000281/2015005 ML15140A4142015-05-20020 May 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000280/20140012015-03-0404 March 2015 Annual Assessment Letter for Surry Power Station, Units 1 and 2 Report 05000280/2014001 and 05000281/2014001 IR 05000280/20140062014-09-0202 September 2014 Mid-Cycle Letter for Surry, Units 1 & 2, NRC Assessment Report 05000280/2014006, 05000281/2014006 IR 05000280/20130012014-03-0404 March 2014 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - Report 05000280/2013001 and 05000281/2013001 ML13262A1812013-09-17017 September 2013 Notification of Inspection and Request for Information ML13246A1352013-09-0303 September 2013 Mid Cycle Assessment Letter ML13123A3552013-05-0202 May 2013 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000280/20120012013-03-0404 March 2013 Annual Assessment Letter, Surry Power Station, Units 1 and 2, 05000280/2012001 and 05000281/2012001 ML12248A1232012-09-0404 September 2012 Mid Cycle Assessment Letter Surry 2012 ML1206506182012-03-0505 March 2012 EOC Report 22 ML1124401072011-09-0101 September 2011 Report 22 - Surry Inspection/Activity Plan, 09/01/2011 - 12/31/2012 2024-08-26
[Table view] Category:Letter
MONTHYEARML24283A0702024-10-0707 October 2024 Annual Submittal of Technical Specifications Bases Changes Pursuant to Technical Specification 6.4.J IR 05000280/20244032024-10-0303 October 2024 Cyber Security Inspection Report 05000280-2024403 and 05000281-2024403 Cover Letter (Public) IR 05000280/20240102024-10-0202 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000280/2024010 and 05000281/2024010 ML24270A0022024-09-25025 September 2024 Inservice Inspection Owners Activity Report (OAR) ML24248A1712024-09-0303 September 2024 Proposed License Amendment Request - Temporary Service Water Supply to the Component Cooling Heat Exchangers IR 05000280/20240052024-08-26026 August 2024 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2024005 and 05000281-2024005), Rev 1 ML24219A2372024-08-23023 August 2024 Issuance of Amendment Nos. 319 and 319, Adoption of TSTF-577, Rev. 1, Revised Frequencies for Steam Generator Tube Inspection, ML24207A0402024-08-21021 August 2024 Summary of July 17, 2024, Public Meeting - TS 3.7/3.14 AOT for SW Piping Maintenance IR 05000280/20240112024-08-13013 August 2024 Comprehensive Engineering Team Inspection Report 05000280/2024011 and 05000281/2024011 ML24164A0012024-08-12012 August 2024 Proposed Alternative Relief Request V-1 Inservice Testing of Pressure Isolation Valves (EPID l-2023-LLR-0060) IR 05000280/20240022024-08-0101 August 2024 Integrated Inspection Report 05000280/2024002 and 05000281/2024002 05000280/LER-2024-001, Troubleshooting Initiated Unknown Turbine Trip Feature in Control System2024-07-30030 July 2024 Troubleshooting Initiated Unknown Turbine Trip Feature in Control System ML24165A2782024-07-17017 July 2024 Issuance of Amendment Nos. 318 and 318, Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection ML24165A1232024-07-17017 July 2024 Proposed Alternative Relief Request P-1, P-2 Inservice Testing of Residual Heat and Containment Spray Pumps (EPID l-2023-LLR-0058) ML24190A4192024-07-0808 July 2024 Inservice Testing (IST) Program for Pumps and Valves Revised Sixth IST Interval Start Date and Updated Technical Specifications References for Alternative Request V-1 ML24179A2932024-07-0101 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24166A0622024-06-18018 June 2024 – Proposed Alternative Relief Request P-3, P-4 Inservice Testing of Boric Acid, Component Cooling Water Pumps ML24157A0542024-06-13013 June 2024 Audit Summary in Support of License Amendment Request for Proposed Reclassification of Low Head Safety Injection Flow Instrumentation Related to Regulatory Guide 1.97 ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24141A2512024-05-20020 May 2024 Proposed License Amendment Request - Reclassification of Low Head Safety Injection Flow Indication Regulatory Guide 1.97 Variable - Supplemental Information ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A2302024-05-13013 May 2024 Core 1 Cycle 33 Pattern Mdr Revision 0 ML24130A2492024-05-0909 May 2024 Submittal of Information in Support of Surry Power Station Unit 1 Thermal Shield Flexure Replacement Campaign ML24130A2032024-05-0909 May 2024 Proposed License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections Supplemental Information ML24130A1192024-05-0707 May 2024 Inservice Test Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests - Response to Request for Additional Information Regarding Alternative Request V-1 ML24142A3852024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report IR 05000280/20240012024-04-30030 April 2024 Integrated Inspection Report 05000280-2024001 and 05000281-2024001 ML24122C6522024-04-30030 April 2024 Annual Radiological Environmental Operating Report ML24122B3032024-04-29029 April 2024 Associated Independent Spent Fuel Storage Installation, Revision to Emergency Plan Report of Change IR 05000280/20244022024-04-29029 April 2024 Security Baseline Inspection Report 05000280/2024402 and 05000281/2024402 ML24115A1952024-04-24024 April 2024 Notification of Surry Power Station Comprehensive Engineering Team Inspection - U.S. NRC Inspection Report 05000280/2024011 and 05000281/2024011 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24108A1812024-04-15015 April 2024 Proposed License Amendment Request - Reclassification of Low Head Safety Injection Flow Indication Regulatory Guide 1.97 Variable Supplemental Information ML24095A2172024-04-12012 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report ML24088A2482024-03-26026 March 2024 Inservice Testing Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests- Response to Request for Additional Information ML24087A2082024-03-22022 March 2024 Proposed License Amendment Request Addition of Containment Limiting Condition for Operation and Surveillance Requirements ML24078A2642024-03-21021 March 2024 – Regulatory Audit in Support of License Amendment Request to Proposed Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection Flow Instrumentation ML24087A1522024-03-18018 March 2024 Annual Changes, Tests, and Experiments Report Regulatory Commitment Evaluation Report ML24023A5762024-03-0808 March 2024 Correction to Issuance of Amendment Nos. 315 and 315, Regarding Revised Emergency Plan for Relocation of the Technical Support Center IR 05000280/20230062024-02-28028 February 2024 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2023006 and 05000281/2023006 ML24032A4712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24051A1782024-02-19019 February 2024 Proposed License Amendment Request - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML24057A0612024-02-19019 February 2024 and Virgil C. Summer Power Nuclear Stations - Nuclear Property Insurance Coverage IR 05000280/20230042024-02-0909 February 2024 Integrated Inspection Report 05000280/2023004 and 05000281/2023004 IR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 IR 05000280/20230102024-01-18018 January 2024 – Age Related Degradation Inspection Report 05000280-2023010 and 05000281-2023010 ML23312A1922024-01-18018 January 2024 Issuance of Amendment Nos. 316 & 316 Regarding a Risk Informed Approach for Tornado Classification of the Fuel Handling Trolley Support Structure 2024-09-03
[Table view] |
Inspection Report - Surry - 2020005 |
---|
|
|
Text
August 24, 2020
SUBJECT:
UPDATED INSPECTION PLAN FOR SURRY POWER STATION UNITS 1 AND 2 (REPORT 05000280/2020005 AND 05000281/2020005)
Dear Mr. Stoddard:
The enclosed inspection plan lists the inspections scheduled through June 30, 2022, for Surry Power Station. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP), including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the May 28, 2020 memo, Inspection Guidance During Transition From COVID-19 Mandatory Telework (ML20141L766). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:
https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains but subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
The NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these inspections is being developed by the NRC staff. The staff expects to communicate the schedule for these inspections to each utility separately.
As stated in NRC Inspection Report 05000281/2020091 (ML20212L517), the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure (IP) 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area. This inspection will be scheduled after you notify the NRC of your readiness.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 404-997-4580 with any questions you have regarding this letter.
Sincerely,
/RA/
Stewart N. Bailey, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos. 05000280 and 05000281 License Nos. DPR-32 and DPR-37 Enclosure:
Inspection Plan SUBJECT: UPDATED INSPECTION PLAN FOR SURRY POWER STATION UNITS 1 AND 2 (REPORT 05000280/2020005 and 05000281/2020005)
DATED: AUGUST 24, 2020 Distribution:
M. Kowal, RII L. Gibson, RII OE MAIL RIDSNRRDRO RidsNrrPMSurryResource ROPassessment Resource ROPreports Resource PUBLIC ADAMS Accession No. ML20237F514 OFFICE RII: DRP RII: DRP RII: DRP NAME P. Niebaum D. Jackson S. Bailey DATE 08/13/2020 8/20/2020 8/24/2020 OFFICIAL AGENCY RECORD
IP 22 Inspection Activity Plan Report Surry 08/17/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count EMERGENCY PREPAREDNESS PROGRAM INPSECTION (CONTINUATION) 1 1, 2 09/09/2020 09/09/2020 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2 09/09/2020 09/09/2020 IP 71114.05 000720 Maintenance of Emergency Preparedness DESIGN BASES ASSURANCE INSPECTION (TEAM) 6 1, 2 09/14/2020 09/18/2020 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
1, 2 09/28/2020 10/02/2020 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
CORPORATE OFFICE AA/FFD INSPECTION 2 1, 2 01/11/2021 01/15/2021 IP 71130.01 000733 Access Authorization 1, 2 01/11/2021 01/15/2021 IP 71130.08 000740 Fitness For Duty Program SURRY REQUAL INSPECTION 2 1, 2 01/25/2021 01/29/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance SECURITY BASELINE INSPECTION 2 1, 2 02/01/2021 02/05/2021 IP 71130.01 000733 Access Authorization 1, 2 02/01/2021 02/05/2021 IP 71130.02 000734 Access Control 1, 2 02/01/2021 02/05/2021 IP 71130.08 000740 Fitness For Duty Program 1, 2 02/01/2021 02/05/2021 IP 71130.09 001656 Security Plan Changes 1, 2 02/01/2021 02/05/2021 IP 71151 001338 Performance Indicator Verification UNIT 1 IN-SERVICE INSPECTION +SG 2 1 04/12/2021 04/16/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
SECURITY BASELINE INSPECTION 2 1, 2 05/24/2021 05/28/2021 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2 05/24/2021 05/28/2021 IP 71130.07 000739 Security Training 1, 2 05/24/2021 05/28/2021 IP 81311 000831 Physical Security Requirements for Independent Spent Fuel Storage Installations RP PUBLIC RAD SAFETY & TRANSPORTATION INSPECTION 3 1, 2 05/24/2021 05/28/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 05/24/2021 05/28/2021 IP 71124.07 000731 Radiological Environmental Monitoring Program 1, 2 05/24/2021 05/28/2021 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &
Transportation 1, 2 05/24/2021 05/28/2021 IP 71151 000746 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report Surry 08/17/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count DESIGN BASES ASSURANCE INSPECTION (PROGRAMS) 3 1, 2 07/12/2021 07/16/2021 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements 1, 2 07/26/2021 07/30/2021 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements EMERGENCY PREPAREDNESS EXERCISE 5 1, 2 07/19/2021 07/23/2021 IP 71114.01 000716 Exercise Evaluation 1, 2 07/19/2021 07/23/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2 07/19/2021 07/23/2021 IP 71151 001397 Performance Indicator Verification SURRY INITIAL LICENSE EXAM 3 1, 2 07/19/2021 07/23/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1, 2 08/23/2021 09/03/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
TRIENNIAL FIRE PROTECTION INSPECTION 4 1, 2 09/20/2021 09/24/2021 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial)
1, 2 10/04/2021 10/08/2021 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial)
FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - SUR 6 1, 2 09/27/2021 10/01/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1, 2 10/18/2021 10/22/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing MATERIAL CONTROL & ACCOUNTING 1 1, 2 10/01/2021 12/31/2021 IP 71130.11 000742 Material Control and Accounting (MC&A)
UNIT 2 IN-SERVICE INSPECTION +SG 2 2 10/11/2021 10/15/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP OCCUPATIONAL RAD SAFETY BASELINE INSPECTION 2 1, 2 10/18/2021 10/22/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 10/18/2021 10/22/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 10/18/2021 10/22/2021 IP 71151 000746 Performance Indicator Verification EVALUATIONS OF CHANGES, TESTS AND EXPERIMENTS 3 1, 2 01/31/2022 02/04/2022 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments SECURITY BASELINE INSPECTION 1 1, 2 03/07/2022 03/11/2022 IP 71130.02 000734 Access Control This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report Surry 08/17/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count SECURITY BASELINE INSPECTION 1 1, 2 03/07/2022 03/11/2022 IP 71130.09 001656 Security Plan Changes 1, 2 03/07/2022 03/11/2022 IP 71151 001338 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.