MONTHYEARML24302A1762024-10-22022 October 2024 Core Operating Limits Report Surry 2 Cycle 33 Pattern Hot Revision 0 ML24283A0702024-10-0707 October 2024 Annual Submittal of Technical Specifications Bases Changes Pursuant to Technical Specification 6.4.J IR 05000280/20240102024-10-0202 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000280/2024010 and 05000281/2024010 ML24270A0022024-09-25025 September 2024 Inservice Inspection Owners Activity Report (OAR) ML24248A1712024-09-0303 September 2024 Proposed License Amendment Request - Temporary Service Water Supply to the Component Cooling Heat Exchangers IR 05000280/20240052024-08-26026 August 2024 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2024005 and 05000281-2024005), Rev 1 ML24219A2372024-08-23023 August 2024 Issuance of Amendment Nos. 319 and 319, Adoption of TSTF-577, Rev. 1, Revised Frequencies for Steam Generator Tube Inspection, ML24207A0402024-08-21021 August 2024 Summary of July 17, 2024, Public Meeting - TS 3.7/3.14 AOT for SW Piping Maintenance IR 05000280/20240112024-08-13013 August 2024 Comprehensive Engineering Team Inspection Report 05000280/2024011 and 05000281/2024011 ML24164A0012024-08-12012 August 2024 Proposed Alternative Relief Request V-1 Inservice Testing of Pressure Isolation Valves (EPID l-2023-LLR-0060) IR 05000280/20240022024-08-0101 August 2024 Integrated Inspection Report 05000280/2024002 and 05000281/2024002 05000280/LER-2024-001, Troubleshooting Initiated Unknown Turbine Trip Feature in Control System2024-07-30030 July 2024 Troubleshooting Initiated Unknown Turbine Trip Feature in Control System ML24165A2782024-07-17017 July 2024 Issuance of Amendment Nos. 318 and 318, Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection ML24165A1232024-07-17017 July 2024 Proposed Alternative Relief Request P-1, P-2 Inservice Testing of Residual Heat and Containment Spray Pumps (EPID l-2023-LLR-0058) ML24190A4192024-07-0808 July 2024 Inservice Testing (IST) Program for Pumps and Valves Revised Sixth IST Interval Start Date and Updated Technical Specifications References for Alternative Request V-1 ML24179A2932024-07-0101 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24166A0622024-06-18018 June 2024 – Proposed Alternative Relief Request P-3, P-4 Inservice Testing of Boric Acid, Component Cooling Water Pumps ML24157A0542024-06-13013 June 2024 Audit Summary in Support of License Amendment Request for Proposed Reclassification of Low Head Safety Injection Flow Instrumentation Related to Regulatory Guide 1.97 ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24141A2862024-05-22022 May 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000280/2024403 and 05000281- 2024403 IR 05000280/20244032024-05-22022 May 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000280/2024403 and 05000281- 2024403 ML24141A2512024-05-20020 May 2024 Proposed License Amendment Request - Reclassification of Low Head Safety Injection Flow Indication Regulatory Guide 1.97 Variable - Supplemental Information ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A2302024-05-13013 May 2024 Core 1 Cycle 33 Pattern Mdr Revision 0 ML24130A2032024-05-0909 May 2024 Proposed License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections Supplemental Information ML24130A2492024-05-0909 May 2024 Submittal of Information in Support of Surry Power Station Unit 1 Thermal Shield Flexure Replacement Campaign ML24130A1192024-05-0707 May 2024 Inservice Test Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests - Response to Request for Additional Information Regarding Alternative Request V-1 ML24142A3852024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report IR 05000280/20240012024-04-30030 April 2024 Integrated Inspection Report 05000280-2024001 and 05000281-2024001 ML24122C6522024-04-30030 April 2024 Annual Radiological Environmental Operating Report IR 05000280/20244022024-04-29029 April 2024 Security Baseline Inspection Report 05000280/2024402 and 05000281/2024402 ML24122B3032024-04-29029 April 2024 Associated Independent Spent Fuel Storage Installation, Revision to Emergency Plan Report of Change ML24115A1952024-04-24024 April 2024 Notification of Surry Power Station Comprehensive Engineering Team Inspection - U.S. NRC Inspection Report 05000280/2024011 and 05000281/2024011 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24108A1812024-04-15015 April 2024 Proposed License Amendment Request - Reclassification of Low Head Safety Injection Flow Indication Regulatory Guide 1.97 Variable Supplemental Information ML24095A2172024-04-12012 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report ML24088A2482024-03-26026 March 2024 Inservice Testing Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests- Response to Request for Additional Information ML24087A2082024-03-22022 March 2024 Proposed License Amendment Request Addition of Containment Limiting Condition for Operation and Surveillance Requirements ML24078A2642024-03-21021 March 2024 – Regulatory Audit in Support of License Amendment Request to Proposed Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection Flow Instrumentation ML24087A1522024-03-18018 March 2024 Annual Changes, Tests, and Experiments Report Regulatory Commitment Evaluation Report ML24023A5762024-03-0808 March 2024 Correction to Issuance of Amendment Nos. 315 and 315, Regarding Revised Emergency Plan for Relocation of the Technical Support Center IR 05000280/20230062024-02-28028 February 2024 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2023006 and 05000281/2023006 ML24032A4712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24051A1782024-02-19019 February 2024 Proposed License Amendment Request - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML24057A0612024-02-19019 February 2024 And Virgil C. Summer Power Nuclear Stations - Nuclear Property Insurance Coverage IR 05000280/20230042024-02-0909 February 2024 Integrated Inspection Report 05000280/2023004 and 05000281/2023004 IR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 2024-09-03
[Table view] |
Inspection Report - Surry - 2007001 |
---|
|
|
Text
rch 1, 2007
SUBJECT:
ANNUAL ASSESSMENT LETTER - SURRY POWER STATION (NRC INSPECTION REPORT 05000280/2007001 AND 05000281/2007001)
Dear Mr. Christian:
On February 8, 2007, the NRC technical staff completed its performance review of the Surry Power Station for the period from January 1 through December 31, 2006. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and the enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and a resultant inspection plan.
Overall, Surry Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as the previous three quarters, was within the Regulatory Response column of the NRCs Action Matrix, based on a White inspection finding in the Emergency Preparedness Cornerstone. The White inspection finding involved the licensees drill critique not identifying that the proper emergency action level was not entered during a full scale exercise. The White finding was identified in the first quarter of calendar year 2006. The NRC conducted a Supplemental Inspection Procedure 95001, Inspection for One or Two White Inputs In a Strategic Performance, in the Emergency Preparedness Cornerstone on November 15, 2006.
Supplemental Inspection Report Nos. 05000280/2006502 and 05000281/2006502 documents no findings of significance were identified and the violation associated with the White finding was considered closed. Therefore, we plan to conduct reactor oversight process (ROP)
baseline inspections at your facility. We also plan on conducting non-ROP inspections of the independent spent fuel storage facility and containment emergency recirculation sump blockage modifications. Additionally, initial reactor operator licensing examinations are scheduled.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through September 30, 2008. The inspection plan is provided to minimize the resource impact on your staff and to allow for the resolution of any scheduling conflicts and
VEPCO 2 personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last twelve months of the inspection plan are tentative and may be revised at the mid-cycle review meeting.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Mr. Guthrie at (404) 562-4662 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Charles A. Casto, Director Division of Reactor Projects Docket No.: 50-280, 50-281,72-002, 72-055 Licensee No.: DPR-32, DPR-37, SNM-2501 Enclosure: Surry Inspection / Activity Plan cc w/encl: (See page 3)
_________________________
OFFICE RII:DRP RII:DRP SIGNATURE LXG1 GXG NAME LGarner:rcm EGuthrie DATE 03/01/2007 03/01/2007 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO
VEPCO 3 cc w/encl:
Chris L. Funderburk, Director Nuclear Licensing and Operations Support Virginia Electric & Power Company Electronic Mail Distribution Donald E. Jernigan Site Vice President Surry Power Station Virginia Electric & Power Company Electronic Mail Distribution Virginia State Corporation Commission Division of Energy Regulation P. O. Box 1197 Richmond, VA 23209 Lillian M. Cuoco, Esq.
Senior Counsel Dominion Resources Services, Inc.
Electronic Mail Distribution Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219
VEPCO 4 Letter to David from Charles A. Casto dated March 1, 2007 SUBJECT: ANNUAL ASSESSMENT LETTER - SURRY POWER STATION (NRC INSPECTION REPORT 05000280/2007001 AND 05000281/2007001 S. P. Lingam, NRR C. Evans (Part 72 Only)
L. Slack, RII EICS OE Mail (email address if applicable)
RIDSNRRDIRS RIDSNRRDIRSIPAB INPO PUBLIC