ML20203L883

From kanterella
Jump to navigation Jump to search
Insp Rept 50-458/98-01 on 980210-13.No Violations Noted. Major Areas Inspected:Licensee Performance & Capabilities During Fullscale,Biennial Exercise of Emergency Plan & Implementation Procedures
ML20203L883
Person / Time
Site: River Bend Entergy icon.png
Issue date: 03/04/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20203L882 List:
References
50-458-98-01, 50-458-98-1, NUDOCS 9803060284
Download: ML20203L883 (20)


See also: IR 05000458/1998001

Text

_ _ _ _ _ - _ _ .

. _.

c .

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket No.: 50-458

1

License No.: NPF-47 '

Report No.: 50-458/98-01

Licensee: Entergy Operations, Inc.

Facility: River Bend Station

Location: 5485 U.S. Highway 61

St. Francisville, Louisiana

Dates: February 10 to 13,1998

Inspector (s): Gail M. Good, Senior Emergency Preparedness Analyst, Team Leader

Michael E. Murphy, Reactor Engineer

'

Thomas H. Andrews, Emergency Preparedness Analyst

Michael C. Hay, Radiation Specialist

Observer: John C. Edgerly, Reactor Engineer

!

Approved By: Blaine Murray, Chief, Plant Support Branch

Division of Reactor Safety

Attachment: Supplemental Information

I

9803060284 980304

PDR ADOCK 05000458

G PDR

____

. _ .

._______-_- -

=

,

2

EXECUTIVE SUMMARY

River Bend Station

NRC Inspection Report 50-458/98-01

A routine, announced inspection of the licensee's performance and capabilities during the full.

scale, biennial exercise of the emergency plan and implementing procedures was performed.

The inspection team observed activities in the control room simulator, technical support center,

operations support center, and emergency operations facility.

Plant Sucoort

.

Overall, performance was generally very good. The control room (CR), technical support

center (TSC), and emergency operations facility (EOF) successfully implemented all

assigned emergency plan functions. Performance in these facilities was very good.

.

The CR crew's performance was very good. Operators promptly responded to plant

events and applied proper mitigating actions. The initiating emergency event was

properly classified. Corresponding offsite agency notifications were correct, and timely.

CR briefings were frequent, structured, and interactive. Normal CR communications,

both intemal and extemal, were very good. Confusion about who was coordinating and

directing operations response teams or individuals could have affected personnel

accountability (Section P4.2).

.

The TSC staffs performance was very good. The facility was promptly activated in an

orderly fashion. Event classifications were made in a timely manner using the proper

emergency action levels. Notifications to NRC were accurate and timely. Protective

actions for onsite perso, nel were very good. Tasks and priorities were not clearly

tracked. Habitability surveys were frequently performed but did not include all areas

(Section P4.3).

.

The Operations Support Center (OSC) staffs performance was satisfactory. Due to the

potentialimpact on mitigation efforts, the failure to promptly and properly dispatch inplant

response teams was identified as an exercise weakness. It took up to an hour to

dispatch several teams, and some teams, including a high priority team, were canceled

before the teams could be dispatched. Work team order documentation was incomplete

and would have hampered event response reconstruction. Habitability controls were

properly implemented. Team tracking status boards were not always maintained and

could have affected personnel accountability. Good ALARA practices were

demonstrated by radiation protection personnel assigned to assist work teams, although

one team did not use proper contamination controls (Section P4.4).

.

The EOF staffs performance was very good. Facility activation was timely and

controlled, although there were no precautions taken for personnel who traveled from the

s

site to the EOF during simulated sevce weather conditions. Management oversight was

very good. Facility briefings were comprehensive and made a positive contribution to

iacility performance. With one relatively minor exception, offsite agency notifications

._________________ _ - _ - .

.- ,

3-

were correct and timely. Dose assessment and field team control activities were well

managed and performed to support protective action recommendations. Protective

action recommendations to offsite authorities were correct and timely. Interactions with

offsite response team members were open and informative (Section P4.5).

.

The exercise objectives were appropriate to meet emergency plan requirements. ~ The

initially submitted scenario was not acceptable because it was too similar to the 1996

exercise scenario (two of four events were the same). Appropriate actions were taken

once the concems were raised. The final exercise scenario was sufficiently challenging

to test onsite emergency response capabilities (Section P4.6),

.

The critique process was identified as a program strength and was significantly improved

when compared to the 1996 biennial exercise self critique. The evaluation team

identified several important areas in need of correction / improvement (Section P4.7).

. _ _ _ _

. _ _ _ - -

e

J,.

IV. Plant Sunnort  !

P4 Staff Knowledge and Performance in Emergency Preparedness

P4.1 ' Exercise Conduct and Scenario Descriotion (82301 and 82302)

The licensee conducted a full-scale, biennial emergency preparedness exercise on

February 11 and 12,1998. The exercise was conducted to test major portions of the

onsite (licensee) and offsite emergency response capabilities. Day 1 consisted of plur a

pathway elements, and Day 2 consisted of ingestion pathway elements. During Day 1,

the licensee activated its emergency response organization and all emergency response

~ facilities. The Federal Emergency Management Agency evaluated the offsite response

capabilities of the state of Louisiana and West Feliciana, East Feliciana, Pointe Coupee,

West Baton Rouge, and East Baton Rouge Parishes. The Federal Emergency

Man 0gement Agency willissue a separate report.

i

The exercise scenario was run using the CR simulator in a dynamic mode. The exercise

scenario began at 7:51 a.m., with the plant operating at 100 percent power. Normal

weekday personnel were available for duties. At the start of the exercise, the area was

under a severe thunderstorm and tomado watch with grid perturbations reported due to

the weather. The crew was in Abnormal Operating Procedure 0029, " Severe Weather

Operation," Revision 12. The low pressure core spray pump was tagged out of cervice

for motor inspection, and Condensate Transfer Pump CNS-P1B was tagged out for

replacement of the motor end bearing.

At 8:02 a.m., the CR received telephone notification from a security guard that a tornado

had touched down just south of the turbine building and that there was apparent damage

to the fire pump house.

At 8:06 a.m., a ground on Condensate Transfer Pump CNS-P1 A occurred, but its

breaker failed to trip. ACB300, load center feeder breaker, tripped causing a loss of

480VAC NJS-LDCIL. At 8:07 a.m., the shift superintendent declared an alert based on

Emergency Action Level 14.3 (tomado touchdown onsite). Plant power reduction, at

10 percent per hour, was in progress due to the deteriorating weather conditions.

At 9:01 a.m., an electrical transient caused a fault on Bus 1NNS-SWG1C which resulted

in a trip and lockout of all feeder breakers to the bus. Significant electricalloads affected

were Chiller HVN CHLR1C and 1E22*S004, Division til 4160 volt bus, causing the high

pressure core spray diesel generator to start and tie on to the E22 switchgear.

At 10:01 a.m., a condensate line common header pipe weld cracked causing a leak in

the turbine building. Reactor feed pumps tripped off, a ma..ual reactor scram was

inserted but all rods did not insert, the turbine inadvertently tripped, and alternate rod

insertion and standby liquid control both failed. At 10:05 a.m., the TSC declared a site

area emergency based on Emergency Action Level 7 (anticipated transient without

scram).

o

__.

. .

-5-

. Shortly thereafter, the CR operators responded to the first turbine building radiation

alarm. As a result, the TSC declared a genomi emergency at 10:17 a.m. based on a

loss of two of three fission product baniers with a potential loss of the third.

At 10:20 a.m., a reactor core isolation cooling steam line break occurred in the steam -

tunnel at the upstream weld on E51*MOVF064, resulting in a reactor _ core isolation

cooling isolation signal on high main steam tunnel temperatures. - The inboard isolation

valve failed to isolate which caused a loss of all high pressure feed and a loss of coolant

accident pathway from the reactor pressure vessel to the steam tunnel. Radioactivny -

was released through the turbine building ventilation system with no charcoal or high

efficiency particulate air filtration.

At 11:11 a.m., all rods were reported in, and the CR personnel continued to work on the

established priorities: recover injection and isolate the leak. At 12:41 p.m., injection was >

reestablished, and the reactor core isolation cooling system was isolated at 1:10 p.m. to

stop the leak. At 1:13 p.m., the CR received confirmation that the release had stopoed

The exercise was terminated at 1:41 p.m.

P4.2 Control Room (CR)

a. Inanection Scone (82301-03.02)  ;

4

The inspectors observed and evaluated the CR simulator staff as they performed tasks in

response to the exercise scenario conditions. These tasks included event detection and

classification, analysis of plant conditions, offsite agency notifications, intomal and

extemal communications, and adherence to the emergency plan and procedures. The

inspectors reviewed applicable emergency plan sections and procedures, operations

procedures, logs, and notification forms.

b. Observations and Findinas

During the exercise, the CR crew quickly recognized, analyzed, and responded to

emergency events. The shift superintendent declared an alert within minutes of being

informed of the initiating conditions, using the correct emergency action level.

Corresponding offsite agency notifications were made within regulatory time limits. The

pager system activation (emergency response organization call-out) was promptly

activated following the alert declaration. H owever, the wrong code was used and the

resulting activation was for an actual emergency, rather than a drill. When the error we.s

recognized, the shift superintendent immediately ordered another pager system

activation with the proper code. The pagers reactivated with the proper drill

announcement. A plant wide announcement was also made to advise all personnel of

the error.

The CR crew consistently responded to system annunciators using the proper

annunewtor response procedure. The crew exhibited excellent team work. Normal CR

communications, both intemal and external, were very good. However, when the tempo

of events increased, there were instances when expected three-part communications-

.9

__ ________-_ _ ____ __________________ - __

. .. . .. .. .. ..

.

.

[

'

6-

were not used, and the target individual was not identified. For example, immediately

after the attempt to manually scram and identification of a failure of the plant to scram,

several communications had to be repeated or personnel had to request a repeat of the

communication. Also, at one point the CR supervisor had to forcefally direct all

personnel to ' slow down" in order to refocus proper communicatiens techniques.

Briefings were frequent, structured, and interactive. However, following the activation of

the TSC and OSC, several briefings were conducted to identify field team activities and

locations. There was apparent confusion about who was coordinating and directing the

operations response teams or individuals (i.e., the CR, TSC, or OSC). As a result,

personnel accountability was questionable.

c. Conclusion 6

The CR crew's performance was very good. Operators promptly responded to plant

events and applied proper mitigating actions. The initiating emergency event was

properly classified. Corresponding offsite agency notifications were correct and timely.

CR briefings were frequent, structured, and interactive. Normal CR communications,

both internal and extemal, were very good. When the tempo increased,- there were

instances when expected three-part communications were not used, and the target

individual was not identified. The initial activation of the pager system was incorrect but

did not affect the emergency response. Confusion about who was coordinating and

directing operations response teams or individuals could have aWeted personnel

accountability.

,

'4.3 Technical Sucoort Center (TSC)

a. Insoection Scooe (82301-03.03)

The inspectors observed and evaluated the TSC staff as they performed tasks

necessary to respond to the exercise scenario conditions. These tasks included staffing

and activation, accident assessment, NRC notifications, personnel accountability, facility

management and control, onsite protective action decisions and implementation, intemal

and external communications, assistance and support to the CR, and prioritization of

mitigating actions. The inspectors reviewed applicable emergency plan sections,

procedures, and logs.

b. Observations and Findinos

The TSC was staffed and activated in a timely manner. The first responder arrived

immediately after the 8:10 a.m. plant announcement for the alert declaration. Upon

arrival, responders signed in on the position staffing board. The last " minimum staffing"

position was filled at 8:26 a.m., and ihe last person signed in at 8:31 a.m. The TSC was

activated at 8:54 a.m. when emergency director / recovery manager duties were

transferred from the CR.

__n

_ - _ _ _ _ _ _ _ - _ _ _ - _ --

-

  • .

7

The emergency director requested current meteorological cla from dose assessment

personnel, because the alert was based on severe weather, Upon learning that the

current indications showed 45 mph sustained winds, the emergency director asked

security to consider suspending any outside walking patrols and use attemative

methods. The emergency director then cautioned against dispatching any personnel

outside of the buildir'g until the weather abated. The emergency director's actions

demonstrated good awareness of conditions and concern for plant personnel protection.

Upon notification from the CR that the reactor scram was not successful (automatic and

manual), the emergency director promptly declared a site area emergency using the

correct emergency action level. Shortly after the anticipated transient without scram,

plant conditions begati to degrade: reactor water level was dropping, tb core was not

!

subcntical, and there was indi(Ation of a :eak within the steam tunnel. Ine emergency

director determined that general emergency conditions existed due to a loss of two

fission product barriers with a potential' ,s of the third. The decision was challenged by

one of the TSC staff to confirm lost /potentially lost barriers. Based on the emergency

director's explanation and th9 available information, the inspectors determined that the

'

general emergency declaration was performed properly. The questioning attitude ci the

TSC Waff demoratrated good cross checking.

Following the emergency classification upgrade, a communicator simulated the NRC

notifications. The information provided wap tecurate and timely.

Personnel accountability within the TSC was quickly established and maintained

throughout the exercise. There were three doors into the TSC envelope: one door led

into the computer room ares and was not used, another door led into the main TSC work

area and was quickly disabled to prevent entry into the center, and the other door had a

key card reader for accountability purposes. Participants used the card readei when

enterirg and exiting the center.

Following the site area emergency declaration, a plant evacuation was simulated.

Security perscnnel performed the prccedural actions to determine personnel

accountability. Using simulated information, accountability was properly established

within 30 minutes of the site area emergency declaration.

The emergency director conducted frecuent and comprehensive briefings. The briefings

were announced in advance and contained a F .cussion of priorities. Occasionally, the

briefings contained a summary of previous ever;ts. Functional area coordinators

participated in the briefings.

The emergency director made good onsite protective action decisions and implemented

them approp iately. Examples included:

.

The decision to make potassium iodide available to workers was made in

accordance with procedures. Personnel in the TSC and OSC were told to

consider taking potassium iodide before leaving the centers.

.

_ . __

.

8-

.

Frequent announcements were made in the TSC and OSC regarding the release

in progress, general direction of the plume, and need to avoid affected areas.

l

.

During the planning discussions for the steam tunnel Ontry, the T3C considered

the increased consumption of ak from self contained breathing apparatuses in

tb high temperature environment. The plans included staging extra air bottles at

the location, prior to actually entering the steam tunnel.

The process for tracking tasks, assignments, and pr%rities was confusing. The TSC staff

used several methods to display tasks, assignments, and prior; ties within the center. A

video link was used to transmit a list of tasks and priorities to the OSC. Tasks and l

priorities were updated and revised as plant conditions changed. A status board was

used to track TSC priorities. A large paper tablet was used to track TSC engineering

tasks. Engineering tasks were listed in sequential order as they wero assigned. On

several occasions, the priorities for the OSC and TSC were not consistent for extended

periods. In addition, the lack of a mechanism to link the engineering tasks to the TSC

priorities could have led to conflicting priorities.

The TSC staff correctly performed dose assessments and projections. TSC personnel

used a 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> default release duration time for dose projections. When it appeared that

the release duration woWd exceed 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, doss assessment personnel performed

several calculations to determine the release duration that would cause the

Environmental Protection Agency protective action guidelines to be exceeded at

,

10 miles. The result was effectively used to establish / focus equipment repair priorities to

! terminate the release. The inspectors determined that this was a good use of dose

projection capability within the TSC.

TSC habitability surveys, including area radiation surveys, contamination surveys, and

air sample measurements, wer? conducteo frequently but wee not alway;. ; .operly

completed Forexample:

.

Area radiation and contamination surveys were only performed in occupied

areas. Rooms that were not routinely occupied were not surveyed. As a result,

contamination could have gone unnoticed.

.

The air sampler was placed in the TSC access hallway inside the TSC ventilation

envelope but outside the door used for accountability control. Sir.ce the location

was different ti,an the main TSC work area, the air sample may not have been

representative of the TSC environment.

.

The ak sampler was operated through the exercise with the flow rate showing

about 85 titers per minute. The applicable procedure stated that the flow through

the charcoal cartridge was to be about 2 cubic feet per minute. Using the

licensee's procedure, the indicated flow rate was actually about 3 cubic feet per

minute. Since there was no mechanism to adjust the air sampler flow rate, it

appeared that the flow indication was simply an indicator that there was air flow

inrough the sampler at the calibrated flow rate. Following the exercise, the

- _-

_ _ _ - _ _ _ _ _ _ _ _ ____-__ -

-

a

.Q.

'

licensee detonnined that the actual flow rate was about 2 cubic feet per minute

and that the indicator was in error. Had the flow rate been as indicated, the air

sampling results could have been nonconservative.

c. Conclusion _s

The TSC stdrs performance was very good. The facility was promptly activated in an

orderly fashion. Event classifications were made in a timely manner using the proper

emergency action levels. Notifications to NRC were accurate and timely. Protective

actions for onsite personnel were very good. Precautions were taken for the simulated,

severe weather, arrangements were made for additional air bottles for the steam tunnel

entry, potassium iodide was authorized, and pt'ar.t personnel were cautioned to avoid

areas affected by the plume. Tasks and priorities wem not clearly tracked. Habitability

surveys were frequently performed but did not include all areas.

P4A Qoerations Suooort Center (QSC)

'

a. Insoection Scope (82301-03.05)

The inspectors observed and evaluated the OSC staff as they performed tasks in

response to the scenario conditions. These tasks included functional staffing and

emergency response team dispatch and coordination in support of CR and TSC

requests. The inspectors reviewed applicable emergency plan sections, procedures,

logs, checklists, and forms.

b. Observation 1 add Findinas

The OSC was promptly staffed and activated. Activation began shortly after the

8:07 a.m. alert declaration and was completed at 8:54 a.m. The OSC director properly

announced the activation to center personne!.

Center briefings were provided on a regular basis by the TSC (via loudspeakers). The

briefings appropriately addressed plant parameters, current emergency classification,

task priorities, and response team work status. The detail and frequency of the briefings

precluded the need for the OSC director to personally conduct regular OSC briefings.

The process used to form and dispatch teams, coupled with the level of activity and the

distribution of responsibilities, inhibited the OSC's ability to promptly and properly

dispatch response teams. This determination was based on the following observations:

.

The OSC director sometimes logged when the TSC notified the OSC to dispatch

a repair team. Using the OSC director'c log and the corresponding team work

order dispatch time, inspectors quantified dispatch times for 6 teams (a total of

16 teams were dispatched). There was insufficient documentation to quantify

dispatch times for the other 10 teams. Of the 6 teams that could be quantified,

4 took opproximately 53-60 minutes to be dispatched following OSC notification

(one may have been 25 57 minutes).

- - -

. - - -

.

l

l

-10-

+ Of the 21 " Team Work Orders" initiated by the OSC director,5 were cancelled

prior to the team being dispatched, because the teams were no longer needed.

As previously mentioned,16 teams were dispatched. One of the cancelled teams

- the number one priority - y " ready to leue the OSC 40 minutes after the

initial TSC request. The team e ince: led because the CR accomplished an

alternate success path.

. The OSC director was actively involved in arranging work team composition.

EIP 2-016, " Operations Support Ceni;r,' Revision 15, Section 4.4, stated that

,

work team composition v'as the responsibility of the woA team facilitator and the

OSC manager Similarly, the OSC director handled communications from inplant

'

work teams, another OSC manager and/or work team fach!tator duty. The

involvement in team formation and communications inhibited the OSC director's

'

ability to provide direction and control.

. Procedurally required documentation was incomplete and would have hampered

event response econstruction. Section 4.2 of EIP 2-016 stated that the OSC

manager wa: t.. ensure that OSC team work orders were completed for all

.

dispatched teams. Attachment 1 to EIP 2-016 stated that tne OSC director was

to ensure that work orders were fully completed for teams that had completed

assigned tasks, inspectors identified the following incomplete work orders:

(1) Radiation protection br efing/ debriefing sections were not completed for

3 of 4 teams that were redirected to perform other tasks while in the field.

(2) Of the 16 dispatched work teams,7 work team orders did not include

dicpatch/ return times.

(3) Of the 16 dispatched teams,12 work team orders did not indicate that the

"OSC Director / Manager Task Briefing" was completed.

The failure to promptiv and properly dispatch inpiant field teams was identified as an

exercise weakness because of the potential impact on mitigation effeds

(50-458/9801 01).

Habitability surveys were performed on a regular basis using calibrated instruments.

Radiological survey data sheets were reviewed and found to be detailed and

comprehensive. Habitability controls implemented in the OSC were very good.

The OSC team tracking status board, maintained by the status communicator, was not

'

always properly rnaintained and could have adversely affec;ed personnel accountability.

information that was known by the OSC director and/or manager concerning work tear 1

status was not always provided to the status communicator. On one occasion, the OSC

had to contact the CR to find out the location of an individual. In general, work teams

were satisfactorily tracked.

1

__________ ___________________-_ _ _________ -

  • .

-11

Teams observed la the field used proper protective clot: Mg, minimizing the potential for

personnel contamination. In contrast, contamination controls were not always properly

performed. !nspectors observed that 3 out of 4 members of r work team, including a

radiation protection technician, passed through a radiological step-off pad without

frisking. Failing to frisk could spread contamination to an uncontrolled area.

Radiation protection personnel assigned to provide work team coverage exhibited good

as low as is reasor, ably achievable (ALARA) job practices. Radiation protection

personnel properly located and informed teams of low dose areas for idle teams / team

members,

c. Conclusions

The OSC staff's performance was satisfactory. */he center was activated in a timely

manner, and briefings were frequent and comp ebensivo. Due to the potentialimpact on

mitigation efforts, the failure to promptly and properly dispatch inplant response teams

was identified as an exercise weakness. It took up to an hour to dispatch several teams,

,

and some teams, including a high priority team, were cancelled before the teams could

be dispatched. Work team order documentation was incomplete and would have

hampered event response reconstruction. Habitability controls were property

implemented. Team tracking status boards were not always maintained and could have

affected personnel accountability, Good Al. ARA practices wero demonstrated by

radiation protection personnel assigned to assist work teams, although one team did not

use proper contamination controls.

P4.5 Emergency Ooerations Facility (EOF)

a. Insoection Scooe (8230103.04)

The inspectors observed the EOF's staff as they performed tasks in response to the

exercise. These tasks included facility activation, notification of state and local response

agencies, development and issuance of protective action recommendations, dose

projections, field team control, and direct interactions with offsite agency response

personnel. The inspectors reviewed applicable emergency plan sections and

procedures, forms, dose projections, and logs.

b. Observations and Findings

The EOF was promptly staffed following the 8:07 a.m. alert declaration. Upon arrival,

personnel simulated locking exterior doors, prepared registration forms to log emergency

responders, initiated position checklists, established communications with counterparts,

and determined facility habitability. Activation steps were completed at 8:57 a.m., and

the recovery manager responsibilities (offsite agency notifications, dose

assessment / protective action recommendations) were assumed by the EOF at 9:05 a.rn.

- The transfer of responsibilities was conducted in a controlled manner to ensure that key

response actions were not overlooked or misunderstood.

I

  • ;

_ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ -

a

12-

l

Although the EOF was staffed promptly, the safety of facility personnel was not

considered after the ?.lert was declared due to a tomado touctdown onsito. No special

precautions were taken or considered for those personnel who traveled from the site to

the EOF, although precautions were taken for onsite and offsite monitoring teams.

Under some circumstances (e.g., security events and severe weather conditions),

judgement may be needed regarding the decision to activate emergency response

facilities.

Management oversight in the EOF was very good. Briefings were frequent and

comprehensive. Facility members were given prior notice to prepare, and all facility

personnel participated in the briefings. The briefings included input from operations,

radiation protection, engineering, administrative, and state personnel. Special emphasis

was placed on facility priorttles and what effect changing plant conditions would have on

EOF activities. As the exercise progressed, briefings included a summary of previous

significant events. During periods of relatively low activity, facility personnel were

encouraged to review and update individual logs. The recovery manager was also

sensitive to noise levels and distractions. On several occasions, the recovery manager

limited observer access to the EOF.

Offsite agency notifications for the site area and general emergency were made within

the required 15-minute time limit. Short notification m'assage forms were uppropriately

used for classification and protective action recommendation changes. Long notification

message forms were usually issued, as necessary, to convey changes in release status

l and dose projection data. Inspectors identified two issues conceming the content of the

l long notification message forms.

1

.

There was a discrepancy between the affected sectors used by the utility and the

state which wculd have been confusing to outside organizations (NRC, media,

etc.). The long notification message form for the general emergency (Message 6)

indicated that the affected sectors were D, E, and F. The state included Sector G

because Scenario 4 included some areas within Sector G. This would be

confusing to organizations who would talk to both the state and the utility.

.

On one occasion, valuable information was not properly communicated to offsite

autnorities. Although projected doses based on the actual release duration time

(2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />) were appropriately calculated, the information was not included on a

long notification message form. Forms issued after the release stopped

incorrectly stated that there were no projected offsite doses gall zeros).

Protectivo action recommendations, identified as scenario numbers (127 based on

different distances and downwind sectors), were correctly formulated and promptly

communicated to offsite authorities. Following the general emergency declaration, a

default 2 mile radius /5-mile downwind evacuation wa1 correctly recommended

(Scenario 4). When the release rate increa,ed, the r9 commendation was appropriately

upgraded to a 5-mile radius /10-mile downwind evacuation (Scenario 16). As required by

procedures, EOF personnel verified that the offsite agencies received the protective

~

___

_- _ _ . _. ._. - - _ -.

. <

,

13-

action recomrnendations and obtained the approved scenario (protective action

decision).

Dose assessment and field team control activities were wil managed and controlled to

support protective action recommendations. Numerous dose projections were calculated

based on plant conditions and field team data. There was good coordination between

the utility and state offsite monitoring tearns, and utility offsite monitoring team doses

were closely monitored to determine the need to issue potassium iodide.

However, the radiation protection advisor was not fully aware of procedural provisions for

a certain area of responsibility. Specifically, the radiation protection advisor was initially

not aware that EIP 2-024, 'Offsite Dose Calculations," Revision 17, allowed the use of

release duration times greater than 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> (Step 6.1.8). As previously discussed, dose

projections using the actual release duration time were eventually calculated. The failure

to use the actual release duration time could result in incorrect protective action

recommendations.

Facility habitability was appropriahly monitored during the exerc;ae. When the lock

failed on the EOF door and repairs were initiated, the effect on EOF habitability was

properly determined. Thormoluminescent dosiraeters and pocket ion chambers were

distributed to facility personnel during the activation process. Personnel were reminded

to read pocket ion chambers during periodic briefings.

interactions with state response team members who were stationed in the EOF were

frequent, open, and constructive. Upon arrival, state representatives were briefed on

plant conditions and prognosis. The state's input was solicited during briefings, and

changing plant conditions were quickly relayed so that offsite impact could be evaluated.

c. Conclusions

The EOF staff's performance was very good. Facility activation was timely and

controlled, although there were no precautiors taken for personnel who traveled from the

site to the EOF during simulated severe weather conditions. Management oversight was

very good. Facility briefings were comprehensive and made a positive contribution to

facility performance. With ane relatively minor exception, offsite agency notifications

were correct and timely. A notification made after the release stopped did not include

projected offsite doces. Dose assessment and field team control activities were well

managed and performed to support protective action recommendations. However, the

radiation protection advisar was not initially aware that the release duration time could

exceed the 2-hour default time. Protective action recommendations to offsite authorities

were correct and timely. Intera .;vns with offsite response team members were open

and informative.

e .c ,

14-

P4.6 Scenario and Exerciss Control

a. Insoection Scope (82301 and 82302)

The inspectors evaluated the exercise to assess the cha!!enge and realism of the

scenario and exercise control.

b. Observations and Findinas

The licensee submitted the exercise objectives and scenario for NRC review on

November 13 and 26,1997, respectively. The exercise objectives were appropriate to

meet emergency plan requirements (reference NRC letter dated December 3,1997). By

letter dated January 22,1998, the licensee was informed that the exercise scenario was

not acceptable. The scenario was rejected, because it was too similar to the 1996

biennial exercise scenario (two of four events were the same), if exercise participants

participated in the 1996 exercise, reviewed the correspondinj NRC report

(60-458/96-07), or were made aware of the outcome during tralning, response actions

could have been affected, it would not be accepabie for exercise participants to have

prior knowledge of exercise scenario events. Appropriate actions were taken once the

concerns were raised. The final exercise scenario was su'ficiently challenging to test

onsite emergency response capabilities.

Due to the initial scenario concern, the inspectors reviewed scenarios used in practice

drills to ensure they did not include exercise scenario events. Emergency planning

I

personnel provided scenario summaries for two integrated drills and three mini-drills.

l Although the scenarios were all different and did not include exercise scenario events,

the inspehrs expressed concerns about the level of pre-exercise training. The

preconditioning was greater than normal and initially caused concerns about whether the

other teams were as pwrared as the exercise team. In response, the licensee explained

that the '. raining was necessary because of a recent erihancement invoMng the CR

simulator. The simulator can now be used to display olant data via computer (in lieu of

using paper data). Moreover, additional training for the other teams was planned

(beginning the week tollowing the exercise). The planne.1 training would include

lessons-leamed by the responding team and mini-drills driven by the simulator. The

licensee's planned actions alleviated the inspectors' concerns.

Inspectors identified one isolated instance r f inappropriate controller / participant

interaction. A controller showed scenario survey data to a radiation protection technician

before the technician earned the data. The technician was not even in the area of

concern.

c. Conclusions

The exercise objectives were appropriate to meet emergency plan requirements. The

initially sut mitted scenario was not acceptable, because it was too similar to the 1996

exercise scenario (two of four events were the same). Appropriate actions were taken ,

.

T . .. .

-15

,

'

once the concerns were raised. The final exercise scenario was sufficiently challenging

to test onsite emergency insponse capabilities.

P4.7 Licaname Self Craique

a. Inanadion Scope (82301-03.13)

.

I

The inspectors observed and evaluated the licensee's post exercise facility ortiques and

the formal management critique on February 13,1998, to determine whether the process ,

would identify and characterire week or deficient areas in need of corrective action. >

b. Claantations andfindings

Post exercise critiques in the CR simulator, TSC, OSC, and EOF were thorough, open, ,

and seti critical. The post exercise critiques included input from controllers, evaluatorc,

and participants. The lack of participation by state representatives in the EOF detracted .

from the overall completenus. Participants in all facilities made a sincere effort to '

identify areas where performance could be improved.

During the February 13,1998, management critique, the emergency planr5g manager

and lead River Bend Station evaluators presented the preliminary exercise findings. The -t

breakdown of findings was as follows: one area for improvement in the CR/ simulator,

one potential weakness and four areas for improvement in the TSC, one weakness and ,

four areas for improvement in the OSC, and five areas for improvement in the EOF.' The '

potential weakness in the TSC involved TSC habitability, and the weskness in the OSC

involved command and control.

In addition to the River Bend Station evaluators, exercise evaluation was performed by

_ quality assurance personnel, licensee management, representatives from other

Region IV sites, and the Entergy peer review groupc- The peer review group consisted of _

the three emergency planning menagers from the other Entergy sites and

representatives from the Entergy Corporate Office. The integrated critique process was ,

considered a program strength.. There was a significant improvement when compared to

the 1996 biennial exercise self critique. Severalimportant areas in need of correction

vrra identified.

c. Conclualons  ;

The critique process was identified as a program strength and was signincantly improved

when compared to the 1996 biennial exercise self critique. The process includod site

evaluators, corporate evaluators, Entergy peer review group, other site evaluators, and

management evaluators. The evaluation team identified several important areas _in need

. of correction / improvement.

-,...-,-.,-4, ,. ,,~._m.,m,...,. - . - .. . . - . . . ~ . , ._ ., . . ..~ , , m,.mm-,.-4.~. ,, _-- m--., +, - - - - , - - -.y-_,, ,. ,,-- , , --

_ _ _ _ _ _ _-_______

. .. .

-16-

P5 Staff Training and Qualification in Emergency Preparedness

a. Insoection Scope (82701)

The inspectors reviewed the Updated Safety Analysis Report (USAR), plant access

training material, emergency plan, and radiolegical controls procedures to determine if

training requirements and commitments werts being met.

b. Observations and Findings

inspectors noted that Procedure EIP-2 012, * Radiation Exposure Controls," Revision 13, I

stated that 10 CFR Part 20 occupational exposure limits applied to all members of the I

emergency response organization, even if they had not received radiation worker

training. Although the licensee required all personnel to attend plant access trainireg,

which included a brief discuscion of radiation, the training did not include a discussion of

regelatory 1,mits, instructions for frisking, protection of the embryo / fetus per the declared

pregnant female program, etc. Since these topics were only discussed in radiation

worker training, inspectors questioned whether emergency response organization

members received training consistent with 10 CFR Part 19.12. The NRC intends to

pursue this matter as an inspection followup item to determine if Part 19.12 training

applies to emergency response personnel who do not normally receive radiation worker

training (50-458/9801-02).

The licensee's emergency plan stated that all personnel would receive emergency

, plan / procedure training in plant access and radiation worker training as described in the

!

USAR. The inspectors reviewed the USAR description of the general employee training

and compared it to the plant access training content. The USAR stated that the training

would include a discussion of Regulatory Guide 8.13 which discusses the effects of

radiation on the embryo / fetus. This subject was included as part of the licensee's

declared pre 0nant female program but was not discussed in the plant access training.

The inspectors did not have sufficient time to determine if the Regulatory Guide 8.13

subject matter was provided as part of other required training. it.e NRC intends to

pursue this matter as an unresolved item to determine if Regulatory Guide 8.13 training

is conducted in accordance with the USAR (50-458/9801-03).

c. Conclusions

One inspection followup item and one unresolved item were identified involving

personnel training.

V. Management Meetings

X1 Exit Meeting Summary

The inspectors presented the inspection results to members of licensee managernent at the

conclusion of the inspection on February 13,1998. The licensee a : knowledged the facts

presented. No proprietary information was identified.

_ - _

. ..-_--.. -

_- - . - . -.-.- -- _ _ -- . ---. - . . - - - ._.- -- . . -

.o .

,

! . 17

i

! The Federal Emergency Management Agency conducted a public meeting in St. Francisville,

Louisiana, on February 13,1998. Representatives from the Federal Emergency Management

Agency and NRC provided a br'ef discussion of preliminary exercise resuNs,

e

1

,

1

l

.'

,

i

l.

t

5

+

ev.- p 4g .g - -.ww--e.-my-w -,.rm% -,,--e. m -.7y,.,c--,#---- .-s, g-,--.m,,w,,,--,e ,

'

---er-v,------ r-e+--ws,-in.w-w----

. _ _ _ _ _ . . _ __ _ _______________ _ _ -_

o .. ,

ATTACHMENT

SUPPLEMENTAL INFORMATION

PARTIAL LIST OF PERSONS CONTACTED

Licensee

J. McGaha, Vice President, Operations

(A. Bellamy, Directoi, Site Support

M. Dietrich, Director, Quality Programs

J. Hurst, Senior Emergency Planner

J. Fowler, Manager, Quality Assurance

K. Huffstatler, Senior Emergency Planner

R. Jobe, Senior Emergency Planner

M. Jones, Senior Operations Instructor / Emergency Planner

R. King, Director, Nuclear Safety & Regulatory Aftairs

D. Lorfing, Supervisor, Licensing

W. O'Malley, Manager, Operations

P. O'Neil, Specialist, Licensinc

B. Ricketts, Supervisor, He .... Physics Shift

W. Spell, Supervisor, Health Physics Shift

i J. Waid, Director, Training

T. Wyrnore, Control Room Supervisor

Other Personnel

A. Morgan, Manager, Emergency Preparedness, Grand Gulf Nuclear Station

NHC

G. Replogie, Senior Resident inspector

LIST OF INSPECTION PROCEDURES USED

IP 82301 Evaluation of Exercises at Power Reacters

IP 82302 Review of Exercise Objectives and Scenarios for Power Reactors

IP 82701 Operational Status of the Emergency Preparedness Program

.

_ _ _ _ _ _ _ _ _ _ . _ _ - _ ___ ___

.

2

LIST OF ITEMS OPENED

Goened

50-458/98001-01 IFl Exercise weakness - Failure to promptly and properly dispatch

aplant response teams (Section P4.4)

l 50 4 8/98001 02 IFl Part 19.12 training for emergency response organization members

(Soction PS)

50 4 58/98001-03 URI Regulatory Guide 8.13 training per USAR (Section PS)

LIST OF ACRGNYMS USED

- Al. ARA As low as is reasonably achievable

l CR Control room

EOF Emergency operations facility

OSC Operations support center

TSC Technical support center

USAR Updated Safety Analysis Report

LIST OF DOCUMENTS REVIEWED

!

Emeroency lmolementina Procedures

EIP 2 001 Classification of Emergencies Revision 9

ElP 2-002 Classification Actions Revision 17

ElP 2-006 Notifications Revision 23

EIP 2-007 Protective Action Recommendation Guidelines Revision 16

EIP-2-012 Radiation F.xposure Controls Revision 13

EIP 2-014 Offsite F diological Monitoring Revision 16

EIP 2-018 Operations Support Center Revision 15

EIP 2-020 Emerg.: f Operations Facility Revision 19

EIP 2 024 Offsite Dose Calculations Revision 17

Other Procedures

AOP-0029 Severe Weather Operation Revision 12

__

o ..o

-3-

QJher Documents

River Bend Station Emergency Plan, Revision 16

River Bend Station Updated Safety Analysis Report, Section 13.2.2,' General Employee

Training,' Revision 7, January 1995

EO S LP-GET-PA~ . . 03, 'EOl Plant Access Training,' October 27,1997

EOl S-LP-GET RWT01.05, 'EOl Rad Worker Training," November 5,1997

Prenatal Information Guide for Radiation Workers (undated)

>