ML20205A413

From kanterella
Jump to navigation Jump to search
NRC Operator Licensing Exam Rept 50-458/99-301 (Including Completed & Graded Tests) for Tests Administered on 990222- 0303.All 14 Applicants Passed Exams
ML20205A413
Person / Time
Site: River Bend Entergy icon.png
Issue date: 03/23/1999
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20205A405 List:
References
50-458-99-301, NUDOCS 9903300376
Download: ML20205A413 (8)


See also: IR 05000458/1999301

Text

. . - . - . - - . . . . . . . . - . . . . - _

l

1

l

,

.

'

ENCLOSURE

,

l

I

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket.No.: 50-458

License No.: NPF-47

Report No.: 50-458/99-301

Licensee: Entergy Operations, Inc.

Facility: River Bend Station

Location: 5485 U.S. Highway 61 i

St. Francisville, Louisiana

Dates: February 22 through March 3,1999 .

Inspectors: Michael E. Murphy, Chief Examiner

Howard F. Bundy, Senior Reactor Engineer, Operations Branch

Thomas R. Meadows, Senior Reactor Engineer, Operations Branch

Steve L. McCrory, Senior Reactor Engineer, Operations Branch

,

Tom O. McKernon, Senior Reactor Engineer, Operations Branch

John L. Pellet, Chief, Operations Branch

Approved By: Arthur T. Howell 111, Director

Division of Reactor Safety

ATTACHMENTS:

Attachment 1: Supplemental Information

l

Attachment 2: Final Written Examinations and Answer Keys j

l

i

!1

~'

9903300376 990323

PDR ADOCK 05000458

V PDR

J

, - , - _ _ _ -. . .. . -- - . - . -.. .

.

.

-2-

EXECUTIVE SUMMARY ,

I

River Bend Station 4

NRC Inspection Report No. 50-458/99-301

NRC examiners evaluated the competency of 6 senior operator and 8 reactor operator license

. applicants for issuance of operating licenses at the River Bend Station. The licensee

developed the initial examinations using NUREG-1021, Interim Revision 8, January 1997. NRC

examiners reviewed and approved the examinations. The initial written examinations were

administered to all 14 applicants on February 19,1999, by facility proctors in accordance with

the guidance in NUREG-1021, Interim Revision 8. The NRC examiners administered the

operating tests on February 22 through March 3,1999.

Ooerations

  • All 14 applicants passed the examinations. No broad knowledge or training weaknesses ,

were identified as a result of evaluation of the graded written examinations. The 1

applicants exhibited good oversight, peer checking and communications. (Sections 04.1

,

and 04.2)

  • The examination submitted was adequate for administration and required only limited

enhancement and editorial corrections. The licensee staff incorporated enhancement

suggestions developed during the NRC review process. (Section 05.1.2)

l

ef

l

l

l

'

i

-3- l

Reoort Details

l

Summary of Plant Status  ;

I

The plant was at approximately 90% power at the start of the inspection and in power coast

down for the upcoming refueling outage during the inspection.

l. Operations

1

'

04 Operator Knowledge and Performance

l

04.1 initial Written Examination 1

a. Insoection Scope

1

On February 19,1999, the facility licensee proctored the administration of the written

examinations approved by the NRC to eight individuals who had applied for initial l

reactor operator licenses, three individuals who had applied for initial instant senior

'

operator licenses, and three individuals who had applied for initial upgrade senior

operator licenses. The licensee proposed grades for the written examinations and

evaluated the results for question validity and generic weaknesses. The examiners  !

reviewed the licensee's results. ,

1

b. Observations and Findinas

The minimum passing score was 80 percent. The candidates' scores for the written

examination ranged from 84 to 94 percent. The overall average score was

88.9 percent. The licensee's post-administration analysis identified that nine questions

were missed by more than 50 percent of the applicants. The questions missed were ,

three common, numbers 36,49,55, and 59; three reactor operator, numbers 76,79,90

and 97; and, three senior reactor operator, numbers 79,90,92, and 97. The chief

l

examiner's review of this analysis datermined that the erroneous answers were

generally dispersed and no broad training or knowledge weaknesses were identified.

1 here were no post-examination comments or changes to the written examination. 1

c. Conclusions l

All 14 applicants passed the written examinations. No broad knowledge or training

weaknesses were identified as a result of evaluation of the graded examinations.

- . - _ - .- .- .- -.- -- . -. .

.

Z

.

4

. 04.2 Initial Operatina Test

' a. Inspection Scope

The examination team administered the various portions of the operating examination to

the 14 applicants on February 22 through March 3,1999. Each applicant participated in

the appropriate number of dynamic simulator scenarios. Each reactor operator and

instant senior operator applicant received a walk-through test which consisted of ten

system and four administrative areas. The upgrade senior operator applicants were

tested in five system and four administrative areas.

'

b. Observations and Findinas

,

'

All applicants passed all portions of the operating test. Overall, the applicants

performed well in the dynamic simulator scenarios with good oversight, peer checks,

and communications noted by the examiners. Good crew briefs and status updates

were consistently practiced in a form meeting licensee expectations. Communications

clearly identified expected actions with consistent acknowledgment by the operators.

The applicants researched and applied technical specifications appropriately and

correctly applied abnormal and emergency procedure entry conditions.

Applicants correctly located and simulated operating local plant components during the

examination. The applicants also displayed alertness and ownership as evidenced

when one applicant noted a local fire alarm panel with a trouble alarm and immediately

notified the control room. The control room acknowledged the report and advised the

applicant that an auxiliary operator was being immediately dispatched to investigate.

The applicants prformed well during the walk-through examination, which indicated a

depth of associated system knowledge.

c. Conclusions

All 14 applicants passed the operating tests. The applicants exhibited good oversight,

peer checking and communications.

05 Operator Training and Qualification

05.1 Initial Licensina Examination Develooment

The facility licensee developed the initial licensing examination in accordance with

guidance provided in NUREG-1021," Operating Licensing Examination Standards,"

Interim Revision 8, dated January 1997.

,

.

. .

-5-

05.1.1 Examination Outline

a. Inspection Scope

The facility licensee submitted the initial examination outlines on October 23,1998. The

chief examiner reviewed the submittal against the requirements of NUREG-1021,

Interim Revision 8.

b. Observations and Findinas

The written examination outlines for both the reactor operator and senior reactor

operator met the knowledge and abilities distribution prescribed in NUREG 1021. The

administrative section outline was acceptable as submitted. The job performance

measure outline was acceptable except that the safety function distribution did not

comply with NUREG-1021 guidance. The chief examiner commented that the licensee

should review and comply with NUREG-1021 guidance prior to completing the draft

examination. The Scenario outlines were acceptable as submitted. The chief examiner

advised the licensee to be careful in differentiating between component failures and

instrument failures. The chief examiner determined that the initial examination outlines

satisfied NRC requirements.

c. Conclusions

i

The licensee submitted adequate examination outlines.

'

05.1.2 Examination Packaae

a. Inspection Scope i

l

The draft examinations were transmitted by the licensee to the NRC on

December 19,1998. The licensee submitted the completed final examination package ,

,

on February 8,1998. The chief examiner reviewed the examinations against the l

requirements of NUREG-1021, Interim Revision 8. l

b. Observations and Findinas

The draft written examination contained 125 questions,75 of which were common to

both the reactor operator and senior reactor operator examinations. Of the 125

questions,116 were new, eight were modified and one was from the licensee's bank.

The draf t examination was considered technically valid, to discriminate at the proper l

level, and responsive to the outline submitted by the licensee on October 23,1998. i

Following two independent NRC examiner reviews, the chief examiner provided editorial i

and enhancement suggestions for 28 questions. The comments generally related to

grammar. spelling, clarity of the question stem and distractor plausibility. After

discussion of the suggested enhancements, the licensee modified the examinations as 4

agreed. The chief examiner concurred with the resolution of the comments and the final

product.

.

-6-

The licensee submitted five scenarios, two of which were designated as backups. The

five scenarios were reviewed and validated during the week of January 25,1999, with

some enhancement and editorial comments to facilitate administration.

To support the system walk-through section of the operating test, the facility licensee

provided job performance measures dev6loped to evaluate selected operator tasks that

contained written task elements, performance standa,Js, and comprehensive evaluator

cues. Thirteen job performance measures were submittej with three designated as

backups. Personnel assignments and scheduling precluded any day-to-day repetition of

operating tests. The NRC review identified several enhancement and editorial

comments related to improved cues, information clarification for the benefit of the

examiner and to facilitate administration. The licensee incorporated all comments.

The licensee submitted six administrative job performance measures and two

administrative topic questions. This provided one set of five administrative job

performance measures for the senior reactor operator applicants and one set of four

administrative job performance measures with two administrative topic questions for the

reactor operator applicants. The NRC review identified only minor enhancement and

editorial comments related to eliminating overlap with operator actions in one of the

scenarios, and improving evaluation capability in one of the tasks. The licensee

incorporated all comments.

c. Conclusions

The examination submitted was adequate for administration and required only limited

enhancement and editorial corrections. The licensee staff incorporated enhancement

suggestions developed during the NRC review process. 1

l

05.2 Simulation Facility Performance l

a. Inspection Scope

'

The examiners observed simulator performance with regard to fidelity during the

examination validation and administration.

b. Observations and Findinas j

The simulation facility supported the validation and administration of the exar.lination

well. There was one instance of two anomalies occurring during a scenario, but they fit

the flow of events and caused neither a disruption nor a compromise in the examination l

ovaluations. The problem was evaluated at the conclusion of the scenario by the

technical support personnel and a potentially bad power supply was idenutied and

replaced. The scenarios were resumed with no further problems and with minimal

delay.

Since the facility was scheduled to accomplish a major modification to the simulator at

the conclusion of this examination, no simulation facility report will be included in this

inspection report.

t

. . . . . - - .

..

.

'.

7-

c. Conclusions

The simulator and simulator staff supported the examination well. No fidelity issues  ;

were identified.

V. Manacement Meetinas

X1 Exit Meeting Summary

The examiners presented the inspection results to members of the licensee

management at the conclusion af the inspection on March 3,1999. The licensee

acknowledged the findings presented.

The licensee did not identify as proprietary any information or materials examined duri.1g

this inspection.

- . . . . . _ . . _ . _ . . . . . - . - . - . . - .

'

,

,

- .

.

.

ATTACHMENT 1

SUPPLEMENTAL INFORMATION

PARTIAL LIST OF PERSONS CONTACTED

Licensee

C. Bush Jr., Operations Superintendent

4 M. Cantrell, Supervisor, Operations Training

B. Heikes, Supervisor, Simulator Support

R. King, Director, Nuclear Safety and Regulatory Affairs

D. Looney, Exam Developer

D. Mims, General Manager, Operations

W. O'Malley, Manager, Operations

J. O'Neil, Licensing Specialist -

M. Rasch, Exam Developer

M. Wagner, Supervisor, Operations Training

J. Waid, Director, Training

L. Woods, Supervisor Training Standards

NRC

N. Garrett, Resident inspector

i

j

,

5