Notice of Violation from Insp on 971125-980122.Violations Noted:Between 971018 & 1216,isolation Capability for Each Required Secondary Containment & Secondary Containment Bypass Penetration Flow Path Was Not Restored
ML20202H749
Person / Time
Site: Clinton Constellation icon.png
Issue date: 02/13/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20202H744 List:
References
50-461-97-25, NUDOCS 9802230013
Download: ML20202H749 (2)


Text

. _ _ _ _ _ _

e NOTICE OF VIOLATION lilinois Power Company : Docket No. 50-461 Clinton Power Station License No. NPF-62 During an NRC inspection conducted between Novamber 25,1997, and January 22,1998, two violations of NRC requirements were identified. in accordance with the " General Statement of =

_ Policy and Procedure for NRC Er..orcement Actions, NUREG 1600 (60 FR 34381; June 30, 1995), the violations are listed below:

1. . Technical Specification 3.5.2, "ECCS (Emergency Core Cooling System) - Shutdown,"

requires, in part, that two ECCS injection / spray subsystems shall be operable. - With two -

i required ECCS injection / splay subsystems inoperable, initiate action to restore wolation capability to each required secondary containment and secondary containment bypass '

penetration flow path not isolated.

Contrary to the above, between October 18 and December 16,1997, isolation capability for each required secondary containment and secondary containment bypass penetration flow path not isolated was not restored in that surveillance testing for Containment :

Building Fuel Transfer Pool Ventilation Plenum Radiation - High instruments was not :

performed. Consequenty, Secondary Containment isolation Dampers 1VF04Y, Tuel ,

Buil: ling Supply Outboard Isolation," 1VF06Y, " Fuel Building Supply Inboard Isolation,"

- 1VF07Y,'" Fuel Building Exhaust inboard isolation Damper," and 1VF09Y, " Fuel Building Exhaust Outboard isole, tion Damper," did not have isolation capability.

This is a Severity Level IV Violation (Supplement I).

2. . Technical Specification 3.8.8, " inverters - Shutdown," requires, in part, that in Mode 4,

- one divisional inverter capable of supplying one division of the Division I or 11 onsite Class IE uninterruptible AC bus electrical power distribution subsystems required by ,

. Limiting Condition of Operation (LCO) 3.8,10, " Distribution Systems - Shutdown," shall be 4

- operable. With one or more required divisional inverters inoperable, the limiting P:ondition for operation requires that actions be initiated to declare the affected required features inoperable immediately or suspend core alterations, suspend handling of irradiated fuel s assemblies in primary and secondary containment, suspad operations with the potential to orain the vessel, and initiate actions to restore required divisional inverters to an operable status immediately.

Contrary to the above, from November 8 to December 28,1997, the licensee did not initiate actions to restore required divisional inverters to an operable status immediately.

Specifically, operations personnel failed to note the impact on the Division I and ll inverters after declaring their respective room cooling fans inoperable.

This is a Suverity Level IV Violation (Supplement 1).

4 9802230013 980213 PDR ADOCK 05000461 G PDR

4-

- Notice of Violation 2- ,

Pursuant to the provisions of 10 CFR 2.201, Illinois Power Company is hereby required to sutimit a written statement or explanation to the U.S. Nuclear Regulatory Commissioni ATT.: Document Control Desk, Washington, D.C. 20555 with a copy to the Regional Administrator l Region III, and a oopy to the NRC Resident inspector at the facility that is the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of Violation.- This reply should be clearly -

marked as a " Reply to e Notice of Violation" and should include for each violation:- (1) the rearon -

- for the violation, or, if contested, the basis for disputing the violation or severity level,-(2) the corrective steps that have been taken and the results achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved; Your

_ response may reference or include previous docketed correspondence, if the correspondence adequately addresses the required response. If an adequate reply is not received within the time -

specified in this Notice, an order or a Domand for information may be iswed as to why the -

license should not be modified, suspended, or revoked, or why such other action as may be -

proper should not be taken. Where good cause is shown, consideration will be given to extending the response time.

~

If you contest this enforcement action, you should also provide a copy of your response to tho'

- Director, Office of Enforcement, United States Nuclear Regulatory Commission,' Washington,

. DC 20555-0001;

~

- Under the authority of Section 182 of the Act,42 U.S.C. 2232, this response shall be submitted under oath or affirmation.

Because your response will be placed in the NRC Public Document Room (PDR), to the extent

- possible, it should not include any personal privacy, proprietary, or safeguards information so that -

it can be placed in the PDR without redaction if personal privacy or proprietary information is l necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information tht:.t should be protected and redacted copy of your -

response that deletes such information. If you request withholding of such material, you my11 specifically identify the portions of your response that you seek to have withheld and provide in :

- detail the bases for your claim of withholding (e.g., explain why the disclosure of information will create an unwarranted invasion of personal privacy or provide the information required by 10 CFR 2.790(b) te wpport a request for withholding confidential commercial or financial

-information), if safegwrds information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.

. Dated at Lisle, Illinois this 13th day of February 1998