|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000155/19990051999-09-30030 September 1999 Insp Rept 50-155/99-05 on 990731-0921,site Insp & 990929 Public Meeting.No Violations Noted.Major Areas Inspected: Routine Decommissioning Insp Covered Aspects of Facility Mgt & Control & Decommissioning Support Activities IR 05000155/19990041999-08-12012 August 1999 Insp Rept 50-155/99-04 on 990609-0730.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities Including Security, Spent Fuel Safety & Radiological Safety IR 05000155/19990031999-06-21021 June 1999 Insp Rept 50-155/99-03 on 990416-0608.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990021999-04-26026 April 1999 Insp Rept 50-155/99-02 on 990226-0415.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990011999-03-19019 March 1999 Insp Rept 50-155/99-01 on 990113-0225.One non-cited Violation Noted.Major Areas Inspected:Aspects of Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980091999-01-15015 January 1999 Insp Rept 50-155/98-09 on 981201-990112.No Violations Noted. Major Areas Inspected:Licensee Management & Control, Decommissioning Support Activities,Sf Safety & Radiological Safety IR 05000155/19980081998-12-0303 December 1998 Insp Rept 50-155/98-08 on 980827-1130.No Violations Noted. Major Areas Inspected:Radiological Safety IR 05000155/19980071998-10-14014 October 1998 Insp Rept 50-155/98-07 on 980827-1007.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Physical Security,Spent Fuel Safety & Radiological Safety IR 05000155/19980061998-09-0303 September 1998 Insp Rept 50-155/98-06 on 980716-0826.No Violations Noted. Major Areas Inspected:Aspects of Licensee Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980051998-07-24024 July 1998 Insp Rept 50-155/98-05 on 980528-0715.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980031998-06-16016 June 1998 Insp Rept 50-155/98-03 on 980407-0527.Violation Noted.Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980021998-04-21021 April 1998 Insp Rept 50-155/98-02 on 980203-0406.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20203A0141998-02-14014 February 1998 Insp Rept 50-155/97-15 on 971205-980202.Violations Noted. Major Areas Inspected:Facility Management & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20197E5901997-12-17017 December 1997 Insp Rept 50-155/97-13 on 971008-1204.Violations Noted. Major Areas Inspected:Major Aspects of Licensee Decommissioning Activities,Including Facility Mgt & Control, Decommissioning Support & Spent Fuel Safety Controls IR 05000155/19970101997-11-26026 November 1997 Insp Rept 50-155/97-10 on 970802-1007.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 05000155/19970121997-10-17017 October 1997 Insp Rept 50-155/97-12 on 970812-1007.Violations Noted.Major Areas Inspected:Miscellaneous Security & Safeguards Issues IR 05000155/19970091997-10-0909 October 1997 Insp Rept 50-155/97-09 on 970617-0804.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering IR 05000155/19970111997-10-0606 October 1997 Insp Rept 50-155/97-11 on 970902-05.Violations Noted. Major Areas Inspected:Various Aspects of Licensee Chemistry Radiation Protection Programs IR 05000155/19970081997-07-22022 July 1997 Insp Rept 50-155/97-08 on 970430-0616.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20140G8931997-06-10010 June 1997 Insp Rept 50-155/97-04 on 970313-0429.Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000155/19970071997-06-0606 June 1997 Insp Rept 50-155/97-07 on 970426-0501.No Violations Noted. Major Areas Inspected:Licensee Fire Protection Program IR 05000155/19970061997-05-23023 May 1997 Insp Rept 50-155/97-06 on 970428-0502.No Violations Noted. Major Areas Inspected:Review of Vehicles Barrier Sys,Audits & Self Assessment,Testing,Maint,Security Contingency Capability & Protected Area Detection ML20141J9951997-05-19019 May 1997 Insp Rept 50-155/97-05 on 970303-0428.Violations Noted. Major Areas Inspected:Event in Which Workers Entered Power Block While Reactor at 9% Power Level Prior to Performance of Adequate Evaluation of Area Radiological Conditions IR 05000155/19970031997-05-13013 May 1997 Insp Rept 50-155/97-03 on 970331-0404.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program IR 05000155/19960121997-02-24024 February 1997 Insp Rept 50-155/96-12 on 961130-970117.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 05000155/19960011997-01-29029 January 1997 Insp Rept 50-155/96-01 on 961019-1129.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20133C5231997-01-0202 January 1997 Insp Rept 50-155/96-11 on 961202-06.Violations Noted.Major Areas Inspected:Radiological Protection & Chemistry Controls,Status of Rp&C Facilities & Equipment IR 05000155/19960071996-12-0606 December 1996 Insp Rept 50-155/96-07 on 960909-12.No Violations Noted. Major Areas Inspected:Emergency Plan & Procedures IR 05000155/19960061996-10-28028 October 1996 Insp Rept 50-155/96-06 on 960727-0906.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000155/19960051996-09-20020 September 1996 Insp Rept 50-155/96-05 on 960608-0726.No Violations Noted. Continued Attention Needed on Maint Work on Plant TS Required Equipment.Major Areas Inspected:Engineering,Maint, & Plant Support IR 05000155/19930191993-12-21021 December 1993 Insp Rept 50-155/93-19 on 931020-1214.Violations Noted.Major Areas Inspected:Operational Safety Verification,Engineered Safety Feature Sys Walkdowns & Maint & Surveillance Activities IR 05000155/19930201993-11-10010 November 1993 Insp Rept 50-155/93-20 on 931025-29.No Violations Noted. Major Areas Inspected:Followup Insp of Previously Identified Edsfi Findings IR 05000155/19930171993-11-0404 November 1993 Insp Rept 50-155/93-17 on 931018-22.No Violations Noted. Major Areas Inspected:Fire Protection Insp of Surveillances, Equipment,Fire Brigade Training,Zebra Mussel Problems & Fire Protection Audits IR 05000155/19930181993-10-28028 October 1993 Insp Rept 50-155/93-18 on 931018-22.No Violations Noted. Major Areas Inspected:Licensed Operator Requalification Training Program in Accordance W/Nrc Temporary Instruction 2515/117 IR 05000155/19930131993-10-22022 October 1993 Insp Rept 50-155/93-13 on 930828-1019.No Violations Noted. Major Areas Inspected:Esf Sys Walkdowns,Radiological Controls,Security,Maint & Surveillance Activities & Mgt Meetings IR 05000155/19930141993-10-14014 October 1993 Enforcement Conference Rept 50-155/93-14 on 931012.Major Areas Discussed:Reviewed Apparent Violations & Areas of Concern Identified During Insp & Corrective Actions Taken or Planned by Licensee IR 05000155/19930161993-10-0404 October 1993 Insp Rept 50-155/93-16 on 930913-17.No Violations Noted. Major Areas Inspected:Inservice Testing Program,Program on Check Valves & License self-assessment ML20057E7721993-10-0404 October 1993 Insp Rept 50-155/93-15 on 930824-0914.Violations Noted Are Being Considered for Escalated Ea.Major Areas Inspected: Conditions Surrounding Hydrostatic Primary Sys Test & Breach of Containment Integrity W/Concurrent Mode Change at Plant IR 05000155/19930111993-09-0909 September 1993 Insp Rept 50-155/93-11 on 930716-0827.No Violation Noted. Major Areas Inspected:Operational Safety Verification,Esf Sys Walkdowns,Maint & Surveillance Activities,Engineering & Technical Support Activities & Safety Assessment ML20057A1311993-09-0808 September 1993 Insp Rept 50-155/93-10 on 930809-20.Violations Noted.Major Areas Inspected:Conditions Surrounding 930708 Event Re Both Containment High Pressure Sensors Outside Allowable TS Tolerances Due to Installation Error IR 05000155/19930121993-08-31031 August 1993 Insp Rept 50-155/93-12 on 930809-13.No Violations Noted. Major Areas Inspected:Radiation Protection Program During Outage IR 05000155/19920261992-12-24024 December 1992 Insp Rept 50-155/92-26 on Stated Dates.Violations Noted. Major Areas Inspected:Mgt Control & Organization,Internal & External Exposure & ALARA IR 05000155/19920251992-12-0101 December 1992 Insp Rept 50-155/92-25 on 921116-20.No Violations Noted. Major Areas Inspected:Organization,Reactor Sys Water QC Programs Qa/Qc Program in Lab & Nonradiological Confirmatory Measurements IR 05000155/19920241992-11-25025 November 1992 Insp Rept 50-155/92-24 on 921020-1123.No Violations Noted. Major Areas Inspected:Maint & Surveillance Activities, Evaluation of Licensee self-assessment Capability & Cold Weather Preparations IR 05000155/19900201990-11-0707 November 1990 Insp Repts 50-155/90-20 & 50-255/90-27 on 900925-28 & 1015-19.Violations Noted.Major Areas inspected:fitness-for- Duty & Corrective Actions for Audit Findings IR 05000155/19900171990-11-0202 November 1990 Insp Rept 50-155/90-17 on 900904-1015.Violations Noted.Major Areas Inspected:Refueling Activities,Surveillance Activities,Maint of Various Components,Operational Safety Verification & Temporary Instruction Closure IR 05000155/19900101990-09-25025 September 1990 Insp Rept 50-155/90-10 on 900723-27 & 0806-10.Violations Noted.Major Areas Inspected:Maint,Engineering,Support of Maint & Related Mgt Activities IR 05000155/19900131990-09-17017 September 1990 Insp Rept 50-155/90-13 on 900724-0903.No Violations Noted. Major Areas Inspected:Followup on Previous Insp Findings, Refueling Activities,Surveillance Activities & Maint Activities IR 05000155/19900151990-08-24024 August 1990 Insp Rept 50-155/90-15 on 900814-16.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program, Licensee Actions on Previously Identified Items,Activations of Emergency Plan,Equipment,Training & Independent Audits IR 05000155/19900141990-08-16016 August 1990 Safety Insp Rept 50-155/90-14 on 900730-0803.No Violations, Deviations or Other Items Noted.Major Areas Inspected:Maint & Inservice Testing of Pumps & Valves 1999-09-30
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000155/19990051999-09-30030 September 1999 Insp Rept 50-155/99-05 on 990731-0921,site Insp & 990929 Public Meeting.No Violations Noted.Major Areas Inspected: Routine Decommissioning Insp Covered Aspects of Facility Mgt & Control & Decommissioning Support Activities IR 05000155/19990041999-08-12012 August 1999 Insp Rept 50-155/99-04 on 990609-0730.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities Including Security, Spent Fuel Safety & Radiological Safety IR 05000155/19990031999-06-21021 June 1999 Insp Rept 50-155/99-03 on 990416-0608.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990021999-04-26026 April 1999 Insp Rept 50-155/99-02 on 990226-0415.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990011999-03-19019 March 1999 Insp Rept 50-155/99-01 on 990113-0225.One non-cited Violation Noted.Major Areas Inspected:Aspects of Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980091999-01-15015 January 1999 Insp Rept 50-155/98-09 on 981201-990112.No Violations Noted. Major Areas Inspected:Licensee Management & Control, Decommissioning Support Activities,Sf Safety & Radiological Safety IR 05000155/19980081998-12-0303 December 1998 Insp Rept 50-155/98-08 on 980827-1130.No Violations Noted. Major Areas Inspected:Radiological Safety IR 05000155/19980071998-10-14014 October 1998 Insp Rept 50-155/98-07 on 980827-1007.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Physical Security,Spent Fuel Safety & Radiological Safety IR 05000155/19980061998-09-0303 September 1998 Insp Rept 50-155/98-06 on 980716-0826.No Violations Noted. Major Areas Inspected:Aspects of Licensee Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980051998-07-24024 July 1998 Insp Rept 50-155/98-05 on 980528-0715.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980031998-06-16016 June 1998 Insp Rept 50-155/98-03 on 980407-0527.Violation Noted.Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980021998-04-21021 April 1998 Insp Rept 50-155/98-02 on 980203-0406.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20203A0141998-02-14014 February 1998 Insp Rept 50-155/97-15 on 971205-980202.Violations Noted. Major Areas Inspected:Facility Management & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20197E5901997-12-17017 December 1997 Insp Rept 50-155/97-13 on 971008-1204.Violations Noted. Major Areas Inspected:Major Aspects of Licensee Decommissioning Activities,Including Facility Mgt & Control, Decommissioning Support & Spent Fuel Safety Controls IR 05000155/19970101997-11-26026 November 1997 Insp Rept 50-155/97-10 on 970802-1007.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 05000155/19970121997-10-17017 October 1997 Insp Rept 50-155/97-12 on 970812-1007.Violations Noted.Major Areas Inspected:Miscellaneous Security & Safeguards Issues IR 05000155/19970091997-10-0909 October 1997 Insp Rept 50-155/97-09 on 970617-0804.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering IR 05000155/19970111997-10-0606 October 1997 Insp Rept 50-155/97-11 on 970902-05.Violations Noted. Major Areas Inspected:Various Aspects of Licensee Chemistry Radiation Protection Programs IR 05000155/19970081997-07-22022 July 1997 Insp Rept 50-155/97-08 on 970430-0616.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20140G8931997-06-10010 June 1997 Insp Rept 50-155/97-04 on 970313-0429.Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000155/19970071997-06-0606 June 1997 Insp Rept 50-155/97-07 on 970426-0501.No Violations Noted. Major Areas Inspected:Licensee Fire Protection Program IR 05000155/19970061997-05-23023 May 1997 Insp Rept 50-155/97-06 on 970428-0502.No Violations Noted. Major Areas Inspected:Review of Vehicles Barrier Sys,Audits & Self Assessment,Testing,Maint,Security Contingency Capability & Protected Area Detection ML20141J9951997-05-19019 May 1997 Insp Rept 50-155/97-05 on 970303-0428.Violations Noted. Major Areas Inspected:Event in Which Workers Entered Power Block While Reactor at 9% Power Level Prior to Performance of Adequate Evaluation of Area Radiological Conditions IR 05000155/19970031997-05-13013 May 1997 Insp Rept 50-155/97-03 on 970331-0404.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program IR 05000155/19960121997-02-24024 February 1997 Insp Rept 50-155/96-12 on 961130-970117.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 05000155/19960011997-01-29029 January 1997 Insp Rept 50-155/96-01 on 961019-1129.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20133C5231997-01-0202 January 1997 Insp Rept 50-155/96-11 on 961202-06.Violations Noted.Major Areas Inspected:Radiological Protection & Chemistry Controls,Status of Rp&C Facilities & Equipment IR 05000155/19960071996-12-0606 December 1996 Insp Rept 50-155/96-07 on 960909-12.No Violations Noted. Major Areas Inspected:Emergency Plan & Procedures IR 05000155/19960061996-10-28028 October 1996 Insp Rept 50-155/96-06 on 960727-0906.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000155/19960051996-09-20020 September 1996 Insp Rept 50-155/96-05 on 960608-0726.No Violations Noted. Continued Attention Needed on Maint Work on Plant TS Required Equipment.Major Areas Inspected:Engineering,Maint, & Plant Support IR 05000155/19930191993-12-21021 December 1993 Insp Rept 50-155/93-19 on 931020-1214.Violations Noted.Major Areas Inspected:Operational Safety Verification,Engineered Safety Feature Sys Walkdowns & Maint & Surveillance Activities IR 05000155/19930201993-11-10010 November 1993 Insp Rept 50-155/93-20 on 931025-29.No Violations Noted. Major Areas Inspected:Followup Insp of Previously Identified Edsfi Findings IR 05000155/19930171993-11-0404 November 1993 Insp Rept 50-155/93-17 on 931018-22.No Violations Noted. Major Areas Inspected:Fire Protection Insp of Surveillances, Equipment,Fire Brigade Training,Zebra Mussel Problems & Fire Protection Audits IR 05000155/19930181993-10-28028 October 1993 Insp Rept 50-155/93-18 on 931018-22.No Violations Noted. Major Areas Inspected:Licensed Operator Requalification Training Program in Accordance W/Nrc Temporary Instruction 2515/117 IR 05000155/19930131993-10-22022 October 1993 Insp Rept 50-155/93-13 on 930828-1019.No Violations Noted. Major Areas Inspected:Esf Sys Walkdowns,Radiological Controls,Security,Maint & Surveillance Activities & Mgt Meetings IR 05000155/19930141993-10-14014 October 1993 Enforcement Conference Rept 50-155/93-14 on 931012.Major Areas Discussed:Reviewed Apparent Violations & Areas of Concern Identified During Insp & Corrective Actions Taken or Planned by Licensee IR 05000155/19930161993-10-0404 October 1993 Insp Rept 50-155/93-16 on 930913-17.No Violations Noted. Major Areas Inspected:Inservice Testing Program,Program on Check Valves & License self-assessment ML20057E7721993-10-0404 October 1993 Insp Rept 50-155/93-15 on 930824-0914.Violations Noted Are Being Considered for Escalated Ea.Major Areas Inspected: Conditions Surrounding Hydrostatic Primary Sys Test & Breach of Containment Integrity W/Concurrent Mode Change at Plant IR 05000155/19930111993-09-0909 September 1993 Insp Rept 50-155/93-11 on 930716-0827.No Violation Noted. Major Areas Inspected:Operational Safety Verification,Esf Sys Walkdowns,Maint & Surveillance Activities,Engineering & Technical Support Activities & Safety Assessment ML20057A1311993-09-0808 September 1993 Insp Rept 50-155/93-10 on 930809-20.Violations Noted.Major Areas Inspected:Conditions Surrounding 930708 Event Re Both Containment High Pressure Sensors Outside Allowable TS Tolerances Due to Installation Error IR 05000155/19930121993-08-31031 August 1993 Insp Rept 50-155/93-12 on 930809-13.No Violations Noted. Major Areas Inspected:Radiation Protection Program During Outage IR 05000155/19920261992-12-24024 December 1992 Insp Rept 50-155/92-26 on Stated Dates.Violations Noted. Major Areas Inspected:Mgt Control & Organization,Internal & External Exposure & ALARA IR 05000155/19920251992-12-0101 December 1992 Insp Rept 50-155/92-25 on 921116-20.No Violations Noted. Major Areas Inspected:Organization,Reactor Sys Water QC Programs Qa/Qc Program in Lab & Nonradiological Confirmatory Measurements IR 05000155/19920241992-11-25025 November 1992 Insp Rept 50-155/92-24 on 921020-1123.No Violations Noted. Major Areas Inspected:Maint & Surveillance Activities, Evaluation of Licensee self-assessment Capability & Cold Weather Preparations IR 05000155/19900201990-11-0707 November 1990 Insp Repts 50-155/90-20 & 50-255/90-27 on 900925-28 & 1015-19.Violations Noted.Major Areas inspected:fitness-for- Duty & Corrective Actions for Audit Findings IR 05000155/19900171990-11-0202 November 1990 Insp Rept 50-155/90-17 on 900904-1015.Violations Noted.Major Areas Inspected:Refueling Activities,Surveillance Activities,Maint of Various Components,Operational Safety Verification & Temporary Instruction Closure IR 05000155/19900101990-09-25025 September 1990 Insp Rept 50-155/90-10 on 900723-27 & 0806-10.Violations Noted.Major Areas Inspected:Maint,Engineering,Support of Maint & Related Mgt Activities IR 05000155/19900131990-09-17017 September 1990 Insp Rept 50-155/90-13 on 900724-0903.No Violations Noted. Major Areas Inspected:Followup on Previous Insp Findings, Refueling Activities,Surveillance Activities & Maint Activities IR 05000155/19900151990-08-24024 August 1990 Insp Rept 50-155/90-15 on 900814-16.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program, Licensee Actions on Previously Identified Items,Activations of Emergency Plan,Equipment,Training & Independent Audits IR 05000155/19900141990-08-16016 August 1990 Safety Insp Rept 50-155/90-14 on 900730-0803.No Violations, Deviations or Other Items Noted.Major Areas Inspected:Maint & Inservice Testing of Pumps & Valves 1999-09-30
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000155/19990051999-09-30030 September 1999 Insp Rept 50-155/99-05 on 990731-0921,site Insp & 990929 Public Meeting.No Violations Noted.Major Areas Inspected: Routine Decommissioning Insp Covered Aspects of Facility Mgt & Control & Decommissioning Support Activities IR 05000155/19990041999-08-12012 August 1999 Insp Rept 50-155/99-04 on 990609-0730.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities Including Security, Spent Fuel Safety & Radiological Safety IR 05000155/19990031999-06-21021 June 1999 Insp Rept 50-155/99-03 on 990416-0608.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990021999-04-26026 April 1999 Insp Rept 50-155/99-02 on 990226-0415.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990011999-03-19019 March 1999 Insp Rept 50-155/99-01 on 990113-0225.One non-cited Violation Noted.Major Areas Inspected:Aspects of Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980091999-01-15015 January 1999 Insp Rept 50-155/98-09 on 981201-990112.No Violations Noted. Major Areas Inspected:Licensee Management & Control, Decommissioning Support Activities,Sf Safety & Radiological Safety IR 05000155/19980081998-12-0303 December 1998 Insp Rept 50-155/98-08 on 980827-1130.No Violations Noted. Major Areas Inspected:Radiological Safety IR 05000155/19980071998-10-14014 October 1998 Insp Rept 50-155/98-07 on 980827-1007.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Physical Security,Spent Fuel Safety & Radiological Safety IR 05000155/19980061998-09-0303 September 1998 Insp Rept 50-155/98-06 on 980716-0826.No Violations Noted. Major Areas Inspected:Aspects of Licensee Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20195C6211998-08-18018 August 1998 EN-98-059,informing Commission That Staff Intends to Exercise Broad Discretion Pursuant to Section VII.B.6 of Enforcement Policy & Not Issue NOV or Propose Civil Penalty for Severity Level II Violation Identified by Licensee IR 05000155/19980051998-07-24024 July 1998 Insp Rept 50-155/98-05 on 980528-0715.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980031998-06-16016 June 1998 Insp Rept 50-155/98-03 on 980407-0527.Violation Noted.Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980021998-04-21021 April 1998 Insp Rept 50-155/98-02 on 980203-0406.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20202J8471998-02-14014 February 1998 Notice of Violation from Insp on 971205-980202.Violation Noted:Chemical Decontamination Worker Working Under RWP B982035 in High Radiation Area for Approx 55 Minutes & Did Not Monitor Dosimetry Time ML20203A0141998-02-14014 February 1998 Insp Rept 50-155/97-15 on 971205-980202.Violations Noted. Major Areas Inspected:Facility Management & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20199A2571997-12-30030 December 1997 EN-97-117:on 980105,informs Commission That Order Prohibiting Involvement in NRC-licensed Activities Issued to Dt Rich.Action Based on Investigation Conducted by Oi,Which Determined on 960721 & 0915,DT Rich Falsified Records IR 07100008/20120041997-12-17017 December 1997 Notice of Violation from Insp on 971008-1204.Violation Noted:On 971029,items Hanging from Spent Fuel Pool Rail Span 19 Had Combined Weight of 497 Pounds.Length of Time That Weight on Rail Exceeded Weight Restriction Not Determined ML20197E5901997-12-17017 December 1997 Insp Rept 50-155/97-13 on 971008-1204.Violations Noted. Major Areas Inspected:Major Aspects of Licensee Decommissioning Activities,Including Facility Mgt & Control, Decommissioning Support & Spent Fuel Safety Controls IR 05000155/19970101997-11-26026 November 1997 Insp Rept 50-155/97-10 on 970802-1007.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20199J4571997-11-19019 November 1997 Notice of Violation from Insp on 961216-971107.Violations Noted:Certain Radiation Surveys Required by Station Procedure RP-29,not Completed.Also Certain Radiation Survey Records Required to Be Maintained,Not Accurate IR 05000155/19970121997-10-17017 October 1997 Insp Rept 50-155/97-12 on 970812-1007.Violations Noted.Major Areas Inspected:Miscellaneous Security & Safeguards Issues IR 05000155/19970091997-10-0909 October 1997 Insp Rept 50-155/97-09 on 970617-0804.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering ML20211J7341997-10-0606 October 1997 Notice of Violation from Insp on 970902-05.Violation Noted: on 970902,maintenance Worker Preparing to Participate in Reactor Head Detensioning Operations Laid Down in Contaminated Area for Several Minutes IR 05000155/19970111997-10-0606 October 1997 Insp Rept 50-155/97-11 on 970902-05.Violations Noted. Major Areas Inspected:Various Aspects of Licensee Chemistry Radiation Protection Programs ML20217J3391997-08-12012 August 1997 Notice of Violation from Insp on 970303-0428.Violation Noted:On 970202 Rj Flowers,Employee of Consumers Power Co, Did Not Exit High Radiation Area After Receiving Alarm on Electronic Dosimeter as Required ML20217K5521997-08-12012 August 1997 Notice of Violation from Insp on 970303-0428.Violations Noted:Licensee Failed to Properly Evaluate Potential Radiological Hazards Associated W/Transfer of Highly Contaminated Filters ML20151J7721997-07-22022 July 1997 Notice of Violation from Insp on 970430-0616.Violation Noted:Inspector Identified That on 960403 & 970502,seven & Five CRDs Respectively Were Left After Insertion Time Testing W/Insert Speeds Greater than 28 IR 05000155/19970081997-07-22022 July 1997 Insp Rept 50-155/97-08 on 970430-0616.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support PNO-III-97-055, on 970611,decision to Permanently Shut Down Plant Three Yrs Before Expiration of Operating License in Yr 2000.Capacity of 67 Megawatts & Future Needed Improvements Would Be Too Expensive.State of Mi Will Be Informed1997-06-11011 June 1997 PNO-III-97-055:on 970611,decision to Permanently Shut Down Plant Three Yrs Before Expiration of Operating License in Yr 2000.Capacity of 67 Megawatts & Future Needed Improvements Would Be Too Expensive.State of Mi Will Be Informed ML20140G8931997-06-10010 June 1997 Insp Rept 50-155/97-04 on 970313-0429.Violations Noted. Major Areas Inspected:Operations,Maint & Engineering ML20140G8851997-06-10010 June 1997 Notice of Violation from Insp on 970313-0429.Violation Noted:Procedures Were Not Followed,In That Required Working Clearances & Protective Tagging Were Not Obtained by Workers Prior to Performing Work Activities IR 05000155/19970071997-06-0606 June 1997 Insp Rept 50-155/97-07 on 970426-0501.No Violations Noted. Major Areas Inspected:Licensee Fire Protection Program IR 05000155/19970061997-05-23023 May 1997 Insp Rept 50-155/97-06 on 970428-0502.No Violations Noted. Major Areas Inspected:Review of Vehicles Barrier Sys,Audits & Self Assessment,Testing,Maint,Security Contingency Capability & Protected Area Detection ML20141J9951997-05-19019 May 1997 Insp Rept 50-155/97-05 on 970303-0428.Violations Noted. Major Areas Inspected:Event in Which Workers Entered Power Block While Reactor at 9% Power Level Prior to Performance of Adequate Evaluation of Area Radiological Conditions IR 05000155/19970031997-05-13013 May 1997 Insp Rept 50-155/97-03 on 970331-0404.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program PNO-III-97-012, on 970224,licensee Notified NRC Resident Inspector Ofc That Loose Radioactive Surface Contamination Spread Throughout Turbine Bldg,During Transfer of Radwaste Processing Filters from Temporary Storage Barrel1997-02-26026 February 1997 PNO-III-97-012:on 970224,licensee Notified NRC Resident Inspector Ofc That Loose Radioactive Surface Contamination Spread Throughout Turbine Bldg,During Transfer of Radwaste Processing Filters from Temporary Storage Barrel IR 05000155/19960121997-02-24024 February 1997 Insp Rept 50-155/96-12 on 961130-970117.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20135D4431997-02-24024 February 1997 Notice of Violation from Insp on 961130-970117.Violation Noted:Use of Inappropriate Surveillance Procedure Causing Uncontrolled Leak & Inline Relief Valve Lifting Due to Failure to Remove Installed Blank Flange IR 05000155/19960011997-01-29029 January 1997 Insp Rept 50-155/96-01 on 961019-1129.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20134C9421997-01-29029 January 1997 Notice of Violation from Insp on 961019-1129.Violations noted:961108 Operators Closed EC Number 1 Loop Inlet Valve (MO-7062) Making Number 1 EC Loop Inoperable & Operability Test Number 2 EC Loop Outlet Valve Not Performed within 1 H ML20133C5231997-01-0202 January 1997 Insp Rept 50-155/96-11 on 961202-06.Violations Noted.Major Areas Inspected:Radiological Protection & Chemistry Controls,Status of Rp&C Facilities & Equipment ML20133C5111997-01-0202 January 1997 Notice of Violation from Insp on 961202-06.Violation Noted: High Radiation & Contaminated Areas Was Not Posted W/Signs Bearing Radiation Symbol IR 05000155/19960071996-12-0606 December 1996 Insp Rept 50-155/96-07 on 960909-12.No Violations Noted. Major Areas Inspected:Emergency Plan & Procedures IR 05000155/19960061996-10-28028 October 1996 Insp Rept 50-155/96-06 on 960727-0906.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support PNO-III-96-064, on 961023,shutdown for Evaluation of Environ Qualification Data Made.Licensee Performed Preliminary Assessment of Effect of Higher than Anticipated Temp Profile on safety-related Electrical Equipment Located1996-10-24024 October 1996 PNO-III-96-064:on 961023,shutdown for Evaluation of Environ Qualification Data Made.Licensee Performed Preliminary Assessment of Effect of Higher than Anticipated Temp Profile on safety-related Electrical Equipment Located IR 05000155/19960051996-09-20020 September 1996 Insp Rept 50-155/96-05 on 960608-0726.No Violations Noted. Continued Attention Needed on Maint Work on Plant TS Required Equipment.Major Areas Inspected:Engineering,Maint, & Plant Support PNO-III-94-039, on 940517,two Persons,Russian Visitor & Interpreter Were Killed in Traffic Accident Near Charlevoix,Mi.Cause of Accident Under Investigation1994-05-18018 May 1994 PNO-III-94-039:on 940517,two Persons,Russian Visitor & Interpreter Were Killed in Traffic Accident Near Charlevoix,Mi.Cause of Accident Under Investigation IR 05000155/19930191993-12-21021 December 1993 Insp Rept 50-155/93-19 on 931020-1214.Violations Noted.Major Areas Inspected:Operational Safety Verification,Engineered Safety Feature Sys Walkdowns & Maint & Surveillance Activities ML20059C1031993-12-21021 December 1993 Notice of Violation from Insp on 931020-1214.Violation Noted:Results of Static Votes Testing at Final Asleft Torque Switch Setting for MO-7053 Were Not Evaluated Prior to Return to Svc of Valve IR 05000155/19930201993-11-10010 November 1993 Insp Rept 50-155/93-20 on 931025-29.No Violations Noted. Major Areas Inspected:Followup Insp of Previously Identified Edsfi Findings 1999-09-30
[Table view] |
See also: IR 05000155/1997013
Text
. . __ .._ _ _ _ _ ___ . . . _ _ _ _ . _ _ _ . . _ _ . _ _ . _ _ _ . . _ __ _ ._._
. i
,
!
U.S. NUCLEAR REOULATORY COMMISSION
REGION lii
Docket No: 50 155
4
Lloonse No: DPR-06
Report No: 50-155/97013(DNMS) ,
'
Licensee: ' Consumers Energy Company ,
!
. Foollity: Big Rock Point Nuclear Power Plant
i
4 8
6
9
- Lou.t!an: 10209 U.S. 31 North
4
Charlevoix, MI 49720 l
Dates:- October 8- December 4,1997 ,
L
- Inspectors: R. J. Loomon, Senior Resident inspector
C. E. Brown, Resident inspector
Approved by; Bruce L. Jorgensen, Chief '
.
Dooommissioning Branch
DMalon of Nuclear Materials Safety ,
,
f
f
),
,
e
,
F
f !
_
i.
_
- = - . -, .. - .._ - - _ -
_ ____ _____--____ _ __ _
-
.
EXECUTIVE SUMMARY
Big Rock Nuclear Power Plant
RC Inspection Report 50-155/97013
.
This routine inspection covered major aspects of licensee decommissioning activities, including
facility rr.anagement and control, decommissioning support, spent fuel safety and radiological
controls.
Eacilityldanagement and control
- The inspectors identified no concems with the conclusions of the PRC that no
unreviewed safety questions were created in changes to the Final Hazards Summary
'
Report and proposed changes to the Technical Specifications. (Sections 1.1 and 1.2)
- The tect.rlty staff coped well with the increased security challenges caused by the
increased work force and decommissioning actMties, (Section 1.3)
Decommisslotg3upport Activiiles
- Maintenance and surveillance activities were correctly performed and accurately
documented. (Section ll.1)
\ * The inspectors identified no safety concems with survelllance tests that were deleted
due to Big Rock Point being In the decommissioning phase of plant operetion.
{ (Section 11.3)
- The inspectors identified no safety concerns with deleted predictive and preventive
activity controls due to Big Rock Point being in the decommissioning phase of plant
operation. (Section ll.4)
SpentfueLSafeti
e The reactor vessel was emptied of core components after an appropriate procedure
change authorized the use of the attemate spent fuei poal(SFP) channel handling tool
for removal of a bowed channel. (Section 111.2) ,
- Operators and reactor engineers had limited guidance and lacked a questioning attitude
conceming the weight of items hanging on SFP rail spans, and the weight of items being
added to the rail 4 pans by the operators. SFP rail span No.19 was found with
components hanging from it with a total weight in excess of the 350 pound procedural
limit. (Section 111.3)
fladiologicaLControls
- Health Physics technicians gave good radiation work permit (RWP) and as low as
reasonably achievable (Al. ARA) pre-job briefings. (Section IV.1)
<
e Soll excaveted to remediate a diesel fuel oil sp(h was properly sampled and stored.
(Section IV.2)
_
2
l
- _
_ - - _ _ _ _ _ _ _ _ _ _ _ _ _ - _
.
Repori_ Details
Summary _of Plant Status
The lic1nsee began the inspection period with the plant in the decommissioning phase of plant
life. All fuel bundles were stored in the spent fuel pool (SFP). On November 10,1997, the last
fuel channel was remnved from the reactor and on December 2,1997, the reactor vessel head
was re-installed. The removal of fuel channels and control rod blades from the reactor core
were performed in preparation for the primary system decontamination flush.
As of November 25,1997, the SFP lodine inventory, after more tha,i ten half lives of lodine 131
decay, would cause a member of the public at the closest site boundary, to receive 1.0 rem
committed dose equivalent (CDE) to the thyroid. The total effective dose equivalent (TEDE) to
the total body would be less than 0.1 rem. In comparison,10 CFR Part 100 limits are 300 rem
CDE to the thyroid and 25 rem TED5 to the total body. The Environmental Protection Agency's
(EPA's) Protective Action Guides are 5 rem CDE to the thyroid and 1 rem TEDE to the total
body. Big Rock Point passed the time at which 10 CFR Pert 100 limits could be exceeded on
September 19,1997,20 days post shutdown. Big Rock Point passed the time at which the
EPA's Protective Action Guides could be exceeded on November 6,1997,68 days post-
shutdown. This data is the licensee's basis for proposed Technical Specification (TS) changes,
LEacility_ Management.And.CQulfD)
1.1 PJaniReview comml11ec.(P.RCRicelings
The inspectors attended PRC meetings and verified that a quorum was present. The
inspectors also evaluated ongoing discussions and the bases for the determination that
the proposed changes were not unreviewed safety cuestions. The following items were
discussed:
- Changes tu Final Hazards Summary Report (FHSR), Chapter 15, " Accident
Analysis " Chapter 15 was re'.vritten to delete those accidents which have no
possib:lity of occurring with the reactor permanently defueled. Accidents which
have a potential to occur during decommissioning were incorporated into
C:', apter 15.
- Change requests to TS, Section 0, " Administrative Controls," were approved to
allow changing the required staffing and operator license requirements.
The inspectors identified no concoms with the PRC conciusions,
l.2 Post ShutdowrtDecommissioning.AcitvlifesReportESDAR
The inspectors reviewed the updated PSDAR to remain cognizant of plans and
schedules. The NRC conducted a public meeting on November 13,1997, where the
changes to the PSDAR were discussed. The inspectors attended this meeting. The
details of the meeting will be documented by the NRC Office of Nuclear Reactor
Regu% tion.
3
.
^
1.3 Increase 1 Security Woiload
Observations were routinely conducted in tha areas of security and safeguard activities
using inspection Procedure 71750. The inspectors observed increases in the number of
plant staff entering and working in the protected area and in the quantity of supplies
entering the protected area. The incr9ased number of workers in the protected area
resulted in an increase in the number of logable security and security conditbn reports
generated. The immediate corrective actions to these reports appeared appropriate.
The inspectors also noted an increase in plant vehicle traffic. The security force coped
well with this increated work load.
ILDecorntnissioningEuppsiActivillas
11. 1 Observation of Actlylties
Numerous work activities and tests were observed and/or reviewed to verify they were
conducted safely and in accordance with appropriate procedural controls,
n. Inspacilon_ScopM62ZD3).IE1226)
The inspectors observed all or portions of the following work activities:
"
MalatenanceActivillas
- WO 12710979: Installing ventilation ductw d for HEPA filter
e WO 12711095: testing standby dieset bre Aker
- WO 12710938: set and tension reactor head
Sutyelllance Activities
- W P.1: standby diesel generator start and run test
- TV 26: !acalleak rate testing
- TV 59: fuel pool heatup test
- T180-01A: containment ventilation valves leak rate test
b. Observations and Findings
The maintenance and surveillance activitiet, observed were property conducted in
accordsnee with applicable procedures. The inspectors did not observe any decrease in
performance nor any imprmer work. Surveillance postponement due to the final plant
shutdown did not occur. Pre-job briefings attended by the inspectors were well
conducted,
c. Conclusions
Maintonance and surveillance activities were correctly performed and accurately
documented,
SpontEuct Pool Heatun Rate Test
'
11. 2
On Nwomber 22,1997, the operators performed SFP heatup tast TV 59. This test was
conducted to confirm that the heatup curves based on 1.4'F/HR were accurate. The
4
.
. - - _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _
-- . . - - . _-- - - - _ . _ _ -.._ _ _ . - .- -. -. _-- - -
.
16consee fic-;-::d chan'A4 To the TS based on the SFP taking greater than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to
heat the pool by 70'F. 'cs 60'F to 150'F. All cooling was shut off to the SFP for 10
hours. The initial pool ww erature was 62'F, and the final SFP temperature was 68'F,
. yield 6ng a hostup rate of v.S'F/HR. This test showed tht it would now take at least 116
hours for the SFP to heat up by 70'f' with loss of oooling to the pool. Based on TV-59,
' the inspedor conclJded that the SFP heating graphs were conservative, and that the
reactor engineer's assessment of ths SFP heat load was conservative. Also, the heat
load to the SFP was within the assuicntion for the proposed TS for a defueled plant.
=l
J
11.3 Deleted Surveillance Tanis
l
'
a. Inapadion haam
As a consequence of permanent shutdown of the reactor, some periodically scheduled <
surveillance tests became unnecessary or inappropriate. The inspectors reviewed the ;
- process which deleted the surveillance tests listed below.
b. Obaarvations and Findings
lhe licensee evaluated surveillances to determine which were not required to be j
performou during the decommissioning phase of plant operation. The applicable plant
procedure required a safety evaluation and having the procedure being deleted undergo
review by the Plant Safety Review Committee (PRC). The following surveillances were
deleted by this process:
o T7-12 Pipe Tunnelinspection
e T718 Bypass Valve Test
e T7-30 Plant Water inventory
- ' T7-33 Check of Auxiliary Shutdown (ASD) System Equipment
e T30-01 - Monthly RPS Logic Test
- T30-03 CRD Selector Valve Reduced Pressure Test
- T30-05 CRD Position Motor Generator Test
e T30-33 Check of ASD System Equipment Checks
c. Conclualon
The inspectors identified no safety concems with surveillance tests that were deleted
. due to Big Rock Point being in the decommissioning phase of plant operation.
ll.4 Deleted Pranctive and Preventive Activitv Controla (PPACA) -
~
- aJ inanadan Scope
The inspectors held discussions with the Predictive and Preventive Activity Control
(PPAC) coordinator and reviewed the list of PPACs deleted as unnecessary or
. inappropriate considering permanent reactor shutdown.
i
5
--.--_=
-
- . . -
. . - . - - - . . . . - . - . .. -. . . .
'
.
b. Obrarvatbnn and findings
A maintenance review comm!ttee met and determined which PPACs had no continuing
regulatory basis in the TS, final hazards summary report (FHSR), insurance, or other
commitments. The deleted PPACs were determined to have no efioct on needed
equipment in the decommissioning mode of operation. Approximately 2,600 PPACs
were reviewed; of those,316 were deleted.
c. Conclusion
The inspectors identified no safety concerns with deleted PPACs due to Big Rock Point
being in the decommissioning phaso of plant operation .
IILSpantfuaLSafety
111. 1 General
The inspectors conducted frequent reviews of ongoing decommissioning activities,
focusing on spent fuel safety. Specifit., events and findings are detailed in the sections
below.
111. 2 Emptying the Reactor of Fuelfhannels and Control Rod Blades
a. Insnection Scope
The inspectors reviewed SOP-44, " Spent Fuel Pool Operations and New Fuel," and
SOP-02, " Refueling Operation," and observed operators perform activities that emptied
the reactor vessel of 88 fuel channels and 32 control rod blades in preparation for the
full primary system dscontamination flush.
b. ObseIYahons and Findings
Pre-job briefs were thorough and contained good Interaction among crew members.
The movement of channe.ls and blades was performed within the guidance of
SOP-02. One channel was too bowed to allow for the use of the normal channel
handling tool, as the tool guide balls would not fit into the channel. Work was stopped
and changes to SOP-02 were made and approved to allow for the use of the SFP
channel handling tool which had no guide balls. On Novernber 10,1997, the channel
was removed from the reactor vessel and placed in the SFP, emptying the reactor
vessel of core components.
c. Conclusion
The reactor vec 'el was carefully and effectively emptied of core components. An
appropriate procedure change was implemented to allow use of the alternate SFP
channel handling toolin successful removal o a bowed channel.
6
_ - _ _ _ . _ _ .
I
Ill.3 SpanEuelEcoLRail Soan N119 Weight Limit Exceeded i
a. Inrtpaction. Scope
On October 9,1997, the inspectors observed that operators wvre hanging core ,
components on spans of the spent fuel pool (SFP) rails. System Operating Procedure l
(SOP)-44, * Spent Fuel Pool Operations and New Fuel Handling," was examined, and
the inspectors questioned plant staff as to the weight of the items already hanging on
the SFP rail spans and the weight of the items being added by the operators. l
b. Obser.vations and Findings
On October 9,1997, the inspectors raised questions with various plant staff as to the
weight of core components which were being hung from the spans of the SFP rails, and
the weight of the components that were already hanging oi, the rail spans. The licensee
did not know or have records as to the weight that was already hanging from the rail
spans. Changes were mad 9 to the applicable procedure, SOP-44 " Spent Fuel Pool
Operators and New Fuel Handling," and items hanging from certain SFP rail spans were
weighed and the weights recorded. On October 29,1997, the operators discovered that
SFP rail span No.19 had core components hangirig from it with a total weight of 497
pounds, exceeding the weight limit of 350 pounds in SOP-44 by 147 pounds. In that
implementation of SOP-44 is a requirement of TS 6.8.1 by reference through the
licensee's Quality Program, exceeding the noted limitation of SOP-44 is considered a
violation (50-155/97013-01(DNMS)).
The licensee lacked records showing weights and dates for placement of components in
suspension off the SFP rails. Therefore, the length of time the welght limit was
exceeded could not be determhed.
After if was discovered that SFP rail span No.19 was weighted beyond procedure limits,
the operators moved some items to other rail spans. The total weight left on SFP rail
span No.19 was 329 pounds. The weight of items on other rail spans were checked
and found to be less than 350 pounds. Condition Report (CR)
C-BRP-97 534," Exceeding 350 pounds on Spent Fuel Pool Rail Spans * was written by
the shift supervisor, immediate corrective cetions were as follows: 1) no additional
material may be hung on rail spans 18,19, and 20; 2) before adding any additional
material on other rail spans, it must be verified that the additional load will not cause the
total weight on the rail span to exceed 350 pounds; 3) SOP-44 was revised to include a
section for weighing items; and 4) the reactor engineer provided the operators with
written instructions containing weights of core components remaining to be removed,
and identifying the rail span on which to hang each component. On November 10,
1997, the last core components were removed from the core. The inspector verified the
components were distributed on the SFP rail spans to ensure that the total weight on
any rail span did not cxceed 350 pounds.
The inspectors found that the safety significance of the excess 147 pounds
hanging on SFP rail span No.19 had not been evaluated by the engineers. When the
inspectors questioned this, the licensee stated that the engineers will provide the
inspectors w;th an evaluation. This is an inspector follow-up item
(50-155/97013-02(DNMS)).
7
.
.
l
c. Condualon
Operators and reactor engineers had limited guidance and lacked a questioning attitude
conceming the weight of items hanging on the SFP rail spans. The weights of items
being added to the rail spans by the operators were not monitored or controlled. SFP
mil span No.19 was found with core components hanging from it with a total weight in
excess of the 350 pound procedurallimit.
Ill.4 Idousekeeping
During frequent tot'n of the contalnment and other buildings, the inspectors noted that
trash and debrie ,a starting to accumulate and the geneial cleanliness throughout the
plant was beg' .g to decline. For example, the inspectors noted that bags of
radioactive mt.t .al were accumulating in many areas of the turbine building. The plant
manager was informed of these observations. On subsequent plant tours, the
inspectors rioted that the conditions had improved.
ILRadiologicaLControls
IV.1 General
Using inspection Procedures 71707 and 71750, the inspectors made frequent tours of
the radiologically protected area (RPA) and discussed specific radiological controls with
the ALARA coordinator and various radiation protection (RP) technicians. The
inspectors observed plant conditions and licensee performance, including radiation
protectinn practices, which were satisfectority performed by plant workers during this
inspection period. Radiation protection practices performed by plant workers removing
the reactor core components were good. There wera two minor contaminations of
worker faces. The RP prejob, and radiation work permit (RWP) and ALARA briefings
were conducted with good interactions and inf ormative details provided by the RP
technicians. The inspectors concluded that the implementation of the radiation
protection program during this insp3ction period was good.
IV.2 BadioactMty Eample of Soll after Diesel olLSpill
a. Inspection Scope
The inspectors monitored the chemistry department's activities related to collecting and
sampling the sollin the area of a diesel oil spill. The inspec6rs also reviewed the
immediate corrective actions of CR C-BRP-97-563, * Diesel Oil Splil."
b. Observations _and Findings
On November 19,1997, a backhoe and bucket tractor were parked on the railroad
tracks near the condensate tank. On November 25,1997, at 7:45 a.m., a worker
discovered that the fuel tank had emptied onto the ground. About 25 gallons of diesel
fuel had leaked from the tank. A broken sediment bulb in the fuel line was the cause for
the fuel oil leak. To prevent potential migration of fuel to Lake Michigan, a cleanup was
required; however, the soll potentially contained rr.diological contamination which also
had to be addressed.
8
'
.
Immediate corrective actions taken by the chemists were to rope off and cover the area
where the oil had leaked. Plant prints showed a 6" perforated pipe buried in the area to
keel the rail-bed dry, so chemists placed an absorbent boom in the drainage ditch. The
chemists then sampled the top soll to determine where on site to store the soll.
As the first stage of environmental cleanup,1.5 cubic yards of soll were remaved and
placed in three 55-gallon drums. The work was then halted until the rails and ties could
be removed for further excavation. Six separate soll samples were taken and analyzed
on the gamma spectroscope analytical system.
Three soll samples identified Co-60 or Cs-137 activity at lavels above background. The
background for Co-60 is considered to be 0.0 uct/gm, and the background for
Cs 137 is 4.2e 7uci/gm. All the samples were below TS limits. The actual results are
shown in the following table, with the background subtracted.
SAMPLE # Co 60 uct/gm Cs 137 uct/gm
2 2.05e 7 2.80e 7
3 1.50e-7 01.8e-7
5 3.28e-6 background
The remaining three samples contained only naturally occurring background peaks with
no identifluition ol plant-origin nuclides.
The inspectors observed that the three drums were properly posted and stored in the
waste hold tank radiation material area. The final disposal of this. soll will be performed
in accordance with existing plant procedures. The sampling of the rest of the sollis an
inspector followup item (50155/97013-03(DNMS)).
c. Conclusion
Soll contaminated from a diesel fuel oil spill was properly sampled to assess potential
radiological content, and was properly stored pending final disposal.
LP_raylously_ identified.lsmuna_(92I00)
V.1 (Closed) LER 50-155/97005: Violation of facility operating license.
Big Rock Point's Operating License, Section B(2)(b), prohibits storage of materials in the
area between spent fuel rack B and the east wall of the SFP, so that local temperatures
in the fuel pool will remain consistent with the cooling analysis of record. Contrary to this
requirement, a 5 Dallon stainless steel bucket was discovered on the SFP floor between
rack B and the east wall of the SFP on October 9,1997. The licensee could t'ot
determine the length of time the bucket was in the pool. Poor lighting in that area of the
pool was a causal factor for not discovering the bucket sooner.
The bucket was removed the same day, and facility procedure SOP-44, " Spent Fuel
Pool Operations and New Fuel" was revised t = e tsure that this area is kept clear. An
engineering safety analysis confirmed that the e was no immediate or past operational
safety concem with the bucket between "B" rack and the east wall of the SFP. The
9
_ -. .- _
. -. -- -- _ . . ..
,
,
conclusion of the evaluation was that there was no significant change in tim heat I
transfer and heat removal capability of the spent fuel pool with the bucket in tte pool.
The inspectors reviewed the engineering evaluation and agreed with the licensee's
conclusion. The inspectors also reviewed the changes to SOP-44 wh:ch require that
material shall not be stored in the area between the *B" Rack and the east wall of the
fuel pool (northeast comer), from the pool floor to the top of the fuel racks. After each
work shift in the SFP this area shall be verified clear and an entry made in the Control
Room Log to document this verification. The inspectors verified by visualinspection that
the area is being maintained clear of objects that could affect heat transfer. In addition,
the inspectors reviewed log entries that documented the area was being inspected by
the operators after work in the SFP and was being maintained clear of objects.
This event had relatively low safety significa,nce, and the licensee's immediate action
taken appeared effective. Therefore, this example of failure to comply with
Section B(2)(b) of the operating license is considered a licensee-identified and corrected
violation. This violation is being treated as a Non Cited Violation, consistent with
Section Vll.a.1 of the NRC Enforcement Policy (50155/97013-04(DNMS)). The
completed corrective actions close LER 50-155/97005, and the inspectors have no -
further concems.
V.2 (Closed)V10 50-155/96010-02: Cold! warm weather checklist sign-off. The cold / warm
weather checklist sign-off (0-VAS 1 Revision 20) was satisfactorily completed on
De,cember 3,1997. The inspectors have no further concems.
VI. Management. Meetings
ExlLMeeting summary
The inspectors presented the inspection results to members of licensee management at the
conclusion of the inspection on December 4,1997. The licensee acknowledged the findings
presented.
The licensee did not identify any of the documents or processes discussed in this report as
being proprietary.
PARTIAL LIST OF PERSONS CONTACTED
Licensee
K. Powers, General Manager
D. Hice, Plant Manager
K, Pallagl, Chemistry / Health Physics Manager
W. Trubilowicz, Outage / Work Control Manager
G. Withrow, Engineering Manager
10
_. . . _ _ - _ __
.
. . _ _ _ _ . . _ - __ _ - > _ _ ___ - _ . _ . .- _ _ . _ _ _ _ _ _ _ . . _ . _ _ . __ _ _ . ~ _
.
INSPECTION PROCEDURES USED
- IP 37551:- Engineering
1061726: Surveillence Observations
IP 62703: Maintenance Observation
IP 71707: Plant Operations !
- IP 71750: Plant Support M l
..
ITEMS OPENED AND CLOSED )
l
Opened
155/9701301 VIO Procedure Violation of SFP Rail Span Weight Limit Exceeded ,
155/9701342 IFl Engineering Evaluation on SFP Rail Span Weight Limit Exooeded l
4
155/97013 03 IFl Diesel FuelOil Spill Soil Sampling
165/97013-04 NCV Failure to Comply with Operating Lloense Section B(2)(b)
.
- Closed
155/96010 02 VIO Cold / Warm Weather Checklist Sign off
LER Violation of Facility Operating Lloonse
'
155/97005
- 155/97013-03 NCV Failure to Comply with Operating Lloonse Section B(2)(b)
i
5
i
4
+
)
11
_
- -s= ==*' -W'=-* *'* 3p t M W& -' '
F TyW
l o
,
LIST OF ACRONYMS USED
ALARA As Low As Reasonably Achievable
CFR Code of Federal Regulations
CR Condition Report
FHSR Final Hazards Summary Report
HEPA High Emcient Particulate and Absolute
HP Health Physics
IFl Inspection Followup Item
IR inspection Report
LER Limnsee Event Report
NCV Non-Cited Violation
NOV Notice of Violation
NRC Nuclear Regulatory Commission
PPAC Predictive and Preventive Activity Control
RP Radiation Protection
RPA Radiologically Protected Area
PRC Plant Safety Review Committee
PSDAR Post Shutdown Decommissioning Activities Report
RWP Radiation Work Permit
SFP Spent Fuel Pool
SS Shift Supervisor
> TS Technical Specification
VIO Violation
WO Work Order
,
's 2
_ . . _ _