|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000155/19990051999-09-30030 September 1999 Insp Rept 50-155/99-05 on 990731-0921,site Insp & 990929 Public Meeting.No Violations Noted.Major Areas Inspected: Routine Decommissioning Insp Covered Aspects of Facility Mgt & Control & Decommissioning Support Activities IR 05000155/19990041999-08-12012 August 1999 Insp Rept 50-155/99-04 on 990609-0730.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities Including Security, Spent Fuel Safety & Radiological Safety IR 05000155/19990031999-06-21021 June 1999 Insp Rept 50-155/99-03 on 990416-0608.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990021999-04-26026 April 1999 Insp Rept 50-155/99-02 on 990226-0415.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990011999-03-19019 March 1999 Insp Rept 50-155/99-01 on 990113-0225.One non-cited Violation Noted.Major Areas Inspected:Aspects of Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980091999-01-15015 January 1999 Insp Rept 50-155/98-09 on 981201-990112.No Violations Noted. Major Areas Inspected:Licensee Management & Control, Decommissioning Support Activities,Sf Safety & Radiological Safety IR 05000155/19980081998-12-0303 December 1998 Insp Rept 50-155/98-08 on 980827-1130.No Violations Noted. Major Areas Inspected:Radiological Safety IR 05000155/19980071998-10-14014 October 1998 Insp Rept 50-155/98-07 on 980827-1007.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Physical Security,Spent Fuel Safety & Radiological Safety IR 05000155/19980061998-09-0303 September 1998 Insp Rept 50-155/98-06 on 980716-0826.No Violations Noted. Major Areas Inspected:Aspects of Licensee Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980051998-07-24024 July 1998 Insp Rept 50-155/98-05 on 980528-0715.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980031998-06-16016 June 1998 Insp Rept 50-155/98-03 on 980407-0527.Violation Noted.Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980021998-04-21021 April 1998 Insp Rept 50-155/98-02 on 980203-0406.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20203A0141998-02-14014 February 1998 Insp Rept 50-155/97-15 on 971205-980202.Violations Noted. Major Areas Inspected:Facility Management & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20197E5901997-12-17017 December 1997 Insp Rept 50-155/97-13 on 971008-1204.Violations Noted. Major Areas Inspected:Major Aspects of Licensee Decommissioning Activities,Including Facility Mgt & Control, Decommissioning Support & Spent Fuel Safety Controls IR 05000155/19970101997-11-26026 November 1997 Insp Rept 50-155/97-10 on 970802-1007.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 05000155/19970121997-10-17017 October 1997 Insp Rept 50-155/97-12 on 970812-1007.Violations Noted.Major Areas Inspected:Miscellaneous Security & Safeguards Issues IR 05000155/19970091997-10-0909 October 1997 Insp Rept 50-155/97-09 on 970617-0804.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering IR 05000155/19970111997-10-0606 October 1997 Insp Rept 50-155/97-11 on 970902-05.Violations Noted. Major Areas Inspected:Various Aspects of Licensee Chemistry Radiation Protection Programs IR 05000155/19970081997-07-22022 July 1997 Insp Rept 50-155/97-08 on 970430-0616.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20140G8931997-06-10010 June 1997 Insp Rept 50-155/97-04 on 970313-0429.Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000155/19970071997-06-0606 June 1997 Insp Rept 50-155/97-07 on 970426-0501.No Violations Noted. Major Areas Inspected:Licensee Fire Protection Program IR 05000155/19970061997-05-23023 May 1997 Insp Rept 50-155/97-06 on 970428-0502.No Violations Noted. Major Areas Inspected:Review of Vehicles Barrier Sys,Audits & Self Assessment,Testing,Maint,Security Contingency Capability & Protected Area Detection ML20141J9951997-05-19019 May 1997 Insp Rept 50-155/97-05 on 970303-0428.Violations Noted. Major Areas Inspected:Event in Which Workers Entered Power Block While Reactor at 9% Power Level Prior to Performance of Adequate Evaluation of Area Radiological Conditions IR 05000155/19970031997-05-13013 May 1997 Insp Rept 50-155/97-03 on 970331-0404.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program IR 05000155/19960121997-02-24024 February 1997 Insp Rept 50-155/96-12 on 961130-970117.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 05000155/19960011997-01-29029 January 1997 Insp Rept 50-155/96-01 on 961019-1129.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20133C5231997-01-0202 January 1997 Insp Rept 50-155/96-11 on 961202-06.Violations Noted.Major Areas Inspected:Radiological Protection & Chemistry Controls,Status of Rp&C Facilities & Equipment IR 05000155/19960071996-12-0606 December 1996 Insp Rept 50-155/96-07 on 960909-12.No Violations Noted. Major Areas Inspected:Emergency Plan & Procedures IR 05000155/19960061996-10-28028 October 1996 Insp Rept 50-155/96-06 on 960727-0906.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000155/19960051996-09-20020 September 1996 Insp Rept 50-155/96-05 on 960608-0726.No Violations Noted. Continued Attention Needed on Maint Work on Plant TS Required Equipment.Major Areas Inspected:Engineering,Maint, & Plant Support IR 05000155/19930191993-12-21021 December 1993 Insp Rept 50-155/93-19 on 931020-1214.Violations Noted.Major Areas Inspected:Operational Safety Verification,Engineered Safety Feature Sys Walkdowns & Maint & Surveillance Activities IR 05000155/19930201993-11-10010 November 1993 Insp Rept 50-155/93-20 on 931025-29.No Violations Noted. Major Areas Inspected:Followup Insp of Previously Identified Edsfi Findings IR 05000155/19930171993-11-0404 November 1993 Insp Rept 50-155/93-17 on 931018-22.No Violations Noted. Major Areas Inspected:Fire Protection Insp of Surveillances, Equipment,Fire Brigade Training,Zebra Mussel Problems & Fire Protection Audits IR 05000155/19930181993-10-28028 October 1993 Insp Rept 50-155/93-18 on 931018-22.No Violations Noted. Major Areas Inspected:Licensed Operator Requalification Training Program in Accordance W/Nrc Temporary Instruction 2515/117 IR 05000155/19930131993-10-22022 October 1993 Insp Rept 50-155/93-13 on 930828-1019.No Violations Noted. Major Areas Inspected:Esf Sys Walkdowns,Radiological Controls,Security,Maint & Surveillance Activities & Mgt Meetings IR 05000155/19930141993-10-14014 October 1993 Enforcement Conference Rept 50-155/93-14 on 931012.Major Areas Discussed:Reviewed Apparent Violations & Areas of Concern Identified During Insp & Corrective Actions Taken or Planned by Licensee IR 05000155/19930161993-10-0404 October 1993 Insp Rept 50-155/93-16 on 930913-17.No Violations Noted. Major Areas Inspected:Inservice Testing Program,Program on Check Valves & License self-assessment ML20057E7721993-10-0404 October 1993 Insp Rept 50-155/93-15 on 930824-0914.Violations Noted Are Being Considered for Escalated Ea.Major Areas Inspected: Conditions Surrounding Hydrostatic Primary Sys Test & Breach of Containment Integrity W/Concurrent Mode Change at Plant IR 05000155/19930111993-09-0909 September 1993 Insp Rept 50-155/93-11 on 930716-0827.No Violation Noted. Major Areas Inspected:Operational Safety Verification,Esf Sys Walkdowns,Maint & Surveillance Activities,Engineering & Technical Support Activities & Safety Assessment ML20057A1311993-09-0808 September 1993 Insp Rept 50-155/93-10 on 930809-20.Violations Noted.Major Areas Inspected:Conditions Surrounding 930708 Event Re Both Containment High Pressure Sensors Outside Allowable TS Tolerances Due to Installation Error IR 05000155/19930121993-08-31031 August 1993 Insp Rept 50-155/93-12 on 930809-13.No Violations Noted. Major Areas Inspected:Radiation Protection Program During Outage IR 05000155/19920261992-12-24024 December 1992 Insp Rept 50-155/92-26 on Stated Dates.Violations Noted. Major Areas Inspected:Mgt Control & Organization,Internal & External Exposure & ALARA IR 05000155/19920251992-12-0101 December 1992 Insp Rept 50-155/92-25 on 921116-20.No Violations Noted. Major Areas Inspected:Organization,Reactor Sys Water QC Programs Qa/Qc Program in Lab & Nonradiological Confirmatory Measurements IR 05000155/19920241992-11-25025 November 1992 Insp Rept 50-155/92-24 on 921020-1123.No Violations Noted. Major Areas Inspected:Maint & Surveillance Activities, Evaluation of Licensee self-assessment Capability & Cold Weather Preparations IR 05000155/19900201990-11-0707 November 1990 Insp Repts 50-155/90-20 & 50-255/90-27 on 900925-28 & 1015-19.Violations Noted.Major Areas inspected:fitness-for- Duty & Corrective Actions for Audit Findings IR 05000155/19900171990-11-0202 November 1990 Insp Rept 50-155/90-17 on 900904-1015.Violations Noted.Major Areas Inspected:Refueling Activities,Surveillance Activities,Maint of Various Components,Operational Safety Verification & Temporary Instruction Closure IR 05000155/19900101990-09-25025 September 1990 Insp Rept 50-155/90-10 on 900723-27 & 0806-10.Violations Noted.Major Areas Inspected:Maint,Engineering,Support of Maint & Related Mgt Activities IR 05000155/19900131990-09-17017 September 1990 Insp Rept 50-155/90-13 on 900724-0903.No Violations Noted. Major Areas Inspected:Followup on Previous Insp Findings, Refueling Activities,Surveillance Activities & Maint Activities IR 05000155/19900151990-08-24024 August 1990 Insp Rept 50-155/90-15 on 900814-16.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program, Licensee Actions on Previously Identified Items,Activations of Emergency Plan,Equipment,Training & Independent Audits IR 05000155/19900141990-08-16016 August 1990 Safety Insp Rept 50-155/90-14 on 900730-0803.No Violations, Deviations or Other Items Noted.Major Areas Inspected:Maint & Inservice Testing of Pumps & Valves 1999-09-30
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000155/19990051999-09-30030 September 1999 Insp Rept 50-155/99-05 on 990731-0921,site Insp & 990929 Public Meeting.No Violations Noted.Major Areas Inspected: Routine Decommissioning Insp Covered Aspects of Facility Mgt & Control & Decommissioning Support Activities IR 05000155/19990041999-08-12012 August 1999 Insp Rept 50-155/99-04 on 990609-0730.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities Including Security, Spent Fuel Safety & Radiological Safety IR 05000155/19990031999-06-21021 June 1999 Insp Rept 50-155/99-03 on 990416-0608.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990021999-04-26026 April 1999 Insp Rept 50-155/99-02 on 990226-0415.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990011999-03-19019 March 1999 Insp Rept 50-155/99-01 on 990113-0225.One non-cited Violation Noted.Major Areas Inspected:Aspects of Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980091999-01-15015 January 1999 Insp Rept 50-155/98-09 on 981201-990112.No Violations Noted. Major Areas Inspected:Licensee Management & Control, Decommissioning Support Activities,Sf Safety & Radiological Safety IR 05000155/19980081998-12-0303 December 1998 Insp Rept 50-155/98-08 on 980827-1130.No Violations Noted. Major Areas Inspected:Radiological Safety IR 05000155/19980071998-10-14014 October 1998 Insp Rept 50-155/98-07 on 980827-1007.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Physical Security,Spent Fuel Safety & Radiological Safety IR 05000155/19980061998-09-0303 September 1998 Insp Rept 50-155/98-06 on 980716-0826.No Violations Noted. Major Areas Inspected:Aspects of Licensee Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980051998-07-24024 July 1998 Insp Rept 50-155/98-05 on 980528-0715.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980031998-06-16016 June 1998 Insp Rept 50-155/98-03 on 980407-0527.Violation Noted.Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980021998-04-21021 April 1998 Insp Rept 50-155/98-02 on 980203-0406.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20203A0141998-02-14014 February 1998 Insp Rept 50-155/97-15 on 971205-980202.Violations Noted. Major Areas Inspected:Facility Management & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20197E5901997-12-17017 December 1997 Insp Rept 50-155/97-13 on 971008-1204.Violations Noted. Major Areas Inspected:Major Aspects of Licensee Decommissioning Activities,Including Facility Mgt & Control, Decommissioning Support & Spent Fuel Safety Controls IR 05000155/19970101997-11-26026 November 1997 Insp Rept 50-155/97-10 on 970802-1007.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 05000155/19970121997-10-17017 October 1997 Insp Rept 50-155/97-12 on 970812-1007.Violations Noted.Major Areas Inspected:Miscellaneous Security & Safeguards Issues IR 05000155/19970091997-10-0909 October 1997 Insp Rept 50-155/97-09 on 970617-0804.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering IR 05000155/19970111997-10-0606 October 1997 Insp Rept 50-155/97-11 on 970902-05.Violations Noted. Major Areas Inspected:Various Aspects of Licensee Chemistry Radiation Protection Programs IR 05000155/19970081997-07-22022 July 1997 Insp Rept 50-155/97-08 on 970430-0616.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20140G8931997-06-10010 June 1997 Insp Rept 50-155/97-04 on 970313-0429.Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000155/19970071997-06-0606 June 1997 Insp Rept 50-155/97-07 on 970426-0501.No Violations Noted. Major Areas Inspected:Licensee Fire Protection Program IR 05000155/19970061997-05-23023 May 1997 Insp Rept 50-155/97-06 on 970428-0502.No Violations Noted. Major Areas Inspected:Review of Vehicles Barrier Sys,Audits & Self Assessment,Testing,Maint,Security Contingency Capability & Protected Area Detection ML20141J9951997-05-19019 May 1997 Insp Rept 50-155/97-05 on 970303-0428.Violations Noted. Major Areas Inspected:Event in Which Workers Entered Power Block While Reactor at 9% Power Level Prior to Performance of Adequate Evaluation of Area Radiological Conditions IR 05000155/19970031997-05-13013 May 1997 Insp Rept 50-155/97-03 on 970331-0404.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program IR 05000155/19960121997-02-24024 February 1997 Insp Rept 50-155/96-12 on 961130-970117.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support IR 05000155/19960011997-01-29029 January 1997 Insp Rept 50-155/96-01 on 961019-1129.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20133C5231997-01-0202 January 1997 Insp Rept 50-155/96-11 on 961202-06.Violations Noted.Major Areas Inspected:Radiological Protection & Chemistry Controls,Status of Rp&C Facilities & Equipment IR 05000155/19960071996-12-0606 December 1996 Insp Rept 50-155/96-07 on 960909-12.No Violations Noted. Major Areas Inspected:Emergency Plan & Procedures IR 05000155/19960061996-10-28028 October 1996 Insp Rept 50-155/96-06 on 960727-0906.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support IR 05000155/19960051996-09-20020 September 1996 Insp Rept 50-155/96-05 on 960608-0726.No Violations Noted. Continued Attention Needed on Maint Work on Plant TS Required Equipment.Major Areas Inspected:Engineering,Maint, & Plant Support IR 05000155/19930191993-12-21021 December 1993 Insp Rept 50-155/93-19 on 931020-1214.Violations Noted.Major Areas Inspected:Operational Safety Verification,Engineered Safety Feature Sys Walkdowns & Maint & Surveillance Activities IR 05000155/19930201993-11-10010 November 1993 Insp Rept 50-155/93-20 on 931025-29.No Violations Noted. Major Areas Inspected:Followup Insp of Previously Identified Edsfi Findings IR 05000155/19930171993-11-0404 November 1993 Insp Rept 50-155/93-17 on 931018-22.No Violations Noted. Major Areas Inspected:Fire Protection Insp of Surveillances, Equipment,Fire Brigade Training,Zebra Mussel Problems & Fire Protection Audits IR 05000155/19930181993-10-28028 October 1993 Insp Rept 50-155/93-18 on 931018-22.No Violations Noted. Major Areas Inspected:Licensed Operator Requalification Training Program in Accordance W/Nrc Temporary Instruction 2515/117 IR 05000155/19930131993-10-22022 October 1993 Insp Rept 50-155/93-13 on 930828-1019.No Violations Noted. Major Areas Inspected:Esf Sys Walkdowns,Radiological Controls,Security,Maint & Surveillance Activities & Mgt Meetings IR 05000155/19930141993-10-14014 October 1993 Enforcement Conference Rept 50-155/93-14 on 931012.Major Areas Discussed:Reviewed Apparent Violations & Areas of Concern Identified During Insp & Corrective Actions Taken or Planned by Licensee IR 05000155/19930161993-10-0404 October 1993 Insp Rept 50-155/93-16 on 930913-17.No Violations Noted. Major Areas Inspected:Inservice Testing Program,Program on Check Valves & License self-assessment ML20057E7721993-10-0404 October 1993 Insp Rept 50-155/93-15 on 930824-0914.Violations Noted Are Being Considered for Escalated Ea.Major Areas Inspected: Conditions Surrounding Hydrostatic Primary Sys Test & Breach of Containment Integrity W/Concurrent Mode Change at Plant IR 05000155/19930111993-09-0909 September 1993 Insp Rept 50-155/93-11 on 930716-0827.No Violation Noted. Major Areas Inspected:Operational Safety Verification,Esf Sys Walkdowns,Maint & Surveillance Activities,Engineering & Technical Support Activities & Safety Assessment ML20057A1311993-09-0808 September 1993 Insp Rept 50-155/93-10 on 930809-20.Violations Noted.Major Areas Inspected:Conditions Surrounding 930708 Event Re Both Containment High Pressure Sensors Outside Allowable TS Tolerances Due to Installation Error IR 05000155/19930121993-08-31031 August 1993 Insp Rept 50-155/93-12 on 930809-13.No Violations Noted. Major Areas Inspected:Radiation Protection Program During Outage IR 05000155/19920261992-12-24024 December 1992 Insp Rept 50-155/92-26 on Stated Dates.Violations Noted. Major Areas Inspected:Mgt Control & Organization,Internal & External Exposure & ALARA IR 05000155/19920251992-12-0101 December 1992 Insp Rept 50-155/92-25 on 921116-20.No Violations Noted. Major Areas Inspected:Organization,Reactor Sys Water QC Programs Qa/Qc Program in Lab & Nonradiological Confirmatory Measurements IR 05000155/19920241992-11-25025 November 1992 Insp Rept 50-155/92-24 on 921020-1123.No Violations Noted. Major Areas Inspected:Maint & Surveillance Activities, Evaluation of Licensee self-assessment Capability & Cold Weather Preparations IR 05000155/19900201990-11-0707 November 1990 Insp Repts 50-155/90-20 & 50-255/90-27 on 900925-28 & 1015-19.Violations Noted.Major Areas inspected:fitness-for- Duty & Corrective Actions for Audit Findings IR 05000155/19900171990-11-0202 November 1990 Insp Rept 50-155/90-17 on 900904-1015.Violations Noted.Major Areas Inspected:Refueling Activities,Surveillance Activities,Maint of Various Components,Operational Safety Verification & Temporary Instruction Closure IR 05000155/19900101990-09-25025 September 1990 Insp Rept 50-155/90-10 on 900723-27 & 0806-10.Violations Noted.Major Areas Inspected:Maint,Engineering,Support of Maint & Related Mgt Activities IR 05000155/19900131990-09-17017 September 1990 Insp Rept 50-155/90-13 on 900724-0903.No Violations Noted. Major Areas Inspected:Followup on Previous Insp Findings, Refueling Activities,Surveillance Activities & Maint Activities IR 05000155/19900151990-08-24024 August 1990 Insp Rept 50-155/90-15 on 900814-16.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program, Licensee Actions on Previously Identified Items,Activations of Emergency Plan,Equipment,Training & Independent Audits IR 05000155/19900141990-08-16016 August 1990 Safety Insp Rept 50-155/90-14 on 900730-0803.No Violations, Deviations or Other Items Noted.Major Areas Inspected:Maint & Inservice Testing of Pumps & Valves 1999-09-30
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000155/19990051999-09-30030 September 1999 Insp Rept 50-155/99-05 on 990731-0921,site Insp & 990929 Public Meeting.No Violations Noted.Major Areas Inspected: Routine Decommissioning Insp Covered Aspects of Facility Mgt & Control & Decommissioning Support Activities IR 05000155/19990041999-08-12012 August 1999 Insp Rept 50-155/99-04 on 990609-0730.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities Including Security, Spent Fuel Safety & Radiological Safety IR 05000155/19990031999-06-21021 June 1999 Insp Rept 50-155/99-03 on 990416-0608.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990021999-04-26026 April 1999 Insp Rept 50-155/99-02 on 990226-0415.No Violations Noted. Major Areas Inspected:Aspects of Facility Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19990011999-03-19019 March 1999 Insp Rept 50-155/99-01 on 990113-0225.One non-cited Violation Noted.Major Areas Inspected:Aspects of Facility Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980091999-01-15015 January 1999 Insp Rept 50-155/98-09 on 981201-990112.No Violations Noted. Major Areas Inspected:Licensee Management & Control, Decommissioning Support Activities,Sf Safety & Radiological Safety IR 05000155/19980081998-12-0303 December 1998 Insp Rept 50-155/98-08 on 980827-1130.No Violations Noted. Major Areas Inspected:Radiological Safety IR 05000155/19980071998-10-14014 October 1998 Insp Rept 50-155/98-07 on 980827-1007.No Violations Noted. Major Areas Inspected:Facility Mgt & Control,Physical Security,Spent Fuel Safety & Radiological Safety IR 05000155/19980061998-09-0303 September 1998 Insp Rept 50-155/98-06 on 980716-0826.No Violations Noted. Major Areas Inspected:Aspects of Licensee Mgt & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20195C6211998-08-18018 August 1998 EN-98-059,informing Commission That Staff Intends to Exercise Broad Discretion Pursuant to Section VII.B.6 of Enforcement Policy & Not Issue NOV or Propose Civil Penalty for Severity Level II Violation Identified by Licensee IR 05000155/19980051998-07-24024 July 1998 Insp Rept 50-155/98-05 on 980528-0715.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980031998-06-16016 June 1998 Insp Rept 50-155/98-03 on 980407-0527.Violation Noted.Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety IR 05000155/19980021998-04-21021 April 1998 Insp Rept 50-155/98-02 on 980203-0406.No Violations Noted. Major Areas Inspected:Licensee Mgt & Control,Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20202J8471998-02-14014 February 1998 Notice of Violation from Insp on 971205-980202.Violation Noted:Chemical Decontamination Worker Working Under RWP B982035 in High Radiation Area for Approx 55 Minutes & Did Not Monitor Dosimetry Time ML20203A0141998-02-14014 February 1998 Insp Rept 50-155/97-15 on 971205-980202.Violations Noted. Major Areas Inspected:Facility Management & Control, Decommissioning Support Activities,Spent Fuel Safety & Radiological Safety ML20199A2571997-12-30030 December 1997 EN-97-117:on 980105,informs Commission That Order Prohibiting Involvement in NRC-licensed Activities Issued to Dt Rich.Action Based on Investigation Conducted by Oi,Which Determined on 960721 & 0915,DT Rich Falsified Records IR 07100008/20120041997-12-17017 December 1997 Notice of Violation from Insp on 971008-1204.Violation Noted:On 971029,items Hanging from Spent Fuel Pool Rail Span 19 Had Combined Weight of 497 Pounds.Length of Time That Weight on Rail Exceeded Weight Restriction Not Determined ML20197E5901997-12-17017 December 1997 Insp Rept 50-155/97-13 on 971008-1204.Violations Noted. Major Areas Inspected:Major Aspects of Licensee Decommissioning Activities,Including Facility Mgt & Control, Decommissioning Support & Spent Fuel Safety Controls IR 05000155/19970101997-11-26026 November 1997 Insp Rept 50-155/97-10 on 970802-1007.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20199J4571997-11-19019 November 1997 Notice of Violation from Insp on 961216-971107.Violations Noted:Certain Radiation Surveys Required by Station Procedure RP-29,not Completed.Also Certain Radiation Survey Records Required to Be Maintained,Not Accurate IR 05000155/19970121997-10-17017 October 1997 Insp Rept 50-155/97-12 on 970812-1007.Violations Noted.Major Areas Inspected:Miscellaneous Security & Safeguards Issues IR 05000155/19970091997-10-0909 October 1997 Insp Rept 50-155/97-09 on 970617-0804.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering ML20211J7341997-10-0606 October 1997 Notice of Violation from Insp on 970902-05.Violation Noted: on 970902,maintenance Worker Preparing to Participate in Reactor Head Detensioning Operations Laid Down in Contaminated Area for Several Minutes IR 05000155/19970111997-10-0606 October 1997 Insp Rept 50-155/97-11 on 970902-05.Violations Noted. Major Areas Inspected:Various Aspects of Licensee Chemistry Radiation Protection Programs ML20217J3391997-08-12012 August 1997 Notice of Violation from Insp on 970303-0428.Violation Noted:On 970202 Rj Flowers,Employee of Consumers Power Co, Did Not Exit High Radiation Area After Receiving Alarm on Electronic Dosimeter as Required ML20217K5521997-08-12012 August 1997 Notice of Violation from Insp on 970303-0428.Violations Noted:Licensee Failed to Properly Evaluate Potential Radiological Hazards Associated W/Transfer of Highly Contaminated Filters ML20151J7721997-07-22022 July 1997 Notice of Violation from Insp on 970430-0616.Violation Noted:Inspector Identified That on 960403 & 970502,seven & Five CRDs Respectively Were Left After Insertion Time Testing W/Insert Speeds Greater than 28 IR 05000155/19970081997-07-22022 July 1997 Insp Rept 50-155/97-08 on 970430-0616.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support PNO-III-97-055, on 970611,decision to Permanently Shut Down Plant Three Yrs Before Expiration of Operating License in Yr 2000.Capacity of 67 Megawatts & Future Needed Improvements Would Be Too Expensive.State of Mi Will Be Informed1997-06-11011 June 1997 PNO-III-97-055:on 970611,decision to Permanently Shut Down Plant Three Yrs Before Expiration of Operating License in Yr 2000.Capacity of 67 Megawatts & Future Needed Improvements Would Be Too Expensive.State of Mi Will Be Informed ML20140G8931997-06-10010 June 1997 Insp Rept 50-155/97-04 on 970313-0429.Violations Noted. Major Areas Inspected:Operations,Maint & Engineering ML20140G8851997-06-10010 June 1997 Notice of Violation from Insp on 970313-0429.Violation Noted:Procedures Were Not Followed,In That Required Working Clearances & Protective Tagging Were Not Obtained by Workers Prior to Performing Work Activities IR 05000155/19970071997-06-0606 June 1997 Insp Rept 50-155/97-07 on 970426-0501.No Violations Noted. Major Areas Inspected:Licensee Fire Protection Program IR 05000155/19970061997-05-23023 May 1997 Insp Rept 50-155/97-06 on 970428-0502.No Violations Noted. Major Areas Inspected:Review of Vehicles Barrier Sys,Audits & Self Assessment,Testing,Maint,Security Contingency Capability & Protected Area Detection ML20141J9951997-05-19019 May 1997 Insp Rept 50-155/97-05 on 970303-0428.Violations Noted. Major Areas Inspected:Event in Which Workers Entered Power Block While Reactor at 9% Power Level Prior to Performance of Adequate Evaluation of Area Radiological Conditions IR 05000155/19970031997-05-13013 May 1997 Insp Rept 50-155/97-03 on 970331-0404.No Violations Noted. Major Areas Inspected:Emergency Preparedness Program PNO-III-97-012, on 970224,licensee Notified NRC Resident Inspector Ofc That Loose Radioactive Surface Contamination Spread Throughout Turbine Bldg,During Transfer of Radwaste Processing Filters from Temporary Storage Barrel1997-02-26026 February 1997 PNO-III-97-012:on 970224,licensee Notified NRC Resident Inspector Ofc That Loose Radioactive Surface Contamination Spread Throughout Turbine Bldg,During Transfer of Radwaste Processing Filters from Temporary Storage Barrel IR 05000155/19960121997-02-24024 February 1997 Insp Rept 50-155/96-12 on 961130-970117.Violations Noted. Major Areas Inspected:Operations,Engineering,Maintenance & Plant Support ML20135D4431997-02-24024 February 1997 Notice of Violation from Insp on 961130-970117.Violation Noted:Use of Inappropriate Surveillance Procedure Causing Uncontrolled Leak & Inline Relief Valve Lifting Due to Failure to Remove Installed Blank Flange IR 05000155/19960011997-01-29029 January 1997 Insp Rept 50-155/96-01 on 961019-1129.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20134C9421997-01-29029 January 1997 Notice of Violation from Insp on 961019-1129.Violations noted:961108 Operators Closed EC Number 1 Loop Inlet Valve (MO-7062) Making Number 1 EC Loop Inoperable & Operability Test Number 2 EC Loop Outlet Valve Not Performed within 1 H ML20133C5231997-01-0202 January 1997 Insp Rept 50-155/96-11 on 961202-06.Violations Noted.Major Areas Inspected:Radiological Protection & Chemistry Controls,Status of Rp&C Facilities & Equipment ML20133C5111997-01-0202 January 1997 Notice of Violation from Insp on 961202-06.Violation Noted: High Radiation & Contaminated Areas Was Not Posted W/Signs Bearing Radiation Symbol IR 05000155/19960071996-12-0606 December 1996 Insp Rept 50-155/96-07 on 960909-12.No Violations Noted. Major Areas Inspected:Emergency Plan & Procedures IR 05000155/19960061996-10-28028 October 1996 Insp Rept 50-155/96-06 on 960727-0906.No Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support PNO-III-96-064, on 961023,shutdown for Evaluation of Environ Qualification Data Made.Licensee Performed Preliminary Assessment of Effect of Higher than Anticipated Temp Profile on safety-related Electrical Equipment Located1996-10-24024 October 1996 PNO-III-96-064:on 961023,shutdown for Evaluation of Environ Qualification Data Made.Licensee Performed Preliminary Assessment of Effect of Higher than Anticipated Temp Profile on safety-related Electrical Equipment Located IR 05000155/19960051996-09-20020 September 1996 Insp Rept 50-155/96-05 on 960608-0726.No Violations Noted. Continued Attention Needed on Maint Work on Plant TS Required Equipment.Major Areas Inspected:Engineering,Maint, & Plant Support PNO-III-94-039, on 940517,two Persons,Russian Visitor & Interpreter Were Killed in Traffic Accident Near Charlevoix,Mi.Cause of Accident Under Investigation1994-05-18018 May 1994 PNO-III-94-039:on 940517,two Persons,Russian Visitor & Interpreter Were Killed in Traffic Accident Near Charlevoix,Mi.Cause of Accident Under Investigation IR 05000155/19930191993-12-21021 December 1993 Insp Rept 50-155/93-19 on 931020-1214.Violations Noted.Major Areas Inspected:Operational Safety Verification,Engineered Safety Feature Sys Walkdowns & Maint & Surveillance Activities ML20059C1031993-12-21021 December 1993 Notice of Violation from Insp on 931020-1214.Violation Noted:Results of Static Votes Testing at Final Asleft Torque Switch Setting for MO-7053 Were Not Evaluated Prior to Return to Svc of Valve IR 05000155/19930201993-11-10010 November 1993 Insp Rept 50-155/93-20 on 931025-29.No Violations Noted. Major Areas Inspected:Followup Insp of Previously Identified Edsfi Findings 1999-09-30
[Table view] |
See also: IR 05000155/1997005
Text
._ _ . _ _ . _ . . _ . _ _ - . _ . . . _ _ _ _ _ _ . _ . . - _ _ _ . . .. . . . _ _ . . _ _
. ,
,
j .
J
' l
'
U.S. NUCLEAR REGULATORY COMMISSION
,
REGION lli ,
,
t
i i
'
Docket No: 50-155 ;
Licenae No: DPR-06 i
!
Report No: 50-155/97005(DRS)
i -
! !
Licensee: Consumers Power Company
!
.
Facility: Big Rock Point Nuclear Power Plant l
,
Location: 10269 U.S. 31 North
Charlevoix, MI 49720
Dates: March 3 - April 28,1997
Inspectors: R. A. Paul, Senior Radiation Specialist
G. W. West, Radiation Specialist
Approved by: Thomas J. Kozak, Chief, Plant Support Branch 2
'
Division of Reactor Safety
9705280200 970519
PDR ADOCK 05000155 ~
G PDR .
--
. . --. - . - . - . - . - .- . . - . - - - - - . - - . - .- - - .-. --
. .
.
EXECUTIVE SUMMARY
Big Rock Nuclear Power Plant
NRC Inspection Report 50-155/97005
The inspectors reviewed an event in which workers bntered the power block while the
reactor was at 9% power level prior to the performance of an adequate evaluation of the
area's radiological conditions, and reviewed a separate but related event that resulted in I
the spread of contamination throughout the turbine building. Also reviewed was an event
in which a station engineer who was not qualified to enter high radiation areas without
accompaniment by a radiation protection technician (RPT), entered a HRA on two
occasions without an RPT. . These events resulted in the identification of three apparent
violations which are described in detail in the enclosed report, and are being considered for
escalated enforcement. The common cause of the apparent violations, which includes the
failure of licenses staff to adequately plan for jobs and to adequately evaluate radiological i
conditions in job areas, indicates radiological programmatic deficiencies in the areas of pre- j
Job planning, ALARA planning, and radiological assessment. Workers also exhibited a lack ;
of sensitivity towards radiation protection controls during these events.
In addition to the events, a review of the radiological environmental monitoring program
and the liquid and gaseous radioactive waste processing programs was performed and no
significant problems were identified in these areas.
l
l
!
l
2
- .. .. . . - - _ - - - . - _ . -
.
4
Renort Details
IV. Plant Suonort
R1 Radiological Protection and Chemistry Controls
R1.1 Control of Rac'ioloolcal Work Activities
a. Insoection Geone (83750)
Using inspection Procedure 83750, the inspectors reviewed the circumstances
surrounding the entry of two individuals into the power block to perform inspection
of the equipment in the area for steam leaks (tour event), and a separate but related
event in which contamination was spread throughout the turbine building while
disposing of contaminated waste processing filters (filter event!. The inspectors
also reviewed the circumstances surrounding the entry of an unqualified individual
into a high radiation area (HRA) without specified procedural controls.
b. Observations and Findinas
Tour Event
On February 2,1997, two workers performed the grand tour in the power block. A
number of problems, which are detailed below, occurred during this job. These
problems were either self-identified in a licensee root cause evaluation or were 44
revealing during the event. The inspectors' independent review of the event
determined that the licensee had accurately assessed the event and the problems
which were encountered in their root cause evaluation. The specific details of the
event are described below.
After a plant shutdown, the licensee performs a tour (known as the grand tour) of
the steam drum and piping areas within the power block to identify steam leaks
that may be present. This tour is normally performed at operating pressure and
with the plant at very low power levels (approximately 1 percent power). Personnel
normally enter at an upper elevation (steam drum level) and proceed down about
three levels via a ladder and out of the area. Dose rates typically encountered
during the tour are less than 2 rem /hr gamma with no appreciable neutron dose
rates.
The licensee was in the final stages of an outage during which main steam isolation
valve work was conducted. Surveillance testing of the valves was required to be
performed with the reactor at approximately 8 MWe (9% power). The operations
department determined that it would be most efficient to perform the grand tour in
conjunction with the MSIV surveillance testing. Radiation protection supervision
was not involved with this decision which indicated that they were not adequately
involved in the job planning process.
3
. _ _ _ . _ _ - - _ _ _ . _ _ . _ _ . _ . _ _ _ _ _ _ _ . _ . - .._._._ _ _ _ _ . _ _ _. _ _ _
t
( .'.
i
j .
,
The normal entry from the steam drum area was locked; therefore, it was !
- necessary to enter the power block from the recirculation pump area in the lower ,
level, up the ladder to the stecm drum and then back down the ladder. The revised
path required traversing the HRA areas twice, thus effectively increasing personal :
! dose. Although the radiological conditions were expected to be worse than those
j normally encountered during the tour, the workers associated with the job did not
- appropriately address these differences during the planning stages or the briefings
l for the job. The radiation work permit covering this activity was not revised '
beforehand to reflect the different radiological conditions which exist during 9%
power operations, nor were the electronic dosimeter (ED) alarm setpoints changed
- to accurately reflect expected dose and dose rate levels. The projob planning and
j' briefing did not address historical data for the radiological conditions at this power
'
) level or special ALARA considerations such as the appropriate tour route. This ,
i- represented a failure to appropriately evaluate the potential radiological hazards
- associated with the job.
t
l The tour was performed by a shift supervisor (SS) who was accompanied by a
j senior radiation protection technician (RPT). The RPT had a dose rate meter but it ;
was dark and very difficult to see. At about the midpoint of the climb up the
- ladder, both person's EDs alarmed for a high dose rate. The RPT did not check the ;
i dose rate meter at this time. They continued up the ladder to a platform where the
RPT indicated that they had to leave the area per procedure. However, after a
i discussion with the SS,it was decided that it would be ALARA to complete their
j tour because the inspection would still have to be completed another time, causing l
.
additional dose. The RPT checked his dose rate meter and determinad dose rates .
l- were approximately 4 rem per hour on the platform. This was the only time during l
l the tour that dose rates were verified. Sometime between receiving the dose rate i
i alarm and arriving at the platform, the individuals' preset accumulated dose alarm
j activated. The individuals proceeded up to the steam drum area, performed the
- required inspection and then proceeded down the ladder and out of the area. The
workers immediately reported the ED alarms and their thought process in a
i condition repcrt (CR) upon exit from the area. i
!
! Based on TLDs for each of the workers their accumulated whole body exposure,
i' including neutron dose, was 273 mrem and 341 mrem respectively. The
!
'
corresponding dose from gamma exposure recorded on the EDs was 245 mrem and
315 mrem respectively, and the maximum gamma dose rate for each individual was
6880 mrem and 7050 mrem respectively. The ED histogram also indicated dose
rates during the tour ranged up to 5 rem /hr (0.05 Sv/hr) to 7 rem /hr (0.07 Sv/hr)
and the tour took about 17 minutes. The inspectors evaluation of the whole body
exposures indicated the results were reasonably consistent with the varying dose
rates and the times recorded on the ED histogram.
i
10 CFR Part 20.1501, requires licensee's to make surveys that are reas,onable
under the circumstances to evaluate the extent of radiation levels and the potential
radiological hazards that could be present. The failure of the workers to evaluate
the extent of radiation levels and the potential radiological hazards that could be
present (gamma dose rates ranged up to 7 rem / hour and the neutron dose rates
4
. ., -
. _ ..
1
,
.
ranged up to 1.5 rem / hour during the grand tour) to ensure compliance with 10 CFR
20.1201(a)(1), is an apparent violation of 10 CFR 20.1501(a) (eel 50-155/97005-
01a). I
1
l
Failure to exit the HRA after receiving electronic dosimetry alarms during the grond 1
tour is an example of an apparent violation of Technical Specification (TS) 6.11. l
This TS refers to Administrative Procedure 5.8, "High Radiation Area Key and j
Access Control," Revision 10, which requires in Step 5.1.f.7. that a HRA be l
. immediately exited on either an ED dose or dose rate alarm (eel 50-155/97005- )
02a).
In addition to the apparent violations which occurred during the entry, the coverage
provided by the RPT for the job was poor. The individuals had a dose rate meter
l
end thus met the TS requirements for control of high radiation area entries.
'
However, the meter was not periodically read and the individuals only determined :
the actual area dose rates on one occasion during the tour. Therefore, they were !
not always aware of the radiological conditions in the area and did not detect the
highest dose rate that they actually experienced. Licensee management indicated
that this performance did not meet their expectations for high radiation area
- coverage by an RPT.
i
a Several immediate corrective actions were taken after this event, including: Plant
i manager approval was temporarily required before performing work in HRAs and all
! RWPs required the HP manager's approval, the workers involved were disciplined, l'
!
accountability for procedural adherence was addressed with all plant personnel, and
a case study was developed on the lessons learned from this event and presented
,
to all station personnel. Other corrective actions included reorganization of the RP
! department to provide stronger oversight of RP related activities and ALARA
i planning; additional personnel were added to the management (including first line
l supervisors) delineating their responsibilities and authority in radiological decisions
i involving radiation safety and ALARA.
l
l The licensee's investigation also found that workers exhibit a casual
'
approach to radiation protection and RWP work practices which were
- evidenced by the following identified weaknesses
- the RWP had not been
updated for the expected dose nor did 'it characterize the actual radiological i
i conditions in the areas being inspected, including not clearly defining the :
l neutron monitoring requirements or actual dose rates; the dose rate and EDL '
i alarms had not been raised and were inappropriate for the actual conditions; i
the ALARA and prejob planning and briefing were weak; and individuals
'
l involved in the evolution did not adequately review and understand the RWP
l conditions and requirements. ,
!
) Filter Event
i
'
On February 24,1997, loose radioactive surface contamination was spread
- throughout the turbine building while radwaste handlers transferred depleted waste
l processing filters from a temporary holding barrel into a filter transfer cask. This
'
I 5
i
i
k
'
i i
.
._ _ _ _ _ . _ . . _ _ . _ _ - - -._ _ _. _ _._ _.__ _ _ _ _ . . . - _ - . _ . _ _ . .
i
!-
j
\
i
event was subsequently reviewed by the licensee and the problems assor.iated with 1
F it were self-identified during the event. The inspectors' independent review of the
,
- event determined that the licensee had occurately assessed the event and the ;
j problems which were encountered in their review. The specific datails of the event ;
.
are desc.ibed below.
L >
4
The event occurred when two radwaste handlers were moving fih n from a l
j storage barrel into a transfer cask. To accomplish this, the radwuste processing ,
'
j area (RWPA) ceiling cover plug was removed so the workers L.ould remotely ;
transfer the filters. .The plant ventilation system had been placed in a cold weather
configurd which required closing turbine building louvers and Tacirculating flow.
,
l The ff - not been previously transferred under this condition, in order to .
l
i- transkt < .cers, the workers had to capture them bv # stabbing / spearing action !
with the pointed end of a long hsndled tool. The filters had been in the storage
[1 -
3
barrel for approximately one month and had dried out. The surface reading on the
,
l
barrel was about 32 rem /hr (0.32 Sv/hr). Contamination on the filter was disturbed l
. by the stabbing / spearing action during their transfer and the ventilation flow carried
3
the contaminated material to the turbine building.
!
l Contamination levels ranged from 300,000 disintegrations per minute (dpm) on i
i large area surveys (smears) in the turbine build 5g to 1,000,000 dpm on large area ;
smears in the RWPA, primarily from cobalt-60. The highest beta dose rate on one ;
l of the smears was approximately 320 mrad / hour (3.20 milli /Sv). Severalindividuals ;
4 were slightly externally and intemally contaminated as a result of this event. The
[ cumulative personnel dose during decontamination activities was approximately 30
j millirem (0.3 milli /Sv) caused primarily from normal radiation dose rates in the areas !
j decontaminated. Access was allowed to the area during the decontamination l
- activities in accordance with licensee procedures and the decontamination of the !
j affected areas was completed in about three days. Because there was no
i measurable increase in the stack particulate monitor during this event and no I
j contamination detected during surveys performed cutside of the plant, it appears
l there was no release of radioactive material to the environment.
!
! Although pre-job and ALARA reviews were performed prior to the filter transfer job,
- insufficient attention was given to the changed plant and radiological conditions
j such as the ventilation system being placed in a cold weather configuration, higher
i than normal dose rates on the filters, and the longer storage time for the filters
i which allowed them to dry out making it much more likely that contamination
! would becorn airborne. Because HRA work was on hold, the fi!ters began to
[ accumulate in the RWPA causing the higher than usual dose Wes, and the filters
i had dried out for a month compared to a normal week or w % 4 significant 1
! airbome radioactive material condition resulted when the fh M " are transferred
j without the use of engineering controls. The failure to properly evaluate the
! potential radiological hazards associated with the transfer of the highly
- contaminated filters is an additional example of an apparent violation of 10 CFR
} 20.1501(a). (EE1 No. 50-155/97005-01b).
1
4
i
i
6
)
.
4
!
L__-_____---__._____,_____ - _ _ - - -. - _ _ . - , . . - - - - _ _ . . _ - . , - - . - - - -
.-,1
- ,
<
,. l
j -
! The gaseous waste management system description in Final Hazards Safety Report
4- (FHSR), Section 11.3.2, states that air flow rates will remain sufficient to minimize
build-up of airborne contamination and that flows begin in radioactively clean areas
j
and are directed to potentially mere highly contaminated areas then exhausted to
-
- the stack. Drawing number 0740G40124, which is referenced in FHSR Section
] 11.3.2, indicetes that air flows from the RWPA directly into the exhaust plenum
- and out the plant stack. During this event, the air flow was reversed (from the
! ' RWPA through the turbine building, into the pipe tunnel, and out the main stack).
4
This flow was from an area of high contamination to ons of lower contamination
i levels. During the licensee's investigation of thu event, the damper on the RWPA
- exhaust pleaum was found to be closed (this was not expected even in a cold ,
l weather configuration), thereby considerably restricting the air flow of the exhaust i
j system, which caused the flow to reverse. It was not determined when or how
' !
long the damper had been closed. This modification to the air flow pathway was !
O
not adequately analyzed. No design change nr 10 CFR 50.59 safety evaluation was
l
l performed to address the new ventilation flow path. This is considered an example {
of an apparent violation of 10 CFR 50.59 (eel No. 50-155/97005-03(DRS)). '
i
.
! )
Several immediate corrective actions were taken following this event, including: i
! the use of engineering controls will be specified for future evolutions of this nature, l
! the damper on the radwaste ventilation system was opened to establish design !
! flow, and the method for transferring the filters was changed from a stabbing l
i action to a grasping action. Longer term actions include the balancing of statinn !
-
ventilation airflows in accordance with design. l
l Unaualified Worker Entries into HRA 1
j On January 20,1997, the licensee identified that a station engineer who was not l
i high radiation area access (HRAA) qualified entered the reactor water clean up .
i pump room on two occasions. Although he was accompanied by an auxiliary '
] operator who was HRAA qualified, this was not in accordance with Administrative
!
Procedure 5.8.c, "HRA Key and Access Control," which states that entry into HRAs
is not allowed unless there are two persons, both of whom should be HRAA l
l qualified, and if one person is not, then he/she will be provideo with dedicated RPT
l coverage. The ares entered was posted and controlled as a HRA with some
! sections having general area dose rates in excess of 1 rem /br. The failure of the
non-qualified engineer to be provided with RPT coverage is an additional example of
j an apparent violation of TS 6.11 requirements that radiation protection procedures 3
J
be established and adhered to. (eel No. 50-155/97005-02b). j !
'
Several performance problems c ontributing to this apparent violation were noted,
j including: the engineer neither anderstood or knew the requirements for HRAA;
i there was no accurate list of HAAA qualified persons available; and operations,
j
'
radiation safety, and engineering personnel associated with this event did not have
a questioning attitude conce.ning the engineers qualifications. In addition to the
general corrective action.* caken to address the station issue of lack of sensitivity to
j radiation protection cor.trols, specific corrective actions for this incident included
l counseling of worke:s involved, briefings with the Health Physics staff concerning
I
7
L
4
.
,,n , ,- , -
_ _ .__ _ _ ___ _ __ _ _ _ . _ . _ _ . _ _ _ ___ _ _ _ _ _ _
.
4
)
counseling of workers involved, briefings with the Health Physics staff concerning
their responsibilities at access control, and the posting of an up-to-date list of HRRA
qualified persons at the access control.
c. Conclusions
The events revealed a number of problems in the radiation protection program
including a lack of effective supervisory oversight and involvement in radiologice.l I
work activities, a failure to adequately address the radiological implications e,i work
activities during the work planning stage, and a generallack of respect for
i radiological hazards and controls by the workforce. Although the events did not
result in a substantial potential for an overexposure, the failure to recognize the
potential radiological hazards present (filter event), the failure to specify appropriate
controls for the work when more severe radiological hazards were recognized to be i
2
present (tour event), and the failure to recognize the lack of qualification to enter
,
HRAs iridicates that significant weaknesses existed in the radiation protection
- prograrn.
l The apparent violations identified above are being considered for escalated
enforcement action in accordance with the " General Statement of Policy and
4
Procedure for NRC Enforcement Actions" (Enforcement Policy), NUREG 1600.
Accordingly, no Notice of Violation is presently being issued for these inspection
findings. Since the circumstances surrounding these apparent violations, the
significance of these issues, and corrective actions were discussed with the
4
licensee at the interim exit meeting for this inspection period on April 3,1997, a
predecisional enforcement conference may not be necessary in order to enable tho
l NRC to make an enforcement decision. Before the NRC makes its enforcement
l decision, the licensee will be provided an opportunity to either respond to the
apparent violations or request a predecisional enforcement conference, as described
in the cover letter to this report.
R1.2 Radioloaical Environmental Monitorina Proaram (REMP) and Liouid and Gaseous
Radwaste Processina
4
a. Insoection Scoos (IP 84750)
J
The inspectors reviewed selected portions of the licensee's liquid and gaseous
l radwaste program including radwaste discharge records and procedures, dose
j
'
quantification methodology, technical documents to determine compliance with
effluent requirements, effluent control instruments, accident monitor calibration
4
procedures and results, establishing ' monitor alarm set points, and discharge batch
releases. The inspectors also reviewed the REMP,
1
!
b. Observation and Findinas
There were two changes to the Off-site Dose Calculation Manual (ODCM) in
January 1996, which were adjustments to reflect an updated land use census.
Specifically, the distance values for residence / garden, cattle, and dairy cows (and
h 8
.
J
.--
. - - . - - - _ _ - - - . - - . . - - - . - - ~ ~ - _ _ - - - - . . - -
4
.
!
j goats) were updated, as were corresponding X/O computations. These changes
! were acceptable. Quantification of gaseous discharges was completed in
l accordance with the appropriate procedures and grab samples taken from the off-
4
gas system, which were used to quantify gaseous releases, were verified by the
, use of stack effluent monitor results.
3 No significant operability problems with gaseous radioactive effluent monitors
i required by Technical Specifications were identified. However, the licensee has had
l chronic problems maintaining isokinetic flow through the stack effluent monitor.
4
The flow through the instrument, which is needed to ensure accurate particulate
i readings, continues to be at the lower range of the licensee's design basis listed in
j the FSAR, and on several occasions the flow velocity had dropped enough for the
'
monitor to be declared inoperable. To ensure the T/S requirements were met during
! those times when the flow was lower than required, the licensee took
- compensatory samples including periodic sampling of reactor coolant. The licensee
l has recently changed to a different type of particulate filter and has performed
, extensive analysis to determine the cause of this problem. At the time of the
j inspection, it appeared to be a design problem with the pumps pulling air through
! the instrument. The licensee planned to replace these pumps during the next
refueling outage. It appears that the licensee has taken appropriate actions to
- review and correct this problem.
j
l All radioactive liquid batch effluent releases were evaluated by analysis of
} representative samples and released through a TS monitor, through a downstream '
i discharge canal monitor, and into Lake Michigan. One abnormal release occurred '
on March 2,1997, when a reactor operator attached a hose to the reverse osmosis
unit drain to transfer slightly contaminated water (about 1E-5 microcuries per
milliliter) to the drain under the caustic tank. This drain was one of two floor drains
in the condensate pump room which were plugged to prevent drainage to the Lake.
There was an obscured sign nearby stating that the drain should not be used for
disposal of contaminated liquids; however, this was not recognized by the operator.
Although this drain was plugged, the licensee discovered a small hole in the drain
bowl, leading them to believe that a minimal amount of water may have been
discharged to the concrete surrounding the line. Subsequent investigation
determined that the defect allowed the water (less than about 0.015 microcuries in
one liter) to leak under the condensate pump room floor. Immediate ccrrective
actions to prevent recurrence included strengthening of administrative procedures
used to control radioactive liquid transfers, training of personnel on those revisions
and performance of an engineerinc evaluation to evaluate other plant drains
susceptible to similar degradation and repair of those drains identified. The licensee
indicated that the contamination would be removed in the near future.
The inspectors walked down all TS-required process monitors and their condition
was good. The inspectors reviewed procedures, past calibrations, channel
functional checks, sources checks, and set point calculations for the TS effluent
monitors. All of the procedures were acceptable and were performed correcdy and
the documentation was complete. In addition, procedures had been appropriately
modified to correct for inspection followup item (IFI) 50155/95005-01(DRS),
9
. __ .- -- -
__ _ _ . _ _ . _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ . . _ - - _ _ _ _ _ _ _ _ _ _
.
'
.
'
l
,
which involved a failure to account for the decay of a cesium-137 standard used in
the calibration of the liquid monitors (Circulating Water Discharge Process Monitor l
and Liquid Radwaste Effluent Monitor).
l
'
The inspectors observed the control room indications for the process and effluent
monitors and interviewed control room personnel about these monitors. The
recorders and indications were in good condition and personnel were comfortable
with monitor alarm procedures and wlth setpoint determination and adjustment on
these monitors. l
Inspectors reviewed the 1995 and 1996 Annual Effluent Reports and determined
that offsite doses were calculated in accordance with the ODCM. Generally, total
gaseous radioactive affluents were down about 30 percent (from 4902 Ci to 3490
Ci) for 1996, except for tritium, which was up substantially (127 percent). Total
liquid radioactive effluents were down about 15 percent (from 562 mci to 480
mci) for 1996, except for tritium, which was down about 43 percent. The licensee
attributes these trends to differences in operating history between 1995 and 1996,
as well as to decreased plant water (and thus tritium) leakage.
The inspectors reviewed a recent audit (January 1997) of the licensee's RETS
(Radiological Effluent Technical Specifications) and REMP. The audit found that the
licensee was effectively implementing the REMP/RETS program while meeting the
requirements of their applicable Technical Specifications, administrative and
working level procedures, and of 10 CFF1 Part 50, Appendix B. Three open items
addressed in the audit included a stack gas sampling instrument flow rate problem
(discussed in this Section; a lack of Chemistry / Health Physics improvements
documentation and self-assessment, and multiple occurrences of corrections on
sample data collection forms not being dated / initialled. Corrective actions for these
items was in progress.
c. Conclusions
Overall, the liquid, gaseous, control instrumentation, and REMP monitoring program
was effectively implemented. Radioactive releases and dose to the public from the
releases were well below the regulatory permissible limits. Quantification of
gaseous and liquid discharges were completed in accordance with the appropriate
procedures, and the inspectors established that offsite doses and effluent release
monitor setpoints were calculated using ODCM methodology. An incomplete
understanding of the liquid radwaste processing system led an operator to direct
slightly contaminated water to a plugged floor drain which in turn led to about one
liter of water to migrate to the concrete surrounding the drain line.
R8 Miscellaneous RP&C lasues
R8.1 (Closed) IFl 50-155/95005-01: failure to account for the decay of a cesium-137
standard used in the calibration of the liquid monitors. The calibration procedures
for the Circulating Water Discharge Process Monitor and the Liquid Radwaste I
10
!
l
_ _
.
T
4
Effluent Monitor have been appropriately modified such that the radioactive decay
l of the source is accounted for. This item is closed.
V. Management Meetings '
X1 Exit Meeting Summary I
l
!
The inspectors presented the inspection results to members of licensee management ,
during an interim exit meeting on April 3,1997 and at the conclusion of the inspection on j
'
April 28,1997. The licensee acknowledged the findings presented. l
!
The inspectors asked the licensee whether any materials examined during the inspection :
should be considered proprietary. No proprietary information was identified. I
,
i
4 1
1
'
,
- i
l
i
. I
4
!
l
I
-
l
i
1
'
'
l
l
i
11
!
)
,
O
PARTIAL LIST OF PERSONS CONTACTED
Licensee
R. Addy, Plant Manager
W. Blosh, Maintenance Supervisor
M. Bourassa, Acting Licensing Manager
L. Darrah, Operations Supervisor
K. Pallagi, Chemistry / Health Physics Manager
T. Popa, Chemistry / Dosimetry Supervisor
K. Powers, General Manager
G. Withrow, Plant Safety and Licensing Director
INSPECTION PROCEDURES USED
IP 83750: Occupational Exposure
IP 84750: Liquid and Gaseous Radwaste
ITEMS OPENED and CLOSED
l
Ooened
50-155/97005-01(a,b) eel two examples of a failure to perform adequate
evaluation >
50-155/97005-02(a,b) eel two examples of a failure to follow procedural
requirements )
50-155/97005-03 eel failure to perform safety evaluation '
Closed
50-155/95005-01 IFl failure to account for the decay of a cesium-137
standard used in the calibration of the liquid monitors
Discussed
No open items were discussed
12
__ _ _ - - .
_. . . _ . . _ _ _ . . _ . . _ . _ . _ . - - - _ . . _ . _ _ _ . . __ _ _._
.
4
. ;
} LIST OF ACRONYMS USED
ALARA As Low As Reasonably Achievable
HRA High Radiation Area
HRAA High Radiation Area Access
HP Health Physics
IFl inspection Followup item
IP Inspection Procedure
IR Inspection Report
LER Licensee Event Report
NOV Notice of Violation
NRC Nuclear Regulatory Commission
RO Reactor Operator
RP Radiation Protection *
RPA Radiologically Protected Area i
RPT Radiation Protection Technician !
SS Shift Supervisor
TS Technical Specification
VIO Violation
l
.
'l
l
l
.
13
. - - . . - - -- - . - . . - . . - . - - . - . . . . - . . - - - - - - . - - -
! *
..
>
l LIST OF DOCUMENTS REVIEWED
1 inspection Procedure 84750
BRP FHSAR Rev. 4 Section 11.5
BRP TS Section 13.1
! BRP Elfluent TS (RETS) and Radiological Environmental
Monitoring Program (REMP) Audit - PT-97-01
(dated 1/20-24/97)
BRP Annual Radioactive Effluent Release Report - 1995
BRP DRAFT Annual Radioactive Effluent Release Report - 1996
NUREG-0660
ANSI N13.1-1969
BRP Procedures:
TR-93/CIP-20 (Rev.13) " Calibration of Stack Monitor Detectors" (3-5-96)
TR-104/CIP-37 (Rev. 2) " Calibration of Liquid Radwaste Effluent Process Monitor"
(1-23-96)
TR-105/CIP-38 (Rev. 2) " Calibration of Circulating Water Discharge Process
Monitor" (1-23-96)
T15-01/CIP-26 (Rev. 5) " Semi-Monthly Source Check of Radwaste to Canal
Process Monitor" (2-21-97)
T30-49/CIP-24 (Rev. 6) " Monthly Source and Response Check of Off Gas
Monitors" (2-21-97)
T30-33A/CIP-19A (Rev.13) " Monthly Source and Response Check of Stack
Monitors" (2-21-97)
T30-50/CIP-25 (Rev. 8) " Monthly Source Check of Circulating Water Discharge
Process Monitor" (2-21-97)
T90-20/CIP-27 (Rev.10) " Radiological Effluent Monitor System Chanoc! Functional
Test" (2-21-97)
TR-53/CIP-18 (Rev. 6) " Calibration of Off-Gas Chambers"
(3-7-96)
Condition Reports:
C-BRP-97-0175, "T90-18, Filter not properly installed"
C-BRP-96-988, "RGEM/SGM Low Flow Condition"
C-BRP-96-1011, "High Range Noble Gas Alert and High Alarms On"
C-BRP-96-146, " Lack of Proper Documentation for Acceptable Surveillance Test
Results"
C-BRP-96-800, "RGEM accident filters not available"
C-BRP-97-0171, "RGEM Skid Loss of Communications Light, Processor Fail LED
Flashing"
C-BRP-97-OOO9, " Canal LPM Alarms"
C-BRP-96-287, " Frozen Canal Liquid Process Monitor Suction Line"
14