IR 05000302/1998009
ML20196C061 | |
Person / Time | |
---|---|
Site: | Crystal River |
Issue date: | 11/13/1998 |
From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
To: | |
Shared Package | |
ML20196C058 | List: |
References | |
50-302-98-09, 50-302-98-9, NUDOCS 9812010240 | |
Download: ML20196C061 (14) | |
Text
- .. . . . . . - - . . . . . .. - - . - . - - _ . .. _ .. _ ........... - . --..-.-.- ......- . - -
'
.
r U.S. NUCLEAR REGULATORY COMMISSION REGIONl'
Docket No: 50-302 License No: DPR-72 l
Report No: 50-302/98-0S Licensee: Florida Power Corporation Facility: Crystal River 3 Nuclear Station Location: 15760 West Power Line Street Crystal River, FL 34428-6708 Dates: . September 13 through October 24,1998 Inspectors: S. Cahill, Senior Resident Inspector l S. Sanchez, Resident inspector C Payne, Reactor Engineer (Sections 05.2,05.3)
G. Wiseman, Reactor inspector (Sections F8.1, F8.2 )
Approved by: L. Wert, Chief, Projects Branch 3 Division of Reactor Projects
!
,
y e
s
-
Enclosure
-
9812010240 PDR ADOCK 05000302 981113 O pg
.
e> ,, , , , , , + , - n s , ,
'
.
I I EXECUTIVE SUMMARY Crystal River 3 Nuclear Station NRC Inspection Report 50-302/98-09 This integrated inspection included aspects of licensee operations, engineering, maintenance, and plant support. The report covers a six-week period of resident inspection; in addition, it includes the results of announced inspections by regionalinspectors in the areas of fire protection and licensed operator requalification trainin Operations l
. The licensee was proactively and thoroughly addressing personnel errors which had previously caused operational equipment configuration control problems. A multi- i disciplined team was established to review the problem. The team issued a I comprehensive and self-critical report with numerous thorough corrective action l recommendations. Effective short-term corrective actions such as full procedural usage l and peer checking requirements were implemented and appropriate long term actions I were being considered (Section 01.2).
. The training provided for a complete revision to the clearance and tagging procmses l was thorough and closely linked to the procedure requirements. Training included j hands-on practical applications for different user levels, which was appropriate due to I the entirely new process being implernented (Section 05.1).
. Simulator training was effective and operator performance during this training was goo The conduct and performance of the simulator examinations was satisfactory. The evaluators were thorough in noting individual performance discrepancies and the scenarios observed were effective in discriminating non-competent from competent operators. Documentation of individual performance results was satisfactory (Section 05.2).
. The licensee conducted remedial training and evaluations as required by 10CFR 55.59 and facility training procedures. Operators that had failed requalification tests and quizzes were removed from shift until remediation was complete (Section 05.3).
l
. The licensee's Correctivo Action Review Board consistently exercised strong and critical oversight of proposed root cause determinations and corrective action plan Expectations for quality were high and the Board's review resulted in improved individual performance. TNs was considered a strength of the licensee corrective action system (Section 07.1).
. The Plant Review Committee (PRC) was upholding high review standards to ensure supplied material was fully developed in order to support a valid PRC approval
! (Section 07.1).
l
,
_ _ . . _ _ _ _ _ . . _ . . _ - - _ . _ . . _ _ _ .._.-. ._ . . __ . _ _ . ._ ._.. - - . _ _ . . ..._
l '
.
l
Enaineerina
.
The licensee was adequately pursuing resolution of open long-term design and inspection open items. A minor deficiency was identified associated with tracking of corrective actions initiated at License Amendments Review Boards (Section E1.1). )
,
.
A Design Review Board for a new diesel driven emergency feed pump was widely .
attended and all groups received an opportunity to identify their concerns and needs for i the modification. Questioning identified numerous valid concerns, addressed lessons I
!
learned from previous major projects, and was reflective of superior performance - 1
. standards (Section E1.2). I i
~
! l
!
,
I I.
i i l
!
l l
l !
l l
'
l
't .
f i
__. , _ - ,_., . - -
.
Report Details Summarv of Plant Status The plant began the inspection period at full rated thermal power and remained at that level throughout the report perio I, Operations 01 Conduct of Operations 01.1 General Comments (71707) i
Using Inspection Procedure 71707 the inspectors performed routine reviews of plant l operations which included shif t turnovers, operator log reviews, daily planning meetings, clearance reviews, operator training, and system walkdowns. Significant observations are discussed in subsequent paragraph l The inspectors performed a complete detailed walkdown of the fluid portion of the I Emergency Feedwater (EF) system, verifying system configurations against licensee l flow print and valve lineup requirements. Walkdown of EF support systems, verification l of EF improved Technical Specification (ITS) surveillance requirements, and review of l EF maintenance and corrective action backlogs were stillin progress at the close of the i report period. During the walkdown, the inspectors observed that the condition of the EF system appeared very good due to the lack of observed equipment deficiencies and work request tags. The inspectors identified several minor discrepancies between the flow prints and the field installation, mainly involving pipe caps, pipe reduction locations, and components not reflected on the flow prints. Most of these discrepancies had been also identified by the licensee during their labeling upgrade project walkdown. The inspector verified all of the deficiencies were either already being corrected or were added to the label project deficiency list for correctio .2 Operational Confiauration Control Insoection Scope (71707)
The inspector reviewed the licensee's actions folicwing several component position problems attributed to poor human performance wnich occurred in July and August of 1998. Some previous similar problems and the licensee's actions were discussed in inspection Report (IR) 50-302/98-0 Observations and Findinas in response to the most recent (August 1998) problems with operational configuration control, the licensee's immediate response included a 30-day requirement for all plant departments to perform 100% peer checking and to have a procedure in hand for any evolution on plant equipment. All troubleshooting activities were also required to use equipment alteration logs and have restoration positions determined by Operation The inspector observed that the number of errors significantly decreased in the two months following implementation of these action *
.
i
The licensee established a multi-disciplined team of maintenance, operations, and chemistry personnel to investigate the problem, review the trends of the previous year, ,
and propose loa term corrective actions. The licensee had previously identified l examples of poor status control over the past year and attempted to correct the underlyine musal factors, but concluded the actions were not fully successful because
, problems continued to occur. The I:censee's Collective Analysis Trend Report issued July 16,1998 for the period from November 1997 through spril 1998, also co:tcluded that generic weaknesses in self-checking hurnan performance techniques were sNil evident. Although none of these recent probiems resulted in significant impact on plant systems, the licensee concluded that an escalated and more comprehensive response to human performance issues was warranted. The previous investigations of component mispositionings concluded that numerous disparate causes, such as inadequate verification of componer ts, poor procedural compliance, and incomplete restoration from troubleshooting, were involve The inspector reviewed the investigation team's detailed summary report, issued on October 6,1998, and found it very candid and comprehensive. The team had reviewed all precursor cards (PC) initiated this year on compor ent mispositions and conducted interviews with workers and supervisors from all plant departments. The team also benchmarked their equipment status control processes with other utilities and reviewed related industry guidance to attempt to find successful strategies for reducing human errors. The report contained conclusions which included specific areas for improvement. Numerous recommendations were made for each conclusion which were diverse, original, and ambitious. Although a cominitted corrective action had not yet been assembled and prioritizeo at the close of the report period, the licensee was conddering a new plant-wide consolidated program to control operational configuration and had decided to periodically implement full procedure usage in weekly increment Conclusions The licensee was proactively and thoroughly addressing personnel errors which had previously caused operational equipment configuration control problems. A multi-disciplined team was established to review the problem. The team issued t comprehensive and self-critical report with numerous thorough corrective action recommendations. Effective short-term corrective actions such as full procedural usage and peer checking requirements were implemented ed appropriate long term actions were being considere Operator Training and Requalification 05.1 Revised Clearance Process Trainina Inspection Scope (71707. 92901)
The inspector attended training given to operators and maintenance personnel on the licensee's new ck rance and tagging processes. The training was a combination of classroom lecture and practical application conducted on September 24 and 25,199 Previous problems with implementation of the licensee clearance tagging process had
_
'
l l
l 3 I been identified as Violation 50-302/98-01-01, Closure of Electrical Linkages While Under a Red Tag Clearance, implementation of a new process and the associated training were licensee corrective actions for that proble Observations and Findinas
The licensee replaced the previous tagging process with two new procedures, one for Operations Danger Tagouts and one for Personal Danger Tags, Caution Tags and Test Tags. The new procesces were developed using industry benchmarks and resulted in a complete change in the philosophy and mechanics for processing clearances and tagging requests. The licensee appropriately determined that this necessitated detailed training for all usurs. The inspector's review focused on the scope and adequay of the training provided to the users of the process. The inspector did not evaluate the adequacy of the new process or the licensee's implementation pla The inspector attended the last of several scheduled training sessions. The classroom lecture portion of the training was thorough and supported by detailed training materials provided to each student. The inspector compared the materials to the revised procedures and found them closely linked. The inspector observed that a member from the dedicated licensee team that created the new process was not present at this training session. The inspector noted that this reduced the efficiency of the training because the training instructor was unable to adequately address questions on the intent or philosophy of the new processes. Questions were captured for later follow-up with the trainees so this did not impact the final effectiveness of the training. The inspector also confirmed that other sessions of the training had included a reinvention team member. The inspector observed that the second day of training consisted of hands-on training specifically designed for each user group. Past performance problems and common errors were specifically addressed in the training. The inspector observed that the overall training was more detailed and thorough than training completed for a previous revision to the clearance process in 199 Conclusicns The training provided for a complete revision to the clearance and tagging processes was thorough and closely linked to the procedure requirements. Training included hands-on practical applications for different user levels, which was appropriate due to the entirely new process being implemente .2 Simulator Trainina and Examinations Inson' ion Scoce (71001)
The inspector observed the licensee s conduct of two training simulator scenarios and administration of iae annual simulator examinations to one crew of licensed operator The inspection served to assess the licensee's compliance and effectiveness in conducting operator requalification training in accordance with 10 CFR 55.59,
"Requalification."
__ _ _ _ - - - - - - - - _ - - - - ---
.
4 Observations and Findinas The inspector observed the licensed operator requalification simulator training for operating Crew E. The crew attended a four hour simulator training session each day of the training week. Each training session consisted of one integrated simulator scenario from the training bank followed by a two hour review session of operator specified equipment failures and transient events. The inspector found the training scenarios were of equivalent complexity and level of difficulty as the examination scenario Following the scenario, the instructor feedback to the operators regarding their actions was accurate, informative and constructiv At the end of the training week, the inspector observed the administration of two examination scenarios (SES-32 and SES-12) to the operating crew which met the NRC requirements for an annual simulator evaluation of the licensed operators. The inspector observed the facility evaluator debrief sessions and reviewed the evaluator documentation of the crew's performance. The post scenario meeting was well organized and conducted. The evaluators kept to an established agenda that focused their attention on the important aspects of the evaluation process and also controlled the amount of time expended to a minimum. The evaluators' comments and findings were appropriate and were similar to NRC observations. The inspector found that both scenarios were challenging and discriminating test tools that were appropriate for measuring the knowledge and skill of the operators . Conclusion Simulator training was effective and operator performance during this training was goo The inspector also determined that the conduct and performance of the sk 'ilator examinations was satisfactory. The facility evaluators were thorough in noting individual operator performe.nce discrepancies and the scenarios observed were judged to be good evaluation tools. Documentation of individual performance results was satisfactory. The inspectc voncluded that this portion of the licensed operator requalification program met the requirements of 10 CFR 55.5 .3 Remedial Trainina and Testina Inspection Scope (71001)
The inspector reviewed the licensee's licensed operator requalification training records and associated procedures to ensure that an appropriate remedial training program was developed, implemented, maintained and documi 'ted as required by 10 CFR 55.59 and the licensee's procedure Observations and Findinas The inspector reviewed attendance records for training administered in cycle 2 of 1998 (96-2) and weekly quiz results for all the requalification training sessions conducted in 1998. For cycle 98-2, the inspector identified that 38 licensed operatorr. were scheduled to receive eight classroom lectures. The inspector found that only two operators missed
.
one lecture each during the cycle for an excellent overall attendance rate of 99.3% The l inspector also noted that four licensed operators had failed one or more weekly written 1 requalification tests during 1998. The inspector reviewed each remedial training i package and evaluated licensee compliance with Training Department Proceaure (TDP) '
203, " Licensed Operator Requalification Training Program," for operator failure of a requalification test. The inspector found that each operator was temporarily removed i
from shift as required by TDP-203, section 5.2.1.6 until he was adequately remediate {
The inspector did not identify any problems with the remediation plans that were implemented nor with the final documentation which showed that the operators had satisfactorily completed their remedial trainin l l Conclusions The licensee lead conducted remedial training and evaluations as required by 10CFR 55.59. Operators that had failed requalification tests and quizzes were removed from l
'
shift until remediation was complet Quality Assurance in Operations l
07.1 Quality Assessment and Corrective M n System Activities (71707)
The inspector rcutinely reviewed the activities and results of the licensee's Nuclear '
Ouality Assessments (NOA) group. Section O7.1 of IR 50-302/98-08 previously documented that NOA was not specifically evaluating responses and corrective action plans to precursor cards (PC) identified by NOA. The inspector reviewed the licensee's response to this problem and verified that the corrective action program software was being revised to address this concern and allow NOA evaluation without impacting 1 schedule commitments of other groups. The inspector confirmed that NOA was '
planning to perform evaluations of all NOA-originated PCs and considered the actions appropriate in response to the original proble The inspector attended numerous Corrective Action Review Board (CARB) meetings in 1998. The inspector cbserved that CARB was consistently attenued by virtually all of the assigned senior managers. The use of alternates or absent members were extremely rare situations. The inspector also observed that CARB reviews of root cause determinations and corrective action plans consistently used high standards, were l constructively entical, and were highly detailed. Frequently, first-time presenters of l investigation results to CARB were unsuccessful in meeting the CARB's high standard The presenters were provided with detailed feedback to upgrade their performanc Subsequent presentations and investigations fulfilled the high CARB expectations. The
- inspector determined that the CARB was a strength of the licensee corrective action l syste .
The inspector also attended one Plant Review Committee (PRC) meeting on October 22,1998. The inspector observed that the PRC Chairman identified a discrepancy between the revision of an issue supplied for PRC member review and the revision used by the issue presenter. While resolvec with no impact, a discussion ensued as to the finality of the issues supplied for PRC review. The inspector noted that
'
.
the PRC chairman expressed appropriate concern that material suppl:ed to the PRC needed to be fu!'y developed to support a valid PRC approval. The inspector concluded the PRC chairman was upholding high standards for PRC review and approva II. Maintenance M1 Conduct of Maintenance M1.1 General Comments (61726. 62707)
The inspectors observed all or portions of the following surveillance activities and some minor troubleshooting efforts in response to testing problems:
- SP-108 Reactor Trip Module and Control Rod Drive Trip Functional Test
- SP-358A Engineered Safeguards (ES) Monthly Actuation Logic Functional Test #1 A relay failure occurred approximately twenty ininutes after the satisfactory performance of SP-358A. The component that failed was determined to be an interposing relay in ES channel 2 that actuated blocks 4 and 6 of the emergency diesel generator block loading circuitry. This failure was not an Agastat relay failure. Failure of Agastat relays is addressed in Section E1.3 of this report.' This relay, which had been replaced earlier this year, wcs again repfaced and successfully tested. The licensee attributed this problem to an early in life electronic component failure. The inspectors concluded that the licensee had appropriately evaluated this relay failure and was tracking all failures for specific relay type performance. No other concerns or problems were noted during the performance of SP-358 . Enaineerina E1 Conduct of Engineering E Enaineerina Recongoility Evaluations and Licensee Amendment Reauests Inspection Scood?7551. 92903)
The inspector reviewed the results of severM sicense amendment requests and reportability evaluations to ensure they eaequately resolved outstanding long term issues and dispositioned problems from open inspection item Observations and Findinas The licensee submitted License Amendment Request (LAR) 229 on October 16,1998 to resolve an issue with the normai position of the decay heat system valves (DHV) 34 and 35. These valves are the suction valves from the Borated Water Storage Tank (BWST)
to the decay heat pumps and had been reconfigured in 1985 to be normally positioned
. -.- - -. .-- .- . _ - - - - - . - - - - - - - -
-
.
7 l closed. The repositioning was the subject of Violation 50-302/97-14-13. The licensee subsequently submitted a LAR because the new normal valve position could represent
'
an Unreviewed Safety Question (USO). The valves were evaluated as operable as closed in the short term under Deficiency Report (DR) 97 7755, using the guidance in NRC Generic Letter 91-18. The licensee's LAR proposed to perform monthly pressure checks as an improved Technical Specification (ITS) surveillance requirement to ensure the suction piping remained full of fluid and free of voids. This was to address a concern for water hammer and operability of the system with the valves close However, the inspector identified that the pressure checks were not addressed in DR j 97-7755 as a specific interim compensatory action and thus were not being routinely implemented by the licensee at the time of the inspection. The inspector subsequently l determined that the licensee had identified the need to revise the DR at their final l
'
!
License Amendment Review Board (LARB) but informally assigned the action to the cognizant engineer. This action had not been completed at the end of the report period l because the engineer was unable to report to work for an extended time due to an l injury. Since the interim action was not formally tracked, it was not being implemente l The licensee initiated a PC to address corrective action for the failure to track LARB !
action items. No violation of regulatory requirements occurred. The licensee had
'
verified the subject pressures at the time of the LARB and was developing a routine
- surveillance procedure for long-term measures.
!
- Violation 50-302/97-12-08 discussed a problem with incomplete qualification records l and post-accident time duration requirements for the rnake-up system pumps (MUP) to l verify that they were capable of fulfilling their emergency functions. Short-term !
l operability of the MUP was dispositioned in DR 9'8-0041. On October 7, after reviewing the results of a vendor review for MUP qualification, the licensee identified that )
guidance would be needed to restrict normal operation time of each MUP to limit 1
< mechanical seal wear, to implement higher lim 4s on MUP gear drive cooling water flow,
! and to ensure MUP flow was throttled to a prescribed flowrate within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> of an l event. These restrictions were needed to ensure the MUP capability to perform its l function for up to 2 months after an event. The inspector verified the restrictions were implemented and reviewed the licensee's detailed operability and reportability
- evaluation. The inspector did not identify any notable discrepancies with the licensee's conclusion that the issue was not reportable and that the MUPs were operable and had been operable in the past.
l The inspector reviewed the results of a Low Pressure injection System Study submitted I by the licensee on October 22,1998. The stady was in response to concerns identified in Unresolved item (URI) 50-302/97-12-09 and URI 50-302/98-02-08 regarding position and throttling of decay heat system (DH) outlet isolation valves DHV-5 and '6, and control of DH crossover line operation. The licensee committed to address the problems by modifying the DH system to add new control valves in their next refueling
) outage. The inspector did not identify any problems requiring immediate action in the study letter.
!
l
4
-
l
-
.
l
The inspector also reviewed the licensee response to ongoing technical investigations ,
of once-through steam generator (OTSG) tube end anomalies discovered in inspections !
done in July 1997. The inspector did not identify any problems with the results of the i investigation relative to new Technical Specification requirements issued in a recent l
license amendment. The inspector concluded the issue was receiving appropriate ]
licenses and vendor attentio Conclusions Tha inspector concluded the licensee was adequately pursuing resolution of open long- l term design and inspection open items. A minor deficiency was identified associated j with tracking of corrective actions initiated at License Amendments Review Board j l
E1.2 Interim Desian Review Board for New Diesel-Driven Erneraency Feed Pump ! Inspection Scooe (37551)
The inspector attended an interim design review board (DRB) conducted on October 5, 1998, for a major modification to add a new diesel-driven emergency feedwater pump (EFP) and building. The inspector reviewed resolution of open items from the earlier ,
conceptual DRB and tracking of concerns raised at the interim DR l I Observations and Findinas j i
The inspector observed that the DRB was broadly attended by all major licensee departments, with several groups represented by more than one attendee. The l
!
inspector verified the required attendees were present to fulfill the DRB quorum requ' cements in licensee design change procedures. The format of the DRB consisted li of a presentation on the current status of the project design by the contractor and .
licensee liaisons performing the engineering work. The contractor also specifically i addressed each open item from the conceptual DRB. The licensee attendees directed !
detailed and varied questions to the presenters that exhibited a high degree of ;
skepticism. The inspector noted that an atmosphere supporting open questioning was encouraged and the broad attendance gave a good multi-discipline review of the projec !
'
Previous problems with other projects were raised to ensure they were addressed, even though not specifically required to be part of the EFP design basis. The licensee i attendees also consistently requested the basis for design limits supplied by the ;
contractor. Specific consequences if these limits were exceeded were requested to be clearly defined in the final modification paperwork to support future operability determination for unexpected circumstance The inspector verified that the concerns identified during the DRB were clearly 1 documented and tracked to completion via 37 specific action items assigned in the DRB minutes. The inspector did not identify any concerns that were not addressed by the license i
!
!
. _ . . m . _ . _ _ . _ _ _ __ ._ _ _ _ ..._ ___ _ _
-
.
9 , Conclusions The inspector concluded the DRB was widely attended and all groups received an opportunity to identify their concerns and needs for the diesel-driven emergency feed pump modification. Questioning identified numerous valid concerns, addressed lessons learned from previous major projects, and was reflective of superior performance standard E1.3 Enaineered Safeauards System (ES) Rehv Failures (37551. 71707)
"
Over the past 30 months Crystal River Unit 3 (CR-3) has experienced twelve Agastat DSC model electronic time delay relay failures, with three occurring in the last two months. These relays were installed in 1991 to alleviate concerns over electromechanical time delay relay accuracy. CR-3 has 33 of these relays installed in the emergency diesel generator block loading sequencer portion of the ES syste Because of the recent increase in the number and trend of failures, the licensee has taken an aggressive approach to understand the potential failure mechanisms. The
"
licensee completed an operability impact and extent of condition review and determined
the failures were specific to the Agastat relays in the ES system and did not affect operability of the ES system. The inspectors reviewed this determination in detail and concluded the licensee had thoroughly and appropriately addressed all operability concerns. The ongoing investigation into the relay failure mechanism requires vendar support for additional review. The licensee has not yet determined if the issue is
, reportable under 10 CFR Part 21. The inspectors concluded the licensee was appropriately pursuing the issue with the involved vendors.
i E8 Miscellaneous Engineering issues (92903)
E (Closed) LER 50-302/97-42-00 and 01: Inadequate Engineering Evaluation Results in
Loss of Diverse Reactor Coolant System Leak Detection Capability. This LER delineated the inability of the gaseous containment radiation monitor to detect a one
,
gallon per minute (gpm) reactor coolant system leak within one hour, rendering the
. gaseous channelinoperable. The licensee also discovered their particulate containment
radiation monitor was inoperable because it was configured for iodine monitoring. This combination did not meet ITS 3.4.14 which required two of three leakage detection monitors to be operable. The inspector verified the licensee has maintained the gaseous channel in an administratively inoperable status and has been relying on the containment sump monitor and the reconfigured and operable particulate containment radiation monitor to comply with the ITS As committed in the LER, on September 30, 1998, the licensee submitted License Amendment Request (LAR) 238 to the NRC to revise the license basis for the gaseous detector one hour detection requirement at described in the ITS 3.4.14 Bases. The licensee determined the gaseous channel culd conservatively detect a Reactor Coolant System (RCS) one gpm leak in 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> and that changing the license basis was an unresolved safety question. The inspector reviewed the LAR and determined it was a complete description of the problem and fulfilled the licensee LER commitments to address the problem. This inspection open item will now be tracked as a license action and no further inspection activity is planne Although this item was a noncompliance with regulatory requirements, for the reasons
-.
.
discussed in inspection Report 50-302/97-21, the licensee met the criteria for enforcement discretion per Section Vll.B.2 of the NRC Enforcement Policy as described in NUREG-1600. Consequently this item is closed and is identified as a further example of Non-Cited Violation NCV 50-302/97 21-01, Examples of Noncompliances in Design Control,50.59 Evaluations, Procedure Adequacy, Reportability, and Corrective Actions That Are Subject to Enforcement Discretio IV. Plant Support P1 Conduct of EP Activities P1.1 Annual Emeraency Plan Drill (71750)
The inspectors participated in the licensee's annual emergency plan (EP) drill conducted on October 14,1998, in the Training Center Simulator, the Technical Support Center (TSC), and the Emergency Operations Facility (EOF). The inspectors observed that the drill scenario was challenging and fully exercised the licensee emergency response capability. Specific observations are discussed in Inspection Report 50-302/98-1 FS Fire Protection Staff Training and Qualification F5.1 Routine Fire Briaade Drill (71750)
The inspectors observed the conduct of a routine fire brigade drill on October 19,1998, by two members of the licensee training staff. The drill was administered to over 10 members of the fire brigade as an annual drill requirement. The inspector noted expectations for equipment status of responders had to be re-emphasized because brigade members arrived in various stages of dress and equipment readiness. The inspectors observed some minor technique errors, but these were identified by the drill instructors. The inspectors also attended the post-drill critique. While the critique was not conducted in a formal manner, the inspectors noted that the licensee adequately addressed the drill deficiencie F8 Miscellaneous Fire Protection Activities F8.1 Actions on Previous inspection Findinas (64704,92904)
r (Closed) inspection Follow-up Item (IFI) 50-302/97-11-10: Post Restart Fire Protection
'
Inspection to Validate Completion of Fire Protection Enhancement Items. This item concerned 12 fire protection post restart commitment items identified during NRC
'
inspections conducted in August and December 1997. These items were previously documented in Section F8.4 of NRC Integrated Inspection Report No. 50-302/97-1 The post restart commitment items were related to the update and enhancement of the Fire Protection Program, Appendix R documentation and the Thermo-Lag Resolution Program which the licensee scheduled to complete af ter the unit was restarted on February 10,199 '
.
The inspector reviewed FPC's letter to the NRC dated April 10,1998, " Notification of Revised Schedules for C ompletion of Appendix R Work identified in NRC Inspection Report No. 50-302/97-10, NRC Inspection Report No. 50-302/96-15, and Revision of Thermo-Lag Resolution Schedules," NRC letters to FPC dated April 23,1998," Consent to Confirmatory Order Modifying License," and May 21,1998, " Confirmatory Order Modifying License." These letters documented the licensee's schedule and NRC's Order for completion of actions committed to address the post restart commitment items and the Thermo-Lag Resolution Progra The inspector verified that the Ucensee issued a discrepancy report (Precursor Card) on each of these items and corrective action was identified for each item. The evaluations for these corrective actions had been completed and the actions required to resolve each issue had been identified. The in.spector reviewed the status of each of the licensee's identified post restart commitment items, reviewed the PC issued to track i corrective actions for each item, and interviewed the responsible licensee fire protection engineers overseeing the Fire Protection / Appendix R Program. The inspector concluded that the resolution of these issues was either complete or in progress and l scheduled for completion in accordance with committed completion dates. For those post restart items not completed, the licensee's tracking program was considered acceptable to assure that the corrective actions would be completed. The licensee's i corrective action system remains adequate and ap,c.opriately documented the originally l identified post restart items in IFl 50-302/97-11-10. This item is close !
F8.2 (Closed) IFl 50-302/97-18-01: Evaluation of Fire Barrier Penetration Seal Enhancement
'
Program. The issue related to the lack of available documentation to verify that fire barrier penetration seals were installed in accordance with design specifications bounded by configurations that had satisfactorily passed 3-hour fire resistance testin The inspector reviewed FPC's letter to the NRC dated April 10,1998, " Notification of Revised Schedules for Completion of Appendix R Work identified in NRC Integrated inspection Report No. 50-302/97-18, NRC Integrated inspection Report No. 50-302/
96-15, and Revision of Thermo-Lag Resolution Schedules," that described the licensee's Penebation Seal Resolution Program (Commitment ID No. 3F0498-22-10).
This program consisted of a three-phase project to: (l) verify the penetration seals are bounded by tested configurations / engineering analysis; (ll) perform a design verification walkdown of penetration seals; and, (Ill) finalize engineering evaluation documentation for resolution of penetration seals not bounded by a tested configuratio The inspector reviewed the scope of implementation for the Penetration Seal Resolution Program, and verified that the licensee's penetration seal design and installation parameters (to be verified during licensee walkdowns and documented in the facility penetration seal computer database) satisfied the guidance described in Sections and 3.2 of GL 86-10. The inspector concluded that the scope of the Penetration Seal Resolution Program was sufficiently documented in the licensee tracking program to assure that the corrective actions identified in IFl 50-302/97-18-01 would be complete This item is close . . _ . _ _ _ _ _ .. . . _ _ _ _
.
V. Manaaement Meetinas X1 Exit Meeting Summary The inspection scope and findings were summarized on October 26,1998. Proprietary ,
information is not contained in this report. Dissenting comments were not received from the license PARTIAL LIST OF PERSONS CONTACTED Licensees S. Bernhoft, Manager, Nuclear Licensing J. Cowan, Vice President, Nuclear Operations R. Davis, Assistant Plant Director, Operations and Chemistry R. Grazio, Director, Nuclear Regulatory Affairs G. Halnon, Director, Nuclear Quality Programs J. Holden, Director, Site Nuclear Operations M. Marano, Director, Nuclear Site & Business Support C.' Pardee, Director, Nuclear Plant Operations W. Pike, Manager, Nuclear Regulatory Compliance M. Rencheck, Director, Nuclear Engineering & Projects M. Schiavoni, Assistant Plant Director, Maintenance R. Thurow, Acting Director, Nuclear Operations Training NRC C. Payne, Reactor Engineer, Region 11 (October 21 - 23,1998)
G. Wiseman, Reactor Inspector, Region 11 (September 28 - October 2,1998)
INSPECTION PROCEDURES USED IP 37551: Onsite Engineering IP 61726: Surveillance Observations IP 62707: Conduct of Maintenance IP 64704 Fire Protection Program IP 71001 Requalification Program IP 71707; Plant Operations IP 71750: Plant Support Activities IP 92901: Followup - Operations IP 92903: Followup - Engineering IP 92904 Followup - Plant Support
-
L .
l
ITEMS OPENED, CLOSED, AND DISCUSSED Opened Tvoe item Number Status Descriotion and Reference None l ' Closed
!
Iyng Itj@ Number Status Descriotion and Reference LER SD 302/97-42-00 Closed inadequate Engineering Evaluation Results in Loss an'.! 97-42-01 of Diverse RCS Leak Detection Capability.
i (Section E8.1)
IFl 50-302/97-11-10 Closed Post Restart Fire Protection inspection to Validate Completion of Fire Protection Enhancement items.
- (Section F8.1)
IFl 50-302/97-18-01 Closed Evaluation of Fire Barrier Penetration Seal Enhancement Programs. (Section F8.2)
'
Discussed
l Iygg -Item Number Status Description and Reference
VIO 50-302/97-14-13 Open - Failure to Take Adequate Corrective Actions to
! ldantify and Correct Design Weaknesses l Associated with Adequacy of Past 10 CFR 50.59 Review for Positioning of DHV-34 and DHV-35
,
During Normal Operation. (Section E1.1)
l VIO 50-302/97-12-08 Open incorrect HPl Pump Purchase Order. (Section E1.1)
URI 50-302/97-12-0 Open Failure to Normally Position LPI Injection Valves DHV 5 and DHV-6 Open. (Section E1.1)
URI 50-302/98-02-08 Open LPI Crossover Cooling Non-Single Failure Proo (Section E1.1)
i NCV 50-302/97-21-01 Closed Examples of Noncompliances in Design Control, 50.59 Evaluations, Procedure Adequacy, Reportability, and Corrective Actions That Are
,
Subject to Enforcement Discretion. (Section E8.1)
e
.
A