MONTHYEARML20153C5061998-09-21021 September 1998 SER Accepting Qualified Unit 1 Supervisor Initial & Continuing Training Program for Dresden Nuclear Power Station,Unit 1 ML20237A1341998-08-0707 August 1998 Safety Evaluation Supporting Amend 163 to License DPR-25 ML20203K5201998-02-25025 February 1998 Safety Evaluation Supporting Amends 165 & 160 to Licenses DPR-19 & DPR-25,respectively ML20203H2441998-02-25025 February 1998 Safety Evaluation Supporting Amends 166 & 161 to Licenses DPR-19 & DPR-25,respectively ML20202E2971998-01-0505 January 1998 Safety Evaluation Supporting Amends 164,159,179 & 177 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20216J8861997-09-10010 September 1997 Safety Evaluation Supporting Amends 162 & 157 to Licenses DPR-19 & DPR-25,respectively ML20210Q4461997-08-21021 August 1997 SE Supporting Amends 161 & 156 to Licenses DPR-19 & DPR-25, Respectively ML20197B9171997-07-23023 July 1997 Safety Evaluation Re Concrete Expansion Anchor Safety Factors for High Energy Line Break Restraints ML20141E1681997-05-16016 May 1997 Safety Evaluation Supporting Amends 159 & 154 to Licenses DPR-19 & DPR-25,respectively ML20140E9741997-04-30030 April 1997 Safety Evaluation Supporting Amends 157 & 152 to Licenses DPR-19 & DPR-25,respectively ML20138D1791997-04-25025 April 1997 Safety Evaluation Supporting Amends 158 & 153 to Licenses DPR-19 & DPR-25,respectively ML20137R6431997-04-10010 April 1997 Safety Evaluation Supporting Amends 156 & 151 to Licenses DPR-19 & DPR-25,respectively ML20136G7731997-03-14014 March 1997 Safety Evaluation Approving Amends 155,150,174 & 170 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20135E1551997-02-28028 February 1997 Safety Evaluation Supporting Amends 153,148,172 & 168 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20134H7601997-02-0707 February 1997 Safety Evaluation Approving Rev 65c of Ceco QA TR CE-1-A ML20112E3921996-05-31031 May 1996 Safety Evaluation Supporting Amend 144 to License DPR-25 ML20092M5091995-09-21021 September 1995 Safety Evaluation Supporting Amends 140,134,162 & 158 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20086C1941995-06-23023 June 1995 Safety Evaluation Supporting Amends 136,130,157 & 153 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20085L6961995-06-14014 June 1995 Safety Evaluation Supporting Amends 135,129,156 & 152 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20085H0301995-06-13013 June 1995 Safety Evaluation Supporting Amends 134,128,155 & 151 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20085K3391995-06-0808 June 1995 Safety Evaluation Supporting Amends 133,127,154 & 150 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20078S8681995-02-22022 February 1995 Safety Evaluation Supporting Amends 132 & 126 to Licenses DPR-19 & DPR-25,respectively ML20078S8301995-02-16016 February 1995 Safety Evaluation Supporting Amends 131,125,152 & 148 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20071G1671994-07-0606 July 1994 Safety Evaluation Supporting Amends 128,122,148 & 144 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20029C9771994-04-25025 April 1994 SE Concluding That Revised EAL Consistent W/Guidance in NUMARC/NESP-007 & Therefore Meet Requirements of 10CFR50.47(b)(4) & App E to 10CFR50 ML20065J4511994-04-0505 April 1994 Safety Evaluation Supporting Amends 126 & 120 to Licenses DPR-19 & DPR-25,respectively ML20059C5481993-12-28028 December 1993 Safety Evaluation Supporting Amends 124 & 118 to Licenses DPR-19 & DPR-25,respectively ML20034G9441993-03-0303 March 1993 Safety Evaluation Supporting Amend 123 to License DPR-19 ML20128C2961992-11-23023 November 1992 Safety Evaluation Supporting Amend 121 to License DPR-19 ML20116A8901992-10-19019 October 1992 Safety Evaluation Supporting Amends 119,115,138 & 134 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20105C7421992-09-11011 September 1992 Safety Evaluation Granting Licensee 920228 Request for Relief Concerning Inservice Testing Program for Facility ML20105A7461992-09-11011 September 1992 Safety Evaluation Supporting Amends 118 & 114 to Licenses DPR-19 & DPR-25,respectively ML20113H6381992-07-24024 July 1992 Safety Evaluation Supporting Amend 117 to License DPR-19 ML20114A5691992-07-24024 July 1992 Safety Evaluation Supporting Amends 113,116,131,& 135 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30 ML20077K9611991-08-0505 August 1991 Safety Evaluation Supporting Amend 110 to License DPR-25 ML20063P9621990-08-0909 August 1990 Safety Evaluation Supporting Amends 112 & 108 to Licenses DPR-19 & DPR-25,respectively ML20246C8561989-06-30030 June 1989 Safety Evaluation Supporting Amends 106 & 101 to Licenses DPR-19 & DPR-25,respectively ML20246H0101989-04-26026 April 1989 Safety Evaluation Supporting Amends 117,113,105 & 100 to Licenses DPR-29,DPR-30,DPR-19 & DPR-25,respectively ML20205L2051988-10-26026 October 1988 Safety Evaluation Supporting Amends 101 & 97 to Licenses DPR-19 & DPR-25,respectively ML20154B8841988-09-0909 September 1988 Safety Evaluation Accepting Response to Generic Ltr 88-05, Boric Acid Corrosion of Carbon Steel Reactor Pressure Boundary Components in PWR Plants ML20153D3181988-08-24024 August 1988 Safety Evaluation Supporting Amends 100 & 96 to Licenses DPR-19 & DPR-25,respectively ML20207B7091988-07-21021 July 1988 SER Accepting one-time Exemption from 2-yr Type B & Type C Test Interval Requirements as Prescribed in App J,Until 880326,per Util Request ML20150D6151988-06-20020 June 1988 Safety Evaluation Supporting Amend 94 to License DPR-25 ML20147A7431988-02-19019 February 1988 Safety Evaluation Supporting Amends 98 & 93 to Licenses DPR-19 & DPR-25,respectively ML20235W8321987-10-0909 October 1987 Safety Evaluation Supporting Amends 96 & 91 to Licenses DPR-19 & DPR-25,respectively ML20213G5011986-11-10010 November 1986 Safety Evaluation Supporting Amends 94 & 90 to Licenses DPR-19 & DPR-25,respectively ML20209B9291986-09-0202 September 1986 Safety Evaluation Supporting Amend 89 to License DPR-25 ML20214K5491986-08-13013 August 1986 Safety Evaluation Supporting Amends 93 & 88 to Licenses DPR-19 & DPR-25,respectively ML20206M6761986-08-13013 August 1986 Safety Evaluation Accepting Util 840410 Request to Acquire & Operate Mobile Low Level Radwaste Vol Reduction Sys Incinerator ML20195C8101986-05-27027 May 1986 Safety Evaluation Supporting Amend 86 to License DPR-25 1998-09-21
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20249C8491999-09-30030 September 1999 1999 Third Quarter Rept of Completed Changes,Tests & Experiments Evaluated,Per 10CFR50.59(b)(2), for Dresden Nuclear Power Station. with ML20217A1691999-09-22022 September 1999 Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers ML20210R6081999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Dresden Nuclear Power,Units 1,2 & 3.With ML20209E1291999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Dresden Nuclear Power Station,Units 1,2 & 3.With ML20209J3481999-06-30030 June 1999 1999 Second Quarter Rept of Completed Changes,Tests & Experiments, Per 10CFR50.59.With ML20210D3071999-06-30030 June 1999 Corrected Page 8 to MOR for June 1999 for DNPS Unit 3 ML20195G6381999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Dresden Nuclear Power Station,Units 1,2 & 3.With ML20195B2591999-05-19019 May 1999 Rev 66a to CE-1-A,consisting of Proposed Changes to QAP for Dnps,Qcs,Znps,Lcs,Byron & Braidwood Stations ML20206N2821999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Dresden Nuclear Power Station,Units 1,2 & 3.With ML20206B1901999-03-31031 March 1999 First Quarter Rept of Completed Changes,Tests & Experiments Per 10CFR50.59 for Dresden Nuclear Power Station. with ML20205N7491999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Dresden Nuclear Power Station,Units 1,2 & 3.With ML20207M6921999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Dresden Nuclear Power Station,Units 1,2 & 3.With ML20207E9311999-02-26026 February 1999 Part 21 Rept Re Sprague Model TE1302 Aluminum Electrolytic Capacitors with Date Code of 9322H.Caused by Aluminum Electrolytic Capacitors.Affected Capacitors Replaced ML20199M0891999-01-22022 January 1999 Part 21 Rept Re Failure of Square Root Converters.Caused by Failed Aluminum Electrolytic Capacitory Spargue Electric Co (Model Number TE1302 with Mfg Date Code 9322H).Sent Square Root Converters Back to Mfg,Barker Microfarads,Inc ML20199D3261998-12-31031 December 1998 10CFR50.59 SER for 1998-04 Quarter, of Changes,Tests & Experiments.With ML20205M7061998-12-31031 December 1998 Unicom Corp 1998 Summary Annual Rept. with ML20199C8951998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Dnps,Units 1,2 & 3 ML20197G8591998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Dresden Nuclear Power Station.With ML20196A4191998-11-19019 November 1998 Safety Evaluation Accepting QA TR CE-1-A,Rev 66 Re Changes in Independent & Onsite Review Organization by Creating NSRB ML20196J0061998-11-19019 November 1998 Rev 66 to Topical Rept CE-1-A, QA Program ML20195D2861998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Dresden Nuclear Power Station.With ML20154N4131998-09-30030 September 1998 1998 Third Quarter 10CFR50.59 Rept, for Dresden Nuclear Power Station of Completed Changes,Tests & Experiments ML20154L3681998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Dresden Nuclear Power Station,Units 1,2 & 3.With ML20153C5061998-09-21021 September 1998 SER Accepting Qualified Unit 1 Supervisor Initial & Continuing Training Program for Dresden Nuclear Power Station,Unit 1 ML20151Y2711998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Dresden Nuclear Power Station,Units 1,2 & 3.With ML20237E2331998-08-21021 August 1998 Revised Pages of Section 20 of Rev 66 to CE-1-A, QA Topical Rept ML20237A1341998-08-0707 August 1998 Safety Evaluation Supporting Amend 163 to License DPR-25 ML20237A7161998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Dresden Nuclear Power Station,Units 1,2 & 3 ML20236M6041998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Dresden Nuclear Power Station,Units 1,2 & 3 ML20236T8391998-06-30030 June 1998 Rev 1 to EMF-96-141, Dresden Unit 3 Cycle 15 Reload Analysis Rept ML20236T8331998-06-30030 June 1998 COLR for Dresden Station Unit 3,Cycle 15 ML20236F8131998-06-30030 June 1998 Rev 0 to Defueled SAR Dresden Nuclear Power Station Unit 1 Commonwealth Edison Co ML20236Q5851998-06-30030 June 1998 1998 Second Quarter 10CFR50.59 Rept, for Dresden Nuclear Power Station of Completed Changes,Tests & Experiments ML20248M3021998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Dresden Nuclear Power Station,Units 1,2 & 3 ML20248F3531998-05-21021 May 1998 Part 21 Rept Re Electronic Equipment Repaired or Reworked by Integrated Resources,Inc from Approx 930101-980501.Caused by 1 Capacitor in Each Unit Being Installed W/Reverse Polarity. Policy of Second Checking All Capacitors Is Being Adopted ML20247F3391998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Dresden Nuclear Power Station,Units 1,2 & 3 ML20217D0281998-04-22022 April 1998 Part 21 Rept Re Additive Constants Used in MCPR Determination for Siemens ATRIUM-9B Fuel by Core Monitoring Sys Were Found to Be non-conservative.SPC Personnel Notified All Customers w/ATRIUM-9B Lead Test Assemblies ML20216C9651998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Dresden Nuclear Power Station,Units 1,2 & 3 ML20216D4411998-03-31031 March 1998 First Quarter Rept of Completed Changes,Tests & Experiments for 10CFR5059 ML20216E2531998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Dresden Nuclear Power Station ML20203K5201998-02-25025 February 1998 Safety Evaluation Supporting Amends 165 & 160 to Licenses DPR-19 & DPR-25,respectively ML20203H2441998-02-25025 February 1998 Safety Evaluation Supporting Amends 166 & 161 to Licenses DPR-19 & DPR-25,respectively ML20202F7831998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Dresden Nuclear Power Station ML20199K1651998-01-23023 January 1998 Rev 65h to Topical Rept CE-1-A, Comm Ed QA Tr ML20202E2971998-01-0505 January 1998 Safety Evaluation Supporting Amends 164,159,179 & 177 to Licenses DPR-19,DPR-25,DPR-29 & DPR-30,respectively ML20198P7021997-12-31031 December 1997 Fourth Quarter Rept of Completed Changes,Tests & Experiments Per 10CFR50.59 ML20216D3611997-12-31031 December 1997 Unicom Corp 1997 Summary Annual Rept ML20198P5321997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Dresden Nuclear Power Station ML20203F8781997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Dresden Nuclear Power Station ML20199B0701997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Dresden Nuclear Power Station 1999-09-30
[Table view] |
Text
c ua o
' UNITED STATES g
[
g NUCLEAR REGULATORY COMMISSION rj WASHINGTON, D. C. 20555
%...../
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION SUPPORTING AMENDMENT NO. 98 TO PROVISIONAL OPERATING LICENSE NO. DPR-19 AND AMENDMENT NO. 93 TO FACILITY OPERATING LICENSE N0. DPR-25 COMMONWEALTH EDIS0N COMPANY DRESDEN NUCLEAR POWER STATI6N, UNIT NOS. 2 AND 3 DOCKET NOS. 50-237/249
1.0 INTRODUCTION
By letter dated August 26, 1986 the Commonwealth Edison Company (CECO or the licensee) subnitted a request to amend Provisional Operation License No.DPR-19, which authorized operations of Dresden Nuclear Powers Unit No.
2, and Facility Operating License No.DPR-25, which authorizes operation of Dresden Nuclear Power Station Unit No. 3.
The proposed amendments would delete certain diesel generator testing requirements to eliminate unnecessary and excessive testing.
In addition, a one and one-half hour maintenance period would be allowed without requiring low pressure core cooling surveillance.
By letter dated July 2,1984 the staff issued Generic Letter 84-15 to all licensees of operating reactors, applicants for operating licenses and holders of construction permits. The subject of Generic Letter 84-15 is "Proposed Staff Actions To Improve And Maintain Diesel Generator Reliability." The main thrust of the GL 84-15 is toward reducing the number of cold fast starts of diesel generators and of lowering the number of required diesel generator starts in general to reduce the potential degrading effects of too frequent testing. The reliability of Emergency Diesel Generators (EDG) is one of the main factors affecting the risk from station blackout and thus the improvement of EDG reliability can reduce the risk of core damage from station blackout events.
In addition to this, the letter addressed the testing of diesel generators as required in some eariter plants when emergency core cooling systems (ECCS) are declared inoperable. The staff was concerned with the number of unnecessary EDG tests for the earlier licensed operating plants f
which are required under their current Technical Specifications (TS) to
[
perform frequent testing for ECCS equipment out of service. No such TS requirements exist for the recently licensed plants.
In an effort to reduce excessive testing of EDGs in these earlier plants and amend their TS to reflect comparable testing with that of Standard Technical yc Specifications, Generic Letter 84-15 recomended that the surveillance requirements for testing EDGs, because of inoperability of emergency core cooling systems, be deleted from plant unique TS.
8803010323 800219 PDR ADOCK 05000237 P
PDR
?
l 2.0 EVALUATION By submittal dated August 26, 1986, CECO proposed changes to Dresden Technical Specification Surveillance Requirements 4.5.A.2, 4.5.A.4, 4.5.A.5 and 4.5.B.3 to eliminate the diesel generator testing when core spray, low pressure coolant injection pump, low pressure coolant injection subsystem and containment cooling subsystem are declared inoperable.
Failures experienced in the above mentioned systems will not affect the performance of diesel generators. Testing of the diesel generator under such circumstances is not warranted. The staff has reviewed the proposed change and finds this proposed change is in accordance with the Generic Letter 84-15, Standard Technical Specifications, and is in the interest of reducing the potential for diesel engine degradation due to frequent testing, and is, therefore, acceptable.
The licensee has proposed an addition to the Technical Specification 3.9.B.2.b which would allow a diesel engine to be taken out of service for a 1 1/2 hour period of preventative maintenance.
This period shall not be allowed unless two offsite lines are available and the alternate diesel generator has been proven operable. The addition of this specification will reduce the number of core spray, low pressure coolant injection and containment cooling service water surveillance which must be performed when a diesel engine is taken out of service for minor maintenance. This Technical Specification change was already approved on similar plants like Quad Cities. The staff has reviewed this proposed change and based on the review finds the change does not degrade the safety of the plant, is consistent with Generic Letter 84-15 and is, therefore, acceptable.
In addition to the changes discussed above, a paragraph on page 3/4 9-4 of the Unit 2 Technicc1 Specifications which included a one-time extension of the 2/3 diesel generator outage time was no longer pertinent and was removed. This is a purely administration action and is acceptable.
Also, for convenience, pages 3/4 9-5 and 3/4 9-6 for each unit have been reproduced to show relocation of paragraphs. No change to the content of the Technical Specifications is involved. During the review no change was found on page 3/4 5-4 of Unit 3, therefore, that page is not included-in this amendment.
3.0
SUMMARY
The licensee has proposed to delete from the Technical Specifications the requirements of testing diesel generators while emergency core cooling system is inoperable.
Based on our review we find that this is in accordance with the engineering rationality used in GL 84-15 and is, therefore, acceptable.
Based on our review we also find that the addition of a requirement in the I
Technical Specification which would allow a diesel engine to be taken out I
of service for a 1 1/2 hour period of preventative maintenance is, acceptable.
l
'l
4.0 ENVIRONMENTAL CONSIDERATION
These amendments involve changes to a requirement with respect to the installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20 and changes to the surveillance j
requirements. The staff has detennined that the amendments involve no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite and that there is no j
significant increase in individual or cumulative occupational radiation exposure. The Comission has previously issued a proposed finding that these amendments involve no significant hazards consideration and there has been no public coment on such finding. Accordingly, these amendments i
meet the eligibility criteria for categorical exclusion set forth in 10 CFR51.22(c)(9).
Pursuant to 10 CFR 51.22(b) no environmental impact statement nor environmental assessment need be prepared in connection with the issuance of these amendments.
5.0 CONCLUSION
The staff has concluded, based on the considerations discussed above, i
that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, and (2) such activities will be conducted in compliance with the Comission's regulations and the issuance of these amendments will not be inimical to the comon defense and security nor to the health and safety of the j
public.
Principal Contributor:
N. Trehan i
Dated: February 19, 1988
';