ML20140F837

From kanterella
Jump to navigation Jump to search
Insp Rept 50-440/97-201 on 970217-0327.Issues Identified Which Challenged Capability of Sys to Perform Complete Scope DBA Mitigation Actions.Major Areas Inspected:Hpcs & Eec Sys
ML20140F837
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 06/10/1997
From:
NRC (Affiliation Not Assigned)
To:
Shared Package
ML20140F796 List:
References
50-440-97-201, NUDOCS 9706130253
Download: ML20140F837 (83)


See also: IR 05000440/1997201

Text

. .

.<

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

i

Docket No.: 50-440

License No.: NPF-58

Report No.: 50-440/97-201

Licensee: Centerior Services Company

7

Facility: Perry Nuclear Power Plant, Unit 1

Location: P.O. Box 97, A200

Perry, Ohio 44081

Dates: February 17-March 27,1997

Inspectors: Morris Branch, Team Leader, Special Inspection

Branch

'

, Robert Hogenmiller, I&C Engineer *

Robert Najuch, Lead Contractor Engineer *

'

Dennis Vandeputte, Mechanical Engineer *

Arvind Varma, Electrical Engineer *

Maty Yeminy, Mechanical Engineer *

  • Contractors from Stone & Webster Engineering Corporation

Approved by: Donald P. Norkin, Section Chief

Special Inspection Branch

Division ofInspection and Support Programs

4

Oflice of Nuclear Reactor Regulation

,

4

9706130253 970610

PDR ADOCK 05000440

G PDR

- - . . . -- . . - . - - - _ _ . - . -- , - . . . _ . . - _ . - . .

. .

j Table of Contents

4

EXECUTIVE SUMMARY . . .

. . i

El.1 Inspection Scope and Methodoloey . .. .. . . . 1

I

El.2 High-Pressure Core Sprav . . .. . .. . 1

El.2.1 System Description and Safety Function 1

El.2.2 Mechanical . ... . . .2

El.2.3 Electrical . .. .. .. 12

El.2.4 Instmmentation and Controls . . .. . 15

El.2.5 System Interfaces . . . 19

El.2.6 System Walkdown .

. . 24

El.2.7 USAR Review .. . . . .26

El.3 Emereency Closed Cooline . . .. . . . . . 28

El.3.1 System Description and Safety Function . . 28 I

El.3.2 Mechanical . . . . . 30 l

El.3.3 Electrical . . .. . 38

El.3.4 Instrumentation and Controls .. . . . .38

El.3.5 System Interfaces ... . . 40

El.3.6 System Walkdown .42

. . . . .

l

El.3.7 USAR Review . . . . 44 ,

i

E1.4 Design Control . . . . 44

Appendix A List of Open Items . . . . . A- 1

l

Appendix B Exit Meeting Attendees .. . . B-1

{

.

Appendix C List of Documents Reviewed , C-1

l

!

Appendix D List of Acronyms . .. . . . D- 1

Attachment 1 Slides Used During Public Exit . . . Attachment 1-1

.

_ _ ___

'

. ,

EXECUTIVE SUMMARY

From February 17 through March 27,1997, the staff of the U.S. Nuclear Regulatory Commission

(NRC), Oflice of Nuclear Reactor Regulation (NRR), Special Inspection Branch, conducted a

design inspection at Perry Nuclear Power Plant, Unit 1 (PNPP-1). The inspection team consisted

of a team leader from NRR and five contractor engineers from Stone & Webster Engineering

Corporation (SWEC).

The purpose of the inspection was to evaluate the capability of the selected systems to perform

the safety functions required by their design bases, the adherence of the systems to their design

and licensing bases, and the consistency of the as-built configuration and system operations with

the updated safety analysis report (USAR). For the purpose of this inspection, the team selected

the high-pressure core spray (HPCS) and emergency closed cooling (ECC) systems, on the basis

of their importance in mitigating design-basis accidents (DBAs) at PNPP-1. In particular, the

inspection focused on the safety functions of these systems and their interfaces with other

systems.

For guidance in performing the inspection, the tearn followed the applicable engineering design

and configuration control portions ofInspection Procedure (IP) 93801, " Safety System

Functional Inspection"(SSFI). The team reviewed portions of the plant's Updated Safety

Analysis Report (USAR), design-basis documents, drawings, calculations, modification packages,

surveillance procedures, and other documents pertaining to the selected systems.

The team identified the following issues, some of which challenged the capability of the systems to

perform their complete scope of design basis accident mitigation actions. Where appropriate, the

licensee took immediate corrective or compensatory actions to ensure system operability.

The licensee changed the ECC surge tank sizing basis from a 7-day supply to a 30-minute

supply, with operator actions required outside the control room to initiate makeup from the

emergency service water (ESW) system. The team concluded that this change constitutes a

potential unreviewed safety question, as defined in Title 10, Section 50.59, of the Code of

FederalRegidations (10 CFR 50.59) since the probability of occurrence of a malfunction of

equipment important to safety was increased. As a result of this change, operators could

incur a calculated total radiological exposure of approximately 12 rem within the first 90

minutes following a DBA. Additionally, the safety evaluation that supported the change did

not adequately assess the potential for operator error, or surge tank overpressurization and

adjacent area flooding when makeup from the ESW system fills the tank water-solid.

-

The operation of the suppression pool cleanup (SPCU), essentially on a continuous basis, is

not consistent with the facility description presented in the USAR and is not supported by a

safety evaluation. Operation in this mode does not support the net positive suction head

(NPSH) evaluations specified by Regulatory Guide (RG) 1.1, as presented in the USAR.

This condition has existed since initial licensing of PNPP-1, as a result ofinsufficient

analysis and corrective actions in resolving design deficiencies concerning improper

i

- _

, .

connection of SPCU piping downstream of the HPCS suppression pool suction valve rather

than upstream. The HPCS/SPCU system interface design and an additional issue regarding

application of pipe crack criteria (rather than pipe break criteria) to nonsafety, non-seismic,

moderate-energy piping systems were referred to the NRC staff for further review.

-

The actual droop setting of the Division III emergency diesel generator (EDG) deviates

from the vendor's recommended setting and constitutes an undocumented modification.

The team was concerned with the treatment of droop bias with respect to Technical

Specification (TS) acceptance criteria and the efrect on end user mechanical equipment.

When droop is considered as a bias, HPCS pump surveillance test results do not meet design

flow requirements for all accident situations.

-

The HPCS and reactor core isolation cooling (RCIC) suction piping and the condensate

storage tank (CST) instrument lines installed between the CST and the concrete

containment dike are not adequately protected against external missiles, and the licensee's

protective provisions were not consistent with the USAR description. On the basis of this

team finding, the licensee determined that the HPCS and RCIC suctions from the CST were

inoperable, and they realigned the systems to the suppression pool. In addition, the licensee

instructed plant operators to maintain HPCS and RCIC suctions aligned to the suppression

pool until the issue could be resolved.

In addition, the team identified the following issues which indicated programmatic deficiencies:

-

The team identified deviations from licensing commitments regarding presem and past

testing / inspection and cleaning of the HPCS room cooler.

l

.

Inconsistencies exist in the plant's design and licensing bases, with regard to ECC surge i

tank makeup and monitoring; passive single failure definitions; and application of pipe crack 1

I

criteria (rather than pipe break criteria) to nonsafety, non-seismic, Category 1, moderate-

energy piping outside containment.

i

.

In several instances, the licensee had difliculty in retrieving design-basis information. This  ;

concern contributed to the licensee's inappropriate "use-as-is" disposition of plant hardware  !

problems concerning the lack of overfrequency protection for the HPCS pump and 1

inadequate protection of exposed equipment against the effects of tornado missiles.

  • The team identified weaknesses in the licensee's development and control of calculations, as

well as the review and approval processes. These included se!ection ofincorrect codes

prescribed by the American Society of Mechanical Engineers (ASME) for evaluation of the

HPCS overfrequency protection relay removal and ECCS heat exchanger tube wall

thickness. Other weaknesses included non-conservative system modeling regarding

overpressure protection, flooding analysis, and system performance associated with the ECC

surge tank; and non-conservative assumptions in the HPCS vortex and NPSH calculations .

Within the electrical area, the licensee did not adequately maintain design-related

ii

. _ . - . -. . _.

. .

calculations in accordance with Nuclear Engineering Instruction (NEI) 0341,

" Calculations." Moreover, in some cases, the calculations were inconsistent with the

USAR.

l

The team identified test control weaknesses. For example, analyses of test results for valve

leakage at the interface between the ECC and nuclear closed cooling (NCC) systems failed

to adjust measured leakage rates for predicted accident system pressures. In addition, when

the licensee used testing to verify calculation assumptions, feedback of test results to close

1

out calculation assumptions was not always timely. l

During the course of the inspection the licensee documented many of the issues in their corrective

action program. The number and nature of the items documented on potential issue forms (PIFs),

represented very good sensitivity regarding problem identification. I

l

i

iii

. - .

>

. .

III. Engineering

l

El CONDUCT OF ENGINEERING

1

El.1 Inspection Scope and Methodo:ory

The primary objectives of the design inspection at Perry Nuclear Power Plant, Unit 1 (PNPP-1),

were to evaluate the capability of the systems to perform their safety functions required by design

bases and to verify whether the licensee, Centerior Services Company, has maintained the plant in

compliance with its design and licensing bases. As the subject of this inspection, the staff of the

U.S. Nuclear Regulatory Commission, Office of Nuclear Regulatory Regulation (NRR), selected

)

the high-pressure core spray (HPCS) and emergency closed cooling (ECC) systems, because of

their importance in mitigating design-basis accidents (DBAs) at PNPP-1. In particular, this I

inspection focused on the safety functions of the selected systems and their interfaces with other

systems throughout the plant. For guidance in performing the inspection, the team fo!! owed the

applicable engineering design and configuration control portions ofInspection Procedure (IP)

93801, " Safety System Functional Inspection" (SSFI).

Appendix A iden'.ifies the open items and issues resulting from this inspection, while Appendix B

lists the individuals who attended the exit meeting on April 22,1997. Appendix C lists the

documents reviewed by the team, and Appendix D defines the various acronyms used in this

report

El.2 Ilieh-Pressure " ore Spray (IIPCS) System

El.2.1 System Description and Safety Function

The HPCS is an emergency core cooling system (ECCS) capable ofproviding coolant at either

high or low reactor pressure. The system is initiated in response to either low reactor water level

(level 2) or high drywell pressure. The HPCS system maintains the reactor vessel water level

above the top of the active fuel for small-break loss-of-coolant accidents (LOCAs). Cycling the

HPCS injection valve at high and low reactor water levels controls the reactor vessel level.

For larger breaks that result in reactor depressurization, the HPCS works in conjunction with

other ECCS equipment and provides spray cooling of the core. The system includes a motor-

driven centrifugal pump that takes suction from either the condensate storage tank (CST) or the

suppression pool. The suppression pool provides the water supply for continuous operation of

the system, and suction from the CST automatically transfers to the suppression pool when the

CST water supply is exhausted or when the suppression pool level is high.

1

_. . _ - _ - . _ . . . _ - _ . __ ._ _ - __

1

. .

The HPCS system also serves as a backup to the reactor core isolation cooling (RCIC) system in

the event that the reactor becomes isolated from the main condenser and feedwater flow is lost

during operation.

As designed, the suppression pool cleanup (SPCU) system interfaces directly with the HPCS,

taking suction from the HPCS suppression pool suction line between the containment isolation i

'

valve and the pump. Therefore, during SPCU system operation it is necessary to align the HPCS

system suction to the suppression pool (instead of the CST, as described in the Updated Safety

i

Analysis Report (USAR)).

The HPCS system operates using normal offsite auxiliary alternating current (AC) power or

,

4

power provided by its own Division III emergency diesel generator (EDG). This EDG is '

designed to achieve its rated speed within 13 seconds, and the HPCS system is designed to

achieve its rated flow within 27 seconds.

El.2.2 Mechanical

! El.2.2.1 Scope of Review

In evaluating the mechanical design of the HPCS system, the team reviewed the basic system

design as depicted in plant documents. Specifically, the team reviewed sections of the USAR,

technical specifications (TS), plant procedures, General Electric (GE) system specifications,

calculations, piping and instrumentation diagrams (P& ids), physical drawings, training manuals,

maintenance records, inservice inspection (ISI) records, and setpoint data packages. In addition,

the team assessed the capability of system equipment to perform its intended functions. The

j review also included a system walkdown, during which the team witnessed a system test in the

control room and conducted interviews with the system engineer, design engineers, and control

] room personnel.

El.2.2.2 Findines

!

a. HPCS Functions

PNPP uses a " Design-Basis Documentation Hierarchy" desk guide to identify sources of

information to define and maintain the current design consistent with the plant's design bases.

, This desk guide cautions the user to verify the accuracy of any information contained in plant-

,

related documents. As of this inspection, the licensee had not yet generated design-basis

documents (or the equivalent) for the PNPP systems.

.

l To facilitate the inspection process, the team requested that the licensee identify the functions of

the HPCS system. The licensee described the HPCS functional design bases through references

to multiple GE design specifications, the USAR, the process flow diagram, a station blackout

.

(SBO) technical assignment file, and HPCS design change packages (DCPs). Together, these

2

_ _ . _ _ . _ _ . _ _ ... _ _ _ _ __ _ _ _ . _ _ _ _ .. _ _ . _ _ - . _

'

. .

4

I

references identified a variety of HPCS functions, including core cooling to prevent fuel damage

4

for large- break LOCAs, core makeup water for small-break LOCAs, backup for RCIC, SBO

makeup water to the vessel, and support ofvarious transients and accidents (identified in Chapter

15 of the USAR) including anticipated transient without scram (ATWS).

b. CST Volume Design Basis

i

.

GE Design Specification 22A3131 AD, "High-Pressure Core Spray," Revision 6,

Requirement 4.3.1, states that each boiling-water reactor (BWR) unit must maintain a condensate

i water storage reserve of 150,000 gallons. The team requested that the licensee provide the design

basis for the GE-imposed 150,000 gallon requirement, since the basis was not apparent. In

i response, the licensee contacted GE, and GE indicated that the required volume reflected the

1

water inventory makeup required for RCIC to remove reactor decay heat during the first 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />

following reactor shutdown, assuming that the safety relief valves (SRVs) maintain reactor

i pressure. The HPCS system is classified as a backup system to RCIC; therefore, requirements

i applicable to RCIC also apply to HPCS. The CST is classified as a nonsafety-related source of

i water and, consequently, is not credited for accident mitigation.

i

~

c. NRC Bulletin 96-03, ECCS Suction Strainers

i

! On May 6,1996, the NRC issued Bulletin 96-03 to all operators of nuclear power plants.

! Specifically, this bulletin warned the operators of potential plugging of emergency core cooling

! suction strainers by debris. In the bulletin, the NRC staffidentified three options to resolve this

j issue, including installation of a large-capacity passive strainer, a self-cleaning strainer, or a

! backflush system.

1

4

In its response to the NRC Bulletin, PY-CEI/NRR-211IL, dated November 4,1996, Cleveland

{ Electric Illuminating (CEI) stated that some events could block the ECCS strainers at PNPP-1

i with insulation from the drywell. This blockage will result in an insuflicient net positive suction

l head (NPSH) for the ECCS pumps, leading to subsequent failure to meet the core cooling

requirements. To address this problem, CEI proposed to install a large passive strainer design

4

(Bulletin 96-03 option 1), which is a floor-mounted strainer that circles the suppression pool.

CEI intends to install the new strainer dpring the next refueling outage (fall 1997). The licensee's

corrective action for this issue appears to be appropriate, and implementation of the licensee's

corrective actions is being controlled through the bulletin commitments. .

p

j d. Review of HPCS System Vortex Formation While Aligned to the CST

! Calculation P11-12,"P11 - Level Setpoints in Condensate Storage Tank for E22 and E51

Instruments" dated March 12,1985, determined the CST low-level swapover se't point required to

i ensure that the HPCS system has adequate NPSH and that no vortex occurs before suction valve

i swapover to the suppression pool. The team reviewed this calculation and idendfied the

following concerns:

i.

-

3

. ,

.

The licensee based the calculation on a flow rate of 700 gpm for RCIC and 1550 gpm for

HPCS, as substantiated by P&ID D-302-012, " Condensate Transfer and Storage System."

The licensee combined the HPCS and RCIC flows since both would be taking a suction

from the CST through a common line. The team questioned the licensee's use of the 2250

gpm flow rate for calculating CST suction line vortex value since a higher flow rate would

be a worst case. Operiting data on the referenced drawing and in the GE Design

Specification 22A313) AS, Revision 3, specifies a maximum HPCS flow rate of 6110 gpm at

200 psi backpressure in the reactor vessel and 7800 gpm at mnout flow. The team also

cordinned that HPCS Process Diagram 4549 20-001, Revision 9A (USAR Figure 6.3.1),

" Accident, System Iriection at Rated Core Spray, Suction from CST," specified the same

high-flow requiremerts for HPCS.

.

Additionally, the CS T water level setpoints did not address continued drawdown of the CST

as the transfer from the CST to the suppression pool takes place. HPCS suction from the

CST continues as the suppression pool suction isolation valve first strokes open, and the

CST suction isolation valve then strokes closed.

On the basis of the teatr's concerns, the licensee issued Potential Issue Form (PIF) 97-0416. The

engineering evaluation on the PIF indicated that the licensee had previously evaluated the

adequacy of the swapover setpoint as part of the system-based instrumentation and control

inspection (SBICI)in 1995, and found it to be acceptable. In resolving the issue in 1995, the

licensee stated that the primary function of HPCS was to alleviate the consequences of a small line

break, when the reactor is at pressure and the required HPCS flow is 1550 gpm. For a large-

break LOCA during which the HPCS will deliver full flow, the licensee contended that

suppression pool swell caused by the LOCA will lead to a transfer of suction to the suppression

pool as a result of the suppression pool high-water level swapover setpoint. However, the

licensee could not identify design-basis documentation that would substantiate the assertion that

pool swell negated the need for the CST level to cause the suction swap during high-flow

conditions, as specified in the GE design documentation. The licensee further indicated that

startup tests, performed at a flow rate of 7200 gpm and a CST level 2 feet below the current

setpoint, verified that no vortex formed before swapover to the suppression pool.

The licensce revised the calculation using a HPCS flow rate of 6110 gpm; however, the team

questioned the revised calculation, since the licensee did not include RCIC flow. Ultimately, the

licensee revised the calculation to consider valve . stroke time and the worst-case pump runout

flow of 7200 gpm. To support the current setpoint, the licensee had to use a less conservative

methodology, which considers operation in the region where vortex formation is possible. In so

doing, the licensee found that air could enter the pipe and travel 380 feet inside the pipe, but the

air would not reach the pump before swapover to the suppression pool. The licensee did not

change the current setpoint level as a result of the revised analysis.

10 CFR Part 50, Appendix B, Criterion III states that the design control measures shall provide

for verifying or checking the adequacy of the design. The licensee's Operations Quality Assurance

4

. .

Program, USAR 17.2 commits to compliance with Regulatory Guides and Standuds as listed in

USAR Table 1.8-2. USAR Table 1.8-2 commits to following ANSI 45.2.11 - 1974 for Quality

Assurance Requirements For The Design of Nuclear Power Plants. Nuclear Engineering

Instruction NEI-0341 Revision 5 " Calculations" applies to all calculations to establish design

bases or to change design documents. Paragraph 6.2, Calculation Revisions states " Design

Engineer are to monitor calculations to determine if a revision is required e.g. receipt of

new/ revised design input, confirmation of assumption etc." Paragraph 6.3 Review and Approval

states " Verification / review and approval of calculation should precede use of the results for

design, but mus: be completed prior to the component, system, or structure being declared

operable."

The team concluded that the licensee's use of non-conservative flow rates and not considering the

impact of valve timing within the original calculation to resolve the issue in 1995 were

inappropriate. The licensee used nonconservative modeling of HPCS flow at 6110 gpm and did

not include RCIC flow in their initial response to the team's concern. The final calculation which

used HPCS pump runout flow was the appropriate value. These issues represent a weakness with

respect to Criterion III," Design Control," established in Appendix B to Title 10, Part 50, of the

Code offedera/ Regulations (10 CFR Part 50). Additionally, the team questioned the licensee's

basis for not resetting the CST low-level setpoint to provide a margin and preclude the entry of

vortexing into the pipe. Consequently, the team identified this item as Unresolved Item (URI) 50-

440/97-201-01.

e. HPCS Pump Net Positive Suction Head (NPSH)

The team reviewed Calculation E22-1,"NPSH Calculation-HPCS System with DCC-02,"

Revision 0, to verify that the licensee had fulfilled all NPSH-related requirements defined in

USAR Table 6.3-1. The team verified that the calculation used the correct pump runout flow

(7800 gpm), containment pressure (0 psig), maximum pool temperature (212*F), maximum CST

temperature (120 F), suppression pool water level (589 feet), suction strainer clogging (80%

plugged with 9.2-foot pressure drop), and equipment elevation. However, the calculation did not

consider the operation of the SPCU system (as discussed in Section El.2.5.2 of this report) and

had to be revised in order to demonstrate acceptable HPCS NPSH.

f. Keep-Full Pump

Test results for the HPCS keep-full pump (from TXI-229, dated March 19,1996) showed that the

pump was not capable of delivering the 40 gpm flow at 32.5 psi pressure specified in USAR

Section 6.3. The pump delivered 32.4 gpm flow at 34.5 psi which equates to a value less than

specified in the USAR. This degraded condition has existed since July 24,1993, when the

surveillance test was conducted. After identifying this condition, the licensee issued PIF 96-1609,

which requested evaluation of this coadition, as well as establishing new US AR acceptance

criteria. The licensee considered the pump operable even though it was not capable of meeting

US AR flow and pressure values.

5

. _ - -

. .

l

!

j

j The licensee indicated that, even though the keep-full pump was degraded, it was capable of

l maintaining system pressure above the alarm setpoint. The licensee further indicated that, if the

alarm is received, operators would attempt to raise system pressure in accordance with Alarm l

l Response Instruction (ARI) H13-P601-16. Revision 4. If unsuccessful, they would confirm that

{

l the system is filled by checking its fill status (SVI-E22-Ti l83) every 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or by performing I

l SOI-E22A, "HPCS High-Point Vent." The licensee had not determined the rate of discharge line l

l pressure decay when the pump is not operating. Consequently, the arbitrary time period of 24 I

hours may exceed the time at which voids are introduced in the system. To address this issue, the

l

licensee issued PIF 97-0513, documenting that if the keep-full pump was inoperable, performing

i the SVI once every 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> may not account for a pressure decay and may create voids in the

pipe.

The team concluded that the degraded condition of the keep-full pump since 1993 represents

untimely corrective action to resolve the condition or revise the USAR. Consequently, the team

, identified this issue as URI 50-440/97-201-02.

g. Suction Relief Valve

The HPCS suction relief valve relieves suction pressure by directing flow to the dirty radwaste

system that is outside containment. This design deviates from GE Specification 22A3131,

l Revision 5, Section 4.2.3.15, which specifies that the pump suction pressure relief valve should l

relieve to the suppression pool inside contamment.

1

During construction, the applicant issued Field Deviation Disposition Request (FDDR), KL1- i

4006, dated September 15,1983, stating that from an HPCS standpoint, this new route would not

degrade the safety or reliability of the HPCS system. Although the disposition included

evaluation of potential water inventory loss from the suppression pool, the licensee failed to

document 10 CFR Part 100 release consequences. The licensee stated that an unacceptable

radiological release from a failure of the relief valve was not considered credible. Since, for a

small-break LOCA when the HPCS suction may be pressurized by back-leakage from the reactor

as the HPCS cycles, no fuel damage was postulated in accordance with 10 CFR Part 100. For

large breaks with the reactor depressurized below 100 psi, back-leakage from the reactor vessel

will not cause pressurization to the relief valve setpoint. The licensee issued PIF 97-351 to

document the lack of traceable documentation as to the acceptability of this deviation from the

design specifications. The team considered the licensee's review of this issue acceptable and that

this was a case where the licensee did not adequately document the design basis of the relief valve

! and the acceptability of the deviation.

l

l h. Pump Performance / Surveillance Testing

l

l On February 20,1997, the team witnessed system surveillance test SVI-E22-T2001, which

verified that the HPCS pump is operable by measuring and verifying that the listed pump

parameters are within acceptable limits. This test satisfied the HPCS pump operability

i 6

i

..

i l

'

l

. .

,

l

l

requirements of Technical Specifications 3.5.1.4 and 3.5.2.5, and included measurements of  !

suction pressure, differential pressure, flow rate, and vibration. l

The pump fulfilled its test acceptance requirements and satisfied the vendor's performance curve.

In addition, the team reviewed historical records of surveillance testing, which demonstrated that

the equipment typically passed its acceptance criteria and when problems have been noted, the i

licensee had initiated appropriate corrective actions. l

I. Motor-Operated Valves-GL 89-10

l

To verify whether the licensee fulfilled the commitments expressed in response to Generic Letter

(GL) 89-10, the team reviewed a sample calculation performed as part of the commitment

program. The sampled calculation, MOV C-0047, "AC Voltage Drop Calculation for Butterfly

MOVs," Revision 3, was performed to determine worst-case motor terminal voltage for the AC-

powered safety-related butterfly motor-operated valves (MOVs). The resulting voltage values

were later used in another calculation to determine the torque output of the butterfly MOVs. On

the basis of this review, both the calculation and the fmal determination were considered

adequate. Item j (below) discusses the effect of the GL 89-10 program on the HPCS injection

valve.

j. Injection Valve Stroke Time

USAR Table 6.3-1 requires the HPCS system to inject at rated flow within 27 seconds. Related

tests record three intervals following a LOCA signal, including the time for the Division III diesel

generator to start and reach rated RPM, the time for the injection valve to reach the full- open

position, and the time for the pump to reach rated flow. The tests do not individually evaluate the

valve opening time and the time required for the pump to reach full flow, but these intervals are

added to diesel start time and are acceptable if the total time is within the required 27 seconds.

The opening time for the injection valve is allowed to reach 29 seconds, since the valve is opened

sufliciently at 27 seconds to allow rated flow to the reactor.

Records of previous valve injection tests showed that the overall time interval was within the

allowable limit, such that even ifeach time interval would have been separately evaluated (not

benefitting from the short diesel start time), it would still have passed its respective acceptance

criterion.

k. IIPCS Testing Mode Operation

GE Design Specification Data Sheet 22A3131 AS and USAR Section 6.3 specify that the liPCS

l must deliver rated flow to the reacter within 27 seconds after receiving an initiation signal. From

l the normal operation standby condition, this requires the HPCS injection valve to stroke open and

'

develop the rated flow to the reactor within the 27-second time constraint. The team reviewed

, the ability of the HPCS to perform its safety function under the full-flow testing mode of

f

,

7

l

l

l

_. - - ~ _ - - -. - -

1

. .

1

'

operation. Specifically, while in the test mode of operation HPCS valve realignment would be

necessary in order to establish injection flow to the reactor. Test valves aligned in the test mode

receive closure signals upon HPCS initiation to realign the HPCS for injection to the core.

The licensee had previously noted that the stroke times for the test valves would not support j

realignment and the 27-second injection time. In particular, Surveillance Procedure SVI-E22-

l T2001 allows test valve closure times of 60 to 80 seconds, depending on valve size. These stroke

! times exceed the 27-second time constraint for the HPCS to reach rated flow and indicate that the ,

j HPCS cannot be considered operable when it is in the test mode configuration. I

Surveillance Instruction SVI-E22-T2001, " Precautions and Limitations," indicates that the HPCS

l should be operated in accordance with SOI-22A. Revision 5 of SOI-22A, effective June 28,

! 1995, requires that the HPCS must be declared inoperable (in accordance with a standing

instruction dated March 8,1995) whenever it is in a secondary mode of operation. Before

March 8,1995, there had been no directives to declare the HPCS inoperable during full-flow

testing.

After recognizing that the HPCS was inoperable while in the test mode the licensee's investigation

failed to determine if other equipment (RCIC, LHSI, LPCS, etc.) was operable as required by TS

when HPCS is inoperable. If the related equipment was inoperable while HPCS was inoperable

because of testing the plant could have been operating in violation ofTS. The licensee issued

PIF 97-0560 to investigate concerns regarding past operability of other systems during HPCS test

performance to determine if the plant had been operated in accordance with the TS.

l

The team concluded that while undergoint, full-flow testing, the HPCS could not reach rated flow

within 27 seconds of HPCS initiation because of the slower closure of test valves diverting HPCS i

injection flow from the reactor. This condition has existed since the initial operation of PNPP-1. I

The licensee recognized this operability condition in 1995. Resolution of PIF 97-0560 will

determine if a TS violation has occurred during HPCS testing for the period from plant stanup to l

l

the issuance of the standing order in 1995. The team identified this issue as URI 50-440/97-201.- l

03.

1. Overfrequency Protection Relay Removal / System Overpressure Protection

GE Design Specification 22A3131, Revision 5, Requirement 4.4.10, specified that the main HPCS

pump circuit breaker shall automatically disconnect the pump motor load if the electrical bus

frequency exceeds 105% of the rated frequency. This specification provides HPCS discharge

piping overpressure protection, as required by Section III of the American Society of Mechanical

l Engineers (ASME) Code. However, during construction of the PPNP-1, the architect / engineer

(AE) decided not to install the HPCS pump motor overfrequency protection relay, on the basis of

l FDDR KLI-3890, dated May 28,1985. The licensee's SSFI of the HPCS system in 1992,

'

recognized that the basis for not installing the relay identified in the FDDR was not well founded.

Consequently, the licensee performed Calculation E22-19," Justification for Elimination of HPCS

,

8

!

_ -

l

l . .

l

l

Overfrequency Relay," Revision 1, dated July 23,1992, to evaluate the efTect of not installing the l

relay. The team reviewed this calculation and identified the following concerns: l

I

e The licensee's calculation referenced Section III, NB-3654.1, of the ASME B&PV Code m l

l order to justify exceeding the system design pressure by 10% in the event that the Division

III EDG frequency goes above 60 IIz. The licensee's calculation did not identify the I

l specific edition or addenda of the Code that was used to justify their decision not to install

I

the overfrequency/ overpressure protection relay. Design Specification (DSP) E22-1-4549- -

00, Revision 3, dated April 18,1986, referenced that the 1974 ASME B&PV Code with

addenda up to and including the winter 197S issue, was the applicable Code for this system. l

l Section NB-3654.1 of the 1974 Code did not apply to overpressure allowance and was the

wrong reference. Although the 1974 Code did contain a provision for overpressure

allowance in NC-3612.3 the NB portion did not contain a similar allowance. It was l

inappropriate for the licensee to apply this current NB code reference to the entire discharge l

piping from the pump to the reactor vessel since NC portions of the Code applied to

equipment within this boundary. Additionally, the licensee did not evaluate the l

'

overpressure condition on components within the boundary.

.

The licensee's calculation methodology provided a relief path to limit pressure using the

minimum flow valve and its actuation circuitry as overpressure protection devices. The

team questioned the licensee's use of this equipment for overpressure protection since

compliance with the requirements with ASME Code Section III, Article NC-7000,

" Protection Against Overpressure." could not be demonstrated for this valve and its

actuation circuitry. I

The licensee's design control process requires that the NSSS review modification and

engineering decisions that afTect system still under their Jesign authority. Based on the

information reviewed by the team it was not evident that GE reviewed or approved the final

design.

The licensee issued PIF 97-0575 to document concerns regarding the overfrequency protection

relay removal calculation and to justify continued operability. The team determined that the

calculation methodology, code application, and review / approval process did not ensure design

quality as specified in the USAR Section 17.2, QA program and 10 CFR Part 50, Appendix B,

Criterion III," Design Control." The licensee stated that they would reevaluate the possible need

to install the overfrequency relay as part of the effort to resolve PIF 97-0575. Additionally, the

team determined that the licensee's improper disposition of the 1992 discovery of this issue

constitutes ineffective 10 CFR Part 50, Appendix B, Criterion XVI, corrective action.

Consequently, the team identified this issue as URI 50-440/97-201-04.

l

l

l 9

. . 1

m. Fuel Oil Storage Tank Chemistry / Water Removal l

To verify that the fuel oil storage tank undergoes periodic water removal and chemistry analysis,

the team reviewed SVI-R45-T1323, dated January 15,1997, and RPI-l 103, dated January 24,

1997. The team also reviewed the history of water removal and chemistry analysis and

determined that little or no water has been detected in the tank's sump, and the chemistry analysis

results of the oil have been acceptable.

n. Testable Rupture Disc

1

The testable rupture disc (TRD) on the safety-related exhaust of the Division III EDG is designed )

to provide pressure reliefin case the nonsafety-related portion of the exhaust or silencer is

l

blocked, restricted, or inoperable. The team reviewed the des;gn of the disc as depicted by j

Drawing D-301-801, Revision A; Calculation R48-8, "EDG Exhaust Vent Valve Size,"

Revision 1; Calculation R48-11," Standby and HPCS DG Exhaust Vent Valve," Revision 2; )

Calculation R48-17, " Seizure of EDG Exhaust Vent Valve Bearings " Revision 0; and

Calculation R48-13,"EDG Exhaust Vent Valve Setpoint Calculation (with DCC-003),"

Revision 0.

'

Through this review, the team determined that the disc is not tested during diesel operation when

realistic operating temperatures and pressures are present. The disk is tested using a test device

to measure the force necessary to lid the disk. This test force is calculated using area of the disk

and allowed back-pressure that should cause the dist to lift. The design of the disc is sensitive to i

temperature differential across the disc and the resulting displacement of the locking mechanism. I

Also, the disc is susceptible to warping, which causes fluctuations in the amount of force required

to open the disc.

During the test on February 19,1997, the Division III disc lifted at 750 lbs force. At a diameter

of 30 inches, this translates to 29.4" water gauge (WG), which was greater than the allowable

exhaust pressure of 10" WG. For this test failure and similarly times when the disc has opened

with a force greater than the allowable, the licensee identified the problem as being related to

testing and did not determine that the disc and the diesel may have been inoperable. In one case,

where the disc was locked closed, the licensee determined that the EDG was inoperable.

The team identified that the TRD test and operational failures appeared to be design related.

Additionally, the team considered that the licensee's corrective actions were deficient, since TRD

reliability problems appear repetitive. There have been more than 12 failures to date, more than 6

years after the first failure to open, and almost 12 years after the disc opened too early. The

licensee's corrective actions have not resolved the problems.

The team questioned the basis for the TRD setpoint value specified in the test procedure. In

response, the licensee stated that numerous vendor letters have provide conflicting values for

j acceptable EDG back-pressure. In a letter from Engine Systems, Inc. dated October 15,1996,

i

1

10

!

. .

! the engine vendor published a maximum back-pressure value of 5" WG. GE the NSSS, allowed a

maximum back-pressure value of 10" WG. The licensee also indicated that another letter from

l MKS Power Systems ( the system service rep.), dated October 13,1995, allowed a back-pressure

!

of 15" WG during a transient, which equates to an engine power reduction of 0.5%. This value

was later translated to 18.5" WG at the location of the TRD and was used to reevaluate high lift

forces experienced during testing.

The licensee established the allowable back-pressure value of 10" WG using the assumption that,

during EDG operation, the nonsafety-related exhaust may become blocked, causing a back-

pressure sufficiently high to cpen the safety-related exhaust equipped with the TRD. However,

the nonsafety-related exhaust may become blocked before the diesel engine starts. In that case, a

high back-pressure may prevent the engine from starting. The licensee had no documentation

from the vendor to justify that the back-pressure setpoint for the TRD would be acceptable for

both situations. At the conclusion of the inspection, the licensee had not obtained vendor

verification that the current setpoint was acceptable for both situations.

The licensee is currently testing the Division III TRD every month until repeatable data

demonstrate that the TRD is reliable. The root cause evaluation for PIF 97-0325, which

documented the latest failure of the Division III EDG TRD, identified that the TRD design is the

most likely cause of the numerous failures. Additionally, the root cause identified that previous

corrective actions have been inefTective in preventing failure recurrence and improving reliability.

The licensee indicated that a TRD design modification was considered in 1990, but was never

implemented. However, because of recent failures, the licensee now plans to implement the

design modification during operating cycle 7.

10 CFR Part 50, Appendix B, Criterion XVI, requires that conditions adverse to quality (such as

failures, malfunctions, deficiencies) must be promptly identified and corrected. However, to date,

the licensee's actions have not been timely or efTective in ensuring reliable operation of the EDG

TRD. Consequently, the team identified this issue as URI 50-440/97-201-05.

El.2.2.3 Conclusions

The team concluded that the mechanical design of the HPCS system was generally acceptable,

and the system was capable of performing its safety function as evidenced by the surveillance

testing reviewed, although some margins may be small. For example, the HPCS pump is

sequenced onto the emergency bus during a loss of off-site power at a bus voltage of 75% in

order to meet the required injection times. During surveillance fall-flow testing the HPCS system

is inoperable because of test valve design (50-440/97-201-03). The current HPCS suction

swapover setpoint from the CST allows air to travel into the suction pipe (50-440/97-201-01).

Additionally, as discussed in Sections El.2.3.3.a and El.2.5.2 of this report, EDG operation in

speed droop and continuous operation of the SPCU system further impact the margins associated

'

with HPCS flows and timely delivery of water into the reactor vessel. Other findings indicate that

a lack of rigor exists in the licensee's documentation and understanding of the design bases, and

11

._ .-. . _ .- . .- -. _

_ .

. .

maintenance of the design- and licensing-basis configuration (50-440/97-201-04). Additionally,

resolution of the Division Ill EDG TRD testing failures was not timely (50-440/97-201-05).

El.2.3 Electrical

El.2.3.1 Scope of Review

The team reviewed the electrical design for normal and emergency operation of the HPCS pump

motors, selected MOVs, circuit breakers, fuses and interlocks. The team also compared the

design drawings to the system description manual (SDM), as well as applicable sections of the

USAR, TS, and surveillance test procedures (SVIs), in order to verify consistency among the

documents. In addition, the team reviewed the calculations related to voltage drop, electrical

loading, and coordination of selected HPCS components and associated electrical components. In

conducting this review, the team sought to determine the adequacy of the available voltages,

equipment loading, protective system coordination, and electrical isolation and independence.

El.2.3.2 System Description and Safety Function

The station's direct current (DC) system supplies power to plant instrumentation and controls

under all modes of plant operation. In addition, upon loss of AC power, the DC system provides

power for emergency lighting and turbine generator auxiliary loads. Batteries, battery chargers,

and distribution equipment for the Class IE 125-V DC system are located in separate rooms in a

seismic Category I structure.

No interdivisional ties are provided between the divisions associated with Unit I or Unit 2.

Maintenance tie buses connect only the same divisions of the two units. In addition, maintenance

tie bus circuit breakers are normally open and are manually operated under administrative control.

They permit isolation of the battery and normal battery charger associated with either Unit 1 or

Unit 2 for maintenance or equalization of the battery.

The Class IE, Division I and Division II 125-V DC system batteries are sized to supply the

required DC loads for a minimum of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> without the final discharge voltage decreasing to less

than the design minimum of 1.75 volts / cell. The 125-V DC system and the associated loads and

controls supplied by the 125-V DC system are designed to operate from 140 V DC (maximum

corrected equalizing charge of 2.33 volts / cell) to 105 V DC (rated discharge to 1.75 volts / cell).

The Division III 125-V DC power system provides a continuous, independent 125-V DC source

of control and motive power, as required for HPCS system logic, HPCS diesel generator control

and protection, and all Division III-related 125-V DC controls. It includes a 60-cell, lead calcium

battery (100 ampere hours at 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />), and battery chargers. The Division III 125-V DC system

is classified as Class IE. The system is independent of all other divisional batteries, and there is no

l manual or automatic connection to the Division I or II battery systems. A manually operated

12

,

l

-

. .

maintenance tie between the Unit I and Unit 2 Division III DC systems is provided for

maintenance or equalization of the battery.

El.2.3.3 Findings

The team verified that the HPCS is powered from a separate emergency power bus and that the

licensee considered the electrical loading of the individual components in the Division III EDG

capacity calculations. The sequence and timing for loading the HPCS pump and valves onto the

EDG was consistent with the USAR.

The system design documents reviewed by the team adequately supported the design, except for

the discrepancies and open items discussed in the following paragraphs.

a. IIPCS Diesel Generator Droop Setting

The Division III diesel generator (DG3) is the emergency source of power for Bus EH13. Bus

loads consist of the HPCS pump, valves, and auxiliaries. DG3 is designed to operate in the

isochronous mode (i.e., as the sole supplier of power to the bus) when the bus is isolated from the

grid, and in the parallel mode when the bus is tied to the grid during testing.

The diesel starts upon receipt of a LOCA initiation signal, and the generator connects to an

isolated EHl3 bus. Loads (such as h10Vs) are permanently connected to the bus and operated in

turn as dictated by the startup and operating sequence of HPCS. The HPCS and emergency

service water (ESW) pump loads are sequenced onto the bus at preset times. As the HPCS

system continues to operate, load changes consist of hiOV operations as the HPCS cycles

between full flow to the reactor and minimum recirculation flow to the sup; ression pool, as

determined by reactor vessel level indication. DG3 continues to operate in this isochronous mode

to supply emergency power. To parallel with the grid, DG3 must be manually synchronized, with

its output breaker closed while the normal bus supply breaker from offsite power remains closed.

The speed of DG3 is controlled by a Woodward UG-8 mechanical governor, and the mechanical

droop setter for the governor is local to the governor. The manufacturer recommends setting the

droop to zero when operating in the isochronous mode, as shown in Section 12 of the General

hiotors " Electro-hfotive Division 6454E4 Turbocharged Engine hiaintenance hianual," PNPP

File 114-G. The licensee indicated that, during initial plant startup, the DG3 droop setting was

kept at zero when in the standby mode. When the diesel was tested, it was paralleled to the grid

after adjusting its droop setting to accor iodate operation in the parallel mode. After the diesel

was shut down and returned to the star.dby mode, the droop setting was returned to zero.

The licensee was not able to determine when the change in droop setpoint occuired but present

practice at PNPP-1 is to maintain the DG3 droop setting at a value of 20 on the dial face at all

times. This setting of 20 equates to -2% of rated speed when the diesel is loaded (-1.2 Hz).

PNPP engineers explained that this practice was established as a convenient way to preclude the

13

-

- - - - . _ .. ._ . . - _. - .

l

, .

l

possibility of the droop being inadvertently left set at an incorrect value. Instrument Maintenance

Instruction (IMI) E3-23, Section 5.2.4, Step 23, dated June 12,1991 (in effect at the time of this

l inspection) instructs plant personnel to " Reset speed droop control, if necessary, to 20." The

! team had the following concerns regarding the licensee's established practices:

The diesel generator was originally qualified to Regulatory Guide (RG) 1.9, Revision 0, and

the licensee was unable to locate documentation to demonstrate the qualification setting at

other than the vendor recommendation of zero droop. The licensee also could not produce

any documentation to support the current setpoint or the impact ofisochronous mode

operation at a droop setting other than zero. The licensee confirmed that no specific testing

i had been performed with this droop setting to revalidate the diesel generator qualification  !

and confirm acceptable operation. USAR Table 1.8-2 commits to following ANSI 45.2.11 -

1974 for Quality Assurance Requirements For The Design of Nuclear Power Plants. l

'

ANSI 45.2.11 - 1974 requires that changes from specified design inputs or quality standards

i including the reasons for the changes shall be identified, approved, documented, and i

controlled. The team concluded that the change in the droop setting constituted an

undocumented modification, and identified this issue as URI 50-440/97-201-06.

  • In a related but separate issue, the licensee had previously issued PlF 97-0165 on

January 28,1997, to assess the impact on the mechanical systems of operat'ing any of the

diesel generators within a frequency band of* 1.2 Hz (or * 2% of rated speed). The l

licensee had not conducted any such analysis before that time. The licensee documented

their review of PIF 97-0165 in a calculation that showed that, at a frequency of 58.8 Hz, the

HPCS pump would be unable to develop minimum discharge pressure by 4 psig. The team

noted that the calculation treated droop as a bias and added it to other errors to calculate the

total loop error. The other errors (including the TS-allowed 2% of rated speed error)

were appropriately treated as random and were statistically added. The team agreed with

this approach.

The licensee provided the inspection team with surveillance test vA;. charts showing

performance of the diesel generator during testing with normal accident loads. In providing

these test results, the licensee's purpose was to substantiate the position that the diesel

generator operates within TS values at a droop setting of 20. These charts showed that,

during startup and load sequencing, the voltage and frequency disturbances associated with

load variations were within the tolerances specified in RG 1.9. However, because droop

l was set at 20, the frequency was shown to decrease as the load increased, to 59.15 Hz at a

load of 2200 kW. The licensee also demonstrated that, with other loads associated with the l

pump operating at runout flows, the full-load projection for DG3 was 2250 kW, with a l

corresponding speed equated to approximately 59.1 Hz (compared to the TS lower limit of

58.8 Hz).

l

The licensee modified the original position and, at the conclusion of the inspection, planned

to revise the original PIF 97-0165 evaluation. The licensee stated that it was inappropriate

14

i

l

. .

to add droop as a bias to the other errors in calculating the total loop error, since the TS l

allow EDG surveillance testing to be considered acceptable if the EDG starts and operates

at 60 1.2 Hz unloaded. As demonstrated by surveillance testing, droop causes the bus

frequency to drop as DG3 is loaded. The licensee noted that the procedure used to shut

'

down DG3 after testing involved reducing the load to approximately 100 kW while i

observing that the speed increases to slightly above 60 Hz. At this point the diesel generator  ;

is stopped. The licensee is using this administrative control to ensure that the TS would be I

met by setting up DG3 to start the next time at 60 + Hz. Because droop biases bus

frequency approximately 2%, the team concluded that the licensee's position (that droop l

should not be considered as a bias added to the other errors in calculating the total loop i

error) was inappropriate. The licensee held discussions with GE at the conclusion of the

inspection in an attempt to gain additional HPCS flow margins to allow droop to be added l

l as a bias as originally planned. Consequently, the team identified the need to review this l

calculation aller revision as URI 50-440/97-201-07.

b. Battery Surveillance Testing

l

SVI-E22-T5217, "18-Month Battery Surveillance Test Data," dated October 7,1996, for  !

Battery lE22-S005 showed that individual cell voltage for Cell 60 dropped below 1.75 V to

1.32 V at the end of test (127 minutes). The licensee concluded that lower voltage for Cell 60 did

not constitute an unusual situation. Institute of Electrical and Electronics Engineers (IEEE) Std.

450-1980, "Large Lead Storage Batteries for Generating Stations," Section 6.4.4, allowsjumping

out individual cells if the voltage begins to approach 0. This review of discharge test data ,

indicated that this cell's capacity is in the high 90% range, well within the acceptance limits of the

test. The performance of this cell, while somewhat below average compared to other cells in the ,

battery, did not significantly affect overall battery capacity, which was verified to be 106%.

l

El.2.3.4 Conclusions

The team concluded that the electrical design for components that perform the engineering

safeguard functions of the HPCS was adequate and operating within the design limits. However,

further analysis of droop bias effects on mechanical equipment performance is needed (50-440/97-

201-07). The deviation from the vendor recommendation for DG3 droop setting without a

documented basis constituted an undocumented modification (50-440/97-201-06).

El.2.4 Instrumentation and Controls G&C)

El.2.4.1 S_ cone of Review

In evaluating the HPCS I&C area, the team reviewed design documentation, conducted

interviews, and performed walkdowns of the HPCS system. The team concentrated on protective

functions that maintain reactor core cooling and vessel inventory during and after a LOOP /LOCA

or LOCA. In addition, the team assessed the design for the ability to meet USAR commitments

15

-. _

, .

and to operate within TS limits. Attributes reviewed comprised instmment installations,

instrument setpoints, instmment power and AC and DC control power provisions, and remote and i

alternative shutdown provisions. Documents reviewed included appli:able sections of USAR

Chapters 1, 3, 5, 6, 7, 8, and 9; TS; SDMs; vendor documents; P& ids; logic diagrams; electrical j

wiring diagrams; instrument installation drawings; calculations; calculation change records; PIFs;

l

action requests (ARs); condition reports (CRs); nonconformance reports (NRs); and DCPs. l

l

l

El.2.4.2 Findings '

a. Missile Protection of CST Suction Piping for HPCS/RCIC and Tank Level I

lustrumentation )

The CST is a nonsafety-related, non-seismic tank located outdoors inside a concrete dike

structure. At 2 feet,0 inches thick, and 23 feet,8 inches high, the dike is a seismic Category I

structure designed to withstand externally generated tornado missiles, and creates an annular

space of 8 feet,0 inches, between the tank and the dike wall with a capacity to retain the total

inventory of the CST. A concrete room to house CST level instrumentation is provided, designed

, and fabricated to the same standards as the dike, and includes a labyrinth entrance for missile

protection.

i

The CST is a source of clean water for the RCIC and HPCS systems. GE Design Specification

Data Sheet 22A3131 AS; Functional Control Diagrams (FCDs); CEI Drawing No. D-308-311,

Sheets 1-4; the HPCS SDM E22A; and USAR Section 6.3 designates the CST as the normal

source of water for the HPCS. When the water level in the CST is drawn down to the low-level

setpoint, the HPCS suction lineup is transferred to draw from the suppression pool as the safety-

t

related source of water.

Instn. mentation monitoring the water level in the CST to effect the transfer to the suppression

poolis safety related. Two safety-related class IE powered transmitters (IE22-N054C and IE22-

N054G) monitor CST water level with a one out of two logic for the suction transfer.

RCIC and HPCS share a common ASME Section 111 suction line from the CST. This suction

piping exits the side of the CST above the 11om stab, bends downward 90 to penetrate the floor

slab in the annular space between the CST and the dike, and is then routed underground to the

Auxiliary Building.

USAR Section 3.5.1.4 states that, safety-related systems and components which are located

outside of Category I structures are provided with unique missile barriers. USAR Table 3.5-7

indicates the HPCS and RCIC piping to the reserve water in the CST is underground, covered

with a minimum of 4.5 feet of compacted earth for protection against external missiles. However,

both the instrument sensing lines and the RCIC/HPCS suction piping are exposed inside of the

dike wall and are unprotected from missiles originating from natural phenomena such as seismic

events or tornadoes. During the CST walkdown, the team identified two non-seismic stacks on

16

.- .. - . . .

l

. .

the top of the Auxiliary Building that may have the potential to fall and hit the CST, CST water

level instrument piping, and RCIC/HPCS suction piping.

Calculations 22:08 and 22:11 address the tornado missile design of the dike wall and document

that protection from externally generated tornado missiles is provided for the instrumentation

4

located inside of the instrument room along the dike wall. However the CST water level

instrument piping and the RCIC/HPCS suction piping inside of the dike were not addressed in the

calculations. Both are vulnerable to damage by either gravitational and tornado-generated

missiles. The instrument lines are routed close together so that a single missile could strike both

of them. In the case of the suction piping, the effect of the piping being struck by any missile  !

would be either the loss ofits pressure boundary and leakage of the CST inventory into the dike

area, or crimping the line and restricting the flow. No analysis existed to substantiate the

licensee's current protection of this equipment from tornado missiles.

The licensee acknowledged this fmding and issued Pli 97-0561 to address the adequacy of the

tornado missile and seismic protection design for the CST level instrument piping and HPCS

suction piping installed between the CST and the concrete containment dike. The licensee

conducted an immediate operability review for the HPCS and RCIC systems. The CST level

instrument piping and HPCS suction piping installed between the CST and the concrete

, containment dike were considered to be inoperable. In accordance with TS 3.3.5.1 and 3.3.5.2, if

'

'

the HPCS and RCIC suction valves are lined up to the suppression pool, these systems need not

be considered inoperable. As a result, the licensee issued instructions to the operators to maintain

a line up of the HPCS and RCIC suction valves to the suppression pool. Operation in this lineup

would continue until further analysis substantiates the acceptability of the design of the CST level

instrument piping and HPCS/RCIC suction piping inside of the concrete containment dike or

corrective measures can be implemented to upgrade the design condition. -

The licensee's initial review of the issues described in PIF 97-0561 (Calculation 1
05.7), indicated

'

that, on the basis of probability, the equipment in question did not need to be protected. This

probability of damage approach was questioned by the team since Section 3.5.1.4 of the Perry

Safety Evaluation Report (SER) (NUREG-0887) used a probability of 1 that a tornado-generated

.

missile would strike exposed equipment. During subsequent discussions the licensee informed the

team that Section 3.5.1.5 of the NRC's Standard Review Plan (SRP) allowed the use of

probability. Use of SRP Section 3.5.1.5 which addresses external not tornado generated missiles

was not appropriate for this review. The team determined that the licensee resolution of this issue

'

was inadequate and informed the licensee. After further review, the licensee agreed that the PIF

resolution was not in accordance with their licensing bases and was therefore unacceptable. The

PIF resolution effectively changed the plant from that described in the USAR and should have

been supported by a safety evaluation pursuant to 10 CFR Part 50.59. PIF 97-0738 was issued

and a walkdown of equipment was initiated by the licensee. The team, therefore, informed the

licensee that the current missile protection design for equipment subjected to tornado-generated

missiles was efTectively a change to the plant from that described in the USAR and represented a

a

17

't

1

i

-- -. - . . . - . - - - . _ . -. _ - .

.

. .

potential unreviewed safety question. In addition, the team identified this issue as URI 50- l

440/97-201-08.

b. Condensate Storage Tank Low-LevelInstrumentation I

1

The two safety-related CST low-level transmitters are both mounted inside boxes located in an

unheated concrete instrument room. The instmment lines from the transmitters to the CST are I

routed through a single penetration in the concrete dike to the storage tank. Once through the

dike the instrument lines are exposed to the elements outdoors. The instrument lines are wrapped

with electrical heat trace from their connection to the transmitter to their connection to the shutoff

,* valves at the CST. The heat trace is fed from a nonsafety-related power source. PIF 96-0425

documented a case where a nonsafety-related transmitter with the same location and heat trace

design as the safety-related transmitters froze. The freezing occurred at the transmitter box. Th:

heat trace was deemed adequate. Leaks in the box insulation and lagging were the cause of the i

problem. All of the heat traced lines have thermocouples for monitoring the operation of the heat

J,

trace. These thermocouples did not repon any abnormal temperatures and checked out as normal

during subsequent walkdowns.

'

The team inquired about the use of nonsafety-related power feeds for heat tracing the CST level

instruments. The licensee responded that all heat trace throughout the plant is fed from

nonsafety-related power sources. In all cases, their performance is monitored by nonsafety-

related temperature monitors. The installations are checked on operator rounds for abnormal

t.smperature conditions and operability of the heat trace and temperature monitors. However, PIF

96-0425 noted that, during the incident in which the lines froze as a result of a short in the heat

trace cable, the failure remained undetected because of a failure of the temperature monitoring

element.

Protection of the line from freezing is lost during loss of AC power events, because the heat trace

is powered from nonsafety-related electrical power sources. In this case, off-normalinstructions

(ONIs) required the operators to monitor the instrument line temperature. ONI-RIO provided a

table of time limits versus on the outside air temperature. From O'F to 16 F an hour and a half

time limit was provided to transfer the CST inventory to the suppression pool in anticipation of

the instrument lines freezing. For an outside air temperature less than O'F the ONI required that

the inventory be transferred immediately.

El.2.43 Conclusions

The HPCS review identified a design deficiency which has existed since the original design phase

of the plant. A section of HPCS suction piping where the piping exits the CST and the CST level

instrumentation piping inside of the concrete dike have not been protected against gravitational

and tornado-generated missiles, as described in the US AR (50-440/97-201-08).

18

. - .-. . _-

, .

'

\

El.2.5 System Interfaces

j

El.2.5.1 Scope of Review

j

l

,

in this portion of the design review, the team considered the safety /nonsafety system interface l

between the HPCS and SPCU systems, the HPCS room coolers, and the Unit 2 batteries, as well I

as the HPCS room flood provisions.

El.2.5.2 Findings

} a. Suppression Pool Cleanup

The PNPP design of the SPCU system interfaces directly with the HPCS. SPCU takes suction

from the HPCS suppression pool suction line between the containment isolation valve and the  !

j pump. This arrangement requires that the HPCS system be aligned to the suppression pool l

4 instead of the CST during SPCU system operation. This system arrangement was the subject of

, Engineering Design Deficiency Repon (EDDR) 10, dated February 13,1984, which was reported

J

to the commission via letters dated April 30 and June 8,1984. EDDR 10 stated that the root

l

cause of the deficiency was that the SPCU piping was improperly connected downstream of the '

HPCS suppression pool suction valve rather than upstream. This indicates the intended design

was to have the SPCU system suction interface between the containment penetration and the

containment isolation valve. EDDR 10 states the SPCU suction valves F010 and F020 (G42) ,

system are normally closed, and if open, automatically close on a LOCA signal corresponding to

reactor water level 1 at which time the SPCU system would receive an isolation signal. Under the

intended design, HPCS would be aligned to the CST and SPCU could be operated from the pool

with the HPCS suppression pool isolation valve closed. Under the as built configuration SPCU

operation required HPCS alignment to the pool. With HPCS initiation at reactor vessellevel 2

and SPCU isolation at reactor vessel level 1, EDDR 10 indicated that HPCS would be inoperative

until the reactor water level reaches level 1. The action taken to correct this situation was to

change the isolation signal to close SPCU suction valves whene "P('S is initiated.

This solution corrected the isolation signal problem only. The mechanical configuration which

requires HPCS alignment to the suppression pool for SPCU operation was left unchanged. As

indicated in the FDDR, the SPCU suction valves F010 and F020 (G42) system were intended to

be normally closed. The SPCU system was not intended to be normally in operation. This is '

consistent with USAR Section 6.2.4.2.2.2, " Justification with Respect to General Design

Criterion (GDC) 56," which states that the suppression pool cleanup return line is used for

suppression pool return flow during periods of suppression pool cleaning and mixing. The US AR

states that containment isolation requirements for the retum line is satisfied, in pan, on the basis

that the line is normally closed. In response to team questions, the licensee indicated that SPCU is

essentially always in operation and HPCS is essentially always aligned to the suppression pool.

The team noted this alignment is not consistent with the HPCS classification and function to

backup the RCIC system, including initially take suction from the CST as the preferred source of

19

, - -

. .

water. Although the licensee indicated that the suppression pool alignment is the safety-related

alignment for normal operation, the team considers this to be inconsistent with the facility

operation as described in the USAR. Because the licensee did not develop a safety evaluation as  ;

required by 10 CFR Pan 50.59 for continuous operation of the SPCU system which was different I

than that described in the USAR, the team identified this issue as URI 50-440/97-201-09

l

The team reviewed the ability of the SPCU system to support HPCS operation by isolating the

suction valves upon HPCS initiation. GE Design Specification 22A3131 AD, Requirement 4.4.1,

specifies that the HPCS system must be capable of starting and delivering rated flow into the

vessel within 27 seconds following receipt of an initiation signal. Two butterfly valves, F010 and

F020 (G42), powered from Division I and II power supplies isolate the SPCU suction from the

HPCS system. The closing time for these valves is 35 seconds without consideration of power

supply startup timing. This exceeds the 27 seconds required for HPCS to reach full flow. The i

team noted the HPCS system would be operating in parallel with the SPCU system until the

SPCU suction valves completed their stroke. This consideration was not consistent with the

mechanical design calculations for HPCS (in particular, Calculation E22-1, "NPSH

Calculation-HPCS System"), nor with the description in USAR Section 6.3.2.2.1 for NPSH

calculations in accordance with RG 1.1. PIF 97-0526 was issued by the licensee to document this

finding.

The licensee initiated a review of the HPCS NPSH calculations to address the effects of SPCU

operation with a normal operating flow rate of 2000 gpm. The team noted that the piping from

the isolation valves to the SPCU pump is nonsafety but seismically-supported, while piping

downstream of the SPC'U pump is nonsafety, nonseismic, and also not seismically supponed. The

team questioned the ba,is for the assumption of a 2000-gpm normal flow rate. The licensee

referred to a letter (PY-DIDR-072), entitled " Revision of Break Type Criteria for Moderate-

Energy, Nonsafety-Related, Non-Seismic, Category I Piping Outside Containment," dated May 6,

1982. This letter provided the basis for relaxation of the original PNPP assumption of full

circumferential breaks in moderate-energy, nonsafety-related, non-seismic, Category I piping

outside containment to permit consideration ofleakage cracks only. On the basis of this criterion,

the licensee indicated the 2000 gpm normal flow rate would be bounding. The team concluded

that the issue of pipe break (versus pipe crack) criteria required funher review of the plant

licensing basis. Consequently, the team deferred this issue to the NRC staff for review as URI 50-

440/97-201-10.

The licensee recalculated available NPSH considering both the normal flow rate of 2000 gpm and

an SPCU pump runout condition of 3500 gpm if a pipe rupture downstream of the SPCU pump

was assumed. Preliminary results of this reanalysis indicate neither the 2000 gpm nor the 3500

gpm SPCU flow rate in parallel with HPCS operation would suppon HPCS NPSH requirements

assuming a maximum suppression pool temperature of 212*F as currently stated in the USAR -

Section 6.3.2.2.1. A reduction in the maximum suppression pool temperature from 212*F to

185*F was required to demonstrate acceptable NPSH results. The licensee stated that 185"F is

above the maximum analyzed suppression pool temperature of 183 F and is consistent with the

20

. __ _

. .

assumptions being used for the ECCS strainer moditication in response to IE Bulletin 96-03. The

licensee has issued PIF 97-526 to document and resolve this issue.

l

Also, as a result of the SPCU system taking suction from the HPCS suction line downstream of

the HPCS suction valve, the SPCU valves are not considered containment isolation valves.

Review of the Pump and Valve Inservice Testing Program, Revision 3, and the program for

Primary Coolant Leakage Reduction for Systems Outside Containment, PAP-1111, Revision 1,

verified that the SPCU suction valves are not leak tested. The ISTP requires only stroke time

testing. This could jeopardize the operation of the HPCS system because, if while HPCS was '

, operating, the SPCU valves developed a significant leak, the HPCS suction valve would have to

'

be closed, terminating HPCS operation.

The team concluded that the design of the SPCU/HPCS interface, which would require HPCS

isolation in the event of a SPCU system leak represents an apparent oversight in the design. This

condition has existed since the initial licensing period because of insufiicient analysis and

<

corrective actions regarding the SPCU deficiencies identified in EDDR 10. The team stated that

j this issue would be reviewed by the NRR technical staff. Consequently, the team identified this

issue as URI 50-440/97-201-11.

b. Surveillance Testing ofIIPCS Room Cooler-GL 89-13

The team reviewed the HPCS Room Cooler with regard to heat exchanger performance test

requirements defined in GL 89-13. The HPCS room cooler is an air-to-water heat exchanger

which rejects heat from the HPCS pump room to the ESW system. The team identified the

following concerns during this review:

4

+

PNPP response to GL 89-13," Service Water Problems Affecting Safety-Related

Equipment," PY-CEI/NRR-l l21, dated January 26,1990, stated that " The ESW air-to-

l

water heat exchanger (HPCS room cooler) will be inspected and cleaned at each refuel

outage, fin and tube side, as an alternative to performance testing." This commitment to

l clean and inspect the heat exchangers is identified in the Perry Regulatory Information

j

Management System as commitment Lol181. In a subsequent submittal to the NRC,

'

Implementation of GL 89-13," Service Water Problems Affecting Safety-Related

i Equipment," PY-CEI/NRR-1734L, dated April 8,1994, the licensee stated that there are 10

ESW heat exchangers at PNPP within the scope of GL 89-13, which have been serviced as

follows. . High-Pressure Core Spray Room Cooler,2 Inspections,2 Cleanings.

'

Documentation of the inspections was available, however, there was no documentation to

substantiate the room cooler was cleaned as committed in PY-CEI!NRR-1121 and

conSrmed in PY-CEI/NRR-1734L. The licensee stated that to their knowledge, inspections

we.e done, but no cleaning was done on the HPCS Room Cooler during the time period

claimed in the letter to the NRC. PIF 97-0463 was issued to document this finding. The

licensee conducted a review to determine the potential impact of the inaccurate information.

The licensee stated that the oversight was not material or willful and intended to correct the

21

. - - .- - - . -

!

. . 1

erroneous information in response to fmdings of this inspection. The team concluded that

the missed cleaning and the licensee's subsequent report that the commitments had been

satisfied constitute deviations from the licensing commitments. Consequently, the team

identified this issue as URI 50-440/97-201-12.

Letter PY-CEI/NRR-1734L, dated April 8,1994, also states "With available improvements

in methodology cited above, the HPCS Room Cooler will now be tested, or alternate

monitoring methods will be determined in accordance with Electric Power Research

Institute (EPRI) NP-7552," and "PNPP will maintain the present testing frequencies of once

per cycle until such time as our testing demonstrates that a reduced frequency is warranted."

The HPCS Room Cooler was tested in June 1995. Calculation M39-6, HPCS Room Cooler

Performance Test Results 1995, deemed the test results inconclusive. Since June 1995, no

other operability test was conducted. The licensee stated that there were no intentions to

inspect the room cooler before October 1998 and maybe not until October 1999, even if no

conclusive testing can be achieved by that time. The team noted the licensee has not

established a performance test program for the HPCS room cooler and has reverted to the

inspection program, but has extended the frequency beyond each cycle without a history of

testing to demonstrate that a reduced frequency is warranted. The team considers this a

deviation from the licensing commitment to inspect and clean the HPCS room cooler during

each refueling outage, as stated in the PNPP response to GL 89-13, " Service Water

Problems Affecting Safety- Related Equipment," PY-CEI/NRR-1121, dated January 26,

1990. In addition the team considers this a deviation from the licensing commitment to

maintain test frequencies of once per cycle until such time as testing demonstrates that a

reduced frequency is warranted, as stated in Implementation of GL 89-13, " Service Water

Problems Affecting Safety-Related Equipment," PY-CEI/NRR-1734L, dated April 8,1994.

The team, therefore, identified these deviations as URI 50-440/97-201-13.

c. HPCS Room Cooler Filters

During the HPCS system walkdown, the ter a observed that the room cooler filters were exposed

without any protection from direct impact by water spray or debris. The licensee indicated that

the only spray the filters could be exposed to is from the HPCS piping. Such a piping failure

would render the HPCS system inoperable in which case the filters would not be needed. The

only non-HPCS pipe in the room is the SPCU pipe, whose location cannot jeopardize the filters.

The team reviewed the rcom cooler vendor manual which did not mention of any protection

requirements for the filters. The team also verified that the existing filters possessed all the

required parameters of the original filters.

d. Battery Room Floor Drains

Floor drains in the Unit 2 Division II and as Unit 1 Division III Battery rooms appear to have a

screen beneath the cover and were full of debris. The team was concerned whether the drains

were functional. PIFs 97-0423 and 0424 address cleaning the drains, and verification that a

22

1

. .

battery spill into the drain system would not create an environmental hazard The licensee's

documentation of these housekeeping items as well as many other items in the corrective action .

process represented good sensitivity as to threshold for problem identification. l

e. Unit 2 Batteries Used to Support Unit i Operation

Unit 2 Division 111 batteries support the Unit 1 Division Ill batteries during maintenance activities.

PNPP initiated a PIF 96-2833 dated 8-30-96 to evaluate incomplete constmetion of Unit 2

Division III battery room for seismic restraints built in accordance with the design drawings.

Engineering performed a walkdown to identify any potential seismic interactions 'in the Unit 2

Division III battery room. The review concluded that there were no credible hazards (i.e., items

ofconsiderable weight with missing or inadequate anchorage) located within a falldown distance

of the batteries. The nonsafety commodities (e.g., conduit, light fixtures, etc.) adjacent to the

batteries are well supported and do not pose a seismic impact or falldown concern. The vertical

cable drop to the batteries is acceptable. The acceptability is contingent upon the cable and/or

conduit being well supported and of adequate length (i.e., with adequate slack) to accommodate

any differential seismic movement between the battery rack and the conduit.

El.2.5.3 Conclusions

The team identified a variety ofitems regarding the HPCS system mechanical interfaces including

the SPCU system, and HPCS Room Cooler testing.

The operation of the SPCU, particularity on a continuous basis, was not consistent with the

description of the facility as described in the USAR and was not supported by a 10 CFR Part

50.59 safety analysis (50-440/97-201-09). Operation in this mode did not support the RG 1.1

NPSH evaluations as presented in the USAR (50-440/97-7.01-11). Deviations from licensing

commitments regarding cleaning and frequency ofinspections made with respect to GL 89-13

l

were identified (50-440/97-201-12 and 13).

An additional issue regarding application of pipe break criteria (rather than pipe crack criteria) to

nonsafety, non-seismic, moderate-energy piping systems has been referred to the NRR technical

staff for review (50-440/97-201-10).

I

El.2.6 System W;lkdown

El.2.6.1 Scone of Review j

The system walkdown included examinations of the HPCS piping and components not inside the

primary containment, as well as the interface with the CST and the SPCU system and the Division l

'

III diesel generator. The walkdown also included interviews with plant operators in the control

room.

23 l

\

. .

El.2.6.2 Findings

a. Battery Hold-Down Straps

The top and bottom rows of batteries on Unit I and 2 Division III racks did not have the same

number of clamp-down supports. Vendor Drawing M-6709-3, " Rack, 2-Step Seismic For 20-

3DCU-9 Battery," shows 6 supports on each side of the battery cells. PIF 97-0407 documents

this discrepancy. The licensee performed an operability determination and verified that the

observed condition did not afTect battery operability. The licensce's corrective action for PIF 97-

0407 should determine the root cause as to why the brackets were not installed. In addition, the

corrective action should result in a revision to the drawing, supported by a detailed calculation.

The team, therefore, identified this issue as Inspection Followup Item (IFI) 50-440/97-201-14.

b. Battery Conductors

Bending Radius - Unit 1 Division III battery cables IE22D206C and IE22D208C, Unit 2 Division

III battery cables 2E22D208C and 2E22D212C were bent in a 3" diameter or greater,360-degree

coil at the termination point. Engineering Instruction (GEI) 0007, " Cable Termination

Instmetion," Attachment 2, Sheet 2 of 2, Termination Data Sheet (Power Cables)," provides a

Step 7.4, " Training Radius Maintained," Drawing D-215-801, " Cable Pulling Criteria, Bending

and Training Radius," Revision J, specifies that the training radius for these cables (EKA-171,1/C

  1. 2) is 1.5." Nonconformance Report PPDS-3846, Revision 1, dated May 15,1989,had

previously dispositioned this condition as acceptable.

c. Battery Maintenance-Vendor

The team noted during their system walkdowns that a vendor was performing repairs on

Division I and II batteries and requested from the licensee details and scope of the work in

progress. According to licensee, during the performance of weekly battery surveillance test (SVI-

R42-T5202) and SVI-R42-T5203) on May 20,1996, an electrolyte leak was discovered in the

batteryjars of various cells at the seam on the top cover. PIF 96-2149 was issued to identify and

correct the leakage problem from the cell covers. The leak resulted from a defective seal between

the celljar and the top cover, as well as poor workmanship during battery fabrication. The

electrolyte leak is not a battery failure and does not impact the system function and operability. j

The manufacturer (Yuasa-Exide) was on site performing the repairs to correct the leakage  :

problem.

d. Cable Separation

Conduits IR33D98A and IR33D102A in the Division I battery charger room were in contact ,

with each other and were wrapped in 3M insulation. Raceway separation barrier installation l

drawing SS-201-146, Sheet 143, Revision EE, criteria allows the conduits to be wrapped with 0" i

separation and therefore the installation was acceptable.

1

24

1

_._ _.___. __ ____._ .___._ _ _. _ _ _ _ _ _ - _ . .__ _

,

. .

s

e. Cable Tray / Raceway / Conduit Fill Walkdown

! Tray and conduit % fill values for Cable Trays "C" 1951 and 1952 and conduit IR33C2977C in 1

the Unit 1 Division III battery room were checked and found acceptable. Summary ofTray Data l

Report CKSR2000, documents tray 1951 as being 31.9% and 1952 being at 38.6% filled.

J

Conduit Summary Report CKSR2200 identifies raceway 1R33C2977C as being 35.9% filled.  !

The fill criteria specified in USAR Section 8.3.1.4.3 are 50% for tray and 40 percent for conduit.

l

l

'

. '

f. Conduit Supports

Unit 1 Division III battery room conduit flex IE22A212C dropped from the ceiling with no

support. Conduit Layout Drawing D-215-004, Sheet 601, Note 6C.2 and Table 3, allow the

maximum conduit length between supports to be up to 10 feet. The conduit in question was field

verified to be 8 feet,6 inches long, and was found to be acceptable.

El.2.6.3 Conclusions i

With the exception of the battery hold-down straps (50-44/97-201-14), the team considered the i

electrical equipment and cable installation including separation and fill to be acceptable in

accordance with licensee design drawings.

El.2.7 IJSAR Review

The team reviewed the appropriate USAR sections for the HPCS and associated electrical and

control systems. The team identified the following discrepancies with regard to statements made

in the USAR:

The team's assessment of the basis and design features for flooding due to passive failures

within the HPCS room identified inconsistencies between the actual design and the design

described in SER (NUREG 0887) regarding control of unisolable post-LOCA leakage

within the ECCS rooms. The ECCS room flood capabilities described in the SER were

difTerent from that contained in USAR Section 6.3.1.3. The licensee indicated that the

USAR description and the design basis was consistent with regulatory requirements in this

area. The licensee issued PIF 97-0488 to clarify their design and licensing basis for

detection and protection from passive failures of either the HPCS pump seal or valve

packing during both normal operation and post-LOCA. The licensee's position on this issue

was discussed with NRR technical staff who agreed that clarification of the USAR was

needed.

The team identified the following administrative discrepancies between Calculation PSTG-

0014, " Diesel Loading Division I, II, and III," Revision 3, and USAR Table 8.3-1: The

licensee had previously identified similar discrepancies with USAR Table 8.3-1 and

Calculation PSTG-0014 as documented in PIF 96-2780.

25

. .

a

a) USAR Table 8.3-1 identifies loads IM43C001C and 2C as OM43C001C and 2C.

b) USAR Table 8.3-1, Note 17, second sentence contradicts Note 20.

c) USAR Table 8.3-1 lists fuel oil transfer pumps IR45C001C and 2C as 0-second loads.

IR45C001C and 2C are 40-minute automatic cyclic loads for both LOOP and LOCA.

d) USAR Table 8.3-1 identifies a 9-kW load for IE22C004B and does not agree with the

8-kW load in Calculation PSTG-0014.

e) USAR Sections 8.3.1.1.3.2B6 and 8.3.1.1.3.386 refer to "Section 8.3.1.1.2.8," but

the correct section is 8.3.1.1.2.6.

I

The team identified discrepancies de. scribed below indicated that design and calculation

changes may not be accurately reflected in the USAR:

a) USA.R Table 8.3-1 lists inrush current for HPCS water leg pump IE22-C003 as 51

amperes, Calculation PRMV-0017, "EHF-1-E Transformer Breaker EH-1305,"

Revision 0, does not reflect inrush currents for the IE22-C003 load.

b) USAR Table 8.3-1 lists the inrush currents for HPCS fuel oil transfer pumps IR45-

C001C and 2C as 109A, whereas Calculation PRMV-0017 lists the inmsh current as

130A.

c) USAR Table 8.3-1 lists the inrush currents for HPCS diesel generator room fans

OM43-C001C and 2C as 362A, whereas Calculation PRMV-0017 lists the inrush

current as 376A.

d) USAR Table 8.3-1 lists the FLA of HPCS diesel generator starting air compressor

IE22-C004B as 13 A, whereas Calculation PRMV-0017 lists the FLA as 11 A.

e) USAR Table 8.3-1 lists the HPCS ESW pump IP45-C002 is as 75 hp,88.5 FLA, and

557A inrush, whereas Calculation PMRV-0017 lists the same load as 75 hp,

85.4 FLA, and 543 A inrush.

f) USA.R Table 8.3-1 lists the rating of HPCS diesel generator space heater IE22-D011

as 2 kW, with a load current of 3 amp. Calculation PRMV-0017 lists the same space

heater as 1.6 kW, with the load current of 2.01 amp. Drawing D-206-029/BB,

" Electrical One Line Diagram, Class IE,480-V Bus EFID," lists the same space

heater as 2.4 kW.

26

'

i

i

g) USAR Table 8.3.11," Penetration Protection," was generated from Calculation ECPC-

2 '

0001, " Electrical Penetration 1 T Verification," Revision 2, dated 8-25-92. Input to

l ECPC-0001 was from Calculation PSTG-0006, "PNPP Short Circuit Study," Revision

l 1, dated 6-21-85. Calculation PSTG-0006 is currently at Revision 2, dated 5-20-92.

Calculation ECPC-001 and USAR Table 8.3-11 have not been revised to reflect the

impact of PSTG-006, Revision 2. The initial review by engineering has determined

! that the present ampacity values in Calculation ECPC-001 are conservative with

respect to PSTG-006, Revision 2, and the I2T values and clearing times in USAR

Table 8.3-1I will not change significantly.

h) USAR Table 8.3-7 does not reflect the current load profiles of Calculation PRDC-

0005, " Load Evaluation and Battery Sizing of Division I and II Battery Load Profiles," .

Revision 3, dated May 23,1996. PIF 97-0425 documents this discrepancy. Currently, 1

all Division I and Il surveillance performance and service tests are performed per

l

USAR Table 8.3-7. Operability of the plant systems, functions, and equipment are not

affected by the inconsistency between USAR Table 8.3-7 and the Calculation PRDC-

0005, Revision 3. The load profiles listed on USAR Table 8.3-7 are greater

(conservative) than the profiles addressed in Calculation PRDC-0005, Revision 3.

Corrective Action 97-0425-001 will revise the USAR Table 8.3-7 for completeness.

The licensee evaluated the above discrepancies by verifying that either the items were

currently being reviewed under an existing PIF or a new PIF was issued. The licensee

issued new PIFs 97-0343,97-0350,97-0395, and 97-0500 to document those items not

captured in the corrective action system.

The licensee had not yet corrected the above discrepancies or updated the USAR to ensure that

the USAR contained the latest information, as required by 10 CFR 50.71(e). Consequently, the

team identified this issue as URI 50-440/97-201-15.

E1.3 Emereency Closed Cooline (ECC) System

El.3.1 System Description and Safety Function

The safety function of the ECC system is to provide a reliable source of cooling water to safety-

related components during and after transient and/or accident conditions. These components

include the control complex chillers: residual heat removal (RHR) pump seal coolers; low-

pressure core spray (LPCS), and RCIC pump room unit coolers; and hydrogen analyzers.

Other ftmetions of the ECC system are to supply cooling water to served components during hot

standby, normal shutdown, and plant testing modes of oper ation and, if required, provide cooling

water to the fuel pool heat exchangers following a DB A, if required.

l

l

! 27

. .

The ECC system is a closed, intermediate cooling water system consisting of two redundant,

independent loops designated as loops A and B. The primary components of each loop include a

pump, heat exchanger, surge tank, MOVs, and interconnecting piping. A chemical addition tank

is shared by both loops. The ECC heat exchangers are cooled by the ESW system. The

components served by each ECC loop are as follows:

Loop A Loop B

LPCS Pump Room Cooler RIIR Pump B Room Cooler

RCIC Pump Room Cooler RHR Pump B Seal Cooler

RHR Pump A Room Cooler RHR Pump C Room Cooler

RHR Pump A Seal Cooler RHR Pump C Seal Cooler

Hydrogen Analyzer A Cooler Hydrogen Analyzer B Cooler

Control Complex Chiller A Control Complex Chiller B

Each ECC pump takes suction on its loop suction header and discharges through the shell of an

ECC heat exchanger to the system loads. After serving the system heat loads, the warmed ECC

water returns to the pump suction. The surge tank ensures that an adequate pump suction head is

available and facilitates system fill and makeup. The ECC system is not normally in operation and

is designed as a standby system. A LOCA or loss of offsite power (LOOP) signal automatically {

starts both ECC pumps, repositions valves to supply ECC water to the control complex chillers,

and isolates the normal, nonsafety-related cooling water supply to the control complex chillers.

The ECC system is designed to perform its required cooling function following a DBA, assuming

any single active or passive failure and LOOP and is protected to withstand the efTects of natural

phenomena including earthquakes and tornadoes. The system is classified as Safety Class 3 and

Seismic Category I, except for its portions that are associated with the chemical addition tank and

piping downstream of vents and drains.

El.3.2 Mechanical

El.3.2.1 Scope of Review

The mechanical design review of the ECC system included design and licensing documentation

reviews, system walkdowns, and discussions with the cognizant system and plant design

engineers. The team reviewed applicable portions of the USAR and TS; the SDM section;

process flow diagrams and other drawings; 12 calculations; 8 DCPs; system operating, inservice

and surveillance test procedures; CRs; PIFs; and operating experience reviews (OERs). The

scope of the review included verification of the appropriateness and correctness of design

28

_ _ . _ . _ _ -_ _ _ _ _ _ _ . .._

. .

assumptions, boundary conditions, and system models; confirmation that design bases are

according to licensing bases; and verification of the adequacy of testing requirements.

Specific topical areas covered during the mechanical design review include system

thermal / hydraulic performance requirements (e.g., heat removal capacity, pump and system

cmves, and pump NPSH); system design pressure and temperature; overpressure protection;

surge tank design parameters; component safety and seismic classifications; component and piping

design codes and standards; and single failure vulnerability.

El.3.2.2 Findinus

.

!

The team verified that each loop of the ECC system was capable of removing the design heat

loads from served safety-related components during and following a DBA. The system appeared I

to have adequate flow and heat transfer margins to accommodate future equipment degradation,

as evidenced by the difTerence between the required and designed flow rates (1820 gpm versus

,

'

2300 gpm) and the current position of valves that are throttling ECC flow to served components. i

The safety classifications and specified codes and standards were appropriate. The design i

pressures and temperatures specified for piping and components, and the provided overpressure j

protection features were adequate. Complete independence of the two ECC loops was verified j

i

'

where no single active or passive component failure would prevent the system from performing its

safety function. However, the team identified USAR clarity and inconsistencies in the manner in

which passive failure was defined. Specifically, USAR Section 1.2.1.2 item I indicates that

j

passive failures only apply to electrical failures. Whereas, USAR Section 6.3.2.6 refers to passive

.

failures as valve stem and pump packing failures. Clarity is needed to define what is the Passive

Failure Design. The licensee is addressing these inconsistencies in PIF 97-0566, and the matter is

'

designated as IFl 50-440/97-201-16. ,

i

The system design documents reviewed by the team adequately support the design and licensing

bases, except for the discrepancies and open items discussed in the following paragraphs.

1

a. Surge Tank Emergency Makeup Design Basis

4

USAR Section 9.2.2 currently states that the ECC surge tanks are designed to maintain a 7-day

i supply of water, with normal system leakage, without the need to provide makeup water.

Expected normal system leakage is stated as 0.5 gallons per hour (gph) from pump seals and valve

stem packing. However, an event that occurred in 1993, as reported in Licensee Event Report

.

(LER)93-021, identified a previously unrecognized post-accident leakage path from the ECC

system. This path would be through closed valves P42-F295A,B and P42-F325A,B that isolate

the ECC system from the nonsafety-related nuclear closed cooling (NCC) system following a

DBA. The NCC system is the normal cooling water source for the Control Complex chillers.

whereas the ECC system cools the chillers afler an accident. The licensee has established

!

allowable leakage limits for the subject va!ves at 3.0 gpm for ECC Loop A and 3.5 gpm for Loop

B, derived in Calculation P42-24," Maximum Allowable Leakage from P42 System," Revision 1.

29

.

- ._

,

. .

These limits are on the basis ofoperator action taking place within 30 minutes afler the DBA to

manually initiate emergency makeup to the surge tanks from the ESW system. Without this

makeup, the surge tanks would empty, NPSH for the ECC pumps would be lost, and the ECC

system would be disabled.

In compliance with 10 CFR 50.59, the licensee prepared Safety Evaluation 96-128, dated October

10,1996 to evaluate the USAR and procedural revisions associated with the change in the surge

tank sizing basis from a 7-day supply without necessary makeup to a 30-minute supply. The

safety evaluation was also used as a basis for the use-as-is disposition of PIF 96-2846, associated

,

drawing change notice (DCN) 5541, and USAR change request (CR)96-150. The safety

evaluation concluded that the change did not constitute an unreviewed safety question, primarily

4

because of the licensee's belief that the modified design continued to satisfy the review procedures

! stated in SRP Section 9.2.2, Part III, which states:

"The system is designed to provide water makeup as necessary. Cooling water

systems that are closed loop systems are reviewed to ensure that the surge tanks

have sufficient capacity to accommodate expected leakage from the system for

seven days or that a seismic source ofmakeup can be made available within a time

frame consistent with the surge tank capacity (time zero starts at low-level

alarm)."

,

Overall, Safety Evaluation 96-128 was comprehensive and well written. However, the team's

'

review of the safety evaluation identified a number of concerns that, collectively, caused the team ,

to challenge the conclusion of the safety evaluation, as described below: l

Multiple operator actions would be required to read the local surge tank level gauges (at

30 minute intervals), locally open valves P45-F508A,B to establish makeup flow from the

ESW system, and subsequently close those same valves if the surge tanks have completely

filled with water and are overflowing. Within the first 90 minutes after a DBA, the

licensee calculated that total operator radiological exposure would be about 12 rem. The

cumulative operator exposure over the entire duration of the accident was not calculated.

'

NUREG-0737, item II.B.2, " Design Review of Plant Shielding and Environmental

Qualification of Equipment for Spaces / Systems Which May be Used in Post-Accident

i Operations," establishes the guidelines of GDC 19, " Control Room", as the dose rate

criterion to be applied for vital areas that are infrequently accessed under post-accident

conditions. This criterion is 5 rem whole body, or its equivalent to any part of the body,

for the duration of the accident. Therefore, a minimum of three separate operators would

be needed to carry out the required actions for the first 90-minute period without

exceeding the GDC 19 dose criterion.

The safety evaluation did not adequately assess the potential for operator error (omission

or commission). It discounted the possibility of operator error, primarily because of the

simplicity of the required actions and operator familiarity with the required activities.

'

,

30

. .

4

However, working conditions immediately following a DB A would be stressful, and there

is no emergency lighting in the areas where actions would be required, necessitating the

use of portable light sources. Thus, the team considered a single-operator error to be

credible. The licensee stated that a single- operator error would result in the failure to

provide makeup to only one surge tank. The licensee does not consider credible the

postulated failure of the operator to provide makeup to both surge tanks, even though a

single procedural step covers filling both ECC surge tanks.

The safety evaluation did not address the potential for surge tank overpressurization when

makeup from the ESW system fills the tank water-solid. The probability of this occurring ,

is increased, since the operator would'open the makeup valves and then leave the surge l

tanks untended and unmonitored for at least 30 minutes. Preliminary licensee calculations l

indicate that the maximum makeup water flow rate from the ESW system is approximately

117 gpm, resulting in a surge tank pressure of about 4 psig. This exceeds the surge tank

atmospheric design pressure, but will not exceed the maximum pressure retaining 1

capability of the tank, as calculated by the licensee. Therefore, the surge tank will not fail I

as a result of filling it water-solid with makeup from the ESW system.

The safety evaluation cited American National Standards Institute /American Nuclear

Society (ANSUANS) 58.8-1984, " Time Response Design Criteria for Nuclear Safety-

Related Operator Actions," as the basis for choosing the 30-minute operator action time, I

although the safety evaluation notes that Perry is not committed to meet this standard.

However, not all of the provisions of the standard have been met regarding safety-related

operator actions taken outside the control room:

1

'

-

No emergency lighting is provided in the two separate areas where the operator

must read the local surge tank level gauges or manually operate the ESW makeup

valves. The use of portable light sources is required.

1

-

No safety-related surge tank level indication is provided in the control room to

inform the operator that actL,n is needed or to provide ir. formation and feedback

regarding the success of performed actions. The hign/ low surge tank annunciators

that are provMed '. ine control room are not safety related and cannot be relied

upon to provide valid post-accident information. The surge tank level will only be

known at 30-minute intervals when an operator is dispatched to read the local-

level gauges.

The team also reviewed the plant's original SER (NUREG-0887), dated May 1982, and noted

that NRC acceptance of the ECC system design appeared to be dependent (in part) on the ability

to initiate ESW makeup to the surge tanks by manual action from the control room. This SER

31

_

. .

I

cceptance was consistent with information presented in the Perry Final Safety Analysis Report

(FSAR) at that time, which stated:

"This is a remote manual function requiring operator action in the control room."

In FSAR Amendment 17, dated March 6,1985, still before receipt of the operating license, the

FSAR was revised to indicate that initiating surge tank makeup from the ESW system was locally

performed. Subsequent SER supplements did not specifically address this change.

.

On the basis of the reviews described, the team concluded that the change to the ECC surge tank

sizing basis from a 7-day supply to a 30-minute supply, with operator actions required outside of {

the control room to initiate makeup from the ESW system, may constitute an unreviewed safety '

question, as defined in 10 CFR 50.59, because it--

Increases the probability of an occurrence of a malfunction of equipment important to

'

safety. Reliance on operator action at 30 minutes afler the accident, under stressful and

hazardous working conditions, increases the probability that the operator will not correctly

perform the required actions.

,

> +

Increases the consequences of an accident. Total cumulative operator exposure has

increased by 12 rem, and the potential exists that an individual operator's exposure may

exceed the GDC 19 limits specified by NUREG-0737, Item II.B.2.

.

This issue was reviewed by NRR technical staff who also determined that a potential unreviewed I

safety question existed. This item is designated as URI 50-440/97-201-17.

The team identified several additional deficiencies that were also related to the licensee's Safety

Evaluation 96-128. The flooding analysis performed for surge tank overflow used a non-

conservative flooding rate of 60 gpm, on the basis of the minimum calculated ESW makeup flow

to one ECC surge tank. The team noted that since the operating procedures would direct the

i operator to initiate ESW makeup to both tanks, the flooding rate should consider the flooding of

l both tanks (i.e.,120 gpm). The licensee issued PIF 97-0406 to address this discrepancy.

Ilowever, the team also pointed out that if the ESW makeup flow rate was calculated using

assumptions that maximized rather than minimized the flow, the flooding rate would be higher.

Preliminary calculations by the licensee determined a maximum ESW makeup flow rate to each

surge tank to be 117 gpm, or a total flooding rate of 234 gpm. 10 CFR Part 50, Appendix B,

Criterion III, " Design Control," requires that licensees correctly trar.. late the design bases into

specifications, drawings, procedures, and instructions. The team concluded that the licensee's use

of the non-conservative flooding rate in Safety Evaluation 96-128 failed to meet this requirement.

~

Consequently, the team identified this failure as URI 50-440/97-201-18.

'

32

. ,

USAR Section 9.2.2.2 (page 9.2-24) states that, "In the event that demineralized water makeup

does not automatically fill the surge tank, a low-level indication with an alarm is annunciated in

)

the control room to indicate that operator attention is required." Similarly, USAR Section 9.2.2.5

(page 9.2-12) states that "The surge tanks have high- and low-level indication." The actual  :

design includes only a level alarm in the control room with level indication local at the tank. The

team considered these statements to be unclear and possibly misleading, since they could imply

that surge tank level indication is provided in the control room. These same statements were

made in the original FSAR. The licensee issued PIF 97-0469 to clarify that surge tank level

indication is only locally provided at the tanks.

b. Non-Conservative ECC Leak Rate Test Procedure

The team reviewed test procedure PTI-P42-P0008, Revision 1, "P42 Leak Rate Test Procedure."

The purpose of this procedure is to determine an approximate leakage rate through the valves that  ;

isolate the boundary between the ECC system and the nonsafety-related NCC system valves P42-

F295A,B and P42-F325A,B. The team determined that the procedure was not conservative

because the prescribed test conditions were not representative of post-accident ECC system

operation. The test differential pressure (approximately 60 psi) was one half of the value that the i

subject valves would experience after an accident. Additionally, the test pressure was bemg j'

applied in the reverse direction from normal accident conditions. The test procedure and

acceptance criteria did not adjust the leakage measured under test conditions to expected leakage .

under post-accident differential pressures. The licensee issued PIF 97-0578 to address these

l

concerns and their initial review determined that current valve leakage, when adjusted to account l

for the higher post-accident differential pressure, would still be acceptable (3.0 gpm for ECC ,

Loop A and 3.5 gpm for Loop B). The responsible system engineer also noted that a new l

surveillance procedure (SVI-P42-T2004) was currently being prepared that would correct the  !

deficiencies noted above.10 CFR Part 50, Appendix B, Criterion XI, " Test Control," and <

Criterion V, " Procedures" as implemented by the licensee's Operational QA Program, US AR

Section 17.2, requires that testing be performed in accordance with written test procedures which

incorporate the requirements and acceptance limits contained in applicable design documents. l

The team concluded that the existing ECC system leak rate test procedure failed to meet this  ;

requirement, and designated this failure as URI 50-440/97-201-19. l

l

c. ECC Pump Minimum Flow Requirement  !

During the review of design documentation, the team noted a discrepancy in values cited for the

minimum required ECC pump flow rate. ECC system operating procedure SOI-P42, Revision 7,

Section 2.0, stated a minimum flow value of 560 gpm; however, the Ingersoll-Rand certified

pump curve (PDB-B0002, Revision 1) indicated that the minimum required continuous flow was

800 gpm. The team was concerned that the pump was being allowed to operate at a minimum I

l

continuous flow rate that is less than that required by the pump vendor. The licensee issued PIF

l 97-0470 to address this concern. The licensee's investigation determined that the pump vendor's

technical manual specified a minimum flow equal to 25% of the best efliciency point or 575 gpm.

i

l

33

J

l

.

l

l

l. ,

1

The change from 800 to 575 gpm was previously evaluated in 1990 in CR-90-106, and PIF 97-

0470 identified appropriate changes to the design documentation and operating procedures.

Resolution of this issue should occur through PIF 97-0470 corrective action resolution.

l

Consequently, the team identified this issue as IFI 50-440/97-201-20. '

d. IIcat Exchanger Tube Thickness and Heat Transfer Coefilcient

Calculation P42-33, " Evaluation of Heat Transfer Coeflicient and Minimum Required Wall

Thickness for ECC Heat Exchangers IP42-B0001 A/B," Revision 0, dated May 1,1996,

evaluated the minimum wall thickness required for the tubes of the heat exchanger. In particular, ,

the licensee based the calculation on acceptance criteria consistent with the ASME B&PV code, I

and established the minimum overall heat transfer coeflicient on the basis of the fouling factor and l

the number of tubes being plugged. The team reviewed the calculation for the minimum wall

thickness determination and sampled the input data used in the heat transfer computer model and

identified the following concern:

Calculation Section 5, " Method of Analysis," considers the heat exchanger as a

pressure vessel and concludes that the rules of ASME B&PV Code,Section VIII,

are applicable. This code selection conflicts with the manufacturer's heat

exchanger specification sheet that indicates the ASME code requirements as

ASME Section III, Class 3. The ASME Form N-1, N Certificate Holders Data l

Report for Nuclear Vessels identifies the applicable ASME Code asSection III, l

1974 Edition, Winter 1975 Addendum, Class 3. The calculation provided no '

technical basis tojustify the use of ASME Section VIII criteria for an ASME

Section III component. PIF 97-0531 documents this condition and a comparison

between the criteria of Sections Ill and Vill. This review indicated Sections III

and VIII use the identical code methodology and the calculation results are

unchanged. The team concluded that the review and approval of this calculation

with reference to inappropriate construction codes without technicaljustification

represents a weakness with respect to 10 CFR Part 50, Appendix B, Criterion III,

" Design Control." Consequently, the team identified this item as URI 50-440/97-

201-21.

c. Evaluation of ECC IIeat Exchanger Test Performance

Calculation P42-31,"ECC A Heat Exchanger Test Results-1995," Revision 0, dated

September 15,1995, evaluates the test data recorded during performance of PTI-P42-P001 on

August 10,1995, to assess measurement uncertainty associated with data acquisition and

analytical methods. The team's review of this calculation identified the following concern:

,

Section 3, " Assumptions," identifies two open assumptions, one assumption

i requires the test data /results be confirmed via test document acceptance signatures

and the second as.lumption assumes test instrumentation to be within calibration

34

. .

limits. Post-test calibration was specified to confirm this second assumption. The I

team noted that this calculation was used as the basis for equipment operability

evaluations and outstanding assumptions, open for 18 months, could affect the

conclusions. The tbam requested information on how these calculations were

controlled to ensure that open assumptions are verified and closed. At the request

of the team, the licensee pursued the status of Calculation P42-31 open

assumptions and found that the post-test calibration indicated that the

instrumentation for 1 of 8 temperature measurements on both the ECC inlet and

outlet were out of calibration. The licensee indicated that Engineering should have

been notified via memo that the test instrument was out of calibration at the .

completion of the post-test calibration. However, no documentation of such

notification was evident. Calculation P42-31 was re-evaluated on the basis of the

)

remaining valid instrumentation readings, with only a minor difference in the l

results attributable to the small error in the measurements and the statistical

methods used. PIF 97-0543 documents the concern with calculation with open

assumptions and includes a panial listing identifying 44 calculations with

unconfirmed assumptions. Identified calculation titles indicate that at least 13 of

these calculations involve equipment performance testing, including Division I and

Iljacket water heat exchanger testing in 1994. Other calculations appear to  !

involve equipment qualification, sizing, and modifications. The team concluded I

that the issues oflong-term unconfirmed calculation assumptions and failure of the

post-test calibration to alert Engineering to instrumentation that is out of '

calibration represent weaknesses with respect to 10 CFR Part 50, Appendix B,

Criterion III, " Design Control." Consequently, the team identified this issue as

URI 50-440/97-201-22.

El.3.2.3 Conclusions

The team concluded that the mechanical design of the ECC system was generally acceptable, and

the system was capable of performing its safety fimetion with operator intervention. However,

the team also concluded that the safety evaluation associated with a change in the design bases for

the ECC system surge tank, from a 7-day supply to a 30-minute supply which relied on extensive

use of early manual operator intervention, was inadequate. The resultant change to the USAR

effectively changed the plant from that described in the USAR. Because the change resulted in an

increase in the potential for failures not previously analyzed and an increased in accident

consequences the NRC determined that a potential USQ exist and NRC approval was required

(50-440/97-201-17).

The flooding rate determined by safety evaluation 96-128 and supponing calculation to be

acceptable used non-conservative values (50-440/97-201-18). Mechanical modifications that

were reviewed by the team were appropriate for resolving the identified problems, and the

modifications did not change the design bases of the system. However, the temperature control

valve modification was not totally effective, as discussed in Section El.3.5 of this report. Other

i

35

.

__ _ - -_. _.

. .

i

l

l

l deficiencies identified during the team's review of design documentation included a non-

conservative test procedure for determining ECC system leakage (50-440/97-201-19);

inconsistent design information regarding the ECC pump minimum flow requirement (50-440/97-

l

201-20); inappropriate code references for heat exchanger evaluations (50-440/97-201-21); and ;

issues of unconfirmed calculation assumptions and test control (50-440/97-201-22).

l

The licensee initiated actions to address these items through their condition reporting and '

corrective action program.

1

El.3.3 Electrical

El.3.3.1 Scooe of Review

The team reviewed the electrical design for normal and emergency operation of the ECC system,

selected MOVs, circuit breakers, fuses, and interlocks. The team also compared the design

drawings to the SDM, applicable sections of the USAR, and TS to verify consistency in the

documents. In addition, the team reviewed the calculations related to voltage drop, electrical

loading, and coordination for selected ECC components and associated electrical components to

determine the adequacy of the available voltages, equipment loading, protective system

coordination, and electrical isolation and independence.

El.3.3.2 Findings

The team verified that the ECC system was powered from a r.eparate emergency power bus and

that the electrical loading of the individual components had been considered in the emergency

diesel generator Division I and II capacity calculations. The sequence and timing ofloading of

ECC pumps and valves onto the respective EDG was consistent with the USAR.

The team determined that the electrical design requirements were appropriate and consistent in

the reviewed documents. No unacceptable conditions were identified during this review.

El.3.3.3 Conclusions

The team concluded that the electrical design of components that perform engineered safeguard

functions of the ECC system was adequate and operating within the design limits.

El.3.4 Instrumentation and Controls (I&C)

El.3.4.1 Scope of Review

The team evaluation of the ECC I&C consisted of design documentation reviews, interviews, and

a walkdown of the ECC system. The review concentrated on protective functions to provide

nuclear safety-related components with a reliable source of cooling during and after a

!

l

i 36

, ,

i

LOOP /LOCA or LOCA. The design was assessed for the ability to meet USAR commitments

and to operate within TS limits. Attributes reviewed comprised ofinstrument installations,

instmment setpoints, instrument power and AC and DC control power provisions, and remote and

altemative shutdown provisions. Documents reviewed included applicable sections of USAR

Chapters 1, 3, 5, 6, 7, 8 and 9; TS, the SDM, vendor documents; P&lDs; logic diagrams; I

electrical wiring diagrams; instrument installation drawings; calculations; calculation change

records; PIFs; ARs; CRs; NRs; and DCPs. ,

l

El.3.4.2 Findings

a. Remote Shutdown Design

The team reviewed the provisions made in the design of the ECC system to operate the system

from outside the control room if the control room had to be vacated. Division A was designated

as the remote shutdown division. Division B was designated as the alternate remote shutdown

division. The ECC system is required for safe shutdown of the reactor. The controls of the

Division A ECC pump can be transferred to the remote shutdown control panel. The transfer

scheme included transferring an alternate source of control power to the ECC pump breaker. The

controls for the Division B ECC pump did not have provisions to transfer control to the

alternative remote shutdown control panel. The pump must be started manually using the control

switch at the ECC pump breaker. No provisions were made to provide an alternate source of ,

control power for the Division B pump controls. The PPNP Appendix R requirements allow 72 l

hours for repairs to be conducted utilizing only onsite resources for alternate remote shutdown. j

The design corresponded to that described in the PNPP Appendix R safe-shutdown analysis.

1

None of the ECC system valves for lining up the system flows and isolating the ECC system from i

the nuclear closed cooling (NCC) system, other non-divisional systems or separating the two j

divisions had provisions for transferring their control out of the control room to the remote and !

alternate remote shutdown control panels. The repositioning of these valves is procedurally i

controlled. Operators manua!!y deenergize and realign these valves as required. The Appendix R

analysis and the respective procedures were reviewed to verify the inspection observation. The

specific tasks to be performed to manually position the valves were reviewed. Extensive operator

action was required to realign the valves. The valves appeared to be accessible from the floor

level without using ladders. Normal lighting in the area was sufficient for operators to execute

their required task.

b. Surge Tank Low-Level Alarm Setpoint

Calculation P42-5," Emergency Closed Loop Cooling Water System Surge Tank Sizing," was

issued to verify that the surge tank had sufficient capacity to accommodate the water expansion

within the ECC system and to determine the capacity of the surge tank at the low-level setpoint

compared to the original design requirement of 250 gal. The calculation used a setpoint value of

667 feet,9 inches, taken from the Master Setpoint List. Calculation P42-T04," Emergency

37

_ _ _. _ .__ _-. .

. .

!

Closed Cooling Surge Tank Level Hi/Lo Alarm," calculated the uncertainties associated with the

j level switches that actuates the alarm. P42-T04 referenced Magnetrol Drawing D119-03 for the

l

setpoint values and noted that the setpoint and reset values are fixed and set at the factony. P42-

T04 gives different values from P42-5 for the setpoints of 667 feet,6.75 inches, for tank A and

l 667 feet,7.875 inches, for Tank B. The difTerence between the two numbers was attributed to a

difference in the elevation of the tanks. The difference from the setpoint value in P42-5 was not

explained.  ;

The licensee issued PIF 97-0540 to address the above setpoint value disagreement.

)

i

El.3.4.3 Conclusions 1

I

The Perry Appendin R resolution for remote shutdown ability, made extensive use of manual

operator action a feature of their design. Calculation P42-5 incorrectly referenced the setpoint list

as the source document for the low-level setpoint value.

El.3.5 System Interfaces

El.3.5.1 Scope of Review

The team selected the following systems that interface with the ECC system and verified that the

interfacing system design information for supporting the function of the ECC system was i

appropriately considered; the ESW system which supplies cooling water to the tube side of the

ECC heat exchangers, provides emergency makeup to the ECC surge tanks, and cross-ties to the

Unit 2 ECC system piping to provide cooling water to the fuel pool heat exchangers following an

accident; the NCC system which provides normal cooling water to the Control Complex chillers

and the fuel pool heat exchangers; and the Two-Bed Demineralized Water System which provides

normal makeup to the ECC surge tanks.

In addition to reviewing the interfacing system design information for the above systems, the team

examined installation of the interfaces during the ECC system walkdown.

'

El.3.5.2 Findings

System interfaces were generally acceptable and consistent with the ECC system design and

licensing bases, except for the items discussed in the following paragraphs.

a. ECC Temperature Control During the Winter

Under accident conditions LOCA and/or LOOP), the ECC system supplies cooling water to

l control complex chillers A and B. These chi.'ers represent approximately 90% of the ECC system

heat load during accident conditions. The cooiing water supplied to these chillers mus: be

l maintained above 55'F to prevent the chillers from tripping because of a low refrigerant

38

.

.

.

.

- .

,

l \

, ,

l

,

' i

temperature. The ECC system heat exchangers are cooled by the e5 W system that draws water

l

directly from Lake Erie. I

1

As previously reported in LER 94-005, in the winter, when the lake water was cold and the heat

l loads on the ECC system were low (i.e., the system was operating to support surveillance

l testing), the ESW system flow to the ECC heat exchangers overcooled the ECC system below

55'F. This could have caused both control complex chillers to trip. It should be noted that this

condition would not have occurred during post-accident ECC system operation, when maximum

heat loads would be imposed on the system. In response to this event, the licensee installed a

temperature control valve (TCV) in each ECC loop (reference DCP 94-0027). This three-way

l TCV causes ECC flow to bypass the heat exchanger, as necessary, to maintain ECC system

temperature above 55*F with minimum heat loads on the ECC system.

Recent experience, as documented in PIF 96-1265, indicates that the TCV modification has not

been totally effective. Because of the configuration of the heat exchanger bypass piping,

previously unrecognized heat transfer phenomena result in the cooling of the ECC water even

when the ECC flow totally bypasses the heat exchanger. To :ompensate for this marginal design

modification, administrative controls had to be reinstated to limit ECC system operation under

minimum heat load (i.e., surveillance testing) conditions, thereby placing a burden back onto the

i

operators. In addition, because the ECC system temperature element is located on the ECC heat

exchanger discharge pipe and in close proximity to the heat exchanger outlet (as confirmed during

the system walkdown), the measured temperature can be significantly influenced by the same heat

transfer phenomena noted above and does not always represent the true ECC system temperature.

If the ECC system is idle and the ESW system is operating, the ECC temperature element may

give a false low-temperature alarm in the control (the alarm setpoint is 60*F). This is a nuisance

alarm that diverts the operator's attention and is meaningless when the ECC system is not actually

operating.

As previously noted, the ability of the ECC system to perform its safety-related function is not

impacted by these temperature control deficiencies since the expected post-accident heat loads

would maintain system temperature above 55 F. The licensee has recognized the temperature

control shortcomings and has planned several actions to address them. These include the

performance of tests to better understand the heat transfer phenomera involved and to determine

the feasibility of operating the control complex chillers at lower ECC condenser inlet temperatures

that would allow a lowering of the ECC low-temperature alarm setpoint. The team found these

actions appropriate and did not have any further questions.

b. Cross-Tie Between Unit 1 ESW and Unit 2 ECC Systems

The Unit 2 ECC system was originally designed to supply safety-related cooling water to the

common fuel pool cooling and cleanup (FPCC) system heat exchangers following a DBA. Since

l Unit 2 is not operational, piping cross-ties were insta!!ed between the Unit 1 ESW system and the

Unit 2 ECC system such that the Unit 1 ESW system can supply safety-related, post-accident

l

l 39

_ ._

. .

1

cooling water to the FPCC heat exchangers. As noted in USAR Section 9.2.2.6, manual actions

are required at greater than 10 minutes following a DBA to establish the ESW-to-FPCC system

alignment. The team reviewed Section 7.5 of system operating instruction SOI-G41, " Fuel Pool

,

Cooling and Cleanup System," which identifies these manual operator actions. The team noted

that the procedure calls for the venting of certain ECC piping and the FPCC heat exchangers to

eliminate voids that could result in water hammer when ESW is admitted to the Unit 2 ECC

system piping.

l

The team questioned whether post-accident operator radiological exposure during the

'

performance of the venting activities had been assessed by the licensee in accordance with

NUREG-0737, Item II.B.2. The licensee responded that a dose assessment had not been

performed; however, PIF 97-0248 has recently been issued to generically address the lack of dose

assessment and specified operator travel paths for all accident mitigating actions required by plant 3

procedures. Proper disposition of this PIF should satisfy the guidance given in NUREG-0737. l

This licensee identified item did not appear to be willful, was not reasonably preventable by

previous corrective actions, and should be corrected in a reasonable time frame commensurate

with the requirements of the licensee's corrective action program. Followup of the licensee's

resolution of these deviations from commitments, stated in USAR Section 12.6 and Appendix 1 A, j

to satisfy NUREG-0737, item II.B.2. is identified as URI 50-440/97-201-23.

El.3.5.3 Conclusions

The design of the ECC system interfaces was generally satisfactory and supported performance of

the ECC system safety functions. Two concerns that do not affect the capability of the ECC

system to perform its safety functions (ECC temperature control and post-accident vital area

access assessments) were identified by the team. The licensee has previously been aware of these

concerns and is taking actions to address them (50-440/97-201-23).

El.3.6 System Walkdown

l

El.3.6.1 Scope of Review

1

The team performed a walkdown of selected portions of the ECC system. Piping and mechanical

components, piping interfaces with the ESW system, and installation ofinstrumentation and

electrical components were examined to verify consistency with plant drawings. Particular

attention was directed to the location and arrangement of the surge tanks, their associated piping

4

(makeup and venting), and level instrumentation to confirm the acceptability of the post-accident

operator actions described in Section El.3.2.2 of this report. The team also visited the control

room to examine instruments and displays used to monitor ECC system operating status.

'

40

. _ _ _ _ _ _ _ _ - . . .- .- - .

. .

j

i

El.3.6.2 Findings

The material condition of the system and general housekeeping appeared to be good, and no cases

were noted where the system configuration deviated from design or licensing documents. Other

specific observations are discussed below.

a. Sanitary Drain Pipe Installation

The team noted that a 4-inch, cast iron sanitary drain pipe traversed the area above the ECC

i

Loop B pump and associated piping and valves. This drain pipe was supported primarily by )

'

i threaded rod hangers, one ofwhich was observed to be missing. The team questioned the ability i

of the drain piping support system to withstand a seismic event, since its failure could result in the

.

pipe falling and damaging the ECC pump and/or pump motor. The licensee confirmed that the

drain piping had been seismically analyzed in Calculation 36:01.3.2.1.5, " Control Complex El.

) '

574-10 Nonsafety Sanitary Floor Drains Seismic Support." Review of this calculation indicated

that the drain piping was adequately supported and restrained such that it would not fall, and that i

the leaded bell and spigot pipejoints would not separate in a seismic event. The licensee issued i

PIF 97-0455 to evaluate the impact of the missing rod hanger and determined that the piping and

its supports remained capable of sustaining a seismic event without falling down with the support

missing. The PIF also directed that the rnissing support be re installed as a maintenance item.

The team had no funher questions with thi issue.

b. Surge Tank Installation and Arrangement

The ECC surge tanks are located at Elevation 665'in the Intermediate Building. The walkdown

confirmed the following items regarding Safety Evaluation 96-128, as discussed in

i

Section El.3.2.2 of this report:

Valves P42-F578A,B in the ESW makeup lines to the surge tanks are locked open as

indicated on drawing D-302-621, the ECC system P&ID.

'

The local surge tank level gauges are approximately one foot above floor level and read in

inches of water level from the tank bottom (verified by the system engineer). The gauges

,

do not have any markings to indicate the normal tank level range or the high/ low alarm

levels.

Should the surge tanks overflow out the vent pipes, the water would discharge directly

onto the top of the tanks, run down the tank sides onto the floor and then to the floor

drain.

ESW makeup valves P45-F508A,B, which the operator must open to initiate emergency

surge tank makeup following an accident, are at Elevation 599' in the Intermediate

Building and are readily accessible from floor level.

41

._ _ .__ .. . _ . _ _ _ _ . _ . _ . . _ . . . _ _ _ _ _ _ _ _ _ _ . _ _ _ , _ _ . . _

l

., .

No emergency lighting battery packs were observed at either the surge tank or ESW

makeup valve locations.

El.3.6.3 Conclusions

l

The system flow diagram was consistent with the as-built system. The surge tank installation and

arrangement are consistent with system drawings and with the descriptions presented in the

l- licensee's 10 CFR 50.59 Safety Evaluation 96-128 (see Section El.3.2.2 of this report). The

l

licensee adequately addressed the observed missing drain piping support and concluded that there

was no impact on ECC system operability.

!

El.3.7 USAR Review

The team reviewed the appropriate USAR sectinns for the ECC system, as well as the associated

electrical and I&C-related sections. The team identified the following discrepancies in the USAR:

USAR Table 3.9-30 lists active valves not associated with the nuclear steam supply system

(NSSS). This table has not been updated to reflect several ECC system modifications.

Valves P42-F315A,B,C should have been deleted from the table, since they were

converted from automatic to manual valves by DCP 92-0060. Valves P42-F550 and P42-

F551 should have been added to the table, since they were converted from manual to

automatic valves by DCP 90-0012. The licensee issued PIF 97-0512 to address these

US AR inaccuracies.

'

i

USAR Tables 9.2-18 (ECC Pumps) and 9.2-19 (ECC Heat Exchangers) list two different

values for ECC system operating flow rate (1860 versus 1820 gpm). Since all pump flow i

is delivered to the heat exchanger, the two values should agree. The licensee issued PIF

97-0469 to address this discrepancy. Pending resolution, the team identified these USAR

discrepancies as another example of URI 50-440/97-201-15.

El.4 Desien Control

'

.

E.1.4.1 Scoce of Review

The licensee's Design Control Process to satisfy 10 CFR part 50 Appendir B Criterion III as

described in Section 17.2.3 of their USAR, as it related to this inspection was reviewed.

Implementation of the licensee's commitments to ANSI- N45.11 were also evaluated.

42

_ __ -

s e

1

E.1.4.2 Findings I

a. Control of Calculations

i

Nuclear Engineering Instruction (NEI) 0341, Revision 5, " Calculations," applies to all

calculations to establish design bases or to change design documents. Paragraph 6.2," Calculation

Revisions," states that design engineers are to monitor calculations to determine if a revision is

required (e.g., receipt of new/ revised design input, confirmation of assumption). Paragraph 6.3,

" Review and Approval," states that verification / review and approval of calculation should precede

use of the results for design, but must be completed prior to the component, system, or structure

l

being declared operable. If necessary, provide suitable means to ensure operability is not declared l

prematurely. Contrary to the above requirements, the licensee has modified various systems as

reflected in design drawings and did not update or revise the calculations:

i

+

Electrical drawing D-206-029, " Electrical One- Line Diagram, Class IE,480-V

Bus EFID," Revision BB, identified the installation of a 10-hp electric motor for

compressor 1E22-C004A. Calculation PRMV-0017 "EHF-1-E Transformer Breaker

EH1305," Revision 0, did not list the compressor motor. The licensee generated PIF 97-

500 to document and resolve this issue and various other calculation discrepancies.

USAR Table 8.3-1 also did not correctly identify the motor loads. In light of the above

discrepancies, Engineering performed an operability evaluation on bus EHF-1-E

transformer breaker EH1305. As a result of this evaluation, Engineering concluded that,

although the revised estimate of 52.6 FLA is greater than 41.5 FLA (on the basis of 4

287 amp inrush as opposed to 251-amp inrush), sufficient margin exists between these

estimated values and the actual 50/51 relay settings. Therefore, operability of breaker

EH1305 is not a concern. Calculation PMRV-0017 was last updated on March 11,1985

(12 years ago), and does not reflect the current plant loads and settings.

Calculation PSTG-0003 "480-V Safety-Related Motor Starting Voltage Drop,"

Revision 2, dated June 29,1995 (page 6), contains an open assumption that required

confirmation. Calculation PSTG-0001,"PNPP Auxiliary System Voltage Study,"  ;

Revision 2, approved on August 24,1995, provided the information to resolve the open

assumption. Although the calculation to close the open item was completed, Calculation

PSTG-0003 remained for approximately I and % years with an open assumption

identified. PIF 97-0497 documents this discrepancy.

System," Revision 0, dated April 8,1991, did not address Division liI HPCS pump

IE22C001 breaker EH1304 spring charging motor load at t=0 second, the load profile for

0-1 min for continuous (L2) load, and the DC control circuit loads (L2 loads) of the

breakers. PIF 97-0511 was written by the licensee to address these concern.

43

. _ __ _ _ _ _ _ . . ._ . . _ . __. _ _ .

. .

Ca;culation FSPC-0020," Division III MON Fuse Sizing," Revision 1, dated April 2,

1996, proposes that the fuse size for MPL lE22F001 be changed from 5.6 amps to

3.2 amps and for IE22F004 be changed from 40 amps to 35 amps. Work Order 93-

0004009 replaced the 40 amp fuse on June 30,1994, in accordance with DCP 93-082.

However, the 5.6 amp fuse is stili not replaced by a 3.2-amp fuse. The team considers this

an example of calculation inconsistent with the as-built conditions without reconciliation

of the disparities. The licensee issued Fuse Size Change Requests 97-0001 to document

the need for fuse change-out to the correct size. This approach was found acceptable to

the team since the incorrectly installed fuses would still provide adequate protection.

.

Calculation PRDC-0004, " Class IE DC Control Circuit Coordination," Revision 2, dated

May 30,1995, does not address switch #12 added to drawing D206-051, " Electrical Main

One-Line Diagram, Class IE DC System" Revision RR, dated May 15,1992, in

accordance with DCP 90-0012. The Drawing D206-051 is at current revision WW, dated

April 7,1996. PIF 97-0496 was issued by the licensee as a result of this team finding to

document the discrepancy.

Calculation PRLV-0004, "480-V Breaker Coordination," Revision 2, dated April 30,

1996, was reviewed against associated electrical drawings D-206 series drawings for

480-V motor control centers (MCCs). Various discrepancies and typographical errors

were found between the calculations and the drawings as noted below:

MPL# Calculation PRLV-0004 Drawing D-206 series

IB21-F065A 6.6 HP 6.4 HP l

P42-F551 MISSING 0.13 HP

P45-D004A 7 HP 1 HP

P42F550 MISSING 0.13 HP

M25-C001B 100 HP 60 HP

IG33-F001 3.0 HP 3.9 HP

IM51-F615B 0.13 HP 0.125 HP

PIF 97-0494 was issued by the licensee to resolve the above deficiencies and

typographical errors. Engineering verified that the calculation is still valid for the

'

overcurrent protective devices of the 480-V switchgear breakers, and adequate protection

of the downstream equipment is still provided without premature tripping on short-time

demand. The fuse sizing for the revised loads will be reviewed as part of the PIF 97-0494

44

_

, .

disposition and will be addressed in Calculation FSPC-0018, Revision 1; Calculation SPC-

0019, Revision 1; Calculation FSPC-0020, Revision 1;"MOV Fuse Sizing," for Divisions

I, II, and III. l

The licensee had not performed a review to determine the extent of the above conditions as they

relate to other (similar) calculations. The licensee generated a generic PIF (97-517) to address  ;

calculation deficiencies in general for accuracy, completeness, level of detail, and consistency with

design drawings and the USAR. The team determined that these calculation control deficiencies

did not meet the licensee's 10 CFR Part 50, Appendix B, Criterion III, Design Control Program

as described in USAR Section 17.2 and identified this item as URI 50-440/97-201-24.

b. Design-basis Documents-Training Manual

The system description manual (SDM) for the ECC system (Revision 8) incorrectly states that the

ECC pump capacity is 2300 gpm at a design pressure of 150 psig. The correct pump rating is

2300 gpm at 130' total developed head (TDH), as shown on the certified pump curve (PDB-

B0002, Revision 1). Since the SDM is intended for training purposes, a PIF was not written, but

the system engineer planned to initiate an appropriate correction to the SDM.

c. Overpressure Protection

Calculation E22-2, " Overpressure Protection Analysis," Revision 0, dated February 23,1983,

performs an overpressure protection analysis on the ASME Section III, Class 2, portion of the

HPCS system. This evaluation was to ensure that no components within the system are subject to

pressures and temperatures beyond the design parameters of the components. The team reviewed

this calculation and identified the following concerns:

The overpressure protection analysis did not identify operating conditions under which

pressure relief devices are required to function including the relief capacity required to

prevent system components from being subjected to pressures exceeding code allowable

values. The maximum pressure considered for the suction piping is 31.25 psig whereas

the suction side reliefis set at 100 psig. Maximum discharge pressure considered was

1130 psig whereas the discharge side thermal relief valve is set at 1560 psig. HPCS pump

discharge piping is designed for 1575 psig so there is no concern with piping

overpressurization. Other concerns with HPCS pump discharge piping protection were

discussed in Section El.2.2.2.1 of this report.

.

Analysis of the maximum pressure to which the suction piping can be subjected is

contingent on the static head from the normal water level of the CST. This yields

nonconservative results by comparison to the maximum overflow level within the CST.

Further, the suction analysis does not evaluate other conditions such as post-accident

alignment from the suppression pool with consideration of containment overpressure, or

45

. .

1

conditions of back-leakage from the reactor pressure vessel (RPV), which may result in

pressurization of the suction line.

.

As the basis for system discharge pressure, the licensee considered a pump TDH at shutoff

of 2630 feet and did not consider coincident suction pressure. The pump TDH within the

calculation conflicts with the actual pump TDH at shutofrof approximately 3300' from l

Byron Jackson Test T-37225, Revision 1, dated February 7,1979. This test curve reflects

operation at 1780 RPM. Consideration of pump overspeed conditions will further

increase the pump TDH but was not included to ensure that no components within the

system are subjected to pressures beyond the values allowed by the code.

PIF 97-0426 documents the discrepancies noted above. The team concluded that the

methodology, system modeling, and review / approval were inadequate and did not satisfy the

licensee's 10 CFR Part 50, Appendix B, Criterion III, Design Control Program (USAR Section

17.2). Therefore, the team identified this issue as URI 50-440/97-201-25.

d. Inconsistent Pipe Size Calculation

The team identified an inconsistency regarding the size of a section of pipe located between valves

F010 and F001. Calculation E22-A, " System Pressure Drop /Line Sizing," states that the pipe size

is 12" but flow diagram D-302-701 and piping drawing D-304-701 call for a 10"line. The

licensee verified that 10" was the correct size and performed Calculation E22-6, "HPCS Pressure

Drop---Test Mode-CST-to-CST," Revision 0. The new calculation confirmed that using the

correct piping size in the calculation had a negligible impact on the calculated line losses and

therefore they did not intend to correct Calculation E22 A. This appeared to be an appropriate

resolution of the issue.

e. Document Discrepancies

During the review of design documentation, the team identified a number of document

discrepancies and inconsistencies, as itemized below. Although individual items are not significant

safety concerns and do not constitute operability concerns, collectively, they are indicative of

weaknesses in the design control program.

e.1 ECC Heat Exchanger Tubesheet I)rawing

The ECC heat exchanger tubesheet drawings 4549-22-140-1 and 4549-22-140-2 (both

Revision 0) were issued with the as-built tube plugging information missing. The licensee

issued PIF 97-0347 to address this deficiency. The system engineer confirmed that the

ECC heat exchangers do not have any plugged tubes.

46

, .

e.2 ECC P&lD

l

The ECC system P&lD, drawing D-302-621, Revision BB, had several deficiencies

including a missing safety-class break line at valve P42-F608B, an incorrectly labeled

process arrow (33B instead of 38B), and a note (Note 10) that had been incorrectly

deleted in a previous revision. The licensee issued PIFs 97-0269 and 97-0346 to address

correction of these items. '

f. Instrument Setpoint Methodology

In Item 14 of Appendix 1B to the USAR, the licensee committed to provide for NRC review and

approval a detailed technical report documenting the basis and methodology for establishing

protection system trip setpoints and allowable values. Specifically, this report would reflect the

work of the Instrument Setpoint Methodology Group (ISMG), as described in CEI letter PY-

CEI/NRR-0368L, dated October 17,1985. In conjunction with GE Topical Report NEDC- 31336, " General Electric Instrument Setpoint Methodology," dated October 1986, this letter

constitutes the followon action to the licensee's commitment. The USAR, Appendix IB, Item 14,

was updated to reflect the ongoing NRC review of the topical report. CEI letter PY-CEI/NRR-

0969L, dated March 3,1989, revised the CEI schedule for fmal closure of commitment 14. Use

of the topical report received NRC approval on March 23,1993. The licensee commenced

updating the affected setpoint and allowable value calculations.

The licensee issued Instrumentation and Control Design Guide D-1, Setpoint Calculation >

Methodology, and Desk Guide ICS-005 to control the process for preparing calculations for I&C

setpoint parameters covering nominal setpoints, allowable limits and analytical limits, leave-as-is-

zone tolerances and reset values. Attachment 2 to the licensee letter PY-CEI/NRR-1706L, dated

October 15,1993, listed the instmment channels to be evaluated. The licensee based this list on

initiating functions found in the USAR Chapter 6 and 15 analyses. The licensee conducted

analyses for these reactor protection systems and engineered safety feature trip functions and

established an ongoing program to apply the setpoint methodology to other related setpoints.

NRC letter, dated July 18,1995, approved the licensee application of the GE methodology to

Perry Nuclear Power Plant. The setpoint calcolations for HPCS and ECC were reviewed in this

inspection and found to be in either conformance or scheduled to be updated to be in agreement

with the setpoint methodology design guide. The new calculations reviewed were found to be of

better quality than the older ones.

g. Review of Licensee's System-Hased I&C Inspection

In early 1995, the licensee conducted an in-house audit of selected instrumentation and controls

that included some HPCS instrument loops. This we.s done in preparation for anticipated

inspections by the NRC. The audit was conducted la accordance with NRC Inspection Procedure

93807. The audit included a detailed review of the design and field installation of the associated

instmment and control systems, setpoint calculations, mechanical system interfaces, calibration i

47

!

- - -.-- - . - . . - - . - - . -. -.- .- - - _ _ . -

. .

procedures, testability, isolation and bypass status iwicators, maintenance and equipment

installation. The scope of the audit and the methodology for evaluation of the design addressed

the line-items of the NRC Inspection Procedure. Findings were documented on PIFs and

processed as potential issues in accordance with the licensee corrective action program.

The HPCS instrument loops evaluated in the licensee audit were reviewed by this inspection team.

The scope of the licensee audit covered all attributes reviewed in this inspection. No additional

findings resulted beyond the observations recorded by the licensee.

h. Design-basis Documents -Desktop Guide

While the " Design-Basis Documentation Hierarchy" desktop guide may provide guidance where

various sources of documentation may be found, the team encountered examples where the design

bases could not be established as readily as expected, or the design-basis documentation had

various inconsistencies. Examples include description of HPCS functions, the CST water volume

design basis, vortex limitations within the CST, the HPCS suction relief valve design basis, and

use of ASME Codes during deficiency resolution.

The team identified several instances in which the licensee had disculty in retrieving design-basis

information. This problem directly contributed to the licensee's inappropriate "use-as-is"

disposition of plant hardware problems associated with the lack of overfrequency protection for

the HPCS pump and inadequate protection of exposed equipment against the efTects of tornado

missiles.

E.1.4.3 Conclusions

Calculation quality was mixed and many calculations were not being controlled in accordance

with the licensee's program. In contrast, instrument setpoint methodology and calculations were

consistent with commitments and calculation quality wasjudged to be good. Inconsistencies and

discrepancies between calculations and other design basis information was evident. There were

several instances in which the licensee had dimculty in retrieving design-basis information. This

problem directly contributed to the licensee's inappropriate "use-as-is" disposition of plant

hardware problems associated with the lack of overfrequency protection for the HPCS pump (50-

440/97-201-04) and inadequate protection of exposed equipment against the effects of tornado

missiles (50-440/97-201-08).

XI Exit Meeting

After completing the on-site inspection, the team conducted an exit meeting with the licensee on

April 22,1997, that was open to public observation. During the exit meeting, the team leader

presented the results of the inspection. A partial list of persons who attended the exit meeting is

contained in Appendix B. Reference material used during the exit meeting is Attached to this

report.

48

- .-, .-

.. _ _ . _ . _ __

. -

, Appendix A

List of Open Items j

This report categorizes the inspection findings as unresolved items (URIs) and inspection I

followup items (IFI)in accordance with Chapter 610 of the NRC Inspection Manual. A URI is a

.

matter about which the Commission requires more information to determine whether the issue in

question is acceptable or constitutes a deviation, nonconformance, or violation. The NRC may I

issue enforcement action resulting from its review of the identified URIs. By contrast, an IFI is a

matter that requires further inspection because of a potential problem, because specific licensee or

NRC -action is pending, or because additional information is needed that was not available at the ,

time of the inspection. 1

'

Item Number Finding Title

h'P3

50-440/97-201-01 URI HPCS Pump Vortex Calculation - 10 CFR Part 50,

Appendix B," Design Control" (El.2.2.2.d) j

i

50-440/97-201-02 URI Untimely Resolution of Keep-Full Pumps Test

Results(El .2.2.2.f) I

!

l

50-440/97-201-03 URI HPCS Secondary Modes Testing - Past Operability I

,

Determination (E l .2.2.2.k)

50-440/97-201-04 URI HPCS Overfrequency Protection Relay Removal Calculation -

10 CFR Part 50, Appendix B," Design Control" and j

" Corrective Action"(El.2.2.2.1)

50-440/97-201-05 URI Resolution of Emergency Diesel Generator Testable Rupture

Disk Failures - 10 CFR Part 50, Appendix B," Corrective

Action" (E 1.2.2.2.n)

I

>

50-440/97-201-06 URI Undocumented Modification to Droop Setting of Division III

EDG (El.2.3.3.a)

50-440/97-201-07 URI Treatment of Droop Bias with Respect to TS Acceptance

Criteria for Reduced Frequency at End User Mechanical

Equipment (El.2.3.3.a)

50-440/97-201-08 URI Protection Against External Missiles for HPCS and RCIC

Suction Not Consistent With the USAR (El.2.4.2.a)

A-1

.- - - _ - . - - _ . _ _ . . _ - - - - - . - . - - - - . . . . . - . . _

. _ - .

. .

I

'

\

l

I

50-440/97-201-09 URI Normal Operation ofHPCS Aligned to Suppression Pool-

l

Inconsistent with the Description of Operation of the Facility as  !

Described in the US AR (El.2.5.2.a)

}.

50-440/97-201-10 URI Pipe Break (versus Pipe Crack) Criteria for Moderate-Energy,

! Nonsafety, Non-Seismic Piping Outside Containment

(E l .2.5.2.a)

a

50-440/97-201-11 URI Potential Unanalyzed Condition Existing from the Initial

Licensing Period As a Result ofInsufficient Analysis and

i

Corrective Actions Regarding Deficiencies Identified in EDDR

l 10 (E 1.2.5.2.a)

50-440/97-201-12 URI Licensing Commitment Deviations Regarding Past Cleaning and

Subsequent Reporting that HPCS Room Cooler Commitments

4

l

i

Had Been Satisfied (El.2.5.2.b)

50-440/97-201-13 URI Licensing Commitment Deviations Regarding Current

Inspection Frequency of HPCS Room Cooler (El.2.5.2.b)

3

50-440/97-201-14 IFI Unit I and 2 Division III Battery Missing Hold-Down Straps

l

j (E l .2.6.2.a)

(

] 50-440/97-201-15 URI Maintenance of USAR and Consistency of USAR and Design l

l Calculations (El.2.7 and El.3.7) ,

i  !

l 50 ?40/97-201-16 IFI USAR Clarity as to Definition of ECC Passive Failure Design

j (E 1.3.2.2)

] 50-440/97-201-17 URI Surge Tank Emergency Makeup Design Basis - Reduction of

j Capacity from 7 Days to 30 Minutes (El.3.2.2.a)

4

i

D-440/97-201-18 URI Non-Conservative Flooding Rate in Safety Evaluation 96-128 -

, 10 CFR Part 50, Appendix B, Criterion III," Design Control"

c (E l .3.2.2.a)

3

5 <

50-440/97-201-19 URI Non-Conservative Analysis of Test Results for ECC/NCC

, System Interface Leakage - 10 CFR Part 50, Appendix B,

] Criterion XI, " Test Control"(El.3.2.2.b)

50-440/97-201-20 IFI ECC Pump Minimum Flow Value Design Documentation and

Operating Procedures Inconsistencies (El.3.2.2.c)

A-2

_

_ _ _ _ _ . _ _ _._.___ _ _ _ _ _ _ _ _ _ . _ . . _ _ _ . _ _ . . . _ _ . . . _ . _ . _

,

. .

j

i

t

<

'

50-440/97-201-21 URI Application of ASME Section N111 Criteria to an ASME

Section III Component Without Documented Technical

Justification - 10 CFR Part 50, Appendix B, Criterion III,

" Design Control"(El.3.2.2.d)

-

50-440/97-201-22 URI Unconfirmed Calculations Assurnprions - 10 CFR Part 50,

l Appendix B, Criterion III, " Design Control" (El 3.2.2.e)

!

, 50-440/97-201-23 URI Deviation from USAR Commitments, Stated in Appendix la

and Section 12.6, to Meet the Requirements of NUREG-0737,

Item II.B.2. (E1.3.5.2.b)

.,

'

50-440/97-201-24 URI Adherence to Procedure NEI-0341 - Calculations for

l; Verification, Review, and Approval of Calculations - 10 CFR

!

Part 50, Appendix B, Criterion III, " Design Control" (El .4.2.a)

l

! 50-440/97-201-25 URI HPCS Overpressure Protection Analysis Methodology, and

i

Review / Approval - 10 rFR Part 50, Appendix B, Criterion III,

" Design Control" (El.4.2.c)

)

i

1

e

1

i

i

a

4

!

l

i

k

!  !

!

l

1

1

i

i

$

1

) A-3

i

!

. -. . _- _ - . - . . _- .

.-

- . - _ . . . . - - - . . - . . - . - . . . - . . . - - - . - . _ . . - - . . . ~ . . - - . - . -

I-. .

!

4

)

I

Appendix B

i

'

Exit Meeting Attendees

j NAME ORGANIZATION

R. Brandt CEI, Plant General Manager

i R. Collins CEI, Manager, Quality Assurance

D. Dervay CEI, Supervisor, Plant Engineering

j J. Grabner CEI, Supervisor, Projects Unit

'

D. Gudger CEI, Regulatory Compliance

. H. Hegrat CEI, Manager, Regulatory Affairs

j J. Hopkins NRC, Sr. Project Manager, NRR/DRPE

! J. Jacobson NRC, Branch Chief, DRP/ Region III

S. Jaffe Reporter, Plain Dealer

i M. Kembic CEI, Corporate Regulatory Affairs

,

i

M. Leach NRC, Acting Deputy Director, DRS/ Region III

, E. Listen Member of the Public j

L. McGuire CEI, Supervisor, Electrical Unit

'

J. Milicia Reponer, Lake County News Herald

D. Norkin NRC, Section Chief, NRR/PSIB

H. Oats CEI, Supervisor, Configuration Control

J. Powers CEI, Manager, Design Engineering

A. Rabe CEI, Independent Safety Evaluation Group

.

T. Rausch CEI, Director, Nuclear Service Department

i M. Ring NRC, Branch Chief, DRS/ Region 11I

, J. Sielicki

.

CEI, Corporate Communications

j R. Twigg NRC, Resident Inspector

,

4

,

J

i

i B-1

. . ._ .

__ . - - _

. .

Appendix C

List of Documents Reviewed

DDunnentho. Egy Qgg Oncument TitlelDeictlDilon

CALCULATIONS

2.6.13 0 10/6/82 ESW/ECCW Cross-Connect

2.6.13.1 1 3/27/89 ESW/ECCW Cross-Connect Hydraulic Analysis

2.6.13.1.1 1 1/4/85 ESW/ECCW Cross Connect System With Standpipe-To-Swale

Hydraulic Analysis

22:08 12/14/78 Condensate Storage Tank Dike and Slab Load Combination

Summary

22:11 07/14/82 Missile Protection For Fuel Oil Day Tank Piping (Vent, Dipstick &

Refill) Unes

22:12 02/24/83 Condensate Storage Tank Instrument Miscila Shields

36:01.3.2.1.5 4 3/21/85 Control Complex El. 574-10 Nonsafety Sanitary Floor Drains Seismic

Support

4.05.1 0 10/6/81 Auxiliary Building - Pump Room Walls

B21-C06 Drywell Pressure

B21-C10 RPV Level 8

821-C11 RPV Level 2

CL-ECA-011 2 7/18/85 Environmental Conditions Analysis (AB-2-W)

CL-SBO-001 1 10/6/92 Steady State Temperature Within Unit 1 Division 2, High Pressure

Core Spray Switchgear Room During Station Blackout

E22-1 0 5/12/81 HPCS System, NPSH Calculations (with DCC 3)

E22-11

<

0 5/23/84 E22 Pump Suction Switchover

'

E22-19 1 7/23/92 Justification For Elimination Of HPCS Overfrequency Relay

E22-2 0 2/23/83 Overpressure Protection Analysis

E22-24 0 7/24/93 High Pressure Core Spray Waterleg Pump Surveillance Test

Acceptability

E22-26 1 3/20/95 Design Limiting U For Heat Exchanger

E22-28 0 10/4/95 Overall Heat Transfer Coefficient For Heat Exchanger

E22-29 3 2/1/96 SVI-E22-T2001 HPCS Pump Performance Acceptance Criteria

-

E22-29 4 2/28/97 SVl-E22-T2001, HPCS Pump Performance Acceptance Criteria

E22-32 0 10/14/95 HPCS EDG JW Heat Exchanger Test Results - 1995

E22-35 0 3/24/97 HPCS Pump - NPSH A With SPCU in Operation

E22-6 0 11/10/83 HPCS System Piping

E22-C01 Suppression Pool High Level

E22-C02 3 9/13/95 HPCS - CST Low Level Transfer Trip - 1E22-N654C(G)

E22-003 HPCS Minimum Flow

E22-C04 Diesel Air Crank Jog

E22-C05 HPCS Discharge Pressure Bypass Valve Interlock

E22-C06 Diesel Low Oil Pressure

E22-C07 Diesel Generator Tachometer

E22-C08 HPCS Diesel Generator Timing Relays

E22-C10 HPCS Discharge Flow ERIS Input

E22-C11 HPCS Discharge Flow Indication

E22-C12 HPCS Discharge Pressure Indication

E22-C133 Diesel Starting Air Pressure Regulator

C-1

_ _ . . _ . _ . ___ _._ _______ _ _ __.

_

_

_ _ _ _ _ _ _ _ _ _ ,

-

!

. .

.

E22-T01 2 6/26/96 Setpoint To erance Calculation For HPCS Diesel Square D

instrumentation Loops

. E22-T03 0 9/24/91 E22 Waterleg Pump Low Pressure Alarm

ECPC-0001 2 8/25/92 Electrical Penetration 12T Verification

3 FSPC-0018 1 4/3/96 Div I MOV Fuse Sizing

FSPC-0019 1 4/1/96 Div 11 MOV Fuse Sizing
FSPC-0020 1 4/8/96 Div 111 MOV Fuse Sizing

l

JL-105 7 10/31/88 Containment and Drywell Break Exclusion Areas

l

- JL-63 0 11/25/81 ECCS and Suppression Pool Level After ECCS Suction Break l

' M39-6 0 7/31/96 HPCS Room Cooler Performance Test Results - 1995 '

M43 2 5/9/91 Diesel Generator Building Vent System Ventilation Load

M43-1 0 8/28/86 Minimum Outside Air Temperature For Diesel HVAC Temporary l

Conditions

MOVC-047 3 5/7/96 AC Voltage Drop Calculation For Butterfly MOVs (With DCCs 3,6,8)

i P11-12 0 3/15/85 Level Setpoints in CST For Adequatti NPSH and No Vortexing

i P11-12 1 3/25/97 P11 - Leve' Setpoints In CST For E22 and E51 Instruments

' ,

P42-11 2 5/25/89 P42 Syttem Operating Temperature (Note: This Calc. Has Been

, Superseded By P42-28)  ;

P42-12 0 12/24/84 P42 System - Heat Exchanger Thermal Relief Valve Analysis 1

t P42-19 0 5/6/94 P42 System Heat Load Subsequent To A LOOP During RF04

P42-23 1 9/6/95 ECC Hx Performance Calculation

P42-24 1 4/28/95 Maximum Allowable Leakage From P42 System l

, P42-25 1 11/17/94 Determine The ESW Winter Bypass Une Flow To The ECC Heat 1

1

Exchanger, in Order To Maintain The C.C. Chiller Condenser Water

l

Temperature Between 55*F and 95*F.  !

! P42-26 Composite Bias Uncertainty Of ECC 'A' ECC Flow

j P42-27 Composite Bias Uncertainty Of ECC 'B' ECC Flow

.

P42-28, 0 6/1/95 ECC Thermal-Hydraulic Analysis

l P42-30 0 4/29/95 Evaluation Of ECCHX Temperature Control Valve 1P42-F0665A/B

2

P42-31 0 9/15/95 ECC A Heat Exchanger Test Results - 1995

P42-32 0 9/29/95 ECC B Heat Exchanger Test Results - 1995

j P42-33 0 5/1/96 Evaluation Of Heat Transfer Coefficient and Min. Required Wall

, Thickness For ECC Heat Exchangers 1P42-80001 A/B

'

P42-4 3 5/24/89 ECCW Heat Exchanger Size and Outlet Temperature

P42-5 3 2/22/85 Emergency Closed Cooling Water System Surge Tank Sizing

P42-6 0 1/7/81 ECCW (P42) Calculation For System Design Pressure

{ P42-7 0 5/26/82 Atmospheric Surge Tank Vent (P42)

1 P42-8 0 7/30/84 Overpressure Protection Analysis

! P42-C01 ECC Flow Switches

l P42-C02 Time Delay Setpoint Chiller MOV Opening

l P42-T02 ECC Hx Outlet Temperature Bistables 1P42N051 A/B

j P42-T04 ECC Surge Tank Level Switches P42-N131 A,8

j P42-T05 ECC Surge Tank Level Switches P42-N130A,8

i P42-T06 ECC Low Flow Alarm

P43-12 0 2/7/94 Seismic Event Inventory Loss Analysis

, PNED-UOO8 2 11/4/96 Fuse Selection and Sizing Methodology

. PRDC-0004 2 5/30/95 Class IE DC Control Circuit Coordination

! PRDC-0005 3 5/23/96 Load Evaluation and Battery Sizing Of Div i & 11 Class IE DC System

l PRDC-0006 0 4/8/91 Load Evaluation and Battery Sizing Of Div Ill Class IE DC System

! PRDC-0007 3 4/3/96 Voltage Drop Control Circuit For Switchgear Fed Equipment

. PRLV-0004 2 4/30/96 480v Breaker Coordination

PRLV-0059 Station Blackout: Div Ill To Div 11 Crosstie

<

PRMV-0001 2 11/22/88 Div I and H Diesel Generator, EH1102, EH1201,1R43S0001 A, B

!

C-2

3.

<

1

a 1

-_ - _ _ . _ __ , l

_ ____ _ _ . . _ . . _ _ _ _ _ _ _ _ _ _ _ . _ _ . . _ _ _ _ _ - _ . _ . _ . . _ . _ . _ . _ _ _ _ _ _ _ _

. -

<

l

! l

4

PRMV-0014 2 11/22/88 Div Ill HPCS Diesel Generator EH1301,1 E22S001

, PRMV-0015 0 3/11/85 EH13 Bus Supply Breakers EH1302, EH1303

PRMV-0017 0 3/11/85 EHF-1-E Transformer Breaker EH-1305

PRMV-0020 2 11/22/88 Degraded Voltage and Loss Off Power Undervoltage Relaying For

] Div 1, ll, and 111

i PRMV-0061 0 8/28/91 Div 1, ll and til Diesel Generator Voltage Controlled, Overcurrent and

i" Load Test Overload Protection

PRMV-0062 07/28/95 4.16kV Class 1E Switchgear Degraded Voltage Instrumentation Loop

Tolerance

, PSTG-0001 2 8/24/95 PNPP Auxiliary System Voltage Study

PSTG-0003 2 6/29/95 480v Safety Related Motor Starting Voltage Drop

! PSTG-0006 2 5/20/92 PNPP Short Circuit Study

l PSTG-0014 3 10/21/96 Diesel Loading I,11 and 111

-

PSTG-0021 1 6/22/93 Voltage Drop in Control Circuit Of Safety Related Size 2,3 and 4

Starters

l PSTG-0027 0 7/14/93 Voltage Drop in Control Circuit Of Safety Related Size 1 Starters

i PY-CEl-96-001 0 10/31/96 Total Amount Of Fibrous Insulation Inside Containment

,

PY-CEl-96-002 0 10/30/96 Amount Of Fibrous insulation Produced By A Line Break inside

, Containment

1 R44-6, Rev. 0 0 7/7/92 Correlation Of EDG Starting Air Properties At System Operating

Pressure Of 250 psig and At Atmospheric Pressure

i R44-7 0 1/7/93 Starting Air Leakage Criteria For The Standby and HPCS Emergency

!

' Diesel Generators Starting Air (R44) System

R45-10 2 4/28/91 Diesel Generator Fuel Oil Storage Tank Correlation

, R45-11 0 11/25/92 Emergency Diesel Generator Fuel Oil Transfer Pump Performance

-

Requirements

R45-3 1 1/16/96 Diesel Fuel Oil Pumps (With DCC 2)

R45-C01 Diesel Fuel Oil Day Tank Level

R48-10 1 3/23/93 Standby and HPCS Diesel Generator intake Air

l R48-11 2 6/29/95 Standby and HPCS DG Vent Valve

i

R48-13 1 12/9/96 EDG Exhaust Vent Valve Setpoint Calculation (With DCC 3)

R48-14 0 12/10/96 Diesel Generator Exhaust Vent Valve Testing (With DCC 2) l

1 R48-17 0 11/13/92 Seizure Of EDG Exhaust Relief Valve Bearings

R48-8 1 3/3/93 EDG Exhaust Vent Va!ve Size

,

CORRECTIVE ACTION DOCUMENTATION ,

CR 89-0032 i

CR 92-016

CR 92-0215

CR 93-0114

CR 93-0245

CR 93-0276 '

CR 93-0486

CR 93-3022

CR 94-0095

CR 94-0428

CR 94-0507

CR 94-0686

CR 94-0889

CR 94-1462

CR 94-2104

CR 95-0132

l

C-3

. _ _ . . . _ _ _ _ _ . . _ _ _ _ _ _ _ . _ _ _ . . _ . _ _ _ . _ _ _ _ - > _ . . . _ .__ _ ._ ___.___. _ _ _

.

. -

3

,

,

,

CR 95-OiS3

CR 95-0570

CR 95-1150 1

i CR 95-1214 i

CR 95-1654

CR 95-2586

!

I CR 96-0169

i

j CR QQC-02345 1

4 NR 91-S-00091  ;

i

'

NR 92-S-00252

'

'

NR 92-S-00289

. NR 94-S-00615

NR MMQS-02965

PlF 94-2196

i

PlF 94-2247

PIF 95-0570

'

PIF 95-1150

PlF E0021

PIF 96-0164

PlF 96-0165

l PIF 96-0325

i PlF 96-0425

j PlF 96-0656

PIF 96-0810

i PlF 96-0900

, P!F E1046

PIF 96-1078

5 PlF 96-1241

PlF E1265

PlF 96-1289

PlF 96-1291

PIF 96-1523

PIF 96-1554

PlF 96-1578

PlF E1866

PIF 96-1869.

PlF 96-2671

PlF 96-2699

PIF 96-2700

PlF 96-2846

PlF 96-2889

PIF 96-3035

PlF 96-3039 ,

PlF 96-3642

PlF 97-0185

PlF 97-0325

PlF 97-0344 ,

PlF 97-0345

PIF 97-0351 i

'

PIF 97-0379

PIF 97-0421

PlF 97-0431

PlF 97-0441

i

!

C-4

l

, ._ - _

. .

PlF 97-0442

PIF 97-0463

PlF 97-0464

PIF 97-0471

PlF 97-0487

PlF 97-0499

PlF 97-0513

PIF 97-0526

PlF 97-0538

PIF 97-0544

PlF 97-0556

PIF 97-0560

PIF 97-0561

PIFRA 96-1609-001

DESIGN CHANGE PACKAGES fDCP)

86-0174 Replacement Of Orifice Plates OP42N0265A & B

86-0224 P45 Low Flow Bypass Around ECCs (P42) Heat Exchanger Outlet

Valve

'

86-0493 Addition Of High Point Vents To Transmitter 1P42N249

89-0117 Delay Control Complex Chiller Start Circuitry During A LOOP Or

LOCA

90-0012 Replace Manual Valves P42-F550 and P42-F551 With MOV's

90-00181 Suppression Pool B Loop LevelInstrumentation

90-00235 Replace Agastat Time Delay Relays

90-0086 Rotate Spectacle Flanges On 2P42/1P45 Interface

90-0275 2 Diesel Generator Exhaust Testable Rupture Disc Modification

91-00104 MOVs in HPCS Starting Air Compressor - Voltage Spike

92-00042 Sliding Unks

92-00060 MOV To Manual Valve Change; Deactivate

92-0060 P42F315A B C Converted To Manually Operated Valves

53-00082 & 82 A MOV Operation During DBA

93-00092 Topaz inverters

93-00,133 No> Remote Shutdown MOV Power Fuse Sizing

93-00148 HVAC Fan Motor Fuse Operation

93-00179 Valve indication Wiring; Torque Switch Setting

94-00161 SIL 435; Stem / Disc Separation

94-0027 ECC Ternperature Control Valve and Bypass Line

96-04067 Relay Replacement - DCPs 68 - 72 Similar

SE 96-126 10/10/96 10CFR50.59 Safety Evaluation - ECC Surge Tank

DESIGN DOCUMENTATION

4

-

HPCS System Functional / Performance Design Bases

-

2/29/80 Target Rock Production Operational Test For Tag Number RNQ201

21 A9236 (GE) 4 Engine Generator For High Pressure Core Spray System

22A3131 (GE) 5 4/77 High Pressure Core Spray

22A3131 AS (GE) 3 12/2/83 High Pressure Core Spray Design Specification Data Sheet

7964-W6 7/31/75 Struthers Wells Specification Sheet

DI-224 0 HPCS Pump Room Cooler Design input

C-5

. .

DSP-E22-1-4549-00, 3 4/18/86 Design Specification High Pressure Core Spray and Pipe Supports

ASME Ill Division 1

FDDR KL1-3980 Overfrequency Protection Relay

NEDO-10905-3 08/00/79 High Pressure Core Spray System Power Supply Unit (Amendment 3)

PDB-B0002 1 Pump Performance Curves

SDM-E22A 6 2/28/96 High Pressure Core Spray System Description Manual

SDM-E228 8 7/25/95 HPCS Diesel Generator System Description Manual

SDM-P42 8 7/25/96 Emergency Closed Cooling (ECC) System Description Manual

SP-646-4549-00 Design Fabrication and Delivery Of Air Handling Units

DRAWINGS

04-4549-S-322-701 C Pipe Support Mk-1E22-H1024

10776-7-2 4 Bishopric Drawing For Nozzle Details For HPCS Diesel Generator

Fuel Oil Storage Tanks l

10776-7-5 7 Bishopric Drawing For HPCS Diesel Generator Fuel Oil Storage

Tanks Assembly

25131 C Stewart and Stevenson Drawing

2C-5588 A Byron Jackson Drawing

3/4 X 1 REH-5-4 G Target Rock Drawing

39347 Bingham Willamette Drawing

39EA35-C893-7 Carrier Drawing HPCS Pump Room Cooling Air Handling Unit

39EA35-C893-7 F Carrier Drawing

4549-22-140-1 0 Emergency Closed Cooling Heat Exchanger Loop "A" Tube Sheet

Drawing

4549-22-140-2 0 Emergency Closed Cooling Heat Exchanger Loop "B" Tube Sheet

Drawing

4549-40-198-3A 24"- 150# Gate Valve (MPL E22-015)

76H-001 G Target Rock Drawing

B-208-013 Sh H101 09/18/95 Nuclear Boiler Nuclear Steam Supply Shutoff System isolation Signal

B-208-013 Sh H104 01/10/92 Nuclear Boiler Nuclear Steam Supply Shutoff System Isolation Signal

B-208-013 Sh H105 01/11/92 Nuclear Boiler Nuclear Steam Supply Shutoff System Isolation Signal

B-208-040 Sh A014 08/01/95 Reactor Protection System Testability Card File Tabulations

B-208-040 Sh A015 08/18/86 Reactor Protection System Testability

B-208-040 Sh H100 09/06/95 Nuclear Boiler Nuclear Steam Supply Shutoff System Isolation Signal

B-208-055 Sh A008 07/26/94 Residual Heat Removal System Relay Logic Bus "B"

B-208-055 Sh A015 07/12/94 Residual Heat Removal System Testability (B)

B-208-055 Sh A036 07/26/94 Residual Heat Removal System RHR "B' Test Return MOV F0248

B-208-055 Sh A066 09/11/91 Residual Heat Removal System Suppression Pool Cooling Via RHR

Bypass Valve F609

B-208-055 Sh A067 09/11/91 Residual Heat Removal System Suppression Pool Cooling Via RHR

Bypass Valve F610

B-208-055 Sh A100 04/21/94 Residual Heat Removal System LOCA Signal

B-208-060 Sh A006 06/09/94 Low Pressure Core Spray System Testability Circuits

B-208-065, Sh.14 N HPCS System Pump Injection Shutoff, MOV F004

B-208-066 Y DIV lil Diesel Generator Control (1E22-S001)

B-208-066, Sh.1 Y HPCS Power Supply System, Pump C001

B-208-094 Sh 000 10/13/86 Suppression Pool Drain and Cleanup Index

B-208-094 Sh 001 04/08/86 Suppress:on Pool Drain and Cleanup Pump C001

B-208-094 Sh 002 10/12/96 Suppression Pool Drain and Cleanup Pump Suction Valve F010

B-208-094 Sh 003 12/14/89 Suppression Pool Drain and Cleanup Pump Suction Valve F020

C-6

_- ._.

. .

B-208-094 Sh 004 12/12/86 Suppression Pool Drain ano ueanup Fump Discharge Va ve F060

B-208-OS4 Sh 005 06/09/94 Suppression Pool Drain and Cleanup Demineralizer Alignment Valve

1G42-F070

B-208-094 Sh 006 11/02/85 Suppression Pool Drain and Cleanup Demineralizer Effluent To RHR

Valve F080

B-208-094 Sh 200 04/17/86 Suppression Pool Drain and Cleanup Flow Process Instrumentation

B-814-842 E Emergency Closed Cooling Surge Tank (1P42A001A) Level

Instrumentation

D-206-027 FFF Electrical One Une Diagram, Class IE, 480v Bus EF1D

D-206-029 BB Electrical One Une Diagram, Class IE, 480v Bus EF1D

D-206-051 WW Electrical One Uno Diagram, Class IE DC System

D-206-052 UU Electrical One Une Diagram, Non Class IE System Bus D1 A/D1B

D-214-004 T Conduit and Tray Separation Criteria

D-215-004, Sh.601 S Electrical Conduit Layout Detail

D-215-801 J Cable Pulling Criteria, Bending and Training Radius

D-217-103 Sh 4 L Electrical Heat Trace - Condensate Storage and Transfer

D-219-001 P Grounding Details Drawing

D-301-801 A No Title

D-302-212 KK No Title

D-302-358 C No Title

D-302-621 (Unit 1) BB Emergency Closed Cooling Water System (P&lD)

D-302-622 (Unit 1) F Emergency Closed Cooling Water System (P&!D)

D-302-623 (Unit 1) H Emergency Closed Cooling Operating Data

D-302-701 AA High Pressure Core Spray System

D-302-791 Z No Title

D-302-792 CC No Title

D-303-016-101.2 11/29/79 Condensate Storage & Transfer

D-303-016-101.3 05/04/81 Condensate Storage & Transfer

D-303-016-101.4 07/06/82 Condensate Storage & Transfer

D-303-016-101.5 03/19/84 Condensato Storage & Transfer

D-304-313-103.2 05/19/80 Condensate Storage & Transfer

D-304-313-103.3 02/16/81 Condensate Storage & Transfer

D-304-313-103.4 12/21/82 Condensate Storage & Transfer

D-304-313-104.2 02/10/81 Condensate Sterage & Transfer

D-304-313-104.3 12/21/82 Condensate Storage & Transfer

D-304-313-104.4 08/30/83 Condensate Storage & Transfer

D-304-314-101.2 12/08/80 Condensate Storage & Transfer

D-304-314-101.3 04/03/81 Condensate Storage & Transfer

D-304-314-101.4 08/30/83 Condensate Storage & Transfer

D-304-701 M High Pressure Core Spray Isometric Piping

D-352-621 (Untt 2) S Emergency Closed Cooling Water System (P&lD)

D-814-409 Sh 901 06/16/85 Condensate Storage Tank Level Instrumentation Pipe Routing

D-814-409 Sh 902 06/16/85 Condensate Storage Tank Level Instrumentation Hanger Orientation

D-814-409 Sh 903 06/16/85 Condensate Storage Tank Level Instrumentation Hanger Fabrication

& Tabulation

D-814-409 Sh 904 04/23/85 Condensate Storage Tank Level instrumentation (1E22-N054C) Rack

Details

D-814-409 Sh 905 04/24/85 Condensato Storage Tank LevelInstrumentation (iE22-N0540) Rack

Fabrication

D-814-409 Sh 906 04/23/85 Condensate Storage Tank Level Instrumentation (1E22-NO35A) Rack

Details

3 C-7

_

..- . . - . . - - - - - - . _ _ _ ~ - _ . . - . . - . ~ . - .- - - . - . --__-

! . -

i'

.

D-814-400 Sh 907 04/24/85 Condensare Storage Tank Level Instrumentation (1 E22-N035A) Rack

i Fabncadon

D-814-409 Sh 908 04/23/85 Condensate Storage Tank Level Instrumentation (1E22-N054G) Rack

s Details

D-814-409 Sh 909 04/24/85 Condensate Storage Tank Level Instrumentation (1E22-N054G) Rack

Fabrication

D-814-409 Sh 910 05/29/85 Condensate Storage Tank Level Instrumentation (1E22-NO35E) Rack

i Details

'

D-814-409 Sh 911 05/29/85 Condensate Storage Tank Level Instrumentation (1E22-NO35E) Rack

j Fabrication

D-814-409 906 C No Title

D-814-409-908 C Hu Title

D-814-728-907 8 No Title

-

D-814-842-901, Emergency Closed Cooling Surge Tank (1P42A001 A) Level

'

instrumentation

D-814-842-903 Emergency Cicsed Cooling Surge Tank (1P42A001 A) Level

Instrumentation

l D304-315 G No Title

D304-316 J No Title

D304-317 M No Title

! D76-95 S No Title

E-303-016 K No Title

i E-303-002 H No Title

l FCD 308-311 Sh 1 0 HPCS Functional Control Diagrams

FCD 308-311 Sh 2 0 HPCS Functicnal Control Diagrams

FCD 308-311 Sh 3 0 HPCS Functional Control Diagrams

FCD 308-311 Sh 4 D HPCS Diesel Generator Functional Control Diagram

T-37225 1 2Hi79 Byron Jackson Test Plot- HPCS Pump

LETTERS

-

07/18/95 General Electric Setpoint Methodology - Perry Nuclear Power Plant,

Unit No.1 (TAC No. M860233)

CEl- 04/26/82A Response To Draft SER Containment Systems Branch

Gilbert /Commonwealt 12/5/77 Perry Nuclear Power Plant Control Complex Flooding

h to CEI

NRC to CEI 12/20/85 Fire Protection Inspections

PY-CEl/NRR-1121 1/26/90 Service Water System Problems Affecting Safety Related Equipment

PY-CEl/NRR-1328L 3/1/91 Supplemental Response To Generic Letter 89-13

PY-CEl/NRR-1706 L 10/15/93 Instrument Setpoint Methodology For Protection System

Instrumentation

PY-CEl/NRR-1734L 4/8/94 Service Water System Problems Affecting Safety Related Equipment

PY-CEl/NRR-2111L 11/4/96 Response To NRC Bulletin 96-03, Potential Plugging Of Emergency

Core Cooling Suction Strainers By Debris in Boiling-Water Reactors

PY-gal /CEl-12043 12/9/81 Minimum Suppression Pool Level Following ECCs Suction Lino Break

MEMOS

PY-STR-1091 06/1999 Perry Nuclear Power Plant FSAR Draft Sub-Section 3.5.1.4

PY-STR-1092 06/2599 Perry Nuclear Power Plant Tornado Missile Protection

PY-STR-1098 07/06/79 Tornado Missile Drawing Review

PY-STR-1102 07/13/79 Tornado Missile Drawing Review

C-8

9

_ . - _ . . _ _ . _ _ _ _ _ . . - . _ _ _ _ _ _ _ _ . _ _ _ _ - .

,

. .

l

RAS-94-0272

'

07/21/94 RHR (LPClf Opetability

OPERATING EXPERIENCE

'

-

10/25/89 Minutes of Public Meeting on Generic Letter 89-04

Generic Letter 86-10 04/24/86 Implementation Of Fire Protection Requirements ,

Generic Letter 86-10, 03/25/94 Implementation Of Fire Protection Requirements  ;

Supp1

Generic Letter 89-04 04/03/89 Guidance on Developing Light Water Reactor Inservice Testing

Programs ,

Information Notice 83- 11/14/83 Air / Gas Entrainment Events Resulting In System Failures (Z00593)

77

Information Notice 87- 02/11/87 Information Notice Potential For Water Hammer During Restart Of

10 Residual Heat Removal Pumps ,

Information Notice 89- 10/19/89 Diversion Of The Residual Heat Removal Pump Seal cooling Water  ;

71 Flow During Recalculation Operation Following Loss-Of Coolant

'

Accident (ZO2722) {

information Notice 92-

'

3?/28/92 information Notice Potential For Loss Of Remote Shutdown Capability

18 During A Control Room Fire ,

'

LER 93-021 1 12/20/96 Improper Setting Of Motor-Operated Valve Results in Loss Of

Emergency Closed Cooling System Safety Function and Condition

Prohibited By Technical Specifications

LER 94-005 1 10/28/94 Loss Of Both Trains Of Control Room Emergency Recirculation Due l

To Low Emergency Closed Cooling Temperature ,

PS 6136 RHR Pump Seal Cooler Shell Side Design Pressure

PROCEDURES. TESTS. INSTRUCTIONS '

All-H13-P601-17 4 9/11/92 Alarm Response Procedure RHR B & C (Unit 1 ) l

ALl-H13-P601-20 11/28/94 Alarm Response Procedure RHR A (Unit 1)  !

ARI-H13-P601-16 4- Alarm Response Procedure HPCS Water Leg Pump Discharge

Pressure Low

ONI-R61 0 10/2/96 Off-NormalInstruction Loss Of Control Room Annunciators (Unit 1), l

through Plc No.1

gel-0007 1 Cable / Wire Termination Instruction

gel-0024 2 Cable Pulung instruction

GMI-180 0 Greer Hydraulic Actuator Maintenance

CMI-156 Operability Test and Maintenance Of Diesel Generator Testable

Rupture Disc

IMI-E3-23 06/12/91 Instrument Maintenance Instruction, Division Ill HPCS Diesel

Generator Woodward Governor

101-11 05/16/95 Integrated Operating Instruction, Shutdown From Outside The Control

P.com

ISTP 3 7/17/94 Pump and Valve Inservice Testing Program Plan (ISTP), through Plc

No. 6 Dated 1/31/97

ONI-D51 4 10/17/96 Off-Normal Instruction - Earthquake (Uniti), through Plc No. 5

ONI-R10 06/01/94 Off Normal Instruction - Loss Of AC Power

-

Pressure Relief Device Test Data Sheet 1E22-F014, W.O. Number

88-8670

- 4/12/94 Pressure Relief Device Test Data Sheet For 1E22-F0014

-

4/13/96 Pressure Relief Device Test Data Sheet For 1E22-F0533B

-

4/28/94 Pressure Relief Device Test Data Sheet For 1E-F0035

-

6/4/92 Pressure Relief Device Test Data Sheet For 1E22-F0533A

C-9 .

l

. . .- - . - . . - . - - .__. .

.

.

\

PTI-M39-P0002 Surveillance Task Number S95-000032

PTI-P42-P0008 1 9/1/95 Periodic Test Procedure P42 Leak Rate Determins. tion

E22A 01/06/89 HPCS Pump and Valve Operability Test

E22A 05/15/96 High Pressure Core Spray System (Unit 1)

E22A Change 01/20/94 HPCS Pump and Valve Operability Test

SOI-G41 8 7/31/95 Fuel Pool Cooling and Cleanup System

sol-P42 7 3/16/96 System Operating Instruction Emergency Closed Cooling System  !

(Unit 1) '

sol-P45/P49 2 9/19/95 System Operating Instruction Emergency Service Water and Screen i

Wash Systems, through PIC No. 8 dated 3/16/96 l

sol-P47 5 4/7/92 System Operating Instruction Control Complex Chilled Water System,

through Plc No.10 dated 2/21/97

E22-T1329 Division 3 HPCS Diesel Generator 18 Month Functional Test  ;

E22-T1339 02/05/96 Division 3 HPCS Diesel Generator 18 Month Loss Of Off-Site Power

Test

E22-T2001 02/03/97 HPCS Pump and Valve Operability Test

E22-T2001 12/05/95 HPCS Pump and Valve Operability Test

E22-T2001 C-1 01/08/96 HPCS Pump and Valve Operability Test

E22-T2001 C-2 05/09/96 HPCS Pump and Valve Operability Test

E22-T2001 C-3 08/28/96 HPCS Pump and Valve Operability Test j

E22-T2001 S85-9278 02/20/97 HPCS Pump and Valve Operability Test Data Sheets

E22-T5397 HPCS Initiation and Loss Of EH13 Response Time Test

SVI-E22-T0194-G 3 HPCS CST Low Level Channel G Calibration For 1E22-N054G

SVI-E22-T0194-G 3 HPCS CST Low Level Channel G Calibration For 1E22-N054G

SVl-E22-T0196 3 HPCS Suppression Pool High Level Channel C Calibration For 1E22-

N055C

SVI-E22-T1192 3 HPCS Logic System Functional Test

SVI-E22-T1319 Surveillance Task Number S85-8474

SVI-E22-T1339 Div 111 Diesel Generator 18 Month LOOP /LOCA Test

SVI-E22-T2001 Surve!llance Task Number S85-9278

SVI-E22-T5217 6 5/24/96 Performance Test of Battery Capacity-Division lli (Unit 1)

SVI-E22-T9409 Type C Local Leak Rate Test Of 1E22 Penetration P409

SVI-GEN-T2000 2 ASME Code Check Valve Disassembly Testing 1

SVI-P42-T2002 4 7/11/95 Surveillance Instruction Emergency Closed Cooling System Valve

Operability Test

SVI-P42-T5326 4 10/13/86 Surveillance Instruction Emergency Closed Cooling System Valve

Position Check, including Temporary Change Nos. 2 Through 7 and

Blanket Change Dated 2/17/95

SVI-R42-T5202 5 6/6/91 Weekly 125V Battery Voltage and Category A Limits Check (Uniti)

SVI-R42-T5211 4 11/15/91 Service Test of Battery Capacity (Unit 1, Division I)

SVI-R42-T5219 1 8/5/91 125V Battery Cat. B Limits, Terminal Corrosion and Electrolyte

Temperature Check (Unit 1, Division I)

SVI-R45-T1323 0 Surveillance Task Number S85-8528

TXI-0148 0 Temporary instruction - Division 3 Diesel Generator Timed Starts

Using One Bank Of Starters

VLI-P42 6 9/29/95 Valve Lineup Instruction Emergency Closed Cooling System, through

Plc No. 3 dated 10/16/96

SELF-ASSE5dMENT REPORTS

ISEG Report 91-005 10/27/92 HPCS and EGD SSFl Assessment Results

PA 95-23 03/20/95 System Based instrumentation and Controlinspection (SBICl)

C-10

, _ _ _ _ _ _ _ _ . _ _ _ . _ . . _ _ _ _ _ _ . _ . . _ . _ _ . _ _ . . _ _ _ _ _ . _ _ _ _ . _ _ _ _ - - . . _ _ _ . _ _

,

. .

!

-

5/1/95 System Operation and Review (SO TR) Reports, System Operation

and Test Review Program HPCS System Report

SAFETY ANALYSIS REPORT

-

l 10/02/89 Appendix R Evaluation: Safe Shutdown Capability Report l

l Secdon 1.8 NRC Regulatory Guide Assessment I

Sec6on 12.6 Design Review of Plant Shielding for Spaces / Systems Which May Be

Used in Postaccident Operations Outside Containment

Sec6on 15 Accident Analyses

Section 3.1 Conformance With NRC General Design Criteria (GDC 5,44,45,46)

Section 3.5 Missile Protection

Section 3.6 Protection Against Dynamic Effects Associated with the Postulated l

Rupture of Piping

Section 6.2.4.2.2.2 Justification With Respect To General Design Criteria 56

Section 6.2.7 Suppression Pool Makeup System

Section 6.3 Emergency Core Cooling System

Section 7.3.1.1.6 Emergency Water System (EWS) Instrumentation and Controls

Section 8.3 Onsite Power Systems

Section 9.2.2 Emergency Closed Cooling System

Section 9.3.3 Equipment and Floor Drainage System

Section 9.4.5 Engineered Safety Features Ventilation System

Section 9.4.9 Chilled Water Systems

Table 3.9-30 Summary Of Active Valves (Non-NSSS)

Table 0.3-1 Connected, Automatic and Manual Loading and Unloading Of Safety

System Switchgear

OTHER LICENSING DOCUMENTS

GESSAR 113.5.1.3 Missiles Generated By Natural Phenomena

GESSAR 113.5.2 Structures, Systems and Components To Be Protected Frcm

Externally Generated Missiles

1.RG 11 Response 1/25/82 Control Of Post-LOCA Leakage To Protect ECCS and Preserve

Paper Suppression Pool Level

LRG ll Working Paper 10/26/81 Control Of Post-LOCA Leakage To Protect ECCS and Preserve

Suppression Pool Level ,

NUREG-0887 5/82 Safety Evaluation Report Related To The Operation Of Perry Nuclear >

Power Plant, Units 1 and 2, including Supplements 1 Through 10

TECHNICAL SPECIFICATIOBS

Section 3.3.5.1 Emergency Core Cooling System (ECCS) Instrumentation

Section 3.5 Emergency Core Cooling Systems (ECCS) and Reactor Core

isolation Cooling (RCIC) System

Section 3.7.10 Emergency Closed Cooling Water (ECCW) System

Section 3.8 Electrical Power Systems

CODES. STANDARDS. GUIDES

IEEE 384-1974 IEEE Trial-Use Standard Criteria for Separation of Class IE

Equipment and Circuits

IEEE 387-1977 09/09/76 IEEE Standard Criteria For Diesel-Generator Units Applied As

Standby Power Supplies For Nuclear Power Generating Stations

!

l C-Il

l

l

t

l

t

-_ ._-

_. - .. _

. .

Regulatory Guide 0 11/00H5 Thermal Overload Protection For Eiectric Motors on Motor-Operated

1,106 Valves

Regulatory Guide 1 03/00/77 Thermal Overload Protection For Electric Motors On Motor-Operated

1.106 Valves

Regulatory Gu'de 04/0098 Tornado Design Classification

1.117

Regulatory Guide 05/00/83 Bypassed and Inoperable Status Indication For Nuclear Power Plant

1.47 Safety Systems

Regulatory Guide 04/00/74 Design Basis Tornado For Nuclear Power Plants

1.76

Regulatory Guide 1.9 0 03/00/71 Selection, Design and Qualification Of Diesel-Generator Units Used

As Standby (Onsite) Electric Power Systems At Nuclear Power Plants

Regulatory Guide 1.9 2 12/00/79 Selection, Design and Qualification Of Diesel-Generator Units Used

As Standby (Onsite) Electric Power Systems At Nuclear Power Pfar>ts

l

4

%

C-12

_ -

. .

!

Appendix D

List of Acronyms

,

AC Alternating Current l

AE Architect-Engineer

ANS American Nuclear Society l

ANSI American National Standards Institute I

AR Action Request

ARI Alarm Response Instruction

ASME American Society of Mechanical Engineers

ATWS Anticipated Transient Without Scram

B&PV Boiler and Pressure Vessel

BWR Boiling-Water Reactor

.

CEI Cleveland Electric Illuminating

CFR Code ofFederalRegidations

CR Condition Report

CST Condensate Storage Tank

DBA Design-Basis Accident '

DC Direct Current

DCP Design Change Package

DG Diesel Generator

DSP Design Specification

ECC Emergency Closed Cooling

ECCS Emergency Core Cooling System

EDDR Engineering Design Deficiency Report

EDG Emergency Diesel Generator

EPRI Electric Power Research Institute

ESW Emergency Service Water ,

l

FCD Functional Control Diagram

FDDR Field Deviatior Disposition Request

FLA Full Load Amperage

FPCC Fuel Pool Cooling and Cleanup

FSAR Final Safety Analysis Report

GDC Gcneral Design Criterion / Criteria

GE General Electric Co. i

GL Generic Letter l

D1

__ . _ _ _ _ _ _ _ _ ____ . _ . _ _ __ _ _

, , ,

I

l

I

HPCS High-Pressure Core Spray

I&C Instrumentation and Control

IE Inspection and Enforcement

IEEE Institute of Electrical and Electronics Engineers

IFI Inspection Followup Item

IMI Instrument Maintenance Instruction

IP Inspection Plan (or Inspection Procedure)

ISI Inservice Inspection

ISMG Instrument Setpoint Methodology Group

IST Inservice Testing

ISTP Inservice Testing Program

LER Licensee Event Report

LOCA Loss-of-Coolant Accident

LOOP Loss ofOffsite Power

LPCS Low-Pressure Core Spray

MCC Motor Control Center

MOV Motor-Operated Valve

NCC Nuclear Closed Cooling

NEI Nuclear Engineering Instruction

NPSH Net Positive Suction Head

NR Nonconformance Report

NRC U.S. Nuclear Regulatory Commission

NRR Nuclear Reactor Regulation, Office of(NRC)

NSSS Nuclear Steam Supply System

OER Operating Experience Review

ONI Off-Normal Instruction

P&ID Piping and Instrumentation Diagram

PIF Potential Issue Form

PNPP Perry Nuclear Power Plant

RCIC Reactor Core Isolation Cooling

RG Regulatory Guide

RHR Residual Heat Removal

RPV Reactor Pressure Vessel

SBICI System-Based Instrumentation and Control Inspection

SBO Station Blackout

! SDM System Description Manual

!

.

D-2

- . _ - . - - . - - - -

- . -. _ . - - - . - .. - . ..--- - .. - _ . .-. - . -

... .

.

.

SER Safety Evaluation Report  ;

SOI System Operating Instruction

'

SPCU Suppression Pool Cleanup

SRP Standard Review Plan

SRV Safety Relief Valve >

SSFI Safety System Functional Inspection '

SVI Surveillance Test Procedure ,

SWEC Stone & Webster Engineering Corporation

l

TCV Temperature Control Valve

TDH Total Discharge Ilead

TRD Testable Rupture Disc

l

TS Technical Specification (s)

URI Unresolved Item  !

!

USAR Updated Safety Analysis Report

WG _ Water Gage I

l i

l

i

t

l

I

l

,

l

?

l

t

l

'

D-3

. - . _ _ _. _ . _ _ _ . _ - . . . _ . . . . - . _ - . __ _ . - . . _ _ . _ . _ _ _ _ _ . - - _ _ _ _ . _ _ . _ . . _ _ _ _ _ .

. .

Attachment 1 -

,

Slides Used During Public Exit

t

l

l

\

I

i

-

,

1

\

i

Attachment 1-1

l

l

.

- --.- ---- - --- --_ -_. _ - . . . - - -

.

.

PERRY NL CLEAR PLANT, UNIT 1

.

.

DESIGN INSPECTION

,

EXIT MEETING

i

!

APRIL 22,1997 .

P

l

-

,

Attachment 1-2

- - - - - - --- - - - - - - - - - - --- - - - - - - - - - - - - - - - - - - ----------- -_ -- - ---- --- ---

1

I

OUTLISE OF PRESE
STATION

!

!

INTRODUCTIONS

i

-

l OBJECTIVES, SCOPE ASD SCHEDULE

1

INSPECTION RESULTS - GENERAL ASSESSENT

INSPECTION RESULTS - SPECIFIC FISDINGS

(

> CONCLUDING REMARKS

1

i

!

1

,

Attachment 1-3

1

4

b

e

,- -n, -w , -w--,-m-r-e-. -r-w r-w - r m += w - v e t dev tN **'-

- - - . - . - ----- -_ - - - - - _ - --- _ -- ----- - --- ---- -

-

.

'

i

,

-

INTRODUCTIONS

'

i

i

INSPECTION REPORT NO. 50-440/97-201

I

.

REPORT WILL BE ISSUED IN APPROXIMATELY 45 DAYS

1

! FOLLOWUP ACTIONS WILL BE BASED ON THE FINDINGS

i

AND MAYBE ACCOMPLISHED BY BOTH REGIONAL AND

HEADQUARTERS PERSONNEL

ENFORCEMENT ACTION WILL BE ISSUED BY THE REGION

Attachment 1-4

.

en

. . _ - - --- - --_ _ --- __ _ - _ - - _ _ . _ - - . . ._

i

!

OBJECTIVES

l

i

! DETERMINE IF PERRY MEETS ORIGINAL DESIGN BASES & TO VERIFY

! DESIGN BASES HAS BEEN MAINTAINED

!

SCOPE

I

EMERGENCY CLOSED COOLING SYSTEM

HIGH PRESSURE CORE SPRAY, INCLUDING THE DEDICATED DIESEL

GENERATOR

!

l SCHEDULE

,

STARTED FEBRUARY 17 COMPLETED MARCH 27

1

Attachment 1-5

i

-

e

-vw .a - _a__ - - -- - _ _ _ _ _ _ - - - - -_ - - - - - _ - - - - - - . _ - - _ . - _ - - _ _ _- - - _ _ . - _ . . _.__

. --. . . - . .

.

l INSPECTION RESULTS - GENERAL ASSESSMENT

i

l e THE TEAM DETERMINED THAT THE SYSTEMS ARE CAPABLE OF

PERFORMING THEIR INTENDED SAFETY FUNCTIONS.

l e CONTINUOUS OPERATION OF THE SUPPRESSION POOL CLEANUP

l SYSTEM RESULTS IN THE HIGH PRESSURE CORE SPRAY SYSTEM BEING

i

OPERATED IN AN ALIGNMENT DIFFERENT THEN DESCRIBED IN THE

i FSAR.

e ALTHOUGH THE LICENSEE'S SAFETY SYSTEM SELF-ASSESSMENTS DID

j NOT IDENTIFY AND CORRECT MANY OF THE ISSUES RAISED BY THE

,

TEAM, MANY GOOD ISSUES WERE IDENTIFIED AND CORRECTED. THE

SYSTEM BASED INSTRUMENT AND CONTROL SYSTEM INSPECTION ,

ALSO RESULTED IN THE IDENTIFICATION AND CORRECTION OF MANY

i ISSUES AS WELL. '

I

Attachment 1-6

, .

- .

_ _- -_ _ _ _-__- _ _-_ _ _ _ _ -___- -_ _ - _ _ --- - --- -- - - - - - - - - - - - -- - - - - _ _ _ _ . - _ - - - - - - _ _

- - - - - _- - - - _- - - _ _ - - _

i

e DESIGN OF THE EMERGENCY CLOSED COOLING SYSTEM WAS

Il . GENERALLY GOOD, WITH MORE THAN ADEQUATE MARGIN IN THE

DELIVERY SYSTEM. HOWEVER, WEAKNESS IN THE ORIGINAL DESIGN

i

OF THE SURGE TANK COMBINED WITH BOUNDARY VALVE SEAT

l

'

LEAKAGE HAS RESULTED IN EARLY MANUAL OPERATOR ACTION

THAT MAY CONSTITUTE AN UNREVIEWED SAFETY ISSUE.

e THE HIGH PRESSURE CORE SPRAY SYSTEM IS CAPABLE OF

1

PERFORMING ITS REQUIRED SAFETY FUNCTION. HOWEVER, THE

SYSTEM HAS LITTLE MARGIN AS TO REQUIRED FLOWS AND TIME

i

RESPONSE. CURRENT OPERATING PRACTICES (SPEED DROOP AND

l OPERATION OF SPCU) ALSO IMPACT SYSTEM MARGIN.

j e THE QUALITY OF CALCULATIONS WAS MIXED. NEWER ONES WERE

,

BETTER THAN OLDER ONES. ELECTRICAL CALCULATIONS WERE NOT

j

BEING UPDATED AS REQUIRED. DESIGN CHANGES REVIEWED WERE

GENERALLY GOOD.

!

i

Attachment 1-7

>

.

.

. _ _ _ . _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ . . - _ _ _ _ _ _ . _ . _ _ . _ . - _ _ _ _ _ _ _ _ . _ _ . _ _ _ _ _ __ __ _ _ _ _ - . . _ . _ _ _ _ _ _ _ _ _ _ - _ _ _

_ _

_ _ _ _ _ _ - - - _.

_

,

e CORRECTIVE ACTION FOR DIVISION III DIESEL EXHAUST TESTABLE

RUPTURE DISK FAILURES HAS BEEN SLOW. ADDITIONALLY, YOUR

STAFF IDENTIFIED THAT THE OVERFREQUENCY RELAY FOR HIGH

PRESSURE CORE SPRAY PUMP DISCHARGE PIPING OVERPRESSURE

l PROTECTION WAS NOT INSTALLED. HOWEVER, THE TECHNICAL

j REVIEW FAILED TO ADEQUATELY CORRECT THIS CODE ISSUE.

e AFTER REMEDIAL ACTIONS BY PERRY THE TEAM DID NOT HAVE ANY

UNRESOLVED OPERABILITY CONCERNS. PERRY IS ADDRESSING LONG

TERM ISSUES THROUGH THE CORRECTIVE ACTION PROCESS

Attachment 1-8

,

9

__ - _ - _ _ _ _ _ _ _ _ _ _ _ _ _ - - _ ..

INSPECTION RESULTS - SPECIFIC FINDINGS

10CFR 50.59 EVALUATIONS

  • SAFETY EVALUATION TO SUPPORT MANUAL OPERATOR

INTERVENTION TO REFILL ECC SYSTEM SURGE TANK APPEARED

INADEQUATE.

  • THERE WAS NO ENGINEERING OR SAFETY EVALUATION PERFORMED

WHEN EDG SPEED DROOP WAS CHANGED FROM WHATTHE VENDOR

RECOMMENDS AND FROM HOW THE EDG WAS ORIGINALLY TESTED

FOR QUALIFICATION. .

  • CONTINUOUS OPERATION OF THE SPCU SYSTEM IMPACTS HOW THE

HPCS SYSTEM IS ALIGNED AND THE NORMAL POSITION OF

CONTAINMENT VALVES. THIS DIFFERS FROM THE FSAR DESCRIPTION

AND THERE WAS NO SAFETY EVALUATION PERFORMED.

Attachment 1-9

L

e

-_ __ -_ . _ _ _ - - - - - - - _ - - - - - - - - - - - - - - - _ - - _

3 TORNADO MISSILE PROTECTION

e PORTIONS OF THE HIGH PRESSURE LORE SPRAY SUCTION PIPING

FROM THE CONDENSATE STORAGE TANK (CST) AND CST INSTRUMENT

,

LINES WERE NOT PROTECTED AS DESCRIBED IN THE FSAR.  !

,

TESTING ISSUES

.

l

! e PREVIOUS AND CURRENT TESTING OF HPCS ROOM COOLERS APPEAR

'

TO DEVIATE FRO-M COMMITMENTS

i

. e METHOD OF TESTING EDG TRD DOES NOT ALWAYS ENSURE

!

,

REPEATABLE RESULTS

!

e TESTING OF ECC/NCC SYSTEM INTERFACE VALVES DOES NOT PREDICT

ACTUAL VALVE LEAKAGE

j e

LEAK TESTING OF SUPPRESSION POOL CLEANUP SYSTEM. INLET

! VALVES IS NOT BEING PERFORMED

,

i

Attachment 1-10

t

4

1

-, , , . , , - , . ,_.....,v.,_,., ._. , .w._r. ,. - .. . - . . , , , . . . . . .. _ _ - . , , ... _ _ , , .. , , , , _ . ,,, .. y . . ,,m. . , _ , , , . _ , - . , , _ , , ,- . . , - - , -e - . - . , 3

__ - . _-_ , - ._ . _ _ _ _ _ _ - - - - _ _ - - _ _ _ _ _ _ _ _ - - - - - _ _ _ - - - - _ _ - . - _ -

. - - - - - - - - _

4

!

!

l DESIGN CONTROL ISSUES

! * CONTROL OF CALCULATIONS

!

1

QUALITY AND ACCURACY OF CALCULATIONS

j DOCUMENTATION ISSUES

l

l * FSAR DISCREPANCIES

,

'

j FAILURE, NON-SEISMIC PIPING DESIGN)

!

MAINTENANCE ISSUES

!

!

1 * CLOGGED FLOOR DRAINS, MISSING HANGER, AND BATTERY

j

HOLDDOWN BRACKETS NOT PER DRAWING .

(

i

,

Attachment 1-11

.

1

. _ _ , , . _ . . .

. . . - - - .