ML20217M131
ML20217M131 | |
Person / Time | |
---|---|
Site: | Perry |
Issue date: | 04/29/1998 |
From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
To: | |
Shared Package | |
ML20217M101 | List: |
References | |
50-440-98-07, 50-440-98-7, NUDOCS 9805040443 | |
Download: ML20217M131 (20) | |
See also: IR 05000440/1998007
Text
I
'
U.S. NUCLEAR REGULATORY COMMISSION
REGION lli
Docket No: 50-440
License No: NPF-58
!
Report No: 50-440/98007(DRS)
Licensee: Centerior Service Company
i
Facility: Perry Nuclear Power Plant
Location: P. O. Box 97, A200
Perry, OH 44081
l
Dates: February 23 to March 5,1998
- Inspectors
- R. Bailey, Reactor Inspector
l M. Bielby, Reactor inspector
i J. Clark, Resident inspector
! C. Lipa, Senior Resident inspector
Approved by: M. Leach, Chief, Operator Licensing Branch
Division of Reactor Safety
!
!
l
!
9905040443 990429
PDR ADOCK 05000440
0 PM
i
!
'
i
I
! .
! EXECUTIVE SUMMARY
Perry Nuclear Power Plant
! NRC Inspection Report 50-440/98007
This operational assessment team inspection (OATI) included aspects of licensee operations,
engineering, and maintenance. The report covers a 2-week period of on site inspection of the
conduct of operations which included a continuous 72-hour period of control room observation.
The conduct of operation's activities at the Perry facility were good; however, the
communication of management expectations was not always clear. The NRC observations
l
noted inconsistencies during operator panel walkdowns and control panel deficiency tagging.
f
The following specific observations were made:
i
Operations
e Shift crew briefings and tumovers were consistent and effective sources of information
to ensure continued safe operations. However, special evolution briefings and turnovers
l were not always conducted in accordance with program guidance. (Section O1.2)
- * A wide diversity in time intervals between panel walkdowns and the quality of panel
l monitoring raised a concern that operators were indifferent to indication problems and,
in some cases, lacked a questioning attitude. (Section 01.3)
e Formal communications resulted in an effective exchange of information among
i operators and other plant personnel. Generally, commands and directions were clear
and concise with repeat backs being expected. (Section 01.4)
e Control room operators effectively coordinated plant personnel during maintenance and
testing evolutions to identify expected plant response and annunciator alarms. (Section
O1.5)
- Work control pre-job briefings emphasized procedure compliance, contingency action
plan, and termination criteria with attention on self checking and personal safety.
However, the pre-job briefing for a reactor core isolation cooling post-maintenance test
failed to include quality control personnel which resulted in an unnecessary challenge to ,
plant operators when an unanticipated heatup of the suppression pool above an I
administrative limit occurred. (Sections 01.6 & M1.1)
e Control room deficiency identification and tagging guidelines were not clearly
i
established and communicated through procedures and instructions. (Section 01.7)
- During the performance of work under a safety tagout, an operator removed the wrong
,
safety tag and installed a fuse in the wrong panel which energized a system tagged out
l for maintenance and jeopardized personnel safety. (Section 01.8)
!
i
2
l
l
l
l
.
,
Maintenance
e A reactor core isolation cooling system testing evolution was conducted within
procedural guidelines. However, a number of deficiencies had been identified in the
planning and implementation of the testing process.' (Section M1.1)
e- Prior to reactor core isolation cooling system maintenance, a pre-job walkdown failed to I
identify the inaccessibility of several steam Jet plugs.' Additionally, maintenance
personnel failed to document management's action to correct work procedure problem. l
(Section M3.1)
Engineering
e A calculation deficiency existed in the licensee's determination of the 7-day diesel
generator (DG) fuel oil supply quantity for division-3. The calculation revealed a
required amount that was not consistent with TS and no corrective action had been
implemented for almost two years. The calculated difference required a TS change to 4
address a non-conservative requirement which constituted a violation of regulatory
requirements. (Section E1.1)
i
j
l
l
,
3
l
I
,
....
,,
.
Report Details
Summary of Plant Status
The Unit operated at or near full power for the duration of the inspection period. '
l. Operations
01 Conduct of Operations
l
l
01.1 General Comments
The inspectors conducted an observation of routina control room activities during a
continuous 72-hour period using Inspection Procedures (IP) 93802 and 71707 as -
guidance. Additionally, the inspectors assessed the licensee's ability to control
maintenance activities and surveillance testing, and provide technical staff support
during routine plant operations. In general, conduct of operations was professional and
focused on operational safety. Specific observations and findings are listed in the
following sections.
01.2 Shift Mannina and Relief Tumovers
a. Insoection Scoce (71707. 93802)
l
The inspectors assessed the licensee's operating shift tumovers and briefings
conducted during the continuous 72-hour monitoring period. The inspectors also
assessed the licensee's effectiveness to control plant operations and coordinate support
activities with the current shift manning. The following procedures were considered in
the process:
- PAP-0126," Shift Relief and Tumover," Revision 0
v PAP-0201," Conduct of Operations," Revision 9
b. Observations and Findinas
Each control room crew consisted of two licensed senior reactor operator positions, Shift
Supervisor (SS) and Unit Supervisor (US); and three licensed reactor operator positions,
Supervisory Operator /At-The-Controls (SO-ATC), Supervisory Operator / Extra (SO-E),
and Operations Foreman (OF). Additionally, each crew consisted of two non-licensed
operator positions: Perry Plant Operators (PPO) and Perry Plant Attendants (PPA), who
performed rounds and system alignments outside of the control room. The inspectors
l
determined that an appropriate level of manning had been maintained.
Shift relief personnel were generally observed arriving early and performing a detailed i
discussion and panel review of plant and equipment status, log entries, planned work,
and operating priorities from their counterparts. During the on-coming shift briefings, the
4
L
inspectors observed a reaffirmation of turnover information with emphasis on personal
safety awareness. An open dialog was normally observed at the briefings, versus
simple dissemination of information from supervision. Although operations personnel
did not express a difficulty in hearing others that spoke, the inspectors had difficulty
hearing all of the brief at varied positions on the edge of the briefing area.
The inspectors also observed some special evolution briefings and subsequent task
performances with noted differences in personnel performance. During a post-
maintenance run of the reactor core isolation cooling (RCIC) turbine, the dedicated
control operator was directed to establish suppression pool cooling. Following initiation
of the task, a shift relief operator was requested to relieve the on-shift control operator
and finish establishing suppression pool cooling. Although the relief operator had
conducted a pre-shift walkdown, no special evolution briefing or detailed tumover was
observed which deviated from program guidance The inspectors noted that an extra on-
shift control operator, who had participated in the evolution briefing, was available but
was not asked to perform the evolution.
c. Conclusions
Shift briefings and turnovers were consistent and effective sources of information to
ensure continued safe operations. However, special evolution briefings and turnovers
performance were not always conducted in accordance with program guidance and
lacked formality.
O1.3 Ooerator Attentiveness to Duty and Panet Monitorina
a. Insoection Scoce (71707. 93802)
The inspectors assessed the licensee's ability to monitor control panel indications during
routine operator walkdowns and to determine all conditions adverse to continued
operations. These observations were conducted during the continuous 72-hour
monitoring period. The following procedures were considered in the process:
o PAP-0201, " Conduct of Operations," Revision 9
e Operations Policy item 1-6, " Control Room Monitoring," dated August 15,1996
b. Observations and Findings
The inspectors observed control room operators during the performance of panel
walkdowns both inside and outside of the horse-shoe control area. The inspectors ,
noted the following regarding the effectiveness to perform horse-shoe panel walkdowns: 1
(1) Each SO-ATC was expected to conduct a panel walkdown inside the horse-shoe
control area approximately once every hour. However, the inspectors noted that
the time between each panel walkdown varied from approximately 30-minutes to
90-minute intervals, with the longest period observed being almost 180 minutes.
5 ,
i
.
^
(2) In general, each SO-ATC was attentive to plant status as evidenced by routine
reviews of each panel's indications and controls. As a follow-up, the inspectors
questioned selected operators about system status and specific panel indication
or control status. The inspectors determined that the operators were
knowledgeable of the items in question. However, the inspectors observed that
a few operators would routinely perform a general scan of the entire control
panel area while sitting / standing in one chosen position. The inspectors had
difficulty determining the status of some major equipment while performing a
similar panel review.
(3) On more than one occasion, the inspectors observed the SO-E position
performing a temporary relief of the SO-ATC position. The inspectors were
informed that operators routinely performed interim reliefs to allow for an
independent review of panelindications and controls.
Each SO-E performed a walkdown of the panels located outside of the horse-shoe area
twice a shift or about once every four hours. At the beginning of each shift, the first
panel walkdown included taking a set of required Technical Specification logs.
Sometime during the middle of shift, the same operator would perform a second
walkdown of the same control panels. The inspectors also observed that the SS and
US made an independent tour of the same panels at least once during the shift which
usually occurrad at the middle of each shift. However, the inspectors noted that the time
between panel walkdowns varied widely from about 2-hours to 4-hours.
A number of deficiencies on the control panels located outside of the horse-shoe area
were not addressed in a timely manner. One of these deficiencies became readily
obvious during an operator's panel walkdown prior to shift tumover. The following items
were noted:
e The inspectors identified an off gas post treatment recorder (D17-R601) with one
of two channels not indicating (ink pen failure) for approximately three hours.
!' The licensee promptly replaced the non-inking pen which corrected the problem.
However, the positioning of the replacement pen caused the other channel's pen
l to stick such that it stopped inking for approximately three hours, until identified
and corrected.
! * The inspectors identified indications for a reactor recirculation flow control valve
I
hydraulic power unit subloop fan had a very dimly illuminated indication (bulb lit
!
on only one of a four-bulb group). The inspectors had a difficult time in
determining whether the bulb was illuminated or not. The inspectors discussed
the observation with the control operators, who verified the indication was dim
l
'
and replaced the bulb once management concurrence was received. Other
dimly illuminated indication bulbs were observed on various control panels.
e The inspectors identified a reactor head vent valve (B21-F005) with intermediate
position indication (both the open and closed indicating lights were illuminated) at
a time when plant operations required the valve to be open. The SO-ATC was
6
e
I
I
'
questioned as to the valve's position for which he responded "The valve is open."
! After repeated questioning, the licensee determined that the closed indicator
!
bulb was grounded causing it to be illuminated. The indicator bulb was replaced
and the valve position was verified to be full open, as expected.
l * The licensee identified an equipment area 6T recorder (E31-R611) which printed
for over 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> at below scale reading before being noticed by an oncoming
operator. The licensee promptly corrected the deficiency with no other problems
noted.
!
,
Operations personnel were generally attentive to the control room panels. However,
inconsistencies in panel walkdown frequencies and level of deta:1 were noted, as
discussed above. These inconsistencies were considered a negative finding by the
inspectors.
l c. Conclusions
! 1
A wide diversity in the frequency of panel walkdown and quality of panel monitoring
raised a concern that operators were not consistently implementing management
l
expectations. Also, an indifferent atmosphere was noted during monitoring of plant
i
conditions and, in some cases, a questioning attitude toward equipment status was not
evident.
i
01.4 Control Room Communications
a. Insoection Scoce (71707. 93802)
l
f The inspectors observed the licensee's communications among various control room
l operators and between plant personnel located outside the control room. Additionally,
l the inspectors observed communications between the various departments during
i
maintenance and testing evolutions. The following procedure was considered in the
process:
l e Operations Policy item 1-2, " Operations Section Communications Policy," dated
February 18,1997
b. Observations and Findinas
i
, in general, good verbal commun. cations were being consistently used by the control
l room operators during all plant evolutions. Management's expectation of using 3-way
j communication skills (i.e. sender's statement - receiver's repeat back - sender's
'
acknowledgment) during all forms of verbal communication was being implemented. A
few instances of improper 3-way communications were promptly corrected by another
operator or the supervisor. The inspectors observed that inplant operators and
attendants used 3-way communications when discussing rounds and when performing
equipment manipulations.
7
f
E '
. . .
l
. The inspectors observed that support personnel (i.e. maintenance or engineering) were i
also required to use 3-way communication skills when discussing work activities with the
control room operators. On r,everal occasions, the US or SS would require
maintenance personnel to repeat-back directions or action commands during testing.
These discussions also required the use of an approved phonetic alphabet.
During the performance of post-maintenance testing on the RCIC turbine (See Section
M1.1 discussion), the inspectors noted a decline in formal communications during
unanticipated plant changes, such as, increasing suppression pool temperature with
suppression pool cooling required.
c. Conclusions
Formal communications resulted in an effective exchange of information and
understanding between operators and other plant personnel. Generally, commands and
directions were clear and concise, and easily repeatable. Additionally, the timely
correction of improper communications by other operators was consistent with
management's expectation.
01.5 Ooerator Resoonse to Alarms and Annunciators
a. Insoection Scone (71707. 93802)
The inspectors assessed the control room operators' ability to respond to expected and I
unexpected control panel annunciator alarms during the continuous 72-hour monitoring
period. The following procedure was considered in the process:
e . Operations Policy item 2-4, " Control Room Response to Annunciators," dated j
August 15,1996 ;
.
b. Observations and Findinas j
l
A majority of the annunciator alarms received during surveillance or testing evolutions
were identified as " expected." Operators were observed discussing planned work
evolutions with plant personnel to establish which annunciators would be received for a !
given activity.- For unexpected annunciator alarms, in general, the SO-ATCs would
acknowledge and announce each alarm to the US or SS, reference the appropriate
Alarm Response Instruction, and dispatch appropriate personnel to investigate the j
problem. Both the US and SS remained in a position of command and control, and l
periodically provided guidance to the Supervisory Operator who was addressing the
event.
c. Conclusions
Control room operators effectively coordinated with maintenance and testing personnel
to identify expected plant responses and annunciator alarms requiring operator
response. Appropriate responses were noted during abnormal situations.
8
_ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _
'
01.6 Work Control and Evolution Briefinos
a. Insoection Scooe (93802)
The inspectors assessed the licensee's effectiveness at conducting pre-job briefings and
controlling work in progress during the continuous 72-hour monitoring period. The
following procedures were considered in the process:
- PAP-0201, " Conduct of Operations," Revision 9
e PAP-1121, " Conduct of Infrequently Performed Tests or Evolutions," Revision 1
e SOI R42 (Div 2),"Div 2 DC Distribution, Buses ED-1-B and ED-2-B: Batteries,
Chargers, and Switchgear," Revision 0
e sol B33, " Reactor Recirculation Flow Control Valve Hydraulic Power Unit
Subloop A-1," Revision 6
- Policy item 2-9, " Operational Activity Evaluation," dated February 24,1997
b. Observations and Findings
A pre-job brief was held on February 20,1998, for the post maintenance testing of the
RCIC turbine. Each step of the procedure was reviewed, including notes and cautions.
Actions and required communications were clarified with emphasis on self checking and
personal safety. However, quality control personnel needed to verify the post
maintenance work were not included in the briefing. (See Section M1.1 for more details)
A pre-job brief was held on February 23,1998, for restoration of the Unit 2, Division 1
batteries to a float charge which followed an equalizing charge evolution. The OF led the
brief and referenced guidance in a prepared Pre-Job Checklist. Appropriate personnel
were in attendance which included two PPOs and one PPA assigned to perform the sol
procedure. Each step of the procedure was reviewed, including notes and cautions.
Actions and required communications were clarified. Related industry and Perry specific
events were discussed. The OF emphasized the importance of self checking and
verification in reference to manipulation of equipment effecting both units. Termination
criteria were established as any unexpected or misunderstood events that may occur
during the evolution.
A pre-job brief was held on the February 24,1998, for restoration of the reactor
recirculation flow control valve hydraulic power unit subloop A-1 to service after
replacement of filter elements that had been leaking. The US led the briefing and
reviewed procedure steps, notes and cautions. Safety precautions and their importance
were emphasized. Contingency actions for an unexplained change in reactor power and
an unexpected or unisolable fluid leak were reviewed and clarified. Additionally, the
licensee stationed an extra licensed operator at the recirculation control panel for
monitoring of the flow control valve operation during restoration.
9
,
___-__ __
The related work activities were completed satisfactorily with no problems identified. I
Control operators maintained a positive control over the evolution with emphasis on !
proper communications. I
I
c. Conclusions !
In general, pre-job briefings were conducted in a formal manner and contained an
appropriate level of information. Procedural steps, notes and cautions were thoroughly
reviewed with contingency actions being clarified, and attention to self checking and
personal safety were emphasized. However, necessary personnel were not always in
attendance during the briefing process.
01.7 Eauioment Deficiencv Identification i
a. Insoection Scoce (93802)
The inspectors assessed the licensee's awareness of component and system status
which included the identification and tagging of system deficiencies that affected control
room operations. Additionally, the inspectors questioned selected operators about the
process for identifying and tracking control room deficiencies. The following procedure
was considered in the process:
o PAP-0902, " Work Request System," Revision 9
b. Observations and Findinas
The operators demonstrated appropriate knowledgeable of the process and were able
to identify deficient equipment located on the control room panels which affected remote
operations capability. The US was observed performing routine updates to the Rolodex
file, at or near the end of each shift. However, a disparity was noted among the control
room operators as to the minimum threshold to tag a component and the type or level of
deficiency needed to be maintained in the control room Rolodex file.
The inspectors were informed that management expectations had been discussed in an
operations department memorandum, dated January 18,1998, which implemented the
use of a Rolodex filing system to track each deficiency. The management directive
emphasized a reduction in the multiplicity of tags on the control panels to reduce the
distraction associated with redundant tag information The control operators were
aware of the management directive but a copy was not available in the control room.
Management expectations were unclear as to the tagging of deficient control room
equipment.
Additionally, section 6.1 of PAP-0902 provided some guidance on when to place a
deficiency tag / sticker on a faulty piece of equipment and how to write a work order once
it had been identified. However, the inspectors expressed a concern that the procedure
l
l
10
I
i
r
l was vague and open to interpretation. Specifically, the operators must make a
!
judgement evaluation as to whether a deficiency sticker would be needed or was
! required.
Conclusions
l
,
The process of identifying and labeling deficient equipment was not being implemented
l in a consistent manner. Management failed to provide clear and concise expectations
l through procedures and instructions as to the proper method of identifying and tagging
l deficient equipment.
01.8 Safety System Tagaing
a. Insoection Scoce
The inspectors assessed the licensee's safety system tagg;ng and isolation program
during the continuous 72-hour monitoring period. This included the review of a
clearance package and a Potential Issue Form (PlF 98-377) associated with safety
system tagging removal activity. The following procedure was considered in the
process:
! * PAP-1401, " Safety Tagging," Revision 8
b. Observations and Findinas
(1) Two PPAs were observed performing a clearance package which required the
removal of safety tags and the restoration of the Feedwater Booster Pump "C"
system alignment. The safety tag removal was performed in accordance with
the prescribed procedure and the PPAs used good self checking techniques (i.e.
verified each tag matched the clearance sheet and component labeling prior to
sign off and removal of the tag). Additionally, the PPAs used the appropriate
tools and safety precautions during the electrical equipment restoration.
(2) On February 27,1998, the inspectors were informed that while performing a
temporary lift evolution, a licensed operator removed an incorrect tag and
inserted a fuse for an incorrect system component. The operator error became
immediately apparent when an unexpected annunciator alarm occurred on the
control panel for the annulus exhaust gas treatment system (AEGTS). The
licensee identified that no work had been in progress on the AEGTS system at
the time the fuse was installed. The licensee documented the occurrence on PlF
98-377. The incorrectly removed tag was promptly restored and verified. The
operator acknowledged in a written statement that he failed to properly verify the
panel and tag numbers matched the temporary lift document before performing
the evolution.
l
Immediately following the event, the licensee initiated corrective actions to suspend all
tagging activities and have all operational personnel receive training on safety tagging.
11
The inspectors noted that a similar personnel error occurred on August 19,1997, as
discussed in Inspection Report 50-440/97012 (DRP). In that case, a non-licensed
operator had removed fuses from a wrong cubicle, which resulted in a loss of power to a
safety-related bus and actuation of several containment isolation valves.
TS 5.4.1.a specified, in part, that written procedures shall be implemented covering the
applicable procedures recommended in Appendix A of Regulatory Guide 1.33, Revision
2, February 1978, which specified equipment control activities, such as tagging. Section
6.11.8 of PAP-1401 specified that the operating representative assigned to remove tags
shall verify the tag to be the correct one by comparison of its tagout number and MPL
number with the listed information on the temporary lift form. The licensed operator's
failure to comply with the requirements in PAP-1401 was a violation of the licensee's
technical specifications. (VIO 50-440/98007-01(DRS))
c. Conclusions
A licensed operator's incorrect action to remove the safety tag and replace a fuse on a
wrong component was contrary to the licensee's procedure and a violation of the
licensee's technical specifications. The inspectors were made aware that a similar
occurrence had been identified by the licensee during another implementation of the
safety tagging program. The licensee's management response was timely and
appropriate.
03 Operations Procedures and Documentation
O3.1 Procedure Revision and Format
a. Insoection Scoce (71707)
The inspectors reviewed operational and administrative procedures during the course of
the 72-hour observation. This review included an assessment of each procedure's
adequacy. The foliowing procedures were considered in the process:
- PAP-0201, " Conduct of Operations," Revision 9
- PAP-0507," Preparation, Review, and Approval of Procedures and instructions,"
Revision 12
- PAP-0522, " Changes to Procedures and Instructions," Revision 9
e SOI-R45/E22B, " Division 3 Diesel Generator Fuel Oil System," Revision 5
b. Observations and Findinas
The control room operators consistently referenced current System Operating
Instructions (sol) and Annunciator Response Instructions (ARI), when required.
However, the inspectors identified one concem regarding the clarity of instructions in
12
Section 2.0.2 of SC;-R45/E228. The instruction specified that when the fuel oil storage
tank level decreased to 95% then order more fuel oil. The inspectors determined that
tank level had been 94% or less between January 21 and February 25,1998, and fuel
had not been ordered as of February 25,1998. Operations Department Management
informed the inspectors that a note in the procedure made a clarification that
engineering would be consulted to determine when to add additional fuel oil. The
inspectors determined that the procedure's intent was vague because it clearly stated
the expectations for ordering fuel oil but did not specify when to refill the tank. The
licensee noted the problem and agreed to review and revise the procedure, as needed.
The inspectors were able to verify that the existing tank volume had met TS
requirements during the time in question.
c. Conclusions
The licensee's procedures were written consistent with program guidelines and provided
the appropriate level of direction, with one exception as noted above.
II. Maintenance
M1 Conduct of Maintenance
M1.1 Post-Maintenance Testino and Surveillances
a. Insoection Scoce (61276)
The inspectors observed the post maintenance run and surveillance testing of the RCIC
pump turbine. The following procedure was considered in the process:
e PAP-0201, " Conduct of Operations," Revision 9
The following post maintenance and TS surveillance tests were reviewed:
- TS Rounds for Modes 1,2, & 3; week of February 16,1998, and week of
February 23,1998.
l 1
e SVI-E51-T2001, "RCIC Pump and Valve Operability Test," Revision 10 l
e SVI-M16-T2001, "Drywell Vacuum Breaker and Isolation Valve Operability Test,"
Revision 5. j
1
e SVI-M45-T1323, " Remove Water From Fuel Storage Tanks," Revision 3.
e SVI-R43-T1318," Diesel Generator Start and Load Division 2," Revision 6.
13
l
)
'
b. Observations and Findinas
The inspectors identified a number of concerns during the conduct of the RCIC turbine
post maintenance testing on February 20,1998, including: (1) lack of coordination j
among support groups; (2) complex sequencing of multiple tests; (3) decline in three- I
way communications during unexpected evolutions; and (4) poor evolution turnover
during suppression pool cooling setup.
(1) Post maintenance testing of the RCIC turbine required a quality control (QC)
inspector to verify that steam leak reduction work activities had been properly
performed. The QC inspector was not included in the pre-job briefing, but had
been made aware that testing would be going on sometime that day. The QC
inspector was not contacted until approximately 25-minutes into the RCIC turbine j
run, when he was directed to begin a system walkdown. The QC inspector
began a system walkdown approximately 55-minutes into the planned 1-hour
run. The inspectors expressed a concern that the pre-evolution briefing had not
incorporated all key personnel. l
(2) The pre-job briefing by an operations supervisor had included a direction that
suppression pool temperature should be allowed to increase to approximately
90 F. The purpose was to allow subsequent testing of the combustible gas
compressors which resulted in a cooling of the suppression pool. Operations
management considered the evolution to run the RCIC turbine for 1-hour as a
normal event. Also, the licensee noted that performing a follow on test activity
was a routine evolution. However, the inspectors questioned the management's
reasoning that scheduling two complex evolutions back-to-back should not be
considered an infrequently performed test or evolution (IPTE) as discussed in
Section 6.3 of PAP-0201. The inspectors expressed a concern following a
critique of operator performance that non-routine evolutions were considered
routine, j
!
(3) During surveillance testing of the RCIC turbine, the licensee acknowledged that {
suppression pool cooling would normally be started early in the evolution to I
minimize any temperature rise as a result of the turbine run, in this case,
however, the licensee had pre-established suppression pool temperature at
approximately 70*F, such that the planned one hour run would not increase pool
temperature above 90*F. An administrative limit of 95'F was established for
starting suppression pool cooling, if needed, but was not anticipated.
The QC inspector's untimely inspection of the RCIC system caused the required
run time to be extend beyond the 1-hour anticipated run period. Suppression
- pool temperature was allowed to rise to 93*F before direction was given to place
I suppression pool cooling in service. The pool temperature exceeded 95"F
before pool cooling was initiated, and increased to 97*F before pool temperature
was stabilized. The inspectors observed a decline in 3-way communications
during this period and expressed a concern that performance had deviated from
those observed during stable plant conditions. j
14
(4) Following the need to place suppression pool cooling in service, the dedicated
RCIC turbine control operator was directed to place the residual heat removal
(RHR) system into suppression pool cooling mode. While establishing the
system lineup, the US directed an on-coming shift relief operator to place the
RHR system in service. The inspectors observed the relief operator look at the
procedure, then perform equipment realignment, as required. Section A.3 of
Attachment 1 in PAP-0201 specified that during equipment manipulations or
activities, if personnel positions change, then the following items shall be
discussed: (1) status of the activity in progress; (2) changes since last worked
on equipment; and (3) present condition of out-of-position components. The
inspectors were informed that the relief operator had reviewed the procedure
and discussed where the control operator had stopped. However, the inspectors
expressed a concern that an incomplete evolution brief and turnover had taken
J
place.
The inspectors determined that no primary containment challenge had occurred during
the pool temperature rise. However, the inspectors noted an indifferent attitude toward
the implementation of multiple planned evolutions.
l
c. Conclusions l
Although the RCIC turbine testing had been conducted within procedural guidelines, the
inspectors were concerned that a number of deficiencies had been identified in the
planning and implementation of the testing process.
M3 Maintenance Procedures and Documentation
M3.1 Work Package Documentation
a. Insoection Scoce (62707. 93802)
The inspectors reviewed the maintenance work package for the RCIC turbine to assess
work control effectiveness. The following procedures were considered in the process:
o PAP-0905, " Work Order Process," Revision 15, dated July 31,1996
- W.O.# 970002020," Identify Leaks on the RCIC Turbine, Tighten Casing Bolts
and Jet Plugs," dated February 10,1998
b. Observations and Findinas
The work package was reviewed and approved in accordance with program guidance.
The work package procedure included a step to tighten seven steam jet plugs.
However, four of the seven plugs were not accessible to the workers which left only
three plugs available. The workers tightened the three accessible plugs and placed a
note in the progress description log confirming the non-conformance action taken. The
inspectors noted the following deviations from program guidance:
I
15
r-
.
(1) Section 6.3.4 of PAP-0905 specified that the work group supervisor was
responsible to ensure the work to be performed could be done as written. The
inspectors expressed a concern that the work package had been approved for
!
implementation without a clear understanding of the work conditions or
limitations.
(2) Section 6.4.1.5 of PAP-0905 specified that the worker was responsible to
perform the work as identified on the work instruction. However, the inspectors
expressed a concern that no procedural guidance existed to address or
, document a deviation from the work procedure. Additionally, no documentation
of the management concurrence had been noted. The inspectors were informed
that the workers had contacted their work supervisor and the control room
supervisor to inform each of the problem encountered.
'
The licensee acknowledged the inspectors' concems. The licensee agreed to review
the concems for possible revision to the process. The inspectors were informed by the
licensee that management expectations had not been satisfied when the workers failed
to document the supervisor's concurrence.
l'
c. Conclusions
The RCIC turbine maintenance had not been completed in accordance with approved
work instructions. The work package documentation of a change to the work performed
was not consistent with management expectations in that maintenance personnel failed
to note management concurrence with actions taken.
Ill. Enaineedng
E3 Engineering Procedures and Documentation
E3.1 Desian Basis Review of Emeraency Diesel Generator (D6) Fuel Oil Reauirements
a. Insoection Scooe
The inspectors reviewed surveillance test data for the emergency diesel generators
(DG). This included a review of past surveillance tests on the diesel generators and the
fuel oil storage tank levels. The inspectors also reviewed and compared related
Technical Specifications, Sys.am Operating Instructions, and the Updated Final Safety
Analysis Report to supporting calculations.
b. Observations and Findinas
The inspectors identified two discrepancies between the calculated and TS values for
emergency DG fuel oil storage tank requirements on all three divisions. The following
concern was noted during a review of the engineering calculation R45-9, Revision 4, ;
dated January 26,1996:
,
16
f
\.
e The minimum required fuel oil volume for 7-days of continuous operation for the
! division-3 DG was determined to be 36,700 gallons. The calculated volume was
! greater than the TS 3.8.3 minimum requirement of 36,100 gallons. The
'
inspectors noted that the system engineer had rounded the value down to agree
with the TS value and were concerned that a non-conservative approach to safe
operations had been applied to the TS value.
- The minimum required fuel oil volume for 6-days of continuous operation for the
Division 1 and 2 DGs was determined to be 62,400 gallons. The calculated
l volume was less than the TS 3.8.3 minimum requirement of 65,100 gallons.
l
The inspectors expressed a concern that the licensee needed to address the design
calculation and TS difference to ensure continued safe operations. The licensee
acknowledged that a TS change was required and initiated PlF 98-496, A prompt
operability determination was made which determined that an adequate amount had
i existed in the tank. The licensee had put administrative controls in place to ensure tank
levels remained above the calculated minimum value.
Criterion lil of 10 CFR 50, Appendix B, states, in part, that measures shall be
established to assure the applicable regulatory requirements and design basis for
structures, systems, and components are correctly translated into specifications,
drawings, procedures, and instructions. The failure to translate division-3 emergency
DG fuel oil tank quantity into the technical specifications resulted in a violation of
Criterion lil in Appendix B of 10 CFR 50. (VIO 50-440/98007-02(DRS))
c. Conclusions _
l The licensee's calculation for determining the minimum 7-day and 6-day diesel
generator fuel oil tank quantities showed a difference from the TS values with no
corrective action being taken by the licensee. In the case of the division-3 DG, a TS
change was required to resolve this issue which was a violation of regulatory
requirements.
V. Management Meetings
X1 Exit Meeting Summary
On March 5,1998, the preliminary results of the team inspection were presented to the licensee
at an exit meeting. The licensee did not identify any material provided during the inspection
report period as proprietary.
1
1
17
l
l
.
"
PARTIAL LIST OF PERSONS CONTACTED
Licensee !
1
P. Arthur Perry Operations Supervisor - US
N. Bonner Director - Perry Nuclear Maintenance Department l
R. Collings Quality Assurance Manager
T. Henderson Compliance Supervisor
H. Hegrat Regulatory Affairs Manager - g
W. Kanda General Manager - Perry Nuclear Power Plant Department
R. Keamy Operations Superintendent
H. Kelly Perry Operations Supervisor- SS ,
J. Kloosterman Corrective Action Program Supervisor
J. Lausberg Senior Engineer
K. Meade Training Instructor >
S. Moffitt Plant Engineering Manager
L. Myers Site Vice-President Nuclear
- J. Powers Design Engineering Manager
'
R. Schrauder Director- Perry Nuclear Engineering Department i
J. Sipp RECS Manager
L. Zerr Quality Assurance
MB.C
M. Dapas Deputy Director, DRP
D. Kosloff Senior Resident inspector
M. Leach Chief, Operator Licensing Branch, DRS
l
}
l
18
l
l . l
I
l
! INSPECTION PROCEDURE USED
IP 61276 Surveillance Observations
l lP 62707 Maintenance Observations
l lP 71707 Conduct of Operations
l IP 93802 Operational Safety Team Inspection (OSTI)
ITEMS OPENED, CLOSED, AND DISCUSSED
Ooened
50-440/98007-01 VIO Incorrect removal of safety tag and installation of fuse
50-440/98007-02 VIO Tech Spec requirement for division-3 DG Fuel Oil was non- j
conservative
'
Closed
i
None )
Discussed ,
None 1
!
l
!
l
I
! 1
1
I
I
'
19
,
~
LIST OF ACRONYMS USED
AEGTS Annulus Exhaust Gas Treatment System
ARI Annunciator Response instruction
DG Emergency Diesel Generators
dPCS High P essure Core Spray
IP inspection Procedure
M&TE Measurement and Testing Equipment
OATI Operations Assessment Team inspection
OF Operations Foremen
PAP Perry Administrative Procedure
PIF Problem identification Form
PPA Perry Plant Attendant
PPO Perry Plant Operator
QC Quality Control
RCIC Reactor Core Isolation Cooling
SO-ATC Supervising Operator- At The Contr< !s
SO-E Supervising Operator- Extra
SOI System Operating Instructions
SS Shift Supervisor
TS Technical Specifications
UFSAR Updated Final Safety Analysis Report
US Unit Supervisor
VIO Violation
,
1
20