ML20084D388

From kanterella
Jump to navigation Jump to search
Informs of Insp Completion Re safety-related Pipe Restraints Accessible During Power Operation,On 740819 Per AEC .All Restraints Are Bergen-Paterson Design & in Satisfactory Condition
ML20084D388
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 08/30/1974
From: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
To: Anthony Giambusso
US ATOMIC ENERGY COMMISSION (AEC)
Shared Package
ML20084D330 List:
References
NUDOCS 8304110139
Download: ML20084D388 (1)


Text

.

l FLORIDA POWER & UGHT COMPANY August 30, 1974 1

i i

i 1

Mr. Angelo Giambusso 4

Deputy Director for Reactor Projects s'

Directorate of Licensing j

Office of Regulation

'Q,/ y,

]

U. S. Atoalic Energy Commission V/'f

.j j

Washington, D. C.

20545 j

8 u >~

l Dear Mr. Giambusso P,. c -

gt

)

-4

,( p-

{

TURKEY POINT UNIT NO. 3 l iT i < ' ?.

1 DOCKET NO. 50-250 l

INSPECTION OF SAFETY RELATED HYDRAULIC j

PIPE RESTRAINTS i

l Inspection of the safety related pipe restraints that are j

accessible during power operation was coatpleted on August 19, 1974, in accordance with the continuing requirements of the

//

j Atomic Energy Comunission Directorate of Licensing letter of

/ /

j November 8, 1973.

All of the restraints were found to be in

_/i j j

satisfactory condition.

The inspection included a total of

/

I j

20 restraints and all are of the Bergen-Paterson design.

i

/

j Very quly yours, (ca j

R. E. Uhrig

/

i Vice President i

REU/DNR/cpc 1

{