OPS~G*
Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038-0236 Nuclear Business Unit OCT 5* *. 1999 LR-N99439 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 UPDATE OF PSE&G RESPONSE TO NRC GENERIC LETTER 98-01 SALEM NUCLEAR GENERATING STATION UNITS NOS.1AND2 HOPE CREEK NUCLEAR GENERA TING STATION FACILITY OPERA TING LICENSES DPR-70, DPR-75 AND NPF-57 (TAC NOS. MA1883, MA-1884 AND MA-1845)
Gentlemen:
This letter provides the current status of Public Service Electric & Gas Company's actions related to Generic Letter 98-01, "Year 2000 Readiness of Computer Systems at Nuclear Power Plants." In the previous response to Generic Letter 98-01, dated-June 30, 1999, PSE&G reported that seven (7) mission critical systems for the Salem Units and four (4) mission critical systems for Hope Creek were not "Y2K Ready". PSE&G
/
also provided a listing of each of these systems along with their scheduled remediation dates.
To date, PSE&G has completed the remediation of the four (4) Hope Creek systems and the four (4) Salem Unit 2 and Common systems. The three (3) remaining Salem Unit 1 systems will be completed during the current refueling outage for the unit, which is scheduled for November 11, 1999. PSE&G does not anticipate any problems in completing these three (3) activities as scheduled, as the corresponding Salem Unit 2 remediations were previously completed successfully. The attached table provides the detailed status of the subject systems. Should you have any questions regarding this request, please contact Mr. Ray Moore at 856-339-17 41.
[\\ ('\\ ~i 991oi3oo69-991o<is _____________,._. __,,__
- PDR ADOCK 05000272 P
PDR The power is in your hands.
E. C. Simpson Senior Vice President &
Chief Administrative Officer 95-2168 REV. 6/94
Document Control Desk LR-N99439 Attachment JPP C
Mr. H. Miller, Administrator-Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. R. Ennis, Licensing Project Manager - Hope Creek U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 8B1 11555 Rockville Pike Rockville, MD 20852 Mr. P. Milano, Licensing Project Manager - Salem U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 8B1 11555 Rockville Pike Rockville, MD 20852 USNRC Resident Inspector Office (X24)
Mr. K. Tosch, Manager IV Bureau of Nuclear Engineering P. 0. Box 415 Trenton, NJ 08625 OBT-5 ~ _1999
Document Control Desk LR-N99439 Plant System 1
Plant Computer Monitoring and Alarm (P250) 2 Advanced Digital Feed Water (ADFW) 3 Overhead Annunciator (OHA) 4 Safety Parameter Display System (SPDS) 5 Emergency Response Data System (EROS) 6 Training Simulator 7
Radiation Monitoring System (RMS) 8 Fire Detection and Alarm System 9
Safety Parameter Display System (SPDS) 10 Emergency Response Data System (EROS) 11 Training Simulator Table 1 Unit GL 98-01 Current Scheduled Status Completion Date Salem Unit 1 Refueling Outage Pending (9/18-11/6/99)
Salem Unit 1 Refueling Outage Pending (9/18-11/6/99)
Salem Unit 1 Refueling Outage Pending (9/18-11/6/99)
Salem 10/29/99 Completed Common 8/27/99 Salem 9/30/99 Completed Common 9/24/99 Salem 10/29/99 Completed Common 9/21/99 Salem Unit2 8/31/99 Completed 8/23/99 Hope Creek 8/31/99 Completed 8/25/99 Hope Creek 10/29/99 Completed 8/27/99 Hope Creek 9/30/99 Completed 9/30/99 Hope Creek 10/29/99 Completed 9/20/99 Page 1 of 1