Forwards Discharge Monitoring Rept for Salem Generating Station, for June 1999.Rept Is Required by & Prepared for EPA & Nj Dept of Environ Protection
ML18107A453
Person / Time
Site: Salem  PSEG icon.png
Issue date: 07/20/1999
From: Robertson J
Public Service Enterprise Group
To:
NEW JERSEY, STATE OF
Shared Package
ML18107A456 List:
References
NUDOCS 9907270288
Download: ML18107A453 (9)


Text

......

Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038-0236 Nuclear Business Unit

July 20, 1999 New Jersey Department of
  • Environmental Protection Division of Water Quality Bureau of Permit Management P.O. Box 029 Trenton, NJ 08625-0029 Certified Mail Number Z 314 291 124 NEW JERSEY POLLUTANT DISCHARGE ELIMINATION SYSTEM DISCHARGE MONITORING REPORTS SALEM GENERATING STATION PERMIT NO. NJ0005622 Attached is the Discharge Monitoring Report for Salem Generating Station containing
  • the information as required in Permit No. NJ0005622, for the month of June1999.

This report is required by and prepared specifically for the Environmental Protection Agency (EPA) and the New Jersey Department of Environmental Protection (NJDEP).

It presents only the observed results of measurements and analyses required to be performed by the above agencies. The choice of the measurement devices and analytical methods is controlled by EPA and NJDEP, not by the company, and there are limitations on the accuracy of such measurement devices and analytical techniques even when used and maintained as required. Accordingly, this report is not intended as an assertion that *any instrument has measured, or any reading or analytical result represents, the true value with absolute accuracy, nor is it an endorsement of the suitability of any analytical or measurement procedure, Sincerely, rflrL P fZcD;;:s-u;;,, P. Robertson Manager - Salem Operations Attachments 270057 1

~907270288 990720 PDR ADOCK 05000272 R PDR

-r~--.c.: ~--l *\;,-c_*~4 i~ Ln ~:{ :*ur h~u~d.~.

95-2168 REV. 6/94

NJPDES Report 2

.. June 1999 C Executive Director - DRBC USNRC - Document Control Desk Unit#1-50-272 Unit#2-50-311 Manager - Salem Operations Director - Licensing, Regulation, and Fuels M. Vaskis D. Hurka J. Schloss Central Record Facility E. Keating

NJPDES Report Explanation of Deviations June 1999 48C - Non-Radioactive Liquid Waste - This system continues to be operated in a batch mode to treat for hydrazine and ammonia by the addition of sodium hypochlorite. No hydrazine has been discharged from this outfall during the reporting period. Residual chlorine is monitored at the outfalls of DSN's 481, 482, 484, and 485, and has not exceeded the permit limits at these outfalls.

The following excursions are included in the attached report and are explained below.

Excursions have not endangered nor significantly impacted public health or the environment.

DSN NO. EXPLANATION None

NJPDES Report Explanation of Deviations June 1999 The following explanations are included to clarify possible deviations from permit conditions.

General- The columns labeled, "No. Ex. " on the enclosed DMR, tabulate the number of daily discharge values outside the indicated limits.

Data reporting and accuracy reflect the working environment, the design capabilities and reliability of the monitoring instruments and operating equipment.

All reported concentrations are based on daily discharge values.

Total residual chlorine is performed three times per week during chlorination unless otherwise indicated.

Analytical values which are less than detectable are reported as zero unless otherwise indicated.

Analytical results for all parameters other than pH, temperature, TSS, TRC and Bioassay results are provided by Raytheon Environmental Services Laboratory. (NJDEP certification 77343) or South Jersey Testing Laboratory (NJDEP certification 06431). Bioassay results are provided by New England Bioassay, Inc. (NJDEP certification 46405).

Net negative discharge values are reported as negative.

  • 489C- Flow thru outfall 489 is calculated based on Oil Water Separator Lift Pump run times.

481-486 - Chlorination of the circulation water system normally does not occur except as otherwise noted. Service water system chlorination is normally continuous and is monitored on the circulating water system outfall.

Chlorination of both systems will be indicated by results reported for both and represents their combined effect upon the circulating water outfall.

COUNTY OF SALEM STATE OF NEW JERSEY I, John P. Robertson, of full age, being duly sworn according to law, upon my oath depose and say:

1. I am the Operations Manager of Salem Generating Station, and as such, am authorized to sign Discharge Monitoring Reports submitted to the New Jersey Department of Environmental Protection pursuant to the Station's New Jersey Pollutant Discharge Elimination System permit.
2. I have reviewed the attached Discharge Monitoring Reports. Pursuant to N.J.

A C. 7: 14A-2.4, I certify under penalty oflaw that I have personally examined and am familiar with the information submitted in this document and all attachments and that based on my inquiry of those individuals responsible for obtaining the information, I believe the submitted information is true, accurate and complete. I am aware that there are significant penalties for submitting false information including the possibility of fine and imprisonment.

3. The signature on the attached Discharge Monitoring Reports is my signature and I am submitting this affidavit in satisfaction of the requirement that my signature be notarized.

anager - Salem Operations Sworn and subscribed before me this ~"day of ~,1999 EILEEN A. BURR NOTARY PUBLIC OF NEW JERSEY My Commission Expires Feb. 3, 2002

f>ps~G MAPLEWOOD TESTING SERVICES REPORT TO: Dave Hurka June 21, 1999 Sr. Staff Engineer - Nuclear Report No.TP99017 PSE&G

SUBJECT:

DETERMINATION OF CIRCULATING WATER FLOW AT SALEM GENERATING STATION - UNIT NO. 2 CONDUCTED BY: Joseph Fiumara Sr. Test Engineer, Maplewood Testing Services PURPOSE To determine the flow capacities of the Unit No. 2 circulating water pumps.

SUMMARY

On June 15 and 16, 1999 the Mechanical Division of Maplewood Testing Services conducted a series of test runs at Salem Unit No. 2 to determine the capacities of the 21A, 21 B, 22A, 228, 23A and 23B (CMS designations I, D, 8, C, G and F respectively) circulating water pumps.

Final test results are shown in Table 1 and Figure 1.

DISCUSSION Discharge pressures could not be measured at the pump due to plugged feeler lines.

The total dynamic heads reported were calculated using the pressures measured at the inlet water boxes which were lower than the pump discharge pressures. The lower pressures are a result of losses in the piping between the pumps and the waterboxes.

,\

Dave Hurka

.. Sr. Staff Engineer - Nuclear June21, 1999 Report No.TP99017 PSE&G TEST METHOD The circulating water flow rate was determined by fluorometry using MTS Mechanical Division Procedure Mech-40 "Determination of Water Flow Using The Turner Fluorometer". Rhodamine WT dye was injected into the bell mouth of each pump using

~ inch PVC pipe with a carrier flow of screen wash water at 3 gallons per minute. The dye was injected at a known rate using a peristaltic pump and a class A burette to measure rate. The diluted sample was retrieved and monitored by taking a sample from the inlet water box piping. The ratio of the injected concentration to the sampled concentration multiplied by the injection flow rate yielded the circulator flow rate.

The total dynamic head was obtained by measuring the pump suction head in feet from elevation 100 and the pump discharge head in feet of water at the water box inlet.

After correcting for elevation the total dynamic head was calculated as the pump discharge head minus the pump suction head.

  • enior Supervising Test Engineer Mechanical Division Manager Mechanical Division cc F. Todd M. Welker S. Davies F:\MAG\TP99017\TP99017.DOC

Table 1 Salem Generating Station Circulating Water Pump Flow Test Maplewood Testing Services Mechanical Division Report Number TP99017

SUMMARY

OF TEST RESULTS Pump CMS Test Measured Pump Pump Total No. Pump Date Pump Suction Discharge Dynamic Desig. Capacity Head Head Head (gpm) (ft h2o) (ft h2o) (ft h2o) 21A I 06/16/99 177,340 -11.8 8.8 20.6 218 D 06/16/99 181,894 -13.2 7.9 21.1 22A 8 06/15/99 169,896 -10.7 6.8 17.5 228 c 06/16/99 170,395 -9.0 11.0 20.0 23A G 06/15/99 162,464 -9.3 12.2 21.5 238 F 06/15/99 167,901 -8.4 14.0 22.4 Note: Pump suction heads and discharge heads corrected to elevation 100'

SALEM GENERATING STATION - UNIT N0.2 TOTAL PUMP HEAD VS. CIRCULATING WATER PUMP FLOW

~.-~.

D Pump I (21A)

  • * * * * ' __g___

'\J Pump D (21B)

Q Pump B (22A) r~ :_~:_:_~-(~_:B_:;~ ..................

0::

w

~

601---"'-----'----'-~--'---l---'---'---'---'---l---!-----:.----:.----:.---11---'---"'-----'----'--+----'----'--~---J LL 0

1-w ....... ; ........... : .......... -~ ..... ***-

w u..

0

<{

w I

0...

~

> GUARANTEE POINT 0...

_J (18~, 27) !  !

~

0 I-

................................................. !.......... **********1**********1**********1********** ................................

0 50 100 150 200 PUMP FLOW - 1000 GPM PSEG Maplewood Tesling Services GSALEM Report No. TP99017 June 1999 FIGURE 1