Forwards Schedule of Inservice Insp Exams to Be Performed During Refueling Outage Scheduled to Begin on 880902.Summary of Inservice Insp Exams Also Encl
ML18093B012
Person / Time
Site: Salem PSEG icon.png
Issue date: 08/02/1988
From: Miltenberger S
Public Service Enterprise Group
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
NLR-N88115, NUDOCS 8808150198
Download: ML18093B012 (4)


Text

c

  • Public Service Electric and Gas Company Steven E. Miltenberger Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-4199 Vice President and Chief Nuclear Officer August 2, 1988 NLR-N88115 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

INSERVICE INSPECTION SCHEDULE SALEM GENERATING STATION UNIT NO. 2 DOCKET NO. 50-311 Attached please find a summary of inservice inspection examinations (Enclosure 1) to be performed during the upcoming Salem Unit 2 refueling outage scheduled to begin on September 2, 1988. The schedule for performance of these examinations prior to and during the outage is noted on Enclosure 2. This information is being provided in accordance with Article IWA-6220(a) of Section XI of the ASME Boiler and Pressure Vessel Code.

If you have any questions, we would be pleased to discuss them with you.

Sincerely, Enclosures

( 8808150198 880802 PDR ADOCK 05000311 G PNU

  • 08-02-88 Document Control Desk 2 C Mr. D. c. Fischer USNRC Licensing Project Manager Mr. R. w. Borchardt USNRC Senior Resident Inspector Mr. W. T. Russell, Administrator USNRC Region I Mr. Frank Dolan, Assistant Director New Jersey Department of Labor and Industry Trenton, NJ 08625 Mr. D. M. Scott, Chief Bureau of Nuclear Engineering Department of Environmental Protection 380 Scotch Road Trenton, NJ 08628

lr

  • ENCLOSURE 1 ISI EXAMINATION

SUMMARY

SALEM UNIT 2 FALL 1988 REFUELING OUTAGE Contract/Station support, under the supervision and direction of the Salem ISI Group, will conduct the following:

A. Southwest Research Institute will conduct:

1. ISI - 121 Ultrasonic examinations (manual) 53 Liquid Penetrant examinations 10 Magnetic Particle examinations 47 Visual examinations B. Contract Personnel will conduct:

- Helium leak detection on 22 & 24 Stearn Generator

- Eddy Current examination of 20% of the tubes in 22 Stearn Generator pursuant to Technical Specification requirements and in response to the North Anna Unit 1 Stearn Generator Tube Rupture incident (NRC Bulletin 88-02)

C. Contract Personnel will conduct:

1. Technical Specification

- Functional testing of four (4) hydraulic and thirty-one (31) mechanical snubbers.

D. PSE&G Maintenance Department - Salem will conduct:

1. ISI

- Approximately twenty (20) Safety/Relief Valve set pressure tests.

E. PSE&G Site Services ISI group will conduct:

1. ISI

- Service pressure leak examinations

- Visual examinations of approximately four hundred seventy-one (471) nuclear class I, II, & III supports and one hundred seven (107) snubbers

- ASME Section XI hydrostatic tests

2. 10CFR50 App. J

- Local Leak Rate Testing of all Type "B" penetrations and Type "C" valves.

3. NUREG 0578

- Waste Gas System Integrated Leak Rate Test

tr -*

ENCLOSURE 2 ISI EXAMINATION SCHEDULE SALEM UNIT 2 FALL 1988 REFUELING OUTAGE The outage is currently scheduled to commence September 2, 1988 and be completed by October 25, 1988.

Week of 8/29/88 Commence Type B, C and Waste Gas System Leak Rate tests Commence Hanger visual examinations Commence Hydrostatic Test program Week of 9/ 5/8 8 Commence Snubber Functional Testing Commence Relief/Safety Valve Testing Week of 9/12/88 Commence examination of welds by Southwest Research Institute Week of 9/19/88 Commence Stearn Generator Primary Side preparations Complete Snubber Functional Testing Week of 9/26/88 Steam Generator Mechanical Plugging & Eddy Current Week of 10/3/88 Complete Stearn Generator Primary Side Work Complete Southwest Research Instituted Weld examinations Week of 10/10/88 Complete Type B & C and Testing Complete Hanger visuals Complete Relief Valve testing Week of 10/17/88 Commence Service Pressure Leak examinations