Forwards Integrated Program Plan for Suppl 1 to NUREG-0737, in Response to Generic Ltr 82-33 Re Implementation of Emergency Response capabilities.C-E Designed Critical Function Monitoring Sys Installed
ML18051A385
Person / Time
Site: Palisades Entergy icon.png
Issue date: 04/14/1983
From: Dewitt R, Vandewalle D
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Crutchfield D
Office of Nuclear Reactor Regulation
Shared Package
ML18051A386 List:
References
RTR-NUREG-0737, RTR-NUREG-737 GL-82-33, NUDOCS 8304210216
Download: ML18051A385 (3)


Text

consumers Power company General Offices: 212 West Michigan Avenue, Jackson, Ml 49201 * (517) 788-0550 April 14, 1983 Dennis M Crutchfield, Chief Operating Reactor Branch No 5 Nuclear Reactor Regulation US Nuclear Regulatory Conrrnission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR PALISADES PLANT - RESPONSE TO GENERIC LETTER 82 SUPPLEMENT 1 TO NUREG-0737 NRC Generic Letter 82-33 and its Enclosure Supplement 1 to NUREG-0737 "Requirements for Emergency Response Capability" dated December 17, 1982 requested that Consumers Power Company furnish no later than April 15, 1983 a proposed schedule for completing each of the basic requirements for the initiatives on emergency response capability identified in Supplement 1 to NUREG-0737. The NRC also requested that we submit a description of our plans for phased implementation and integration for each of the emergency response activities. Our integrated program plan for accomplishing these requests is attached. The program plan contains all information requested by the NRC during the regional workshops on Supplement 1 to NUREG-0737.

In developing this plan, Consumers Power Company assumed that it could rely on the "good-faith efforts" made to date for completing requirements of the Safety Parameter Display System, Control Room Design Review, Emergency Operating Procedures and Emergency Response Facilities. Further assumptions are discussed in Section 1 of the attached plan. The current status of each of the initiatives is identified in Section 2 of the plan. The implementa-tion, the remaining workscope, the completion and the integration of related activities between initiatives are described in Section 3. Also described in Section 3 is the integration plan for Consumers Power Company's training and verification and validation programs.

Section 4.0 contains the milestone schedule for completion of the initiatives.ADr.>~

Where actual dates have been determined, they have been included on the .1..1 'Vi /.sot./

schedule. Where some progress has been made on an initiative or activity, butv~* ~~

not enough to identify an actual completion date, the date Consumers Power can identify the completion date is provided in place of the anticipated comple-tion date. Where current information is insufficient to determine a conrrnit-ment date or date we could determine a conrrnitment date, our plan for completing the activity and arriving at required date information is provided.

OC0483-0006A-NL02 8304210216 830414 PDR ADOCK 05000255 F .. PDR

DMCrutchfield, Chief 2 Palisades Plant RESPONSE TO GENERIC LETTER 82-33 April 14, 1983 Because we have completed the installation of a CE designed Critical Functions Monitoring System at Palisades Plant we do not anticipate the need for a pre-implementation Safety Parameter Display System (SPDS) review by the staff.

We are looking forward to reviewing our Program Plan in detail with the NRC Palisades Plant Project Manager.

Nuclear Licensing Administrator CC Administrator, Region III, USNRC NRC Resident Inspector - Palisades Attachment OC0483-0006A-NL02

Consumers Power Company Palisades Plant Docket 50-255 - License DPR-20 RESPONSE TO GENERIC LETTER 82-33 SUPPLEMENT 1 TO NUREG-0737 At the request of the Commission and pursuant to the Atomic Energy Act of 1954 and the Energy Reorganization Act of 1974, as amended, and the Commission's Rules and Regulations thereunder, Consumers Power Company submits our response to Generic Letter 82-33 dated December 17, 1982, entitled "Requirements for Emergency Response Capability". Consumers Power Company's response is dated April 14, 1983.

CONS~~OMPANY ~-==--=...--~~~-

BY ,~~7Jb RB DeWitt, Vice President Nuclear Operations Sworn and subscribed to before me this 14th day of April 1983.