MONTHYEARIR 05000395/20240022024-08-12012 August 2024 Integrated Inspection Report 05000395/2024002 ML24180A0062024-08-0505 August 2024 Issuance of Amendment No. 227 to Modify Technical Specification 3.8.3.1 to Increase Completion Time for 120-Volt A.C. Vital Busses ML24218A3002024-08-0101 August 2024 Environmental Review Response to NRC Requests for Additional Information and Response to NRC Requests for Confirmation of Information Set 1 ML24158A3882024-07-31031 July 2024 Issuance of Amendment No. 226 to Change Emergency Plan Staff Augmentation Times and Relocate Emergency Operations Facility ML24162A3292024-07-0505 July 2024 Letter to E Carr - V.C. Summer Unit 1 - Summary of the May 2024 Audit Regarding the Environmental Review of the Subsequent License Renewal Application IR 05000395/20240112024-06-26026 June 2024 – Comprehensive Engineering Team Inspection Report 05000395/2024011 ML24178A1192024-06-25025 June 2024 Update to License Amendment Request- Inverter Allowed Outage Time (AOT) Extension ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A1382024-06-25025 June 2024 Aging Management Audit Report- VC Summer, Unit 1 - Subsequent License Renewal Application ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24171A0152024-06-17017 June 2024 Update to Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Set 2 Safety Review ML24157A3352024-06-0606 June 2024 – Notification of an NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000395-2024404 and Request for Information ML24155A2042024-05-31031 May 2024 Proposed Alternative Request RR-24-123, Containment Unbonded Post-Tensioning System Inservice Inspection Requirements ML24155A1462024-05-30030 May 2024 Update to Subsequent License Renewal Application (SLRA) -Response to NRC Request for Additional Information Set 1 Response to NRC Request for Confirmation of Information Set 1 and Supplement 3 ML24143A1792024-05-22022 May 2024 Special Report 2024-001-01 for Virgil C. Summer Nuclear Station (Vcsns), Unit 1, Waste Gas System Inoperability ML24141A2822024-05-20020 May 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes IR 05000395/20240012024-05-10010 May 2024 Integrated Inspection Report 05000395/2024001 ML24129A2002024-05-0606 May 2024 Update to Subsequent License Renewal Application, Supplement 2 IR 05000395/20240402024-05-0101 May 2024 95001 Supplemental Inspection Report 05000395/2024040 and Follow-Up Assessment Letter ML24121A1002024-04-29029 April 2024 Response to Request for Additional Information Regarding Alternative Request RR-5-V2 ML24120A2072024-04-29029 April 2024 Submittal of Annual Radiological Environmental Operating Report ML24116A2052024-04-23023 April 2024 Annual Radioactive Effluent Release Report ML24109A1792024-04-19019 April 2024 Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML24108A0392024-04-18018 April 2024 Letter to E Carr-V.C. Summer Unit 1- Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application ML24108A0672024-04-17017 April 2024 Submittal of Summary for Condition of the Service Water Intake Structure Provided in Accordance with License Condition 2.C.5.d ML24100A7312024-04-0909 April 2024 Personnel Exposure and Monitoring Annual Report ML24095A2072024-04-0101 April 2024 Update to Subsequent License Renewal Application (SLRA) Supplement 1 ML24088A2062024-03-26026 March 2024 Annual Operating Report ML24087A2262024-03-26026 March 2024 License Amendment Request - Inverter Allowed Outage Time Extension Response to Request for Additional Information ML24087A2182024-03-26026 March 2024 (Vcsns), Unit 1 - License Amendment Request - Emergency Response Organization (ERO) Augmentation Time Change, Emergency Operations Facility Relocation and Other Emergency Plan Changes - Response to Request. ML24067A0232024-03-0707 March 2024 (Vcsns), Unit 1 - Readiness for 95001 Supplemental Inspection; EA-23-093 IR 05000395/20230062024-02-28028 February 2024 Annual Assessment Letter for Virgil C. Summer Nuclear Station - Report 05000395/2023006 IR 05000395/20244032024-02-27027 February 2024 Security Baseline Inspection Report 05000395/2024403 ML24057A1132024-02-22022 February 2024 Special Report 2024-001 Waste Gas System Inoperability ML24051A0112024-02-20020 February 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Proposed Project Location or May Be Affected by Proposed Project for V.C. Summer SLR ML24057A0612024-02-19019 February 2024 and Virgil C. Summer Power Nuclear Stations - Nuclear Property Insurance Coverage ML24032A3062024-02-15015 February 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24040A1802024-02-12012 February 2024 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000395/20244012024-02-0808 February 2024 Security Baseline Inspection Report 05000395/2024401 ML24038A0322024-02-0707 February 2024 (Vcsns), Unit 1, 10 CFR 21 Report - Emergency Diesel Generator Flash Contactor Relay IR 05000395/20230042024-01-31031 January 2024 Integrated Inspection Report 05000395/2023004 ML24022A1202024-01-22022 January 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000395/2024403) ML24022A1582024-01-22022 January 2024 (Vcsns), Unit 1 - Reply to a Notice of Violation: EA-23-093 ML24018A0112024-01-18018 January 2024 CFR 21 Report Emergency Diesel Generator Fuel Oil Piping ML23361A1042023-12-21021 December 2023 Inservice Testing Program for Pumps and Valves Fifth Interval Update and Associated Relief and Alternative Requests IR 05000395/20230912023-12-21021 December 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letternrc Inspection Report 05000395/2023091 ML23354A1802023-12-20020 December 2023 301 Examination Report with Cover Letter ML23347A0492023-12-12012 December 2023 Technical Specification Bases Changes Updated Through November 2023 ML23334A2462023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23334A2372023-11-30030 November 2023 (Vvsns), Unit 1 - Annual Commitment Change Summary Report 2024-08-05
[Table view] Category:Licensee 30-Day Written Event Report
MONTHYEARML19010A2872019-01-10010 January 2019 (Vcsns), Unit 1 - Special Report 2019-001 for Meteorological Monitoring Channels Inoperable ML17349A6572017-12-15015 December 2017 Special Report (Spr) 2017-011 RC-17-0112, Special Report (Spr) 2017-007 Regarding Waste Gas Holdup System Explosive Gas Monitoring System Being Inoperable for Greater than Thirty Days2017-09-0101 September 2017 Special Report (Spr) 2017-007 Regarding Waste Gas Holdup System Explosive Gas Monitoring System Being Inoperable for Greater than Thirty Days RC-17-0116, Special Report (Spr) 2017-009 Regarding Fire Barrier Assembly Not Being Restored to Operability within Seven Days After Declaration of Inoperability2017-08-24024 August 2017 Special Report (Spr) 2017-009 Regarding Fire Barrier Assembly Not Being Restored to Operability within Seven Days After Declaration of Inoperability RC-17-0085, Special Report (Spr) 2017-0052017-06-13013 June 2017 Special Report (Spr) 2017-005 RC-17-0072, Special Report (Spr) 2017-003 Regarding Electrical Fire Barrier Assembly Not Being Restored to Operability within Seven Days After Declaration of Inoperability2017-06-0101 June 2017 Special Report (Spr) 2017-003 Regarding Electrical Fire Barrier Assembly Not Being Restored to Operability within Seven Days After Declaration of Inoperability RC-17-0062, Special Report (Spr) 2017-001 Regarding a Fire Barrier Assembly Not Being Restored to Operability within Seven Days After Declaration of Inoperability2017-05-0505 May 2017 Special Report (Spr) 2017-001 Regarding a Fire Barrier Assembly Not Being Restored to Operability within Seven Days After Declaration of Inoperability ML16319A1032016-11-0808 November 2016 Submittal of Special Report 2016-004 ML14209A8472014-07-24024 July 2014 Special Written Report of Theft or Loss of Licensed Material on 05/30/2014 ML0934804922009-12-11011 December 2009 Special Report (Spr) 2009-003 Re Electric Driven Fire Service Pump Being Out of Service for Greater than 7 Days Due to Loss of Power ML0909302862009-04-0101 April 2009 Special Report (Spr) 2008-005-01 for Virgil C. Summer Inoperability of the Main Steam Line Radiation Monitor RM-G19C for Greater than 72 Hours ML0821004482008-07-24024 July 2008 LER, Virgil C. Summer, Special Report 2008-004 on Inoperability of the Plant Vent High Range Radiation Monitor RMA00131 for Greater than 72 Hours ML0614402922006-05-22022 May 2006 Special Report (Spr) 2006-003 Re Inoperability of the Main Plant Vent & Reactor Building Purge Supply & Exhaust System Radiation Monitors for Greater than 72 Hours RC-05-0116, Special Report (Spr) 2005-032005-07-29029 July 2005 Special Report (Spr) 2005-03 RC-05-0099, Special Report 2005-0012005-07-0707 July 2005 Special Report 2005-001 RC-04-0171, Special Report 2004-0022004-10-13013 October 2004 Special Report 2004-002 ML0218602052002-07-0202 July 2002 Special Report 2002-001. Digital Metal Impact Monitor System Has One Channel Which Has Been Inoperable in Excess of 30 Days 2019-01-10
[Table view] |
Text
George A. Lippard Vice President, Nuclear Operations 803.345.4810 A SCANA COMPANY December 15, 2017 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555
Dear Sir/ Madam:
Subject:
VIRGIL C. SUMMER NUCLEAR STATION (VCSNS), UNIT 1 DOCKET NO. 50-395 OPERATING LICENSE NO. NPF-12 SPECIAL REPORT (SPR) 2017-011 South Carolina Electric & Gas Company (SCE&G) is submitting this Special Report pursuant to the requirements of Technical Specifications 3.3.3.9.a and 6.9.2. This report addresses the Oxygen Monitoring Instrumentation in the Waste Gas Holdup System Explosive Gas Monitoring System being out-of-service for greater than thirty (30) days.
On October 30, 2017, at 02:30, the outlet oxygen monitor IAE01119A was out of tolerance, could not be calibrated, and was declared inoperable. Compensatory action was taken by analyzing grab samples to maintain the Waste Gas System Explosive Gas Monitoring System operable, as described in Technical Specifications Table 3.3-13 Line Item 1a notation (Action 44).
Maintenance was performed under Work Order 1716322. Defective equipment and instrumentation was replaced, calibrated, and the monitor was verified to be within tolerance.
Oxygen monitor IAE01119A was returned to service on November 29, 2017 at 07:10.
Should you have any questions, please call Mr. Michael S. Moore at (803) 345-4752 at your convenience.
JRB/GAL/rp c: K. B. Marsh W. M. Cherry RTS (CR-17-05701)
S. A. Byrne C. Haney File (818.08)
J. B. Archie S. A. Williams PRSF (RC-17-0179)
N. S. Cams K. M. Sutton INPO Records Center J. H. Hamilton NRC Resident Inspector G. J. Lindamood NSRC SCE&G l V.C. Summer Nuclear Station