Monthly Operating Rept for Aug 1994 for WNP-2.W/940906 Ltr
ML17291A377
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 08/31/1994
From: Embree D, Galen Smith
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GO2-94-209, NUDOCS 9409130244
Download: ML17291A377 (10)


Text

P 8:IC3 RIDS PROCESSING)

R.IMY'ACCELERATED

~

IL REGULATORY INFORMATION DISTRIBUTXON SYSTEM (RIDS)

ACCESSION NBR:9409130244 DOC.DATE: 94/08/31 NOTARIZED: NO DOCKET FACIL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH. NAME AUTHOR AFFILXATION EMBREE,D.G. Washington Public Power Supply System SMITH,G.O. Washington Public Power Supply System RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operating rept for Aug 1994 for WNP-2.W/940906 ltr.

DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs)

NOTES:

RECIPIENT COPIES RECIPIENT COPXES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD4-2 PD 1 1 CLIFFORD,J 1 1 INTERNAL: ACRS 10 10 AEOD/SPD/RRAB 1 1 RR DORS/OEAB 1 1 NRR/PMAS/XRCB-E 1 1 REG F1DE 01 1 1 RGN4 1 1 EXTERNAL: EG&G BRYCE,J.H 1 1 NOAC NRC PDR 1 1 NOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE iVASTE! CONTACTTlfE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 504-2083 ) TO ELlb,flVATEYOUR VAME PRO!Lf DISTRIBUTION LISTS I'OR DOCL'ME. JTS YOU DON "I'L'ED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 20 ENCL 20

Sr WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O. Bec 968 ~ 3000 George Wasbfngton Way Rtcb!and, Wasbtngton 993524968 ~ (509) 372-5000 September 6, 1994 G02-94-209 Docket No. 50-397 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555

Dear Sirs:

Subject:

NUCLEAR PLANT NO. 2 MONTHLY OPERATING REPORT AUGUST 1994 Transmitted herewith is the=Monthly Operating Report for the month of August, 1994 as required by our. Technical Specifications 6.9.1.6.

Sincerely, G.. Smith Operations Division Manager (MD 9270)

GOS:DGE CC: NRC, MN BB-7602, Washington, DC NRC, Administrator, Region IV NRC, Resident Inspector (927N)

INPO ANI Library Utility Data Institute, ..

BPA (399) 9409'130244 940831 PDR ADOCK 05000397

.PDR

C 4 p

I'

'i~) + ~ c

~ c s g ~

OPERATING STATUS REPORT for WNP-2 Date: September 1, 1994 Docket: 50-397

2. Reporting Period: AUGUST 1994 Outage + On-Line Hours: 744.0
3. Utility

Contact:

David G. Embree (509) 377-8448 4 Licensed Thermal Power (MW, ):

5. Nameplate Rating (Gross MW, ):
6. Design Electrical Rating (Net MW,):
7. Maximum Dependable Capacity (Gross MW,):
8. Maximum Dependable Capacity (Net MW, ):
9. If changes occur above since last report, give reasons:
10. Power to which restricted, if any (Net MW,): None
11. Reasons for restrictions, if any:

MONTH YEAR CUMULATIVE

12. Report Period Hours 744.0 5,831.0 85,159.2
13. Hours Reactor Critical'x 744.0 3,661.4 59,771.6
14. Reserve Shutdown Hours 0.0 0.0 340.4
15. Hours Generator On-Line 744.0 3,571.6 57,638.6
16. Unit Reserve Shutdown Hours 0.0 0.0 381.7
17. Gross Thermal Energy (MWH) 2,401,349 10,800,821 169,562,127
18. Gross Electrical Energy (MWH) 823,450 3,680,420 56,992,630
19. Net Electrical Energy (MWH) 791,331 3,504,431 54,589,816
20. Unit Service Factor 100.0% 61.3% 67.7%
21. Unit Availability Factor 100.0% 61.3% 68. 1%
22. Unit Capacity Factor (MDC Net) 97.9% 55.3% 58.7%
23. Unit Capacity Factor (DER Net) 95.0% 53+7% 58.1%
24. Unit Forced Outage Rate 0.0% 2.3% 12. 1%
25. Forced Outage Hours 0.0 85.8 7,971.1
26. Shutdowns scheduled over the next 6 months (type, date, duration): None
27. Ifcurrently shutdown, estimated startup date: N/A Note: Cumulative Unit CaIIacity Factors (MDC & DER) are calculated with weighted averages.

4 41 4

II 4 4 h T I 4 II 4 WT ~ h ~ h,,th444 4

~ NI, 4 "h ! Tt,!I; 4 hi '(!I'.

hl I ~ T IN

'4 ~

I

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.: 50-397 UNIT: WNP-2 DATE: September 1, 1994 COMPLETED BY: D. G. Embree TELEPHONE: (509) 377-8448 REPORT PERIOD: AUGUST 1994 AVERAGE DAILYPOWER LEVEL AVERAGE DAILYPOWER LEVEL DAY (Net MWe) DAY (Net MWe) 559 16 1096 905 17 1097 1054 18 1101 1087 19 1093 1056 20 1099 1100 21 1100 1099 22 1098 1096 23 1098 1102 24 1099 10 1099 25 1098 1095 26 1096 12 1094 27 981 13 1022 28 1092 14 1092 29 1092 15 1097 30 1091 31 1086 INSTRUCTIONS On this form, list the average daily unit power level in MWe (net) for each day in the reporting month.

Compute to the nearest whole megawatt.

These figures will be used to plot a graph for each reporting month. Note that when maximum dependable capacity is used for the net electrical rating of the unit, there may be occasions when the daily average power level exceeds the 100% line (or the restricted power level line). In such cases, the average daily unit power output sheet should be footnoted to explain the apparent anomaly.

Ij i'

E 4 ( l

't I

l II C

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-397 UNIT NAME: WNP-2 DATE: 'eptember I, 1994 COMPLETED BY: D.G. Embree TELEPHONE: (509) 377-8448 REPORT PERIOD: AUGUST 1994 No. Date Type Hours Reason Method LER Number System Component Cause and Corrective Action To Prevent Recurrence None SU1VPMRY: WNP-2 completed the annual refueling and maintenance outage (R-9) last month and was ramping up to full power at the beginning of the month. The plant was operating at full power during most of the month.

TYPE REASON METHOD SYSTEM & COMPONENT F - Forced A - Equipment Failure E - Operator Training & 1 - Manual NUREG-0161 Exhibits F & H S - Scheduled B - Maintenance or Test License Examination 2 - Manual Scram C - Refueling F - Administration 3 - Auto Scram D - Regulatory Restriction G - Operational Error 4 - Continued H - Olher 5 - Reduced Load 9 - Other

'\ J J

J "I 1 4 4

I" I.

1

} a III 4

f I

II

(497] From: HEATHER L. TOWNSEND at -SERVER23 9/1/94 11:29AM (2038 bytes: 29 ln)

To:'OHN H. SWAILES at -S~R2 ccc, JOHN W. DABNEY at -SER~R2, MICHAEL R. KELLER at - RVER2, TAMMY S. LOVE, ~

DONALD W. MERHAR at -SERVER2, CHRISTOPHER J. SCHWARZ, EULES K. WORTHEN at

-SERVER2, JOHN E. WYRICK at -SERVER2, JOSEPHINE J. AMES at -SERVER2, WINDY N. FRANK at -SERVER2, ANITA E. POOLE at -SERVER2, JOSEPH V. PARRISH at

-SERVER1,'RACI M. HARDY at -SERVER1, LINDA M. MAR at -SERVER4, SHARON M. GRUNST at -SERVER2, MARK E. REDDEMANN at -SERVER5, BEVERLY A. CADWELL at -SERVERS, JOHN R. SAMPSON at -SERVER2, LUELLA R. HAWKINS at -SERVER2, WILLIAM H. BARLEY at -SERVER2, CARMEN M. SAWYER at -SERVER24, JOHN F. PETERS at -SERVER2, DONNA E. MCCAULEY at -SERVER1 bcc: G. O. SMITH at -SERVER2

Subject:

Delegation of Authority Message Contents eeeeeeeeeeeeeeeeeeeeeeeeeeeef INTEROFFICE MEMORANDUM aeeeeeeeeeeeeeeeeeeeeeeeeeeeY DATE: September 1, 1994 TO: J.H. Swailes, WNP-2 Plant Manager (927M) r

'FROM: G.O. Smith, Operations Division Manager (9270)

SUBJECT:

DELEGATION OF AUTHORITY

REFERENCE:

During my absence on September 2-5, 1994, Mr. C.J. Schwarz will act for the Operations Division Manager. Mr. Schwarz will have full authority of the position with the exception of personnel and salary actions.

Should my scheduled return be delayed, this delegation shall continue until my actual return.

hit "Original signed, and filed"