Monthly Operating Rept for Nov 1996 for WNP-2.W/961210 Ltr
ML17292A631
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 11/30/1996
From: Kasko B, Galen Smith
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GO2-96-239, NUDOCS 9612190113
Download: ML17292A631 (7)


Text

CATEGORY j.

REGULATO. INFORMATION DISTRIBUTION JSTEM (RIDS)

ACCESSION NBR:9612190113 DOC.DATE: 96/11/30 NOTARIZED: NO DOCKET FACIE:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH. NAME AUTHOR AFFILIATION KASKO,B. washington Publ'c Power Supply System SMITH,G.O. Washington Public Power Supply System RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operating rept for Nov 1996 for WNP-2.W/961210 ltr.

DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs)

NOTES:

E RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD4-2 PD 1 1 COLBURN,T 1 1 INTERNAL 1 1 AEOD/SPD/RRAB 1 1 FILE C 1 1 NRR/DRPM/PECB 1 1 OC DBA/PAD 1 1 RGN4 1 1 EXTERNAL: LITCO BRYCE,J H 1 1 NOAC 1 1 NRC PDR 1 1 D

0 U

N NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM OWFN SD-5(EXT. 415-2083) TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 11 ENCL . 11

WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O. Box 968 ~ Richland, Washington 99352-0968 December 10, 1996 G02-96-239 Docket No. 50-397*

U. S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555 Gentlemen:

Subject:

WNP-2 OPERATING LICENSE NPF-21 MONTHLYOPERATING REPORT NOVEMBER 1996 Transmitted herewith is the Monthly Operating Report for the month of November 1996 as required by Technical Specification 6.9.1.6.

Respectfully, G. O. Smith Plant General Manager Mail Drop 9270 cc: LJ Callan - NRC RIV TG Colburn - NRR KE Perkins, Jr. - NRC RIV, WCFO NRC Sr. Resident Inspector - 927N NS Reynolds - Winston & Strawn INPO ANI Library Utility Data Institute DL Williams - BPA / 399 9612i9011S Pgiig0 PDR ADOCK 05000397i R PDR ygaoc ~i

OPERATING STATUS REPORT for WNP-2 Date: December 1, 1996 Docket: 50-397

2. Reporting Period: NOVEMBER 1996 Outage + On-line Hours: 720.0
3. Utility

Contact:

Bernice Kasko (509) 377-4473

4. Licensed Thermal Power (MW, ): 3486
5. Nameplate Rating (Gross MW, ): 1199
6. Design Electrical Rating (Net MW, ): 1153
7. Maximum Dependable Capacity - summer (Gross MW,): 1153
8. Maximum Dependable Capacity - summer (Net MW, ): 1107
9. Ifchanges occur above since last report, give reasons: none
10. Power to which restricted, if any (Net MW,): none Reasons for restrictions, if any:

MONTH YEAR CUMULATIVE

12. Report Period Hours 720.0 8,040.0 104,888.2
13. Hours Reactor Critical 720.0 5,492.8 75,128.6
14. Rx Reserve Shutdown Hours 0.0 985.9 1,730.8
15. Hours Generator On-Line 720.0 5,255.6 72,506.1
16. Unit Reserve Shutdown Hours 0.0 997.4 1,956.2
17. Gross Thermal Energy (MWH) 2,404,370 14,805,337 215,262,887
18. Gross Electrical Energy (MWH) 821,320 4,924,840 72,502,320
19. Net Electrical Energy (MWH) 791,479 4,699,102 69,457,420
20. Unit Service Factor 100.0% 65.4% 69.1%
21. Unit Availability Factor 100.0% 77.8% 71.0%
22. Unit Capacity Factor (MDC Net) 99.3% 52.8% 60.6%
23. Unit Capacity Factor (DER Net) 95.3% 50.7% 59.7%
24. Unit Forced Outage Rate 0.0% 2.3% 10,4%
25. Forced Outage Hours 0.0 123.3 8,443.0
26. Shutdowns scheduled over the next 6 months (type, date, duration): Refueling outage begins 4/12/97, duration is 42 days
27. Ifcurrently shutdown, estimated startup date:

Note: Cumulative Unit Capacity Factors (MDC & DER) are calculated with weighted averages.

e t AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.: 50-397 UNlT: WNP-2 DATE: December 1, 1996 COMPLETED BY: B Kasko TELEPHONE: (509) 377M73 REPORT PERIOD: NOVEMBER 1996 AVERAGE DAILYPOWER LEVEL AVERAGE DAILYPOWER LEVEL DAY (Net MWe) DAY (Net MWe) 1052 16 1144 627 17 1127 1131 18 1149 1145 19 1151 1152 20 1150 1140 21 1152 1151 22 1153 1142 23 1152 766 24 1154 10 709 25 1158 26

'146 1151 12 1142 27 1153 13 1135 28 1145 1147 29 1152 15 1152 1149 INSTRUCTIONS On this form, list the average daily unit power level in MWe (net) for each day in the reporting month. Compute to the nearest whole megawatt.

These figures will be used to plot a graph for each reporting month. Note that when maximum dependable capacity is used for the net electrical rating of the unit, there may be occasions when the daily average power level exceeds the 100% line (or the restricted power level line). In such cases, the average daily unit power output sheet should be footnoted to explain the apparent anomaly.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-397 UNIT NAME: WNP-2 DATE: December 1, i/96 COMPLETED BY: B Kasko TELEPHONE: (509) 377M73 REPORT PERIOD: NOV1MBER 1996 No. Date Type Hours Reason Method LER Number System Component Cause and Corrective Action To Prevent Recurrence 96-14 11/2/96 F Zero N/A N/A CB MOTORX Reduced power to 49% to perform maintenance on ASD channel.

96-15 11/11/96 S Zero B N/A N/A HB/HE VALVEX Reduced power to 75% to perform monthly turbine valve testing.

SUKSXARY: At the end of the month WNP-2 was operating at 100% power.

TYPE REASON METHOD SYSTEM & COMPONENT orced A - Equipment Failure E - Operator Training & ~1- Manus VREG-01 1 E its F &

S - Scheduled B - Maintenance or Test License Examination 2 - Manual Scram C - Refueling F - Administration -

3 Auto Scram D - Regulatory Restriction -

G Operational Error 4 - Continued H - Other 5 - Reduced Load 9 - Other